This document is a detailed painting and coating specification for Pinellas County Schools' Northeast High School Roof Replacement project, covering Buildings 3, 6, 19, and 28. The specification provides comprehensive guidelines for surface preparation, painting, and coating applications for both new construction and previously painted surfaces across various materials including concrete masonry units, steel, wood, gypsum wallboard, and roof decks. The document, issued on 3/27/17 and revised on 6/3/25, outlines specific product types, surface preparation requirements, coating systems, dry film thickness (DFT) measurements, and quality control procedures for exterior and interior painting applications.
The specification emphasizes rigorous quality assurance processes, including mandatory manufacturer site visits, quality control inspections, and detailed surface preparation protocols. It provides specific instructions for addressing surface conditions such as mildew, algae, cracks, rust, and other imperfections, with particular attention to matching textures, ensuring uniform appearance, and achieving proper coating thickness. The document includes extensive notes on testing methods, warranty requirements, and acceptable product types, with references to specific PCS (Pinellas County Schools) product numbers and coating systems. The specification is designed to ensure consistent, high-quality painting and coating applications that meet the school district's stringent standards for durability, appearance, and long-term performance.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pinellas County Schools 09 90 00 Painting and Coating Facility Name: Northeast HS Roof Replacement
- Buildings 3, 6, 19, & 28 PCS Project No.: 9505 / WDA: 2412-02
Issued: 3/27/17 1 of 23 Revised: 6/3/25
PART 1 – GENERAL
1.1 RELATED DOCUMENTS AND SECTIONS
A. The Bidding Requirements, Contractual Conditions and General Requirements of
Division 1 shall apply to all work hereunder.
B. Section 00 65 36.05 Manufacturer’s Coating Warranty C. Section 00 65 36.06 Contractor’s Coating Warranty D. Section 09 90 00 Appendix A Approved Products List
1.2 SCOPE AND GENERAL REQUIREMENTS
A. Work required under this Section consists of all necessary services, tools, equipment, supervision, material and labor required to do all painting work referenced in the Drawings and/or by these specifications.
B. The Contractor shall examine the Paint/Coatings Specifications and understand the applicability to the project. Including but not limited to, surfaces to be painted, surfaces to be unfinished (i.e. protected), shop priming, factory treatments and field application.
C. Paint, painting, painting work, paintwork: As used herein, the term(s) shall mean all coating systems not specifically described in other Sections of these Specifications or which are not explicitly excluded from this Section, including primers, emulsions, enamels, sealers, fillers, and finishing coats.
D. Paint all exposed surfaces whether or not materials are designed in "schedules" except where unfinished "natural" finish of material is obviously intended or specifically noted as surface not to be painted. Where items are surfaces not specifically mentioned, paint these the same as adjacent similar materials or areas. If color or finish is not designated, the Project Architect/ Engineer (PA/E) will select such from standard colors available for materials systems specified.
E. Shop priming of ferrous and non-ferrous metals are to be prepared and primed according to the appropriate sections herein. Including, but is not limited to Structural Steel, Hollow Metal Work, Miscellaneous Metals, Electrical, Mechanical and similar items.
F. Caulking of joints adjacent to painted surfaces. Caulking is also required on exposed structural steel and steel fabrications to provide corrosion protection.
G. For new construction - Items also to be painted include (but are not limited to):
1) Roof top equipment (A.C. units, fans, vents, etc. - except plumbing vents)
2) Door closers.
3) Galvanized metal exposed to view.
4) Grilles and vents which occur indoors (except aluminum)
5) Miscellaneous metals, such as ladders, access doors
H. Items also to be painted include (but are not limited to):
1) Roof top equipment (A.C. units, fans, vents, etc. - except plumbing vents)
2) Door closers
3) Galvanized metal exposed to view
2 of 23 Revised: 6/3/25
4) Grilles and vents which occur indoors (except aluminum)
5) Miscellaneous metals
6) Ladders
7) Access doors
8) Poles
9) Beams
10) Pipes
11) Electrical boxes
12) Conduit (exposed to view)
13) HVAC Cabinets and Supports (Do not paint or pressure wash coils, internal parts, moving parts or labels)
14) Handrails
15) Basketball poles and backboards
16) Baseball and Softball foul ball markers
17) Soccer and Football goal posts
18) Flag poles
19) Safety bollards
20) Concrete posts
21) All factory-finished items with visible rusting or corroding, peeling and/or color fading
22) Faded fire alarm equipment
23) Roof top equipment including plumbing vents
24) Fire Hydrants (osha yellow body with white caps) School board owned only.
1.3. WORK NOT INCLUDED
A. Pre-finished items: Except where specifically called for otherwise, do not include painting when full factory-finishing or installer-finishing is specified for such items (but not limited to):
Toilet partitions, acoustical materials, finished mechanical and electrical equipment such as light fixtures, panels, switch gear, motors, pumps, air handling equipment, and the like.
B. Concealed surfaces: Unless otherwise specifically called for, finish painting is not called for on surfaces above ceilings, behind walls or partition surfacing, nor in inaccessible areas, foundation spaces and duct shafts.
C. Finished metal surfaces: Finished metal surfaces of anodized aluminum, stainless steel, and chromium plate, copper, bronze and similar finished metal materials will not require finish paint.
D. Operating parts: Do not paint any moving parts of operating units, mechanical and electrical parts such as valve and damper operators, linkages, sensing devices, motor and fan shafts.
Do not paint over fire labels; code required labels, equipment identifications, performance ratings, and name or nomenclature plates.
E. Painting of pipe work and supports as covered under Sections Supplementary Provisions
Mechanical and Electrical. This should be painted under maintenance painting
1.4. QUALITY CONTROL
A. The Paint/Coatings Contractor shall be capable of verifying all requirements outlined herein, including referenced standards and Paint Manufacturer’s product data, using visual and/or instrumental methods.
3 of 23 Revised: 6/3/25
B. The Paint/Coatings Contractor shall not begin painting work until surfaces and environmental conditions are satisfactory. Commencement of painting work shall imply the Paint/Coatings Contractor's acceptance of surfaces and environmental conditions. If such surfaces or conditions are not satisfactory, this Paint/Coatings Contractor shall notify the General Contractor in writing.
C. A Quality Control (QC) Inspector, employed or contracted by either the General Contractor or the Paint/Coatings Contractor shall be identified, qualified and equipped to perform required testing. Test methods and/or observations shall be made to verify conformance to all specified requirements outlined herein or in the manufacturer’s product data sheet (PDS).
1) The QC Inspector shall document all inspections performed and submit to the General Contractor or Project Manager.
2) All QC inspections shall be documented on the PCS Quality Control Inspection Report.
3) The General Contractor or Painting Contractor shall maintain all QC inspection reports and make available to the PA/E or PCS upon request.
D. A representative of the paint/coating manufacturer of the company providing the
Paint/Coatings for this project is required to visit the project periodically at the phases listed below. At a minimum, each of the below phases shall be inspected twice per building:
1) During surface preparation;
2) After surface preparation;
3) After patch or substrate repair;
4) After primer or sealer application; and
5) After the finish coat (final completion).
E. Coverage (Opacity) and Dried Coating Thickness
1) All applications shall include the sufficient number of coats to provide full opacity, but in no event, shall the dry film thickness (DFT) be less than specified herein. If additional coats are needed to provide full opacity, this shall be performed at no additional cost to the Owner.
2) Shop-primed steel surfaces: Measure DFT in accordance with SSPC-PA 2 prior to field-application.
3) Field-painted steel surfaces: Measure DFT in accordance with SSPC-PA 2 prior to application of finish coat.
4) In event the DFT of any surface is disputed, destructive testing shall be performed in accordance with ASTM D 4138 Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means. The number of tests and locations shall be determined by the PA/E or Poject Manager. Upon completion of the testing, repairs to the test areas shall be performed. The General Contractor/ Coatings Contractor shall bear the costs for repairs related to destructive DFT testing.
F. Shop-Applied Paint/Coatings
1) QC Inspection Reports (QCIR) shall be provided for all shop-coated steel (fabrications, components or structural shapes).
4 of 23 Revised: 6/3/25
QCIRs shall include the following:
a) Identifiable piece numbers and date inspected.
b) Inspection tools, methods and standards used to verify conformance to the requirements.
c) Number of tests performed.
d) Replica tape from blast profile testing (if applicable).
e) Paint/coating materials applied.
f) Results of testing including a designation of pass/fail.
g) Signature and contact information of the person who performed the inspection.
2) Contractors shall inform the PA/E or PCS if any deficiencies are identified prior to shipment to the jobsite.
1.5. QUALITY ASSURANCE
A. The PA/E at his discretion may employ a 3rd Party Paint/Coatings Consultant to periodically visit the site of painting work. This consultant will advise the PA/E and the PCS Representative/ Inspector.
B. A pre-work meeting shall be held prior to the beginning of the paint/ coatings field work. The meeting shall be attended by the General Contractor, Paint/ Coatings Contractor QC Inspector, 3rd Party Paint/Coatings Consultant, PCS Representative/ Inspector and the PA/E.
C. The PA/E and PCS Representative/ Inspector shall have a fair opportunity to inspect each phase of preparation and painting including use of in-place scaffolding, ladders, lift equipment etc.
D. Samples of the Paint/Coatings may be periodically removed from unopened containers by the
PA/E and subjected to laboratory analysis.
1.6. PAINT/COATING MATERIALS GENERAL
A. Paint/Coating materials shall be pre-approved and listed on the PCS Qualified Products List
(QPL).
B. When information listed on the manufacturer's PDS conflicts with requirements herein, the more stringent shall take precedence.
C. Use only thinners recommended by paint manufacturer and only within manufacturers recommended limits.
D. All materials not listed in PCS-QPL shall be pre-approved by PCS.
1.7. PAINT/COATING DELIVERY AND STORAGE
A. Deliver all materials to job site in original, new and unopened packages and containers bearing manufacturer's name and label.
B. Each container shall have legible labels with the following information:
5 of 23 Revised: 6/3/25
1) Product name
2) Manufacturer's stock number
3) Manufacturer's name
4) Batch number
C. Store materials in a safe, dry area adequately protected against fire, explosion or other damage which may be caused by paint materials. Good housekeeping practices shall be enforced.
D. A temperature-controlled area or room shall be made available and used for storage of paint materials. Floors and other surfaces of this area shall be adequately protected from damage, and should materials be spilled, or damage occur the Paint/Coatings Contractor shall bear the cost to remedy such.
1.8 SUBMITTALS
A. The General Contractor shall provide to the PA/E six (6) copies of the submittals described herein for Shop- and Field-Painting activities (Electronic copies in portable document format (PDF) shall be provided upon request):
1) Substrate and paint/coating material cross-reference: Document that includes each surface to be coated, PCS number (and product name/ number).
2) Name and contact numbers for all subcontractors who will be performing surface preparation and coating application (field and shop).
3) Work schedule of any task related to this specification (field and shop).
4) Product data sheet (PDS) and safety data sheet (SDS) for each product; including abrasive media to be used by shop painting facility.
5) Written statement from the manufacturer (paint/coatings) stating that the materials have not changed since District approval.
6) Letter of Intent to Warranty: The paint/coatings manufacturer shall provide a Letter of
Intent to Warranty signed by the Corporate Warranty Manager. The letter shall reference the warranty requirements outlined herein (no modifications or qualifications).
7) Color and Dried Coating Samples: Six (6) drawdowns for each product and color on a sealed display chart (e.g. Leneta Company, 800-663-6324). Label all samples as to the product name/ number, PCS number and location(s) to be used. Color samples shall be kept on file by the:
a) PA/E
b) PCS – Facilities, Design and Construction Departments (Construction Coordinator)
c) Job Trailer/General Contractor
d) Maintenance Department (Project Manager)
e) PCS Document Center
f) Head Plant Operator (HPO)
1.9 COLORS
6 of 23 Revised: 6/3/25
A. The Project Architect/ Engineer (PA/E) shall select all Paint/Coatings material colors shades textures and finishes subject to approval by the Pinellas County School Board. The preset color standard shall be the Nuance Color System by Colwell-General.
B. Each applied coat shall have a sufficient color contrast to provide identification between coats
(e.g. underlying colors shall be significantly lighter than each subsequent coat).
C. Color Information for Estimating
1) PA/E will provide a schedule of colors and finishes as approved by Owner for this project.
2) Number of colors for bidding purposes unless otherwise shown on Drawings:
a) Interior stain/varnish finishes ...................... Limited to ONE
b) Colors for interior ........................................ Limited to FIVE
c) Colors per room or space ........................... Limited to TWO
d) Colors per common area ............................ Limited to THREE
e) Colors for Exterior ....................................... Limited to THREE
3) Color strength for estimating unless otherwise shown on Drawings:
a) Light paint hues .......................................... 80-percent of areas
b) Medium paint hues ..................................... 15-percent of areas
c) Strong dark paint hues ............................... 5-percent of areas
4) Approval of the in-place color against approved color chips shall be the right and judgment of the PA/E and PCSB.
1.10 HAZARDOUS PAINT DISTURBANCE
A. Testing for hazardous paint constituents of existing paint/coatings will be performed on a case by case basis. Generally, if the existing paint requires surface preparation prior to paint/coating application, testing shall be performed.
B. The PA/E shall contact the PCS Facilities, Design and Construction Department to request paint chip testing for each existing paint/coating. In some cases, the testing may have been previously performed and reports can be provided.
C. The PA/E shall provide all information necessary to sample each existing paint system where surface preparation will be performed. At a minimum, the information shall include the following:
1) School name
2) Building Numbers
3) Room Numbers
4) Surfaces and color of each
5) Estimated square footage of each surface/color
6) Date test results required
1.11 PREPARATION FOR PAINTING/COATING - GENERAL
7 of 23 Revised: 6/3/25
A. Surface preparation shall be in accordance with manufacturers printed instructions. Any conflict between the manufacturer’s requirements and this specification shall be brought to the attention of the PA/E or PCSB. In general, the most stringent requirement shall prevail.
B. Surfaces to be painted shall be free from scratches thoroughly dry and well sanded / grinded, feathering edges (where appropriate) before painting work is started. Minor defects shall be corrected by the Paint/Coatings Sub-Contractor.
C. PDCA P14-06 Levels of Surface Preparation shall be the Level 4 Supreme for metal substrates and Level 3 Superior for all others.
1.12 LEAD-BASED PAINT
A. When the scope of work requires sanding, scraping or paint stripping, the Contractor shall request copies of the Lead-Based Paint (LBP) survey performed by PCS.
B. If a LBP Survey had not been performed, all surface preparation shall be limited to wet cleaning (e.g. wet sanding, wet scraping etc.) and all paint chips shall be stored in double-lined plastic trash bags and delivered to PCS.
1.13 APPLICATION GENERAL
A. Apply paints/coatings in accordance with manufacturer's recommendations, printed instructions and industry standards. Any conflict between the manufacturer’s requirements and this specification shall be brought to the attention of the PA/E. In general, the most stringent requirement shall prevail.
B. Do not apply paint in rain, fog, or mists or when relative humidity exceeds that specified by the Manufacturer; nor to wet or damp surfaces. Painting may be continued during inclement weather only if areas and surfaces to be painted are enclosed and heated to temperature, relative humidity and time parameters as specified by the manufacturer.
C. All spray application on porous or textured surfaces shall be back-rolled and the roller texture shall be minimized; excessive ropiness is not acceptable.
D. When a roller is used, the roller nap size shall be appropriate for the existing surface condition, porosity, and finish in a manner to assure a smooth, uniform finish will result.
E. All coats shall be free from noticeable laps, brush marks, streaks, runs, sags, wrinkles, pinholes, holidays, etc.
F. Finish coats shall be uniform and shall be applied in a manner which will not show differences in gloss or appearance finish when viewed at a 20-degree angle with a light source at far end of surface being viewed. Uneven appearance shall be resolved by applying additional coats.
1.14 APPLICATION OF SEALANTS
A. Inspect interior and/or exterior caulking at various junctures (e.g. wall penetrations, window returns, window frame to substrate, substrate to substrate, floor to wall, ceiling to wall expansion joints, control joints etc.) All existing sealant joints shall be removed and replaced per sealant manufacturer’s requirements.
8 of 23 Revised: 6/3/25
B. Sealant materials shall be one-part or two-part polyurethane (e.g. Tremco Dymonic).
C. Colors to be approved in writing by PA/E or PCS prior to application.
D. All caulking/sealant joints shall be tooled smooth and non-uniform texture (e.g. chatter) or blistering will not be acceptable.
E. All sealants shall be over coated with finish coat from adjacent substrates. Sealant shall cure for minimum of 4-days prior to application of paint; do not apply textured coatings over sealants).
F. When installing expansion joints, install COLORSEAL from EMSEAL in the expansion joint the lower 12’ install COLORSEAL PR and all walkways DSM system with ADA appoved cover plate. All colors approved by PCS. The EMSEAL products shall be installed per manufactures specifications and any substitutions shall be approved in writing by PCS.
G. Backer rod or bond-breaking tape shall be used with all dynamic joints (i.e. potential for movement).
1.15 PROTECTION
A. Schedule work so painting is performed prior to installation of new fixtures and hardware.
B. Protective devices shall be used (e.g. clean drop cloths, masking film etc.) to prevent overspray or damage to adjoining surfaces, fixtures, equipment, surfaces etc. The Contractor shall be responsible for and shall repair or replace any damage resulting from paint/coatings operations.
1) Provide suitable filters over all HVAC return grills within the work area.
2) Provide "Wet Paint" signs to protect newly painted finishes.
3) Provide barriers that will allow students and staff to move throughout the areas.
1.16 TOUCH-UP AND CLEANING
A. After completion of the project, touch-up painting shall be performed where needed. When a color or sheen difference is discernible when viewed at any angle, corner to corner painting shall be performed.
B. Overspray and paint drips shall be removed from surfaces which are not specified to receive paint/coatings. Repair of surfaces due to removal activities shall be the Contractor’s responsibility.
1.17 WASTE DISPOSAL
A. On a daily basis, properly dispose of all waste materials used to prepare or paint.
B. Liquid waste shall not be disposed in plumbing fixtures, drains or cleanouts.
C. Waste from equipment cleaning shall be contained and disposed off-site.
9 of 23 Revised: 6/3/25
1.18 WARRANTY/GUARANTEE
The Manufacturer, the Paint/Coatings Subcontractor applying the Paint/Coatings and the Contractor each shall in writing, (with six copies originally signed), warrant and guarantee the specific coatings as set forth in the attached Warranties and Guarantees. (See paragraph 8 for submittals).
1.19 TOUCH-UP PAINT
The Paint/Coatings Contractor shall provide the school with five single gallons of each product and color of finish coats only. Each gallon container shall be new and unopened and properly identified as to type and color.
PART 2 - PRODUCTS
2.0 NEW CONSTRUCTION - EXTERIOR PAINT/COATING SYSTEMS -
A. Concrete Masonry Unit (CMU) Walls
1) Surface Preparation: Remove surface dust, dirt and mortar smears; repair damage to CMU and fill large voids. Notes: 1, 2, 3, 4, 5 and 6
Product Type PCS No. DFT (mils)
2) First Coat: Block Filler SBp-01 Note 2
3) Second Coat: Block Filler SBp-01 Note 2
4) Third Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 – 2.0
5) Fourth Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 – 2.0
B. Portland Cement Plaster (Stucco)
1) Surface Preparation: Remove surface contamination; patch hairline cracks; Note 7 and 18
Product Type PCS No. DFT (mils)
2) First Coat: Acrylic Primer SBp-02 2.0 - 3.0
3) Second Coat: Acrylic Primer SBp-02 2.0 - 3.0
5) Fourth Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 – 2.0
C. Pre-Cast and Poured-In-Place Concrete
1) Surface Preparation: After installation, clean with potable water and stiff nylon brush to remove surface contamination. Notes 1, 9 and 18
Product Type PCS No. DFT (mils)
2) First Coat: Acrylic Primer SBp-02 2.0 - 3.0
3) Second Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 - 2.0
10 of 23 Revised: 6/3/25
4) Third Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 - 2.0
D. Hot-Dip Galvanized (HDG) Steel and Non-Ferrous Metal
1) Surface Preparation: Remove surface contamination using detergent, degreaser or solvent.
Note 10, 11, 12, 14 and 18
Product Type PCS No. DFT (mils)
2) First Coat: Acrylic Bonding Primer SBp-15 2.0 - 3.0
3) Second Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
4) Third Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
E. HDG Hollow-Metal Doors, Door Frames and Window Frames
Notes 10, 11, 12, 14 and 18
Product Type PCS No. DFT (mils)
2) First Coat (Shop): Two-Part Surface Tolerant Epoxy Primer SBp-07 3.0 - 5.0
3) Field Touch-up: Two-Part Surface Tolerant Epoxy Primer SBp-07 N/A
4) Second Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
5) Third Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
F. Carbon Steel (Structural and Miscellaneous Fabrications)
1) Surface Preparation: Prepare in accordance with SSPC-SP 6 with a 2.0 – 3.0 mil profile.
Notes 13, 14 and 18
Product Type PCS No. DFT (mils)
2) First Coat (Shop): Two-Part Surface Tolerant Epoxy Primer SBp-07 8.0 - 10.0
3) Field Touch-up: Two-Part Surface Tolerant Epoxy Primer SBp-07 Note 12
4) Second Coat: Acrylic Rust-Inhibitive Primer SBp-08 2.0 - 4.0
6) Fourth Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
G. Split-Faced CMU, Brick or Miscellaneous Masonry
1) Surface Preparation: Pressure clean to remove dirt and efflorescence. Note 15 and 20
Product Type PCS No. DFT (mils)
2) First Coat: 40-percent Silane Water Repellent SBs-01 Note 15
H. Wood (Non-Bleeding) Species
11 of 23 Revised: 6/3/25
1) Surface Preparation: Counter sink and patch fastener holes with spackling. Caulk seams and intersection of dissimilar materials. Note 16, 17 and 18
Product Type PCS No. DFT (mils)
2) First Coat: Acrylic Wood Primer SBp-03 1.4 – 2.0
I. Wood (Bleeding) Species
1) Surface Preparation: Counter sink and patch fastener holes with oil-based spackling. Caulk seams and intersection of dissimilar materials after primer application.
16, 17 and 18
Product Type PCS No. DFT (mils)
2) First Coat: Oil-based Wood Primer SBp-04 2.3 – 3.0
J. Concrete (Slab-on-grade) Sidewalks and Miscellaneous Pads – Opaque Stain
1) Surface Preparation: Ensure the moisture content and moisture vapor transmission is not detrimental for coating application. Note 21
Product Type PCS No. DFT (mils)
2) First Coat: Concrete Stain (Solvent-Based) SBf-04 Note 18
3) Second Coat: Concrete Stain (Solvent-Based) SBf-04 Note 18
2.1 NEW CONSTRUCTION - INTERIOR PAINT/COATING SYSTEMS
1) Surface Preparation: Remove surface dust, dirt and mortar smears; repair damage to CMU and fill large voids. Notes: 1, 2, 3, 4, 5 and 6
Product Type PCS No. DFT (mils)
2) First Coat: Block Filler SBp-01 Note 2
3) Second Coat: Block Filler SBp-01 Note 2
4) Third Coat: Two-part Water-Based Epoxy SBc-01 2.5 - 3.0
5) Fourth Coat: Two-part Water-Based Epoxy SBc-01 2.5 - 3.0
B. HDG Hollow-Metal Doors, Door Frames and Window Frames
Notes 10, 11, 12 and 18
12 of 23 Revised: 6/3/25
2) First Coat (Shop): Two-Part Surface Tolerant Epoxy Primer SBp-07 3.0 - 5.0
3) Field Touch-up: Two-Part Surface Tolerant Epoxy Primer SBp-07 N/A
4) Second Coat: Two-Part Water-based Polyurethane SBc-02 1.5 - 3.0
5) Third Coat: Two-Part Water-based Polyurethane SBc-02 1.5 - 3.0
C.
Pre-Cast and Poured-In-Place Concrete
1) Surface Preparation: After installation, clean with potable water and stiff nylon brush to remove surface contamination. Notes 1, 9 and 18
Product Type PCS No. DFT (mils)
2) First Coat: Acrylic Primer SBp-02 2.0 - 3.0
3) Second Coat: Two-part Water-Based Epoxy SBc-01 2.5 - 3.0
D. Gypsum Wallboard (GWB) – Walls
1) Surface Preparation: Remove all dust from walls by wiping with damp sponges.
Note 8
Product Type PCS No. DFT (mils)
2) First Coat: Drywall Primer SBp-10 1.1 - 2.0
E. GWB Ceilings and Mechanical Rooms
1) Surface Preparation: Remove all dust from walls by wiping with damp sponges.
Note 8
Product Type PCS No. DFT (mils)
2) First Coat: Drywall Primer SBp-10 1.1 - 2.0
3) Second Coat: Semi-gloss Latex SBc-06 1.6 - 2.5
4) Third Coat: Semi-gloss Latex SBc-06 1.6 - 2.5
F. HDG Roof Decks
2) First Coat: Acrylic Dryfall SBc-07 Note 18
3) Second Coat: Acrylic Dryfall SBc-07 Note 18
13 of 23 Revised: 6/3/25
G. Gypsum Plaster Walls
1) Surface Preparation: Ensure the plaster is sufficiently cured and ready for painting. Note 19
2) First Coat: Plaster Primer SBp-11 1.6 - 2.5
H. Wood Wall Surfaces
1) Surface Preparation: Counter sink and patch fastener holes with spackling. Caulk seams and intersection of dissimilar materials; lightly sand the primer prior to the 2nd coat. Note 16, 17 and 18
Product Type PCS No. DFT (mils)
2) First Coat: Enamel Undercoat SBp-09 1.8 – 2.5
I. Concrete Floors – Opaque Finish – Moderate Duty detrimental for coating application. Clean and mechanically abrade the floor surfaces. Notes 20
Product Type PCS No. DFT (mils)
2) First Coat: Acrylic Floor and Deck Paint SBf-02 1.5 - 2.0
3) Second Coat: Acrylic Floor and Deck Paint SBf-02 1.5 - 2.0
J. Concrete Floors – Pedestrian Walkway – Heavy Duty detrimental for coating application. Clean and mechanically abrade the floor surfaces. Notes 20
Product Type PCS No. DFT (mils)
2) First Coat: Polyurethane Base coat SBf-01 22 - 25
3) Second Coat: Single-component Aliphatic polyurethane SBf-01 2.0 - 2.6
K. Concrete Floors – Clear Finish (Solvent-based)
14 of 23 Revised: 6/3/25
1) Surface Preparation: Remove surface contamination.
2) First Coat: 40% Silane Water Repellant SBs-01 Note 21
L. Concrete (Slab-on-grade) Sidewalks, Pads and Floors – Opaque Stain
1) Surface Preparation: Pressure clean to remove dirt, paint, chalk and miscellaneous contamination.
Add non-slip additive to stain
2) First Coat: H & C Solvent Based Concrete Stain SBf-18 Note 21
2.2 PAINT SYSTEM NOTES – NEW CONSTRUCTION:
CMU or pre-cast concrete with relatively large voids and localized, excessive porosity may require application of spackling to prevent visible “holes” after the complete system application.
The application of spackling (e.g. light weight spackling) shall be performed prior to the 1st coat of finish. For CMU, the intent is to match the general appearance of the surrounding CMUs not to level out all inherent concavities.
DFT measurements shall not be the only method used to verify conformance. The final appearance is the primary determination (e.g. sealed voids, uniform appearance, minimal roller texture, fully opaque etc.).
Mortar shall be cured according to the mortar manufacturer’s recommendations or other approved test method (e.g. hardness, pH etc.). At a minimum, the mortar shall be hard and not able to be gouged with moderate pressure (i.e. not friable).
Repairs to walls after application of paint/coatings shall include, at a minimum, the same number of coats, or more coats in order to reach a uniform appearance.
Concrete and masonry surfaces shall be rubbed and pointed prior to paint/ coating or sealer application. If appropriate conditions do not exist notify the General Contractor of the defect for correction.
Mortar repairs shall be performed using polymer-modified mortar and verified to be hard prior to paint/coating application.
If paint application is to be performed prior to 14 calendar days after Portland cement plaster (stucco) application, document testing of all elevations for sufficient cure. Testing shall be performed by the paint/coating manufacturer or 3rd party and include pH and general hardness (texture and finish coat).
If trowel marks or other minor defects on gypsum plaster necessitate sanding the surface, follow by thoroughly washing and wiping with clean potable water or as per manufacturer’s recommendation.
Pre-Cast concrete components that are dense and smooth (e.g. window sills) shall be etched with ASTM D 4260 Acid Etching Concrete. Acid etch with muriatic acid (20 Baume) to produce a porous substrate and a finish similar to 80 grit sandpaper. Thoroughly rinse after effervescing action and do not allow drying prior to rinse. This operation shall be performed prior to installation and verified (documented) using water penetration testing.
Repair damage to the HDG coating per ASTM A 780 Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings (use of aerosol spray “cold galvanizing” is not permitted).
The total DFT range shall be increased by 1.0 mils to account for the DFT of the HDG. Field touch-up shall be performed prior to installation into the wall and after installation, inspect to determine if additional touch-up is necessary.
15 of 23 Revised: 6/3/25
2.2 PAINT SYSTEM NOTES – NEW CONSTRUCTION:
Field touch-up is required where the shop-applied epoxy primer has been mechanical damaged.
Proper mixing of “partial kits” is acceptable for this application. The surface preparation shall be as follows: Sand the surface to remove loose rust and/or to smooth the surface followed by solvent cleaning. If the mechanical damage exposed the base metal (i.e. visible rust), two spot coats shall be applied and the repaired surface sanded smooth prior to the finish coat application putty body filler repairs shall be spot painted with SBp-08 prior to finish coat application.
Steel profile shall be measured in accordance with ASTM D 4417 Field Measurement of Surface Profile of Blast Cleaned Steel, Method C. A minimum of three (3) locations shall be measured.
Replica tape shall be affixed to all QC reports. Abrasive blasting and primer application shall be performed only when the steel surface temperature is at least 5-degrees F above the dew point temperature; verified through instrumental testing in the work area.
DFT shall be measured in accordance with SSPC-PA 2 Measurement of Dry Coating Thickness with Magnetic Gages and documented.
A mock-up application shall be performed and evaluated by the PA/E prior to beginning the full application. The manufacturer or 3rd party shall perform “RILEM Tube” testing and at least two locations shall be measured (one location over a mortar joint). The results of the RILEM Tube testing shall be reported based on the amount of water-uptake and respective number of minutes (e.g. 1.0 mL in 15 minutes). The results of the testing will determine the pass-fail criteria for the entire project. Porous substrates may require more than one application to meet the acceptable criteria established by the water repellent supplier (to receive the warranty).
After the prime coat has been applied on wood surfaces, nail holes shall be filled with putty.
Putty shall be brought flush with the surface of woodwork and sanded.
Knots sap and pitch streaks in lumber shall be sealed with SBP-12 before the prime coat is applied.
DFT measurements will not be used to verify conformance. The final appearance is the primary determination (e.g. fully opaque, uniform color and sheen etc.).
Cure testing shall be performed by the paint/coating manufacturer or 3rd party and include pH and general hardness.
Apply flood coat to entire surface and maintain uniform wet-look for 20 minutes. If suction/penetration is observed, re-apply.
Etch in accordance with ASTM D 4260 Acid Etching Concrete; utilize muriatic acid (20 Baume) to produce a porous substrate. Thoroughly rinse after effervescing action and do not allow drying prior to rinse. Test surfaces for pH and if found to be acidic, treat with a solution of sodium bicarbonate and water.
16 of 23 Revised: 6/3/25
2.3 PREVIOUSLY PAINTED SURFACES - EXTERIOR PAINT/COATING SYSTEMS
1) Surface Preparation: Note 1, 2, 3, 5, 8, 9
2) First Coat: Acrylic Chalk Binder (Pigmented) SBp-05 n/a
3) Second Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 – 2.0
B. Portland Cement Plaster (Stucco)
1) Surface Preparation: Note 1,2, 3, 4, 5, 8, 9
2) First Coat: Acrylic Chalk Binder (Pigmented) SBp-05 n/a
3) Second Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 – 2.0
1) Surface Preparation: Note 1,2 3, 8,9,
4) *Third Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 - 2.0
*Third Coat is required only if full opacity and uniform sheen is not achieved with Second Coat.
17 of 23 Revised: 6/3/25
D. Hot-Dip Galvanized (HDG) Steel and Non-Ferrous Metal
1) Surface Preparation: Note 1, 6, 7, 8,10, 13
2) First Coat: Acrylic Bonding Primer SBp-15 2.0 - 3.0
3) Second Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
4) *Third Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
*Third Coat is required only if full opacity and uniform sheen is not achieved with Second Coat.
E. HDG Hollow-Metal Doors, Door Frames and Window Frames
1) Surface Preparation: Note 1, 6, 7, 8, 10, 13
2) *Spot Primer: Alkyd Rust inhibitive primer SBp-06 N/A
3) Tie-Coat Primer: Acrylic Bonding Primer SBp-15 2.0 - 3.0
4) Second Coat: One part water-based polyurethane Gloss SBc-02 2.0 - 4.0
5) Third Coat: One part water-based polyurethane Gloss SBc-02 2.0 - 4.0
* Spot Prime surfaces prepared according to Note 7.
F. Carbon Steel (Structural and Miscellaneous Fabrications)
1) Surface Preparation: Note 1, 6, 7, 8, 10, 13
3) Tie-Coat Primer: Acrylic Bonding Primer SBp-15 2.0 - 3.0
4) **Second Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
5) **Third Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
** Finish Coat can be substituted to match surrounding finish (e.g.
Semi-Gloss Acrylic).
18 of 23 Revised: 6/3/25
G. Split-Faced CMU, Brick or Miscellaneous Masonry
1) Surface Preparation: Pressure clean to remove dirt and efflorescence. Note 11
2) First Coat: 40-percent Silane Water Repellent SBs-01 Note 15
H. Wood (Non-Bleeding) Species
1) Surface Preparation: Note 1, 2, 6, 8, 12, 13
I. Wood (Bleeding) Species
1) Surface Preparation: Note 1, 2, 6, 8, 12, 13
2) *Spot Primer: Oil-based Wood Primer SBp-04 2.3 – 3.0
3) First Coat: Acrylic Primer SBp-02 2.0 - 3.0
4) Second Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 - 2.0
5) Third Coat: Acrylic Latex Semi-Gloss Exterior Coating SBc-03 1.4 - 2.0
*Spot Prime bleeding knots and other areas where tannin stains are observed.
J. Concrete (Slab-on-grade) Sidewalks, Pads and Floors – Opaque Stain
1) Surface Preparation: Note 1, 18
Add non-slip additive to stain
Product Type PCS No. DFT (mils)
2) First Coat: Concrete Stain (Solvent-Based) SBf-18 Note 18
3) Second Coat: Concrete Stain (Solvent-Based) SBf-18 Note 18
19 of 23 Revised: 6/3/25
2.4 PREVIOUSLY PAINTED SURFACES - INTERIOR PAINT/COATING SYSTEMS
1) Surface Preparation: Clean surfaces to remove dirt and miscellaneous contamination.
Note 5, 8, 9, 13, 16
2) Tie-Coat Primer: Acrylic Bonding Primer SBp-15 2.0 - 3.0
4) Fourth Coat: Two-part Water-Based Epoxy SBc-01 2.5 - 3.0
B. HDG Hollow-Metal Doors, Door Frames and Window Frames
1) Surface Preparation: Note 6, 7, 8, 10, 13
3) Tie-Coat Primer: Acrylic Bonding Primer SBp-15 2.0 - 3.0
4) Second Coat: Two-Part Water-based Polyurethane SBc-02 2.0 - 4.0
1) Surface Preparation: Clean to remove dirt and miscellaneous contamination.
Note 6, 8, 13, 16, D.
Gypsum Wallboard (GWB) – Walls
Note 8, 13, 16
2) Spot Primer: Acrylic Bonding Primer SBp-15 2.0 - 3.0
3) Tie-Coat Primer: Acrylic Bonding Primer SBp-15 2.0 - 3.0
4) Second Coat: Two-part Water-Based Epoxy SBc-01 2.5 - 3.0
20 of 23 Revised: 6/3/25
5) Third Coat: Two-part Water-Based Epoxy SBc-01 2.5 - 3.0
E. GWB Ceilings and Mechanical Rooms
Product Type PCS No. DFT (mils)
2) Tie-Coat Primer: Acrylic Bonding Primer SBp-15 2.0 - 3.0
3) Second Coat: Semi-gloss Latex SBc-06 1.6 - 2.5
4) Third Coat: Semi-gloss Latex SBc-06 1.6 - 2.5
F. HDG Roof Decks
Note 8, Product Type PCS No. DFT (mils)
2) First Coat: Acrylic Dryfall SBc-07 N/A
3) Second Coat: Acrylic Dryfall SBc-07 N/A
*Second Coat is required only if full opacity and uniform sheen is not achieved with First Coat.
G.
Gypsum Plaster Walls
H. Wood Wall Surfaces
Note 8, 12, 13
2) Spot Primer Enamel Undercoat SBp-09 N/A
3) Tie-Coat Primer: Acrylic Bonding Primer SBp-15 2.0 - 3.0
4) Second Coat: Two-part Water-Based Epoxy SBc-01 2.5 - 3.0
5) Third Coat: Two-part Water-Based Epoxy SBc-01 2.5 - 3.0
21 of 23 Revised: 6/3/25
I. Varnished / lacquer Wood Doors
Note 17
Product Type PCS No. DFT (mils)
2) Spot Primer Satin Water-Based Varnish SBc-11 N/A
3) first Coat: Satin Water-Based Varnish SBc-11 2.0 - 3.0
4) Second Coat: Satin Water-Based Varnish SBc-11 2.5 - 3.0
J. Concrete Floors – Opaque Finish – Moderate Duty
Note 6, 8 and 18 if need
2) First Coat: Acrylic Floor and Deck Paint SBf-02 1.5 - 2.0
3) Second Coat: Acrylic Floor and Deck Paint SBf-02 1.5 - 2.0
K. Concrete Floors – Pedestrian Walkway – Heavy Duty
Note install per manufactures recommendations
2) First Coat: Polyurethane Base coat SBf-01 22 - 25
3) Second Coat: Single-component Aliphatic polyurethane SBf-01 2.0 - 2.6
L. Concrete Floors – Clear Finish (Solvent-based)
1) Surface Preparation: Remove surface contamination. Note 15
2) First Coat: 40% Silane Water Repellant SBs-01 Note 18
22 of 23 Revised: 6/3/25
2.5 PAINT SYSTEM NOTES – PREVIOUSLY PAINTED SURFACES
A. Mildew and algae shall be treated prior to pressure cleaning by (1) a solution of one quart “household bleach” (3 – 6-percent sodium hypochlorite) to one-gallon potable water applied using a low-pressure sprayer, or (2) pressure cleaner with chemical injector using “pool chlorine” (10 – 12-percent sodium hypochlorite). Do not allow solution to dry on surface prior to pressure cleaning.
B. If pressure cleaning is used to completely remove/strip deteriorated paint, the surfaces shall be permitted to dry for a minimum of 72 hours prior to primer application.
C. Cracks in exterior stucco shall be patched using elastomeric patching compound using the
“texture” that matches the surfaces being patched (e.g. sand textured or smooth textured).
1) Hairline cracks (i.e. less than 1/64-inch at its widest point) shall be patched using “brush grade” patch worked into the crack and flush with the surface.
2) Cracks between 1/64-inch and 1/8-inch shall be raked-out and wire brushed to remove loose materials. Patched with “knife grade” patch with build-up over the crack and sufficiently textured to match surrounding stucco texture. Two applications may be required.
3) Cracks larger than 1/8-inch shall be saw-cut to a uniform depth (e.g. 1/4 – 1/2-inch, wire brushed and vacuumed, install bond-breaking tape or closed-cell backer rod, install one-part polyurethane sealant (tooled flush). After 4-days of cure time, use “knife-grade” elastomeric patching compound to blend with surrounding stucco.
D. Tap surfaces to determine the soundness of the stucco. Locations to focus are as follows:
(1) where cracks are observed, (2) base of wall, (3) around windows and doors.
E. Remove loose stucco and mortar; patch using pre-mixed cementations patch (i.e. Euclid
Eucopatch). For stucco, the mix shall be enhanced using a 100-percent acrylic additive (e.g.
Euclid Flex-Con).
F. Scarify all surfaces to be coated to achieve a uniform anchor pattern for the subsequent coatings. Solvent wipe (e.g. denatured alcohol) to remove all particulate created as a result of abrading.
G. Steel surfaces showing signs of rust (bleed-through or blistering) shall be prepared in accordance with SSPC-SP 3, Power Tool Cleaning.
H. All loose, peeling paint, raised paint edges shall be scraped back until tightly bonded. Paint edges shall be sufficiently bonded as not to be lifted by the blade of a dull putty knife.
I. DFT measurements shall not be used to verify conformance. The final appearance is the primary determination (e.g. sealed voids, uniform appearance, minimal roller texture, fully opaque etc.).
J. DFT shall be measured in accordance with SSPC-PA 2 Measurement of Dry Coating
Thickness with Magnetic Gages and documented.
K. A mock-up application shall be performed and evaluated by the PA/E prior to beginning the full application. The manufacturer or 3rd party shall perform “Rilem Tube” testing and at least two locations shall be measured (one location over a mortar joint). The results of the
Rilem Tube testing shall be reported based on the amount of water-uptake and respective
23 of 23 Revised: 6/3/25 number of minutes (e.g. 1.0 mL in 15 minutes). The results of the testing will determine the pass-fail criteria for the entire project.
L. After the prime coat has been applied on wood surfaces, nail holes shall be filled with putty.
Putty shall be brought flush with the surface of woodwork and sanded.
M. DFT measurements will not be used to verify conformance. The final appearance is the primary determination (e.g. fully opaque, uniform color and sheen etc.).
N. Cure testing shall be performed by the paint/coating manufacturer or 3rd party and include pH and general hardness.
O. Apply flood coat to entire surface and maintain uniform wet-look for 20 minutes. If suction/penetration is observed, re-apply.
P. Cracks, damage and holes in interior stucco, plaster, and drywall shall be patched using proper patching compounds per manufactures recommendations using the “texture” that matches the surfaces being patched (e.g. sand textured or smooth textured).
Q. Hairline cracks (i.e. less than 1/64-inch at its widest point) shall be patched using “brush grade” patch worked into the crack and flush with the surface.
R. Cracks between 1/64-inch and 1/8-inch shall be raked-out and wire brushed to remove loose materials. Patched with “knife grade” patch with build-up over the crack and sufficiently textured to match surrounding sub-straight texture. Two applications may be required.
S. Cracks larger than 1/8-inch shall be saw-cut to a uniform depth (e.g. 1/4 – 1/2-inch, wire brushed and vacuumed, install bond-breaking tape or closed-cell backer rod, install one-part polyurethane sealant (tooled flush). After 4-days of cure time, use “knife-grade” patching compounds to blend with surrounding surface to match texture.
T. Patch gouges and damage using stainable putty followed by sanding smooth and staining to match color.
U. Etch in accordance with ASTM D 4260 Acid Etching Concrete; utilize muriatic acid (20
Baume) to produce a porous substrate. Thoroughly rinse after effervescing action and do not allow drying prior to rinse. Test surfaces for pH and if found to be acidic, treat with a solution of sodium bicarbonate and water.
END OF SECTION