014050 System Quality Control.docx
DOCX document 26 KB Posted
- Attached to
- HUD Granite Facade Replacement Federal contract opportunity
- Solicitation number
- 47PM0120R0008
About this file
This solicitation requests proposals for a design-build contract to replace the granite facade of the Robert C. Weaver building located at 451 7th Street SW in Washington, DC. Work includes survey, removal and reinstallation of existing granite panels, cleaning, installation of a new anchoring system, panel repairs, installation of roof davits, metal roof repairs at stair towers, potential exterior HAZMAT abatement, and waterproofing of the existing wall facade. A small amount of concrete patching is also required. The work will be located on the northeast, northwest, and southeast exterior building corners. The estimated price range for this project is between $10 million to $15 million. Proposals are due by August 14, 2020 at 4:00 PM EST. Interested firms must be registered in the System for Award Management and have a local office within 50 miles of Washington, DC. A virtual pre-proposal conference will be held on July 8, 2020.
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name Project Location PCN #
Div 1 Reviewer/Writer Instructions: 1. Turn ON Show/Hide feature in the Home tab to see hidden instructions embedded in each and every specification. Turn OFF after completing your final version. 2. Comments in [ ] are guidance for spec. writers to consider during the design phase. Delete in final version.] Retain this section if Section 014000 refers to quality control requirements for coordinated or systematic construction activities not related principally to a single individual section, and references this section. Use this section for required testing, inspection or other quality control services that are not included in only one technical section, either because the primary components of the assembly to be tested are specified in two or more sections, or because the condition to be tested is produced as a result of the work of two or more sections. For example, this might include the following services when they concern the work of many sections:
Testing of composite mockups for compliance with structural, wind and moisture resistance, blast or ballistic resistance, or seismic criteria.
Measurement of total acoustical performance for compliance with functional criteria.
Verification of the relative absence of contaminants or other unwanted substances for compliance with health standards or cleanliness criteria.
Determination of envelope heat transfer or air infiltration sources and rates for compliance with environmental criteria.
Such quality control tests should only be considered for verification of those critical programmatic requirements that can not be adequately assured by standard submittals and routine practices.
SECTION 014050 - SYSTEM QUALITY CONTROL [This section may not be needed. Project Team has option to keep or to delete.]
GENERAL
SUMMARY
This section includes quality control requirements for coordinated or systematic construction activities not related principally to a single individual section in Divisions 2 through 33.
The administrative and procedural requirements of Division 1 Section "Quality Assurance and Control" apply to the work of this section.
Add an article, beginning with 1.2, for each mockup or other preconstruction system test, inspection or service, if any. Include paragraphs with a description of the procedure, identification or qualifications of the testing agency, extent and timing of the activities, criteria to be met for acceptable results, and other information for a full explanation.
PRODUCTS (Not applicable)
EXECUTION
Add an article, beginning with 3.1, for each system test, inspection or service during or after construction, if any. Include paragraphs with a description of the procedure, identification or qualifications of the testing agency, extent and timing of the activities, criteria to be met for acceptable results, and other information for a full explanation. "
END OF SECTION 014050
FY15 Update Oct. 1, 2014 System Quality Control 014050 - 1 image1.png