10_Attachment_F_-_Protest_Information.docx

DOCX document 227 KB Posted

Attached to
SW1045 Emerging Technologies
Solicitation number
EV00000871
Issued by
Oklahoma County, Hobart City, Oklahoma

About this file

This is a protest information attachment for a Request for Proposals issued by the State of Oklahoma in collaboration with NASPO ValuePoint for Emerging Technologies Consulting and Services (Solicitation Number EV00000871). The document outlines the protest procedures and requirements available to suppliers under Oklahoma's procurement law. Suppliers may protest a contract award to the State Purchasing Director within ten business days of the contract award announcement. The State Purchasing Director will review the protest and contract award documents, then issue a written decision to deny or sustain the protest within ten business days of receipt. If a supplier's protest is denied, they may appeal to the OMES Director within ten business days of the denial notice.

The protest appeal process includes provisions for administrative hearings conducted in accordance with Oklahoma's Administrative Procedures Act. Appeals may be heard by the OMES Director or assigned to an Administrative Law Judge retained by the agency. The burden of proof rests with the protesting supplier, which must demonstrate its case by a preponderance of the evidence. Corporations must be represented by legal counsel licensed under Oklahoma Bar Association rules. Proper parties to the proceedings include the protesting supplier, OMES, the awarded supplier, and the state agency. The Administrative Law Judge may recommend that the OMES Director deny the appeal or cancel and rebid the contract award. All costs associated with processing a supplier's appeal are the responsibility of the state agency responsible for the initial solicitation. Suppliers may further appeal an OMES Director denial pursuant to Oklahoma Statutes Title 75, Section 309 et seq.

View the file

Other files

File Type Posted
05_Attachment_B_-_Scope_of_Work.docx DOCX document
14_Attachment_J_ProposedModification_to_SampleMasterAgreemt.docx DOCX document
15_Attachment_K_-_Claim_of_Business_Confidentiality.docx DOCX document
13_Attachment_I_-_Cost_Proposal_Form.xlsx XLSX spreadsheet
02_Attachment_A_-_RFP_Terms_and_Conditions.docx DOCX document
12_Attachment_H_-_Requirements_Response_Table.xlsx XLSX spreadsheet
16_Attachment_L_-_Supplier_Bid_Submission_Guide.pdf PDF
03_Attachment_A1_OMES_FormCP004_Non-Collusion_Certification.docx DOCX document
07_Attachment_D_-_Sample_Master_Agreement.docx DOCX document
SW1045_EV00000871_Amendment_2.pdf PDF
NASPO-eMarketPlace-Terms_of_Use.pdf PDF
Attachment_E_-_Participation_Information(Amended1).docx DOCX document
5-22-25_Stdardized_Detailed_SalesReporting_Temp_-all_Vend1.xlsx XLSX spreadsheet
EV00000871_Amendment_1.docx DOCX document
11_Attachment_G_Offeror_Info._Acknowledgement___Cert.docx DOCX document
Attachment_E_-_Participation_Information_Amended.docx DOCX document
12_Attachment_H_-_Requirements_Response_Table_Amended.xlsx XLSX spreadsheet
08_Attachment_D1_-_Sample_Master_Agreement_Cover_Page.docx DOCX document
04_Attachment_A2_Form_CP076_Responding_Bidder_Information.pdf PDF
09_Attachment_E_-_Participation_Information.docx DOCX document
01_RFP_Overview.docx DOCX document
06_Attachment_C-__RFP_Evaluation_Plan.docx DOCX document
13_Attachment_I_-_Cost_Proposal_Form_Amended.xlsx XLSX spreadsheet
05_Attachment_B_-_Scope_of_Work_Amended.docx DOCX document
06_Attachment_C-__RFP_Evaluation_Plan_AMENDED.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposals for

[PORTFOLIO NAME]

Issued by the State of [Lead State] Solicitation Number: [#######]

Request for Proposals for Emerging Technologies Consulting and Services Issued by the State of Oklahoma Solicitation Number EV00000871 EV00000871 Attachment F

PROTEST INFORMATION

This attachment is intended to provide Offerors with an overview of the Lead State’s protest law, procedures, and requirements, which may be updated and amended without notice. Offerors filing a protest are wholly responsible for locating, understanding, and complying with protest law, procedures, and requirements in effect at the time of the protest.

OAC 260:115-3-19 - Supplier's Protest

1. A supplier may protest a contract award by a state agency or OMES to the State Purchasing Director. All remedies available to suppliers through the sealed bid process pursuant to the Oklahoma Central Purchasing Act are also available to online bidders in an online bidding process.

0. Supplier notification. A supplier shall submit written notice to the State Purchasing Director of a protest of an award of contract by a state agency or OMES within ten (10) business days of contract award. The supplier protest notice shall state all facts and reasons in specificity for protest.

0. State Purchasing Director review and determination. The State Purchasing Director shall review the supplier’s protest and contract award documents.

1. The State Purchasing Director may determine to respond to the protest or delegate the responsibility by written notice to the state agency that awarded the contract.

1. The State Purchasing Director or state agency, whichever is applicable, shall send written notice of the decision to deny or sustain the protest to the supplier within ten (10) business days of receipt of the protest.

0. Supplier appeal of decision to deny protest. The supplier may appeal against the denial of a protest by the State Purchasing Director or a state agency to the OMES Director.

2. Such appeal shall be filed by the supplier within ten (10) business days of the date of the State Purchasing Director’s or state agency’s notice of denial pursuant to 75 O.S. §§309 et seq.

2. The OMES Director may enter an order staying with contract performance upon such terms and conditions as the OMES Director determines to be proper. Any request for stay of contract performance must be made in writing and filed during the ten (10) business daytime period in which an appeal may be commenced to the OMES Director. The OMES Director shall have continued jurisdiction to modify any such orders made in connection with a stay during the pendency of the appeal as appropriate under the circumstances presented.

0. Director’s actions and determination. The OMES director may hear the appeal or assign the supplier’s appeal to an Administrative Law Judge retained by the agency.

3. If the appeal is assigned to an Administrative Law Judge, the Administrative Law Judge shall review the appeal for legal authority and jurisdiction. If legal authority and jurisdictional requirements are met, the Administrative Law Judge shall conduct an administrative hearing and provide proposed findings of fact and conclusions of law to the OMES Director.

3. If the appeal is heard by the OMES Director, the OMES Director shall have all powers granted by law including all powers delegated to the Administrative Law Judge by this section.

3. The OMES Director shall send a written notice of the final order sustaining or denying the supplier’s appeal to the parties.

3. The cost of actions necessary to process a supplier’s appeal, together with any other expenses incurred due to the appeal, shall be paid by the state agency responsible for the initial solicitation.

0. Conduct of administrative hearing. Administrative hearings shall be conducted in accordance with the Administrative Procedures Act and the following procedures:

4. Prehearing conference. A prehearing conference shall be scheduled to determine the legal or factual issues which shall be limited to those brought by the supplier in its initial protest to the State Purchasing Director.

4. Burden of proof. The burden of proof shall be upon the supplier, which must prove its case by a preponderance of the evidence. A preponderance of the evidence is that evidence which, in light of the record as a whole, leads the Administrative Law Judge to believe a fact is more probably true than not true.

4. Representation. Corporations must be represented by legal counsel in accordance with Oklahoma law. Legal counsel must be licensed or registered pursuant to the Rules Creating and Controlling the Oklahoma Bar Association.

4. Proper parties. In addition to the supplier protesting the contract award, OMES, the supplier awarded the contract and the state agency for which the bid was let may participate in the bid protest proceedings as a proper party.

4. Discovery. The conduct of discovery is governed by the Administrative Procedures Act, 75 O.S. §§ 309 et seq. and other applicable laws.

4. Authority of the Administrative Law Judge. The Administrative Law Judge may:

5. Establish a scheduling order;

5. Establish reasonable procedures such as authorizing pleadings to be filed by facsimile or electronic mail;

5. Rule on all interlocutory motions;

5. Require briefing on any or all issues;

5. Conduct hearings;

5. Rule on the admissibility of all evidence;

5. Question witnesses; and

5. Make proposed findings of facts and conclusions of law to the OMES Director.

4. Remedies. The Administrative Law Judge may recommend that the OMES Director deny the supplier’s appeal or that the contract award be cancelled and rebid.

0. Supplier appeal of OMES Director decision to deny appeal. If the OMES Director denies a supplier’s appeal, the supplier may appeal pursuant to provisions of 75 O.S. §§ 309 et seq.

Page 2 of 9 – Attachment [X], RFP TERMS AND CONDITIONS

Attachment F, PROTEST INFORMATION image1.png image2.png