About this file

This solicitation requests proposals for a design-build contract to repair and replace granite facade panels on the Robert C. Weaver Federal Building in Washington, DC. Work includes removing and reinstalling existing granite, cleaning panels, installing a new anchoring system, concrete and stone repairs, and potential HAZMAT abatement. The estimated price range is $10-15 million. Interested offerors must have a local office within 50 miles of DC and be registered in SAM. Proposals are due August 14, 2020. A pre-proposal conference will be held virtually on July 8, 2020 and questions are due by July 17, 2020. The North American Industry Classification System code is 236220 and the solicitation is set aside for local small businesses. The General Services Administration Public Buildings Service National Capital Region will administer the contract.

View the file

Other files for this federal contract opportunity

Other files attached to HUD Granite Facade Replacement, newest first.
File Type Posted
LIVE Bid Spreadsheet_REV 7.23.20.xlsx XLSX spreadsheet
Past Performance Questionnaire.docx DOCX document
012700 Unit Prices_REV.docx DOCX document
Solicitation Amendment 47PM0120R0008_0002.pdf PDF
Solicitation Amendment 47PM0120R0008_0001 (2).pdf PDF
013220 Photographic Documentation.docx DOCX document
013200 Construction Progress Documentation.pdf PDF
013510 Historic Building Treatment Procedures.pdf PDF
017000 Execution Requirements.pdf PDF
009010 Competency of Specialist for Facade.pdf PDF
017350 Fire Prevention Precautions for Hot Work.pdf PDF
017310 Cutting and Patching.pdf PDF
011000 Summary.pdf PDF
Bid Spreadsheet 47PM0120R0008.xlsx XLSX spreadsheet
009040 Competency of Conc Repair Spc.pdf PDF
017810 Project Record Documents.docx DOCX document
013110 Critical Path Method Scheduling.pdf PDF
Optional GFE AFrame Details.pdf PDF
020850 Asbestos Abatement Procedures.pdf PDF
013000 Electronic Project Management.pdf PDF
HUD Granite Facade Repair Phase 2 Drawings.pdf PDF
013300 Submittal Procedures.docx DOCX document
SOW HUD Ph 2 2020 06 08.pdf PDF
012300 Alternates.pdf PDF
016000 Product Requirements.pdf PDF
011400 Work Restrictions.pdf PDF
012500 Substitution Procedures.docx DOCX document
Vol1 1999 Robert C Weaver Fed Building Historic Structure Report.pdf PDF
015930 Security Regulations.pdf PDF
012900 Payment Procedures.pdf PDF
014050 System Quality Control.docx DOCX document
200408 HUD Mortar Analysis and Permeability Study MTFA D P.pdf PDF
015950 Safety and Health.pdf PDF
Preproposal Agenda 2020 07 08.pdf PDF
020900 Removal and Testing of Lead Based Paint.pdf PDF
018200 Demonstration and Training.docx DOCX document
020890 PCB Abatement Procedures.pdf PDF
017320 Selective Demolition.docx DOCX document
018111 Sustainable Design Requirements.docx DOCX document
017419 Const Nonhaz Waste Mgmt Disp.docx DOCX document
Solicitation Pkg 47PM0120R008.pdf PDF
015000 Temporary Facilities.pdf PDF
017700 Closeout Procedures.pdf PDF
014200 References.pdf PDF
014000 Quality Assurance and Control.pdf PDF
013100 Project Management Coordination.pdf PDF
Vol2 1999 Robert C Weaver Fed Building Historic Structure Report.pdf PDF
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Robert C Weaver Federal Building, Granite Façade Repairs, Phase 2 Washington, DC Project Number # VDC00213

SECTION 012700 - UNIT PRICES

PART 1 - GENERAL

1.1 SUMMARY

A. A unit price provides an amount proposed by the Contractor and stated on the Bid Form as a price per unit of measurement for materials or services that will be added to or deducted from the Contract price by change order if the estimated quantity of the corresponding work required by the Contract Documents is increased or decreased.

1. The Base Bid Quantity is the estimated quantity to be included in the Contractor’s lump sum base bid.

2. The Limits of Variation from the Base Bid Quantity is the maximum variation in quantity, positive or negative, to be applied to the Base Bid Quantity for which the Unit Price is applicable.

3. Unit Rates for quantities in excess of the Limits of Variation quantity will be determined as by the Contract Agreement.

B. Unit prices include all necessary material and labor costs, overhead, profit, taxes, shipping and other related expenses for the added or deducted work.

1.2 PROCEDURES

A. List of Unit Price Items: A schedule of unit price items is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

1. Submit a list of Unit Price Items with the unit prices filled in as part of the bid.

B. Measurement: Method of measurement for each unit price is specified in the section applicable to the work.

1. Submit updated measurements for each unit price item with payment applications.

C. Verification: The Government reserves the right to reject the Contractor's measurement of work in place that involves use of an established unit price, and to have this work measured at the Government's expense by an independent surveyor.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 UNIT PRICE ITEM SCHEDULE

A. Unit Price Item No. 1: Dutchman Stone Repair.

FY15 Update Oct. 1, 2014 Unit Prices 012700 - 1

Robert C Weaver Federal Building, Granite Façade Repairs, Phase 2 Washington, DC Project Number # VDC00213

1. Description: Remove existing damaged stone greater than 3” with square cuts and affix new stone piece of matching size and appearance using stainless steel pins and epoxy adhesive, including all necessary preparation, protection, and cleanup measures, and in accordance with the “Granite” section of the “Dimension Stone Design Manual” published by the Marble Institute of America.

2. Measurement: each location of Dutchman Stone Repair.

3. Base Bid Quantity included in the Contract Documents: 40 locations.

B. Unit Price Item No. 2: Broken Stone Epoxy Repair.

1. Description: Remove cleanly broken stone pieces, drill and insert stainless steel pins, adhere intact pieces with epoxy grout, including all necessary preparation, protection, and cleanup measures, and in accordance with the “Granite” section of the “Dimension Stone Design Manual” published by the Marble Institute of America.

2. Measurement: each location of Broken Stone Epoxy Repair.

3. Base Bid Quantity included in the Contract Documents: 50 locations.

C. Unit Price Item No. 3: Mortar Patch Stone Repair.

1. Description: Repair existing damaged stone measuring 3 inches or less patching with approved epoxy stone patching mortar using stone dust at the finish surface to match the existing appearance, including all necessary preparation, protection, and cleanup measures, and in accordance with the “Granite” section of the “Dimension Stone Design Manual” published by the Marble Institute of America. .

2. Measurement: each location of Mortar Patch Stone Repair.

3. Base Bid Quantity included in the Contract Documents: 40 Locations.

D. Unit Price Item No. 4: Stone Crack Repair.

1. Description: Repair existing cracked stone in place by injecting crack with epoxy grout, finishing surface with epoxy and stone dust to match existing stone appearance, including all necessary protection and cleanup measures including all necessary preparation, protection, and cleanup measures, and in accordance with the “Granite” section of the “Dimension Stone Design Manual” published by the Marble Institute of America. .

2. Measurement: Linear feet of Stone crack repair.

3. Base Bid Quantity included in the Contract Documents: 200 Linear Feet.

E. Unit Price Item No. 5: Concrete Patch Repair.

1. Description: Concrete Patch Repair with architectural finish at areas exposed to view to match existing concrete texture and color. Work includes demolition, cleaning of existing reinforcing steel(rebar), coating existing rebar with zinc rich primer, adjusting rebar placement, supplementing badly corroded rebar, and also includes all preparation, protection, and cleanup measures, and shall be in accordance with the appropriate ACI RAP bulletins .

2. Measurement: Square Feet of Concrete Repair.

3. Base Bid Quantity included in the Contract Documents: 200 Square Feet.

END OF SECTION 012700

FY15 Update Oct. 1, 2014 Unit Prices 012700 - 2