This document package includes construction documents for the Interagency Natural Resource Center Office Building - Phase III project along with a related federal contract opportunity notice.

The construction documents detail plans for a new 29,000 square foot office building to support 173 employees from the U.S. Forest Service, Fish & Wildlife Service, and Bureau of Land Management. The project will include a wood-framed structure with fiber cement siding and stone cladding, as well as meeting rooms, conference rooms, private offices, and open office space. Construction is scheduled to occur from 2018-2019.

The federal contract opportunity notice indicates the USDA Forest Service Northern Region intends to award a contract for construction of Phase III of the Interagency Natural Resource Center in Coeur d'Alene, Idaho. The project magnitude is estimated between $5-10 million. A request for proposals will be posted on June 5, 2018 with responses due 30 days after.

Drawing cover page

View the file

Other files

File Type Posted
INRC_Second_Floor.dwg DWG drawing
INRC_First_Floor.dwg DWG drawing
7-12-18_Q&A.XLSX XLSX spreadsheet
Amendment_0002.pdf PDF
Revised_B-1.pdf PDF
Questions_and_Answers_062918.pdf PDF
L1.5_(rev1).pdf PDF
125900_SF_-_SYSTEMS_FURNITURE.pdf PDF
Amendment_0001.pdf PDF
S0.1_(rev1).pdf PDF
C1.3_(rev1).PDF PDF
Prebid_Notes_6-19-18.pdf PDF
Prebid_Attendance.pdf PDF
Questions_and_Answers_061818.pdf PDF
Part_2_Project_Manual_2018_06_01.pdf PDF
Drawings_Part_1_2018_06-01.pdf PDF
Drawings_Part_13_2018_06-01.pdf PDF
Drawings_Part_6_2018_06-01.pdf PDF
Drawings_Part_9_2018_06-01.pdf PDF
Drawings_Part_3_2018_06-01.pdf PDF
Drawings_Part_12_2018_06-01.pdf PDF
J-5_Past_Performance_Questionnaire.pdf PDF
Part_4_Project_Manual_2018_06_01.pdf PDF
Drawings_Part_4_2018_06-01.pdf PDF
Drawings_Part_5_2018_06-01.pdf PDF
Drawings_Part_2_2018_06-01.pdf PDF
Drawings_Part_11_2018_06-01.pdf PDF
Part_5_Project_Manual_2018_06_01.pdf PDF
Part_6_Project_Manual_2018_06_01.pdf PDF
Drawings_Part_8_2018_06-01.pdf PDF
J-1_Wage_Rate_Decision_ID180031_Mod_3_Dated_05112018.pdf PDF
Drawings_Part_10_2018_06-01.pdf PDF
Drawings_Part_14_2018_06-01.pdf PDF
Short_Set_Solicitation_12034318R0017_Final_06072018.pdf PDF
J-4_State_of_Idaho_Workers'_Insurance.pdf PDF
Part_3_Project_Manual_2018_06_01.pdf PDF
Drawings_Part_7_2018_06-01.pdf PDF
Solicitation_12034318R0017_Final_06072018.pdf PDF
Part_7_Project_Manual_2018_06_01.pdf PDF
Part_1_Project_Manual_2018_06_01.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SUMMARY

PROJECT NAME:

PROJECT ADDRESS:

PROJECT SUMMARY / SCOPE OF WORK:

INTERAGENCY NATURAL RESOURCE CENTER (INRC) OFFICE BUILDING - PHASE 3

47°43'01.4"N 116°48'55.7"W

3600 W. NURSERY RD, COEUR D'ALENE, ID, KOOTENAI COUNTY, 83815 - CLIMATE ZONE B5

PROJECT INCLUDES A ENTIRELY NEW OFFICE BUILDING STRUCTURE THAT WILL BE WOOD FRAMED. MATERIALS TO INCLUDE: FIBER-CEMENT SIDING, STONE CLADDING, TIMBER-FRAMED ENTRYWAY, ETC. SPACES WILL INCLUDE:

MEETING ROOMS, CONFERENCE ROOMS, PRIVATE OFFICES AND OPEN OFFICE SPACE.

IDAHO STATE MAP VICINITY MAP

Image Courtesy of Google Earth

PROJECT LOCATION

COEUR D'ALENE

IDAHO FALLSBOISE

TWIN FALLS

POCATELLO

SPOKANE

LEWISTON

MISSOULA

I90

N . R

A M

S E

Y R

D

W. KATHLEEN AVE.

L

IN

C O

L N

W A

Y

MT

WA

NOTE: SEE A0.3 FOR ACTUAL AREAS AS

THEY RELATE TO THE BUILDING CODE

DRAWING INDEXPROJECT TEAM

OWNER

US DEPARTMENT OF AGRICULTURE - USDA

IDAHO PANHANDLE NATIONAL FORESTS

3815 SCHREIBER WAY

COEUR D'ALENE, ID 83815

(208) 765-7204 office

MIKE SHOUP, CONTRACTING OFFICER REPRESENTATIVE

ARCHITECT

A&E ARCHITECTS

222 NORTH HIGGINS

MISSOULA, MT 59802

406.721.5643 office

CHRIS MARTISON, AIA, PRINCIPAL-IN-CHARGE

BRANDON PRINZING, ARCHITECT

CIVIL ENGINEER

MORRISON-MAIERLE, INC.

3011 PALMER ST

MISSOULA, MT 59808

406.542.8880 office

TOBY MCCLUE, CIVIL ENGINEER

STRUCTURAL ENGINEER

DCI ENGINEERS

131 W. MAIN ST

MISSOULA, MT 59802

406.721.7315 office

TOM BEAUDETTE, STRUCTURAL ENGINEER

M/P/E ENGINEER

MORRISON-MAIERLE, INC.

3011 PALMER ST

MISSOULA, MT 59808

406.542.8880 office

ARIAN BLOOMFIELD, ELECTRICAL ENGINEER

JODY WAVEREK, MECHANICAL / PLUMBING ENGINEER

LANDSCAPE ARCHITECT

KENT WATSON & ASSOCIATES

225 BLACK PINE TRAIL

MISSOULA, MT 59803

406.721.3500 office

KENT WATSON, LANDSCAPE ARCHITECT

SYSTEMS FURNITURE DESIGNER

INSITE INC.

631 PARK LANE

BILLINGS, MT 59102

(406) 256-6232 office

MARY SUE GUNNIFSON, INTERIOR DESIGNER

1. EVERY ATTEMPT HAS BEEN MADE TO ASSURE THE ACCURACY OF THE DRAWINGS. NOTIFY ARCHITECT IMMEDIATELY FOR WRITTEN CLARIFICATION IF ANY DISCREPANCY

EXISTS.

2. DRAWINGS CONTAINED WITHIN THESE DOCUMENTS ARE ABBREVIATED IN NATURE. THE CONTRACTOR IS EXPECTED TO USE QUALITY, ACCEPTABLE, CONSTRUCTION

PRACTICES & TECHNIQUES FOR THE EXTENT & TYPE OF WORK DESCRIBED HEREIN.

3. ALL CONSTRUCTION SHALL CONFORM TO ALL APPLICABLE STANDARDS & REGULATIONS AS PRESCRIBED BY THE INTERNATIONAL EXISTING BUILDING CODE, UNIFORM MECHANICAL CODE, UNIFORM PLUMBING CODE, UNIFORM FIRE CODE, AMERICAN NATIONAL STANDARDS, NFPA, THE AMERICANS WITH DISABILITIES ACT, & ANY APPLICABLE LOCAL CODES & REGULATIONS AND ALL WORK SHALL BE PREFORMED IN ACCORDANCE WITH ALL REQUIREMENTS OF THE LOCAL AUTHORITY OF JURISDICTION

4. DO NOT SCALE DRAWINGS. IF A DIMENSION DOES NOT EXIST OR IS IN ERROR, CONTACT THE ARCHITECT IMMEDIATELY FOR WRITTEN CLARIFICATION.

5. CONTRACTOR(S) SHALL GUARANTEE THEIR WORK FOR A PERIOD OF NO LESS THAN ONE YEAR FROM THE DATE OF SUBSTANTIAL COMPLETION. CONTRACTOR(S) SHALL

REPLACE ALL DEFECTIVE PARTS & SUPPLIES AT THEIR COST.

6. CONTRACTOR SHALL SUPPLY ALL PARTS, MATERIALS, & LABOR REQUIRED TO COMPLETE THE WORK INDICATED INCLUDING ALL ACCESSORIES, FINISHES, & SYSTEMS NECESSARY OR APPLICABLE TO ENSURE A COMPLETE & FUNCTIONAL PROJECT UPON COMPLETION.

7. ANY ITEM SHOWN OR REFERENCED IN ONE INSTANCE SHALL BE AS IF SHOWN IN ALL INSTANCES.

8. CONTRACTOR TO REFER TO ALL DRAWINGS INCLUDED IN THIS SET FOR DESCRIPTION OF WORK. CONTRACTOR IS RESPONSIBLE FOR COORDINATION OF ALL REQUIREMENTS BETWEEN THE DRAWINGS & THE WORK OF ANY & ALL EMPLOYEES, SUB-CONTRACTORS, SUB-SUB-CONTRACTORS OR ANY PERSON OR TRADE PARTICIPATING

IN ANY ASPECT OF THE WORK OUTLINED.

9. PROVIDE & MAINTAIN ALL NECESSARY BARRICADES, FLAGMEN, SIGNAGE, & TEMPORARY STRUCTURES NECESSARY TO FACILITATE SAFE ACCESS & TRAVEL TO THE

GENERAL PUBLIC.

10. ALL FINISHES SHALL BE SCRIBED TO ADJACENT SURFACES TO ENSURE COVERAGE OF ANY GAPS OR SPACES NOT INTENDED TO BE EXPOSED.

GENERAL NOTES

PHASING PLAN

PHASE 1 - 2017, 2018

SITE WORK, UTILITIES AND WAREHOUSE (NORTH END)

PHASE 2 - 2017, 2018

WAREHOUSE (SOUTH END)

PHASE 3 - 2018, 2019

OFFICE BUILDING, SITEWORK & LANDSCAPING

(DESCRIBED IN THESE DOCUMENTS)

REFER TO C1.2 FOR SITE WORK PHASING INFORMATION

PHASE 1

PHASE 1 SITEWORK

P H

A S

E

PHASE 3

PHASE 3 SCOPE OF WORK

PHASE 1 (NOT IN SCOPE OF WORK)

NOTE: REFER TO CIVIL DRAWINGS

FOR SITEWORK PHASING

PHASE 1

PHASE 2

SITEWORK BOUNDRY (REFERENCE C1.2)

PHASE 2 (NOT IN SCOPE OF WORK)

PHASE 1

FOREST SUPERVISOR

DATETECHNICAL SERVICES OFFICER

DATE

REGIONAL ENGINEER DATE

SIGNATURES

REGIONAL FACILITIES PROGRAM MANAGER DATE

1.1 SYSTEMS FURNITURE - F2.1, F2.2 125900

OPTION ITEMS

OPTION ITEM #1

OPTION ITEM #2

2.1 INFORMATION PAVILION - A1.1 -

2.2 SMOKING STRUCTURE - A1.2 -

2.3 ADHERED STONE MASONRY NS A4.1 044313.16

2.4 FIBER-CEMENT SIDING FS-1, FS-2 A4.1 074646

2.5 ACOUSTICAL PANEL CEILINGS ACT-1, ACT-2 A7.1, A7.2 095113

2.6 CARPET TILE CPT-1,2,3 A2.1F, A2.2F 096813

2.7 PAINTING, INTERIOR GWB - A9.0 099123

2.8 PAINTING, EXTERIOR - A4.1, A4.2, A4.3 099113

2.9 FOLDING PANEL PARTITIONS AC-2 A2.1 102239

2.10 ROLLER SHADES AC-1 A2.1, A2.2, A9.0 122124

2.11 AMPHITHEATER - L1.5 -

# ITEM SHEET PROJECT MANUAL

# ITEM SHEET PROJECT MANUALTAG

TAG

CONTRACTOR TO BID OPTION ITEMS LISTED IN THEIR ENTIRETY. TAG, SHEET, AND

SPEC REFERENCE FOR CONVENIENCE ONLY.

A MINIMUM TWO GREEN GLOBES CERTIFICATION IS REQUIRED WITH THIS PROJECT. REFER TO

PROJECT MANUAL FOR SPECIFICS. CONTRACTOR TO USE GREEN GLOBE SURVEY (INCLUDED IN

PROJECT MANUAL) AS A GUIDING DOCUMENTS TO ACHIEVE GREEN GLOBES CERTIFICATION.

GREEN GLOBES

0 1 2 3 4 5 6 7 8 9 10 inches

DRAWING NO.

PKG

NO.

SHEET

OF

PROJECT NO.:

REVISIONS:

DESIGNED

TECH. REVIEW

CADD

DESIGNED SUB SHEET NO. TITLE OF SHEET

06.01.2018

6/

/2

3:

:0

P

M

06.28.181

CV

06.01.18C O

N S

T R

U C

T

IO

N D

O C

U M

E N

T S

COVERSHEET

13083

INRC OFFICE BUILDING - PHASE 3

USDA FOREST SERVICE

INRC OFFICE BUILDING - PHASE 3

GENERAL INFORMATION

1 CV COVERSHEET

ARCHITECTURAL DRAWINGS

55 A6.10 INTERIOR ELEVATIONS

56 A6.11 INTERIOR ELEVATIONS

57 A6.12 INTERIOR ELEVATIONS

58 A7.0 RCP - LOWER LEVEL

59 A7.1 RCP - FIRST/GROUND LEVEL

60 A7.2 RCP - SECOND LEVEL

61 A8.0 VERTICAL CIRCULATION - STAIR 1

62 A8.1 VERTICAL CIRCULATION - STAIR 2

63 A8.2 VERT. CIRC. - ELEVATOR

64 A9.0 SCHEDULES - ROOM FINISHES

65 A9.1 SCHEDULES - DOOR & WINDOW

66 A9.2 DOOR AND WINDOW TYPES

67 A9.3 DETAILS - CANOPIES

68 A9.4 DETAILS - CASEWORK

69 A9.5 DETAILS - CASEWORK

70 A9.6 DETAILS - CEILINGS / FLOORS

71 A9.7 DETAILS - INTERIOR

72 A9.8 DETAILS - SCREEN & MURAL

73 A9.9 DETAILS - PAINT & SIGNAGE

74 A9.10 DETAILS - STAIR

75 A9.11 DETAILS - DOOR

76 A9.12 DETAILS - WINDOW

77 A9.13 DETAILS - STOREFRONT

ARCHITECTURAL DRAWINGS

18 A0.1 GENERAL INFORMATION

19 A0.2 INTERIOR WALL ASSEMBLIES

20 A0.3 CODE ANALYSIS / LIFE SAFETY

21 A1.0 ARCHITECTURAL SITE PLAN

22 A1.1 INFORMATIONAL PAVILION

23 A1.2 SMOKING STRUCTURE

24 A2.0 LOWER LEVEL PLAN

25 A2.0C LOWER LEVEL CONSTRUCTION PLAN

26 A2.1 FIRST/GROUND LEVEL PLAN

27 A2.1C FIRST/GROUND LEVEL CONSTRUCTION PLAN

28 A2.1F FIRST/GROUND LEVEL FLOOR FINISH PLAN

29 A2.2 SECOND LEVEL PLAN

30 A2.2C SECOND LEVEL CONSTRUCTION PLAN

31 A2.2F SECOND LEVEL FLOOR FINISH PLAN

32 A2.3 ATTIC LEVEL PLAN

33 A2.4 ROOF PLAN - MAIN

34 A2.5 ROOF PLAN - CANOPIES

35 A2.6 ROOF DETAILS

36 A3.0 ENLARGED FLOOR PLANS

37 A4.1 EXTERIOR ELEVATIONS

38 A4.2 EXTERIOR ELEVATIONS

39 A4.3 EXTERIOR ELEVATIONS

40 A5.0 BUILDING SECTIONS

41 A5.1 BUILDING SECTIONS

42 A5.2 WALL SECTIONS

43 A5.3 WALL SECTIONS

44 A5.4 WALL SECTIONS

45 A5.5 EXTERIOR DETAILS

46 A6.1 INTERIOR ELEVATIONS

47 A6.2 INTERIOR ELEVATIONS

48 A6.3 INTERIOR ELEVATIONS

49 A6.4 INTERIOR ELEVATIONS

50 A6.5 INTERIOR ELEVATIONS

51 A6.6 INTERIOR ELEVATIONS

52 A6.7 INTERIOR ELEVATIONS

53 A6.8 INTERIOR ELEVATIONS

54 A6.9 INTERIOR ELEVATIONS

MECHANICAL DRAWINGS

93 M0.1 HVAC NOTES AND LEGENDS

94 M0.2 HVAC SCHEDULES

95 M0.3 HVAC SCHEDULES

96 M0.4 HVAC SCHEDULES

97 M0.5 MEP COORDINATION

98 M2.0 LOWER LEVEL HVAC PLAN

99 M2.1 FIRST/GROUND LEVEL HVAC PLAN

100 M2.2 SECOND LEVEL HVAC PLAN

101 M2.3 ATTIC HVAC PLAN

102 M2.4 FIRST/GROUND LEVEL HVAC PIPING PLAN

103 M2.5 SECOND LEVEL HVAC PIPING PLAN

104 M5.0 HVAC SECTIONS

105 M9.1 HVAC DETAILS

106 M9.2 REFRIGERANT PIPING SCHEMATICS

PLUMBING DRAWINGS

107 P0.1 PLUMBING SCHEDULES AND LEGENDS

108 P2.0 LOWER LEVEL PLUMBING PLAN

109 P2.1 FIRST/GROUND LEVEL UNDERFLOOR PLUMBING PLAN

110 P2.2 FIRST/GROUND LEVEL PLUMBING PLAN

111 P2.3 SECOND LEVEL UNDERFLOOR PLUMBING PLAN

112 P2.4 SECOND LEVEL PLUMBING PLAN

113 P9.1 PLUMBING DETAILS

LANDSCAPE DRAWINGS

12 L0.1 LANDSCAPE SCHEDULE

13 L1.1 LANDSCAPE SITE PLAN

14 L1.2 LANDSCAPE DETAILS

15 L1.3 IRRIGATION SCHEDULE

16 L1.4 IRRIGATION SITE PLAN

17 L1.5 AMPHITHEATER

ELECTRICAL DRAWINGS

114 E0.1 SYMBOLS AND ABBREVIATIONS

115 E1.1 ELECTRICAL SITE PLAN

116 E2.0 LOWER LEVEL POWER PLAN

117 E2.1 FIRST/GROUND LEVEL POWER PLAN

118 E2.2 SECOND LEVEL POWER PLAN

119 E2.3 ATTIC LEVEL POWER PLAN

120 E2.4 LOWER LEVEL SIGNAL PLAN

121 E2.5 FIRST/GROUND LEVEL SIGNAL PLAN

122 E2.6 SECOND LEVEL SIGNAL PLAN

123 E2.7 ATTIC LEVEL SIGNAL PLAN

124 E7.0 RCP LOWER LEVEL LIGHTING PLAN

125 E7.1 RCP FIRST/GROUND LEVEL LIGHTING PLAN

126 E7.2 RCP SECOND LEVEL LIGHTING PLAN

127 E7.3 ATTIC LIGHTING PLAN

128 E9.1 DETAILS

129 E9.2 DETAILS

130 E9.3 DETAILS

131 E9.4 DETAILS

132 E9.5 DETAILS

133 E9.6 DETAILS

134 E9.7 DETAILS

135 E9.8 SCHEDULES

136 E9.9 SCHEDULES

137 E9.10 SCHEDULES

138 E9.11 SCHEDULES

139 E9.12 SCHEDULES

140 E9.13 SCHEDULES

PERSPECTIVE SHOWN FOR REFERENCE ONLY

STRUCTURAL DRAWINGS

81 S0.1 GENERAL NOTES

82 S1.1 FOUNDATION PLAN

83 S2.1 MAIN FLOOR PLAN

84 S2.2 UPPER FLOOR PLAN

85 S2.3 ROOF FRAMING PLAN

86 S2.5 SMOKING STRUCTURE PLANS - OPTION ITEM #2

87 S2.6 PAVILION PLANS - OPTION #1

88 S3.1 SHEAR WALL PLANS

89 S9.1 DETAILS

90 S9.2 DETAILS

91 S9.3 DETAILS

92 S9.4 DETAILS

FIRE PROTECTION DRAWINGS

141 FP0.1 FIRE PROTECTION NOTES

142 FP2.1 FIRE PROTECTION PLANS

143 FP9.1 FIRE PROTECTION DETAILS

FURNITURE DRAWINGS

78 F2.1 FIRST/GROUND LEVEL FURNITURE PLAN

79 F2.2 SECOND LEVEL FURNITURE PLAN

80 F9.1 FURNITURE - DETAILS

CIVIL DRAWINGS

2 C1.1 2013 TOPOGRAPHIC SURVEY

3 CD1.1 DEMOLITION PLAN

4 C1.2 OVERALL PHASING PLAN

5 C1.3 PROPOSED SITE PLAN

6 C1.4 GRADING & DRAINAGE PLAN

7 C1.5 SIGNAGE PLAN

8 C1.6 COORDINATE LAYOUT PLAN

9 C1.7 PROPOSED UTILITY PLAN

10 C9.1 CIVIL DETAILS

11 C9.2 CIVIL DETAILS

BUILDING AREAS

Name Area (GSF)

1ST LEVEL GROSS 14607 SF

2ND LEVEL - GROSS 14324 SF

28931 SF

RUNNING SHEET COUNT

1. CONSTRUCTION DOCUMENTS, 06.01.18 TOTAL OF 142

2. REVISION #1, 06.28.18: ADDED (ONE) 1 SHEET TO SET TOTAL OF 143

File details come from the government source that posted it. Updated .