011400 Work Restrictions.pdf

PDF 35 KB Posted

Attached to
HUD Granite Facade Replacement Federal contract opportunity
Solicitation number
47PM0120R0008
Issued by
General Services Administration Public Buildings Service

About this file

This solicitation requests proposals for a design-build contract to replace the granite facade on the Robert C. Weaver Federal Building in Washington, DC. The General Services Administration seeks a single firm-fixed price contract to survey, remove, reinstall, clean, and repair existing granite panels; install a new anchoring system; repair metal roofs; and conduct potential exterior hazardous materials abatement. Proposals are due by August 14, 2020. The work is located on the northeast, northwest, and southeast exterior corners of the building. The project value is estimated between $10-15 million. The solicitation is set aside for local small businesses within 50 miles of Washington, DC. A virtual pre-proposal conference will be held on July 8, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to HUD Granite Facade Replacement, newest first.
File Type Posted
LIVE Bid Spreadsheet_REV 7.23.20.xlsx XLSX spreadsheet
Past Performance Questionnaire.docx DOCX document
012700 Unit Prices_REV.docx DOCX document
Solicitation Amendment 47PM0120R0008_0002.pdf PDF
Solicitation Amendment 47PM0120R0008_0001 (2).pdf PDF
013220 Photographic Documentation.docx DOCX document
013200 Construction Progress Documentation.pdf PDF
013510 Historic Building Treatment Procedures.pdf PDF
017000 Execution Requirements.pdf PDF
009010 Competency of Specialist for Facade.pdf PDF
017350 Fire Prevention Precautions for Hot Work.pdf PDF
017310 Cutting and Patching.pdf PDF
011000 Summary.pdf PDF
Bid Spreadsheet 47PM0120R0008.xlsx XLSX spreadsheet
009040 Competency of Conc Repair Spc.pdf PDF
017810 Project Record Documents.docx DOCX document
013110 Critical Path Method Scheduling.pdf PDF
Optional GFE AFrame Details.pdf PDF
020850 Asbestos Abatement Procedures.pdf PDF
013000 Electronic Project Management.pdf PDF
HUD Granite Facade Repair Phase 2 Drawings.pdf PDF
013300 Submittal Procedures.docx DOCX document
SOW HUD Ph 2 2020 06 08.pdf PDF
012300 Alternates.pdf PDF
016000 Product Requirements.pdf PDF
012500 Substitution Procedures.docx DOCX document
Vol1 1999 Robert C Weaver Fed Building Historic Structure Report.pdf PDF
015930 Security Regulations.pdf PDF
012900 Payment Procedures.pdf PDF
014050 System Quality Control.docx DOCX document
200408 HUD Mortar Analysis and Permeability Study MTFA D P.pdf PDF
015950 Safety and Health.pdf PDF
Preproposal Agenda 2020 07 08.pdf PDF
020900 Removal and Testing of Lead Based Paint.pdf PDF
018200 Demonstration and Training.docx DOCX document
020890 PCB Abatement Procedures.pdf PDF
017320 Selective Demolition.docx DOCX document
018111 Sustainable Design Requirements.docx DOCX document
017419 Const Nonhaz Waste Mgmt Disp.docx DOCX document
Solicitation Pkg 47PM0120R008.pdf PDF
015000 Temporary Facilities.pdf PDF
017700 Closeout Procedures.pdf PDF
014200 References.pdf PDF
014000 Quality Assurance and Control.pdf PDF
013100 Project Management Coordination.pdf PDF
012700 Unit Prices.pdf PDF
Vol2 1999 Robert C Weaver Fed Building Historic Structure Report.pdf PDF
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Robert C Weaver Federal Building, Granite Façade Repairs, Phase 2 Washington, DC Project Number # VDC00213

FY15 Update Oct. 1, 2014 Work Restrictions 011400 - 1

SECTION 011400 - WORK RESTRICTIONS

PART 1 - GENERAL

1.1 CONTRACTOR USE OF PREMISES

A. The Contractor will review and document the existing conditions surrounding the project premises. Provide documentation to the Government prior to the commencement of any construction activity.

B. During the construction period, the Contractor shall have full use of the designated premises for construction operations, including full use of the indicated work site, limited only by the Government's right to perform work or retain other Contractors to perform work on portions of the project.

C. The Contractor shall limit use of the premises to the work in areas indicated, and to allow for Government occupancy and public use.

1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.

2. Keep driveways, entrances, the drive-through and pick-up lane for the childcare center, bus stops, and other areas serving the premises clear and available at all times to the Government, Government employees and to visitors. Do not use these areas for parking or storage of materials. Existing parking lots must be minimally impacted. Any impact to specifically designated parking spots must be replaced and accounted for in the Contractor’s Site Logistics Plan. The Contractor’s Site Logistics Plan (including any impact to existing parking lots) must be reviewed and approved by the Government prior to implementing the Contractor’s plan. Keep emergency exits clear at all times.

3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.

4. Maintain existing building in a safe and weather-tight condition throughout the construction period. Repair damage caused by construction operations to the satisfaction of the government. Take precautions to protect the building, its occupants and the public during the construction period. A representative of the Contractor shall be available to arrive on site within one (1) hour of notice should an emergency occur.

5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.

6. Limited space on the premises will be made available for the Contractor's storage and related activities, provided that its use will not interfere with operations of the Government. Limited areas may be made available in the parking lot for the Contractor.

Off-site staging and storage is acceptable as well. Arrange and gain approval for use of space on the premises must meet the requirements and restrictions set forth in this Scope of Work and must be approved by the Government prior to mobilizing. All transportation of materials to and from off-site repair/storage location shall be the responsibility of the Contractor.

7. The existing loading dock facilities are not available for use by the Contractor.

8. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the Contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.

FY15 Update Oct. 1, 2014 Work Restrictions 011400 - 2

9. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. When not required for powering unloading operations, turn off engines when docked.

10. Smoking is not permitted in or around the building, see Facilities Management Regulation (FMR) Case 2008-102—3. Also see Code of Federal Regulations (CFR) 41 CFR Part 102-74.

11. No parking will be available on site during working hours. The Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site.

12. Cell Phones: Contractor is to provide company cell phone during this contract. All cell phones to be “on vibrate” at all times. If a telephone begins audibly ringing, the building guards will take the cell phone and hold until the end of the working day prior to the con-tractor leaving the property. Cell phones are only permitted in construction area and Contractor’s office space.

13. No apparatus with an open flame is allowed to be used within the facility without the prior receipt of a burn permit. Contact the Field Office to obtain burn permits. Burn permits are required for each separate occurrence.

14. Permits: Refer to FAR 52.236-7

15. The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.

16. Coordinate with the GSA Building Manager and the COR for site access.

17. Coordinate with the GSA Building Manager and the COR on correct response procedures for any building system alarms occurring during or resulting from the construction process.

18. All building systems outside the immediate construction area shall be kept fully operational during normal working hours.

19. Protect building site and adjacent areas from flying debris.

1.2 GOVERNMENT OCCUPANCY

A. The Government will occupy the site and the existing building during the entire period of construction. Cooperate with the Government's representatives during construction operations to minimize conflicts, mitigate noise, and facilitate Government usage. Perform the Work in a manner that does not interfere with the Government's operations.

B. The Government reserves the right to occupy, place, and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.

2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.

1.3 WORKING HOURS

A. Government Occupied Hours: Government personnel are scheduled to occupy the building from Monday through Friday, 6:00 AM until 7:00 PM, except for Federal holidays.

FY15 Update Oct. 1, 2014 Work Restrictions 011400 - 3

B. Government Unoccupied Hours: Government personnel are not scheduled to occupy the building during times that are not indicated as Government Occupied Hours.

C. Contractor's General Working Hours: The Contractor’s working hours shall be generally established to occur during Government Occupied Hours.

D. Contractor's Working Hour Restrictions:

1. Noisy and/or odor-producing work that may disrupt tenant operations in adjacent spaces may not be performed during Government Occupied Hours.

2. All deliveries in the Child Care area shall be made before 7:30 AM.

E. Work accomplished during Government Unoccupied Hours shall be performed at no additional cost to the Government. The Contractor shall submit a proposed schedule and gain the Contracting Officer's approval at least 48 hours before proceeding with any work not identified under “Contractor’s Working Hour Restrictions” during Government Unoccupied Hours.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011400