017350 Fire Prevention Precautions for Hot Work.pdf

PDF 33 KB Posted

Attached to
HUD Granite Facade Replacement Federal contract opportunity
Solicitation number
47PM0120R0008
Issued by
General Services Administration Public Buildings Service

About this file

This solicitation requests proposals for a design-build contract to replace the granite facade on the Robert C. Weaver Federal Building in Washington, DC. The General Services Administration seeks a firm-fixed price contract to survey, remove, and reinstall existing granite panels; clean panels; install a new anchoring system; repair panels as needed; install roof davits; repair metal roofs at stair towers; and conduct potential exterior hazardous materials abatement and waterproofing. The estimated price range for this project is between $10-15 million. Interested firms must be located within 50 miles of the project site and registered in the System for Award Management. Proposals are due by August 14, 2020. A pre-proposal conference will be held virtually on July 8, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to HUD Granite Facade Replacement, newest first.
File Type Posted
LIVE Bid Spreadsheet_REV 7.23.20.xlsx XLSX spreadsheet
Past Performance Questionnaire.docx DOCX document
012700 Unit Prices_REV.docx DOCX document
Solicitation Amendment 47PM0120R0008_0002.pdf PDF
Solicitation Amendment 47PM0120R0008_0001 (2).pdf PDF
013220 Photographic Documentation.docx DOCX document
013200 Construction Progress Documentation.pdf PDF
013510 Historic Building Treatment Procedures.pdf PDF
017000 Execution Requirements.pdf PDF
009010 Competency of Specialist for Facade.pdf PDF
017310 Cutting and Patching.pdf PDF
011000 Summary.pdf PDF
Bid Spreadsheet 47PM0120R0008.xlsx XLSX spreadsheet
009040 Competency of Conc Repair Spc.pdf PDF
017810 Project Record Documents.docx DOCX document
013110 Critical Path Method Scheduling.pdf PDF
Optional GFE AFrame Details.pdf PDF
020850 Asbestos Abatement Procedures.pdf PDF
013000 Electronic Project Management.pdf PDF
HUD Granite Facade Repair Phase 2 Drawings.pdf PDF
013300 Submittal Procedures.docx DOCX document
SOW HUD Ph 2 2020 06 08.pdf PDF
012300 Alternates.pdf PDF
016000 Product Requirements.pdf PDF
011400 Work Restrictions.pdf PDF
012500 Substitution Procedures.docx DOCX document
Vol1 1999 Robert C Weaver Fed Building Historic Structure Report.pdf PDF
015930 Security Regulations.pdf PDF
012900 Payment Procedures.pdf PDF
014050 System Quality Control.docx DOCX document
200408 HUD Mortar Analysis and Permeability Study MTFA D P.pdf PDF
015950 Safety and Health.pdf PDF
Preproposal Agenda 2020 07 08.pdf PDF
020900 Removal and Testing of Lead Based Paint.pdf PDF
018200 Demonstration and Training.docx DOCX document
020890 PCB Abatement Procedures.pdf PDF
017320 Selective Demolition.docx DOCX document
018111 Sustainable Design Requirements.docx DOCX document
017419 Const Nonhaz Waste Mgmt Disp.docx DOCX document
Solicitation Pkg 47PM0120R008.pdf PDF
015000 Temporary Facilities.pdf PDF
017700 Closeout Procedures.pdf PDF
014200 References.pdf PDF
014000 Quality Assurance and Control.pdf PDF
013100 Project Management Coordination.pdf PDF
012700 Unit Prices.pdf PDF
Vol2 1999 Robert C Weaver Fed Building Historic Structure Report.pdf PDF
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Robert C Weaver Federal Building, Granite Façade Repairs, Phase 2 Washington, DC Project Number # VDC00213

FY15 Update Oct. 1, 2014 Fire Prevention Precautions for Hot Work 017350 - 1

SECTION 017350 - FIRE PREVENTION PRECAUTIONS FOR HOT WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This section applies to safeguards to be observed in performing hot work, including welding, soldering, brazing and other operations where open flames or implements utilizing heat are used.

B. Hot Work Permit: Comply with NFPA 51B. Do not conduct operations involving the use of open-flame, electrical arc equipment, or flammable substances until a permit for welding, cutting, and burning has been issued by the Government.

1. GSA will identify and delineate the responsibilities of the Government permit authorizing individual before or during the Preconstruction Meeting.

C. Hot work permit duration shall be one work shift for a specific location unless otherwise agreed to by the Government and Contractor.

1.2 SAFETY PRECAUTIONS

A. Prior to operations, the site shall be visited and suitable locations established for the portable equipment storage during non-working hours. The Contractor and the Government shall coordinate and designate such locations.

B. The Contractor shall ensure that operations involving the use of open-flame, electrical arc equipment or flammable substances are not conducted until a permit for welding, cutting, and burning has been completed, signed and issued by the GSA Building Manager.

C. Prior to commencing operations, a positive determination shall be made that it is impractical to conduct the hot work in a shop area or outside of the building. Coordinate suitable locations for hot equipment operations agreeable to the Contracting Officer’s Representative.

1.3 NOTIFICATON

A. The Contractor shall notify GSA’s Building Manager at least 72 hours in advance of the area of operations for each day and of all subsequent changes that occur.

B. The Contractor shall notify the GSA Building Manager of all locations where hot work has been performed not less than 30 minutes before the work or no more than 90 minutes after work is completed or stopped for the day.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 INSPECTION

FY15 Update Oct. 1, 2014 Fire Prevention Precautions for Hot Work 017350 - 2

A. Before starting operations, the Contractor shall furnish trained personnel to provide fire watches for locations where hot work is to be performed. One fire watcher may observe no more than two (2) locations if in a relatively small contiguous area if approved by the Contracting Officer's Representative and in compliance with applicable fire codes. Contractor shall furnish suitable type, fully-charged, operable portable fire extinguisher to each fire watcher. The Contractor shall provide fire watchers who know how to operate the fire extinguisher, how to initiate a fire alarm and how to summon the fire department.

B. Before starting operations, take suitable precautions to minimize the hazard of a fire communicating to the opposite side of walls, floors, ceilings and roofs from the operations.

3.2 SAFETY MEASURES

A. Hot work shall not be done in or near rooms or areas where flammable liquids or explosive vapors are present or thought to be present. A combustible gas indicator (explosimeter) test shall be conducted to assure that each area is safe. The Contractor is responsible for arranging and paying for each test.

B. Insofar as possible, the Contractor shall remove and keep the area free from all combustibles, including rubbish, paper and waste within a radius of 25 feet (7.62 m) from hot operations.

1. If combustible material cannot be removed, the Contractor shall furnish fireproof blankets to cover such materials. At the direction of the Building Manager or Contracting Officer's Representative, floors, walls, and ceilings of combustible material shall be wetted thoroughly with water before, during, and after operations sufficiently to afford adequate protection.

2. Where possible, the Contractor shall furnish and use baffles of metal or gypsum board to prevent the spraying of sparks, hot slag and other hot particles into surrounding combustible material.

C. The Contractor shall prevent the spread of sparks and particles of hot metal through open windows, doors, and holes and cracks in floors, walls, ceilings and roofs.

D. Cylinders of gas used in hot work shall be placed a safe distance from the work. The Contractor shall provide hoses and equipment free of deterioration, malfunction and leaks. Suitable supports shall be provided to prevent accidental overturning of cylinders. All cylinder control valves shall be shut off while in use with the gas pressure regulator set at 15 psi (103 kPa) or less.

E. When hot work operations are completed or ended for the day, each location of the day’s work shall be inspected by the Contractor 60 minutes after completion of operations to detect for hidden or smoldering fires and to ensure that proper housekeeping is maintained. Contractor shall cleanup the area of work at the end of each shift or workday. Contractor shall provide a continuous fire watch at least 24 hours after the burning work has been completed.

F. Where sprinkler protection exists, the sprinkler system shall be maintained without interruption while operations are being performed. If operations are performed close to automatic sprinkler heads, gypsum board sheets or damp cloth guards may be used to shield the individual heads temporarily. The heads shall be inspected by the Contractor immediately after hot work operations cease, to ensure all materials have been removed from the heads and that the heads have not been damaged.

G. Suitable type, fully-charged, operable portable fire extinguisher shall be available at all times during hot work operations.

FY15 Update Oct. 1, 2014 Fire Prevention Precautions for Hot Work 017350 - 3

H. If any of the above safeguards are not employed or are violated, the Government may verbally stop the Work followed by written notice until compliance is obtained. Such stoppage shall not relieve the Contractor form performing his work within the Contract period for the Contract price.

END OF SECTION 017350