12-QA 1.pdf

PDF 20 KB Posted

Attached to
General Engineering Consultant (GEC) Services
Solicitation number
RFQ 27-002
Issued by
Florida

About this file

This is a Questions and Answers document for RFQ 27-002 issued by the South Florida Regional Transportation Authority (SFRTA) Engineering and Construction Department regarding General Engineering Consultant (GEC) Services. The RFQ solicits professional design and engineering services from individual consultants or consultant teams structured as prime consultants with subconsultants. The technical proposal submission is limited to 25 pages, which includes all resume information for personnel. Proposers have discretion in determining which resume information to include based on the evaluation criteria outlined in Exhibit 1. Additional lines may be added to Sections 7 and 8 of the Contractor's Qualification Form beyond the standard table allocations to list references and similar projects, though proposers may include projects where they held subconsultant roles.

The evaluation and selection process will focus exclusively on the proposer's Technical Proposal; the Contractor's Qualification Form serves as a supporting document. No specific FDOT (Florida Department of Transportation) qualifications are required for this solicitation, allowing a broader pool of qualified consultants to compete. The document does not specify pricing terms, contract duration, renewal options, award dates, or funding sources, indicating this Q&A addresses procedural and submission requirements rather than contractual or financial terms.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ 27-002 General Engineering Consultant (GEC) Services Questions and Answers 1

1 Question: Are resumes included within the 25-page limit?

Answer: Any resume information will be part of the 25-page limit of the Technical Proposal.

2 Question: Are we required to add resumes for key personnel only, or all personnel listed on the organizational chart?

Answer: Please see the Evaluation Criteria in Exhibit 1. Proposers are to determine what resume information to provide in the Technical Proposal.

3 Question: For the listed references and similar projects (7,8) within the Contractor's Qualification Form, can we include more than the table provides for?

(Total of 4 for References and 3 for Similar Contracts), and can we utilize projects for which we had a subconsultant role?

Answer: Proposers may include additional lines in Sections 7 and 8 of the Contractor’s Qualification Form. However, the Evaluation and Selection Committee will only be reviewing and evaluating the proposer’s Technical Proposal.

4 Question: Is there an FDOT Qualifications Requirement that must be met or shown?

Answer: There are no FDOT Qualification Requirements for this solicitation.