This solicitation package describes a design-build contract opportunity for granite facade repairs and replacement on a federal building in Washington, DC. The General Services Administration is seeking proposals for repairing, altering, and constructing services including surveying and removing existing granite panels, installing a new anchoring system, repairing panels, installing roof davits, repairing metal roofs, and potential exterior hazardous materials abatement. The work location is the exterior facade of the northeast, northwest, and southeast corners of the Robert C. Weaver Federal Building. Proposals are due by August 14, 2020. The estimated price range for this project is between $10-15 million. The North American Industry Classification System code for this work is 236220.
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Robert C Weaver Federal Building, Granite Façade Repairs, Phase 2 Washington, DC Project Number # VDC00213
SECTION 012300 - ALTERNATES
PART 1 - GENERAL
1.1 SUMMARY
A. An alternate provides an amount proposed by the Contractor and stated on the pricing form for certain work that will adjust the Base Contract Amount if the Government decides to accept the corresponding scope of work products, materials, equipment, systems or installation methods described in the Contract Documents.
B. The amount for an alternate is the total net adjustment to the Base Bid to incorporate the alternate work into the project.
C. Alternate work shall include miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation, whether or not mentioned as part of the alternate description.
1.2 PROCEDURES
A. Selection: Acceptance or rejection of each alternate will be made by the Government prior to award of the Contract, and the Base Bid amount will be adjusted accordingly for accepted alternates to establish the contract price.
B. Coordination: The Contractor shall modify or adjust affected work as necessary to completely and fully integrate the accepted alternate work into the project Work.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 SCHEDULE OF ALTERNATES
A. Alternate No. 1: Substitute Roof Requirements to protect, repair, and provide limited areas of new flashing at the stairwell roofs and top of façade described in the Scope of Work section “Roof Requirements”, for completely replacing the existing lead coated copper stairwell roofs and flashings as described in the Scope of Work section, “Alternates”.
END OF SECTION 012300
FY15 Update Oct. 1, 2014 Alternates 012300 - 1
File details come from the government source that posted it. Updated .