01-Volume 1-Technical Specifications .pdf

PDF 12 MB Posted

Attached to
Eisenhower Lock Visitors' Center Construction Federal contract opportunity
Solicitation number
6923G522R0578
Issued by
Department of Transportation Saint Lawrence Seaway Development Corporation

About this file

This solicitation is for the Eisenhower Lock Visitors' Center Construction project located in Massena, New York. The project is a 100% Small Business Set-Aside for commercial and institutional building construction with a magnitude between $5,000,000 and $10,000,000 to be awarded by the Department of Transportation Saint Lawrence Seaway Development Corporation. Offerors must be registered in SAM.gov and site visits will take place on May 10th, 2022. Requests for information are due May 16th, 2022 by 2:00pm EST and proposals are due May 30th, 2022 by 2:00pm EST. A bid bond is required with proposals and performance and payment bonds will be required within ten days of award.

View the file

Other files for this federal contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Great Lakes St. Lawrence Seaway Development Corporation 180 Andrews Street Massena, NY 13662

Project & Location:

Visitors’ Center Eisenhower Lock Massena, NY 13662

Architect/Engineer Aubertine and Currier Architects, Engineers & Land Surveyors, PLLC 522 Bradley Street Watertown, NY 13601 A&C Project #: 2011-087.001

Mechanical/Electrical Engineer Jade Stone Engineering, PLLC 444 Vanduzee Street Watertown, New York 13601

Fire Protection Engineer Ran Fire Protection Engineering 1062 Central Avenue Albany, NY 12205

Exhibit Designers Hadley Exhibits Inc.

1700 Elmwood Avenue Buffalo, NY 14207

VOLUME 1

Technical Specifications for:

MARCH 2022—100% FOR CONSTRUCTION

This page intentionally left blank for duplicate printing

TABLE OF CONTENTS

EISENHOWER LOCK VISITORS’ CENTER

Great Lakes St. Lawrence Seaway Development Corporation Massena, New York

Table of Contents

VOLUME 1

Division Section Title

DIVISION 1 - GENERAL REQUIREMENTS

011000 Summary 011400 Work Restrictions 013000 Administrative Requirements 014000 Quality Requirements 014200 References 014533 Special Inspections & Structural Testing

014533.1 SUP Statement of Special Inspections

015000 Temporary Facilities and Controls 016000 Product Requirements 016116 Volatile Organic Compound (VOC) Content Restrictions 017300 Execution and Surveying 017419 Construction Waste Management and Disposal 017700 Closeout Procedures 017823 Operation and Maintenance Data 017839 Project Record Documents

DIVISION 2 – EXISTING CONDITIONS

020000 Limited Hazardous Material Survey 021000 Subsurface Investigation and Geotechnical Evaluation Services 024116 Structure Demolition

DIVISION 3 - CONCRETE

033000 Cast in Place Concrete

DIVISION 4 - MASONRY

042000 Unit Masonry

DIVISION 5- METALS

051200 Structural Steel Framing 052100 Steel Joist Framing 053100 Steel Decking 054000 Cold-Formed Metal Framing 054400 Cold-Formed Metal Trusses 055000 Metal Fabrications 055213 Pipe and Tube Railings

DIVISION 6 – WOOD, PLASTICS AND COMPOSITES

061000 Rough Carpentry

DIVISION 7 – THERMAL AND MOISTURE

072100 Thermal Insulation 072500 Weather Barriers 074113 Metal Roof Panels 074213 Metal Wall Panels 075000 EPDM Roof Membrane 079200 Joint Sealants

DIVISION 8 - DOORS AND WINDOWS

081113 Hollow Metal Doors and Frames 083000 Specialty Doors and Frames 084113 Aluminum-Framed Entrances and Storefront 087100 Door Hardware

DIVISION 9 – FINISHES

092600 Gypsum Board Assemblies 093013 Ceramic Tiling 095110 Acoustical Panel Ceilings 099120 Painting

DIVISION 10 – SPECIALTIES

102113 Toilet Compartments 102800 Toilet, Bath and Laundry Accessories 105200 Fire Extinguishers, Cabinets and Accessories

DIVISION 12 – FURNISHINGS

123040 Plastic Laminate-Faced Casework

VOLUME 2

DIVISION 14 – CONVEYING EQUIPMENT

142100 Electric Traction Passenger Elevations

DIVISION 21 – FIRE SUPPRESSION

210524 Backflow Preventers 210529 Pipe Hangers and Supports 211300 Sprinkler Piping 211313 Sprinkler Systems

DIVISION 22 – PLUMBING

220510 Basic Plumbing Requirements 220515 Plumbing Firestopping 220553 Plumbing Identification 220719 Plumbing Piping Insulation 221005 Plumbing Piping 221006 Plumbing Piping Specialties 224000 Plumbing Fixtures

DIVISION 23 – HEATING VENTILATING & AIR CONDITIONING

230510 Base Mechanical Requirements 230515 Mechanical Firestopping 230553 Identification for HVAC Piping and Equipment 230593 Testing, Adjusting and Balancing of HVAC 230713 Duct Insulation 230719 HVAC Piping Insulation 232300 Refrigerant Piping 233100 HVAC Ducts and Casings 233300 Air Duct Accessories 233416 Centrifugal HVAC Fans 233700 Air Outlets and Inlets 237413 Packaged Roof-top Units 238101 Terminal Heat Transfer Units 238129 Variable Refrigerant Flow HVAC Systems

DIVISION 26 – ELECTRICAL

260513 Medium-Voltage Cables

260519 Low-Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding For Electrical Systems 260529 Hangers and Supports For Electrical Systems

260533.13 Conduit For Electrical Systems

260533.16 Boxes For Electrical Systems

260553 Identification for Electrical Systems 260573 Power System Studies 260583 Wiring Connections 260923 Automatic Lighting Controls 261200 Medium-Voltage Transformers 262416 Panelboards 262726 Wiring Devices 262813 Fuses

262816.16 Enclosed Switches

263213 Engine Generators 263600 Transfer Switches 265100 Interior Lighting

DIVISION 27- COMMUNICATIONS

271000 Structured Cabling

275129.13 Two-Way Communication Systems

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

284600 Fire Detection and Alarm

VOLUME 3

DIVISION 31 – EARTHWORK

311000 Site Clearing 312200 Grading 312316 Excavation

312316.26 Rock Removal

312319 Dewatering and Drainage 312323 Fill 315000 Excavation Support and Protection

DIVISION 32 – EXTERIOR IMPROVEMENTS

321216 Asphalt Paving 321313 Concrete Paving 321373 Concrete Paving Joint Sealants 323113 Chain Link Fences and Gates 323119 Decorative Metal Fences and Gates 323300 Site Furnishings 329219 Seeding

DIVISION 33 – UTILITIES

331416 Site Water Utility Distribution 333113 Facility Sanitary Sewers 334211 Stormwater Gravity Piping 334211 Stormwater Drains

DIVISION 34 – EXHIBIT DOCUMENTS

34100 Summary of Work and Special Requirements 34150 Submittals and Prototypes 34200 Project Coordination 34250 Project Meetings 34300 Submittal Procedures 34350 Work Restrictions 34400 Architectural Woodwork

34450 Metal Fabrication and Finishing 34500 Wall Coverings and Murals 34550 Graphics 34600 Artifacts, Models and Objects 34650 Electrical Wiring 34700 Audio Visual and Interactive Systems 34750 Closeout Procedures 34800 Closeout Submittals Design Development Package

EISENHOWER LOCK VISITORS' CENTER March 2022

Massena, New York

Summary 011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 PROJECT

A. Project Name: GLSDC Eisenhower Lock Visitors' Center

B. Owner's Name: Great Lakes Seaway Development Corporation.

C. Architect's Name: Aubertine & Currier Architects, Engineers & Land Surveyors, PLLC.

D. Architect's Consultants: The Architect has retained the following design professionals who have prepared designated portions of the Contract Documents:

1. Structural Engineer: Aubertine and Currier Architects, Engineers & Land Surveyors, PLLC.

2. Mechanical, Electrical, and Plumbing Engineers: Jade Stone Engineering

3. Fire Protection Engineer: RAN Engineering

4. Exhibit Design: Hadley Exhibits Inc.

E. Background: The Great Lakes Seaway Development Corporation (Corporation) is a wholly owned U.S. Government corporation within the U.S. Department of Transportation which owns and operates that portion of the St. Lawrence Seaway in U.S. territorial waters between Lake Ontario and Montreal, Canada. The Corporation’s mission is to facilitate the safe and efficient passage of commercial vessels through the Seaway. A major part of this function is the operation and maintenance of the Eisenhower and Snell Locks located in Massena, New York. These locks were constructed in the 1950’s and opened to deep draft navigation in 1959. Soon after the locks opened, a Visitors’ Center was constructed in the early 1960’s at the south side of Eisenhower Lock. This facility is visited by an average of 50,000 visitors per year to watch ships pass through the Eisenhower Lock. Designs, specifications, and drawings were completed for a Security/Restroom Building at the site of the Eisenhower Lock Visitors’ Center, and it was constructed in 2014.

F. Task Scope: The Project consists of demolition of the existing Visitors' Center and to replace it with a new Visitor's Center to include the latest federal sustainable building design requirements, the design of static and interactive displays to be housed in the new facility and the development of the exterior green space for use by visitors.

1. The plan is for the existing Visitors’ Center to remain open until construction is completed on the new facility and it is ready to be opened to the public. The new Visitors’ Center shall be connected by a breezeway to the Security/Restroom Building. It will be necessary

Massena, New York

Summary 011000 - 2 for visitors to pass through the Security/Restroom Building prior to proceeding to the Visitors’ Center.

2. The new Visitors’ Center shall be constructed in accordance with current building codes and accessibility and energy efficiency standards.

3. Materials and equipment must not be specified as a certain model number of a given manufacturer unless specified on an “or equal” basis and if they are specified on an “or equal” basis, the specification must provide the physical characteristics and performance requirements upon which the “or equal” status will be evaluated.

1.2 SUSTAINABILITY

A. As much as practicable, the project should be designed and constructed to meet current Guiding Principles for Sustainable Federal Buildings criteria where applicable. The following shall be included in the designs, specifications, and drawings as applicable:

1. Underwriters Laboratories, Inc. (UL™) Standards. Where items/materials to be supplied are available with UL™ standard of approval, they shall be provided including Health and Sustainability standards as created through UL™ Environment and the GREENGUARD Environmental Institute (GEI). Where determined that the UL™ standard is in conflict with Paragraph a. below,

a. Paragraph a. shall take precedence over meeting the UL™ standard.

2. Compliance with Executive Orders. Pursuant to Executive Order 13423, “Strengthening Federal Environmental, Energy and Transportation Management,” and Executive Order 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” the Contractor shall exert its best efforts to provide its services in a manner that will promote the natural environment and protect the health and well-being of Federal employees and contract service providers.

3. To the extent that the construction services provided by the Contractor require provision of any of these types of products, the Contractor is expected to provide the green type of product unless that type of product is not available competitively within a reasonable time, at a reasonable price, is not life cycle cost efficient in the case of energy consuming products, or does not meet reasonable performance standards.

a. Energy Independence and Security Act of 2007, Energy Policy Act of 2005, Executive Orders and Federal Acquisition Regulation (FAR) Compliance. The Contractor shall comply with Sections 524 and Sections 525 of the Energy Independence and Security Act of 2007; Section 104 of the Energy Policy Act of 2005; Executive Order 13514, “Federal Leadership in Environmental, Energy, and Economic Performance,” dated October 5, 2009; Executive Order 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,”

Massena, New York

Summary 011000 - 3 dated January 24, 2007; and the Federal Acquisition Regulation (FAR) to provide ENERGY STAR® qualified and FEMP designated products in performance of construction.

4. The Contractor shall ensure that construction is performed with products that meet and/or exceed ENERGY STAR qualified and FEMP designated guidelines. The Contractor shall provide products that earn the ENERGY STAR label and meet the ENERGY STAR specifications for energy efficiency. The Contractor shall utilize ENERGY STAR qualified products as specified at www.energystar.gov/products, where can be found complete product specifications and updated lists of qualifying products. The Contractor shall utilize the purchasing specifications as specified for FEMP designated products at www.femp.energy.gov/procurement. The Contractor shall use these products to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user.

5. The following is a list of construction products for which ENERGY STAR qualified and FEMP designated products are available. It is not all inclusive and is evolving.

a. Air Conditioners

b. Ballasts

c. Boilers

d. Chillers

e. Doors

f. Electric Motors

g. Furnaces

h. Heat Pumps

i. Lamps

j. Lighting Controls

k. Luminaries

l. Plumbing (faucets, showerheads)

m. Roofs

n. Seals and Insulate

o. Windows

Massena, New York

Summary 011000 - 4

6. The Corporation believes that a demonstration of how to use ENERGY STAR qualified and FEMP designated products, creation of an effective training program for the products selected, and technical assistance are central to the selection and eventual success of purchasing and using ENERGY STAR qualified and FEMP designated products.

7. The Contractor shall comply with the clause at FAR 52.223-15, Energy Efficiency in Energy-Consuming Products.

8. The Contractor shall report on the purchases of ENERGY STAR qualified and FEMP designated products in the performance of this contract. The report shall include the following:

a. A list of all energy consuming products purchased during the past quarter.

b. A list of all ENERGY STAR qualified and FEMP designated products purchased during the past quarter.

c. For each ENERGY STAR qualified or FEMP designated product purchased, include the savings in dollars and Btu’s due to the purchase of the product.

d. Percentage of purchased products that are ENERGY STAR qualified and FEMP designated against the total number of energy consuming products purchased.

e. Total value of the purchased products that are ENERGY STAR qualified and FEMP designated against the dollar value of all energy consuming products purchased.

9. The Contractor shall add the following service, surveillance methodology, and performance threshold to the present Performance Requirements for Construction:

a. Required Service – Performance Objective/Standard – Ensure the mandatory purchasing of ENERGY STAR qualified and FEMP designated products.

b. Surveillance Methodology/ Method of Assessment – Random Sampling.

c. Performance Threshold – Up to 100% compliance, assuming life cycle cost efficient.

10. Use of Low Emitting Materials. The Contractor shall include the use of low emitting materials for building modifications and construction, and maintenance and cleaning when applicable during Contract period. In particular, the following materials and products are to have low pollutant emissions: composite wood products, adhesives, sealants, interior paints and finishes, solvents, carpet systems, janitorial supplies, and furnishings.

11. Use of Integrated Pest Management Practices and Products. The Contractor shall include the use integrated pest management techniques as appropriate to minimize pesticide usage within the project. Only EPA-registered pesticides will be used and only when needed.

Massena, New York

Summary 011000 - 5

12. EPA's Recycled Content Recommendations for Building Construction and Modifications, Maintenance, and Cleaning. Per section 6002 of RCRA, for EPA-designated products, the Contractor shall meet or exceed EPA's recycled content recommendations for building modifications and construction, and maintenance and cleaning when applicable during the Contract period. For other products, use materials with recycled content such that the sum of postconsumer recycled content plus one-half of the pre-consumer content constitutes at least 10% (based on cost or weight) of the total value of the materials in the project. EPA's recycled content products designations and recycled content recommendations are available on EPA's Comprehensive Procurement Guideline web site at www.epa.gov/cpg.

13. USDA's Bio-based Content Recommendations for New Buildings, Building Modifications, Maintenance, and Cleaning. Per section 9002 of Farm Security and Rural Investment Act, for USDA-designated products, the Contractor shall use products with the highest content level per USDA's bio-based content recommendations. For other products, the Contractor shall use bio-based products made from rapidly renewable resources and certified sustainable wood products. If these designated products meet performance requirements and are available at a reasonable cost, a preference for incorporating them into the project shall be provided. USDA's bio-based product designations and bio-based content recommendations are available on USDA's BioPreferred web site at www.usda.gov/biopreferred.

14. Use of Products That Have a Lesser or Reduced Effect on Human Health and the Environment. The Contractor shall use products that have a lesser or reduced effect on human health and the environment over their lifecycle when compared with competing products or services that serve the same purpose. A number of standards and ecolabels are available in the marketplace to assist in making environmentally preferable decisions. For recommendations, consult the Federal Green Construction.

15. Guide for Specifiers at www.wbdg.org/design/greenspec.php.

16. Reuse and Recycling of Materials. The Contractor shall provide salvage and/or recycle materials generated from building demolition, construction and/or renovations to the greatest extent practical and feasible in the regional market.

17. Eliminate/Minimize the Use of Ozone Depleting Compounds. The Contractor shall eliminate/minimize the use of ozone depleting compounds in the project where alternative environmentally preferable products are available, consistent with either the Montreal Protocol and Title VI of the Clean Air Act Amendments of 1990, or equivalent overall air quality benefits that take into account lifecycle impacts.

END OF SECTION 011000

EISENHOWER LOCK VISITORS' CENTER March 2022

Massena, New York

Work Restrictions 011400 - 1

SECTION 011400 - WORK RESTRICTIONS

PART 1 - GENERAL

1.1 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to areas of work.

2. Owner Occupancy: Allow for access by Owner and inspectors.

3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

4. The contractors shall establish staging areas with construction coordinator.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011400

Massena, New York

Administrative Requirements 013000 - 1

SECTION 013000 - ADMINISTRATIVE REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. General administrative requirements.

B. Preconstruction meeting.

C. Progress meetings.

D. Construction progress schedule.

E. Progress photographs.

F. Submittals for review, information, and project closeout.

G. Number of copies of submittals.

H. Requests for Interpretation (RFI) procedures.

I. Submittal procedures.

1.2 RELATED REQUIREMENTS

A. Section 016000 - Product Requirements: General product requirements.

1.3 GENERAL ADMINISTRATIVE REQUIREMENTS

A. Comply with requirements of Section 017000 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.

B. Make the following types of submittals to Architect:

1. Requests for Interpretation (RFI).

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

Massena, New York

Administrative Requirements 013000 - 2

8. Progress schedules.

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

PART 2 - PRODUCTS - NOT USED

PART 3 - EXECUTION

3.1 PRECONSTRUCTION MEETING

A. Schedule meeting after Notice of Award.

B. Attendance Required:

1. Owner.

2. Architect.

3. Contractor.

C. Agenda:

1. Execution of Owner-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

5. Designation of personnel representing the parties to Contract and Architect.

6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

7. Scheduling.

3.2 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the work at maximum weekly intervals.

B. Attendance Required:

Massena, New York

Administrative Requirements 013000 - 3

1. Contractor.

2. Owner.

3. Architect.

4. Contractor's superintendent.

5. Major subcontractors.

C. Agenda:

1. Review of work progress.

2. Field observations, problems, and decisions.

3. Identification of problems that impede, or will impede, planned progress.

4. Review of submittals schedule and status of submittals.

5. Review of RFIs log and status of responses.

6. Maintenance of progress schedule.

7. Planned progress during succeeding work period.

8. Effect of proposed changes on progress schedule and coordination.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.

3.3 CONSTRUCTION PROGRESS SCHEDULE

A. Within 10 days after date of the Agreement, submit preliminary schedule defining planned operations for the first 60 days of work, with a general outline for remainder of work.

B. If preliminary schedule requires revision after review, submit revised schedule within 2 days.

C. Submit updated schedule with each Application for Payment.

3.4 PROGRESS PHOTOGRAPHS

A. Photography Type: Digital; electronic files.

B. Provide photographs of site and construction throughout progress of work, acceptable to Architect.

C. In addition to periodic, recurring views, take photographs of each of the following events:

Massena, New York

Administrative Requirements 013000 - 4

1. Completion of site clearing.

2. Excavations in progress.

3. Foundations in progress and upon completion.

4. Structural framing in progress and upon completion.

5. Enclosure of building, upon completion.

6. Final completion.

D. Take photographs as evidence of existing project conditions as follows:

1. Exterior views: All existing conditions prior to demolition and new construction..

E. Views:

1. Provide non-aerial photographs from four cardinal views at each specified time, until date of Substantial Completion.

2. Consult with Architect for instructions on views required.

3. Provide factual presentation.

4. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

F. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.

1. Delivery Medium: Via email.

2. File Naming: Include project identification, date and time of view, and view identification.

3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.

3.5 REQUESTS FOR INTERPRETATION (RFI)

A. Definition: A request seeking one of the following:

1. An interpretation, amplification, or clarification of some requirement of Contract Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.

Massena, New York

Administrative Requirements 013000 - 5

B. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.

1. Prepare a separate RFI for each specific item.

a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.

b. Do not forward requests which solely require internal coordination between subcontractors.

2. Prepare in a format and with content acceptable to Owner.

3. Combine RFI and its attachments into a single electronic file. PDF format is preferred.

C. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.

1. Include in each request Contractor's signature attesting to good faith effort to determine from Contract Documents information requiring interpretation.

2. Unacceptable Uses for RFIs: Do not use RFIs to request the following:

a. Approval of submittals (use procedures specified elsewhere in this section).

b. Approval of substitutions (see Section - 016000 - Product Requirements)

D. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.

1. Official Project name and number, and any additional required identifiers established in Contract Documents.

2. Owner's, Architect's, and Contractor's names.

3. Discrete and consecutive RFI number, and descriptive subject/title.

4. Issue date, and requested reply date.

5. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).

6. Annotations: Field dimensions and/or description of conditions which have engendered the request.

Massena, New York

Administrative Requirements 013000 - 6

7. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example;

routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.

E. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.

F. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.

G. Review Time: Architect will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.

1. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.

H. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Owner.

3.6 SUBMITTAL SCHEDULE

A. Submit to Architect for review a schedule for submittals in tabular format.

1. Submit at the same time as the preliminary schedule.

2. Coordinate with Contractor's construction schedule and schedule of values.

3. Format schedule to allow tracking of status of submittals throughout duration of construction.

4. Arrange information to include scheduled date for initial submittal, specification number and title, submittal category (for review or for information), description of item of work covered, and role and name of subcontractor.

3.7 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

Massena, New York

Administrative Requirements 013000 - 7

3. Samples for selection.

4. Samples for verification.

B. Submit to Architect for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.

C. Samples will be reviewed for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below.

3.8 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Other types indicated.

B. Submit for Architect's knowledge as contract administrator or for Owner.

3.9 SUBMITTALS FOR PROJECT CLOSEOUT

A. Submit Correction Punch List for Substantial Completion.

B. Submit Final Correction Punch List for Substantial Completion.

C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 017800 - Closeout Submittals:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

Massena, New York

Administrative Requirements 013000 - 8

5. Other types as indicated.

D. Submit for Owner's benefit during and after project completion.

3.10 NUMBER OF COPIES OF SUBMITTALS

A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.

1. After review, produce duplicates.

2. Retained samples will not be returned to Contractor unless specifically so stated.

3.11 SUBMITTAL PROCEDURES

A. General Requirements:

1. Use a separate transmittal for each item.

2. Transmit using approved form.

a. Use Contractor's form, subject to prior approval by Architect.

3. Sequentially identify each item. For revised submittals use original number and a sequential numerical suffix.

4. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.

5. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.

a. Submittals from sources other than the Contractor, or without Contractor's stamp will not be acknowledged, reviewed, or returned.

6. Deliver each submittal on date noted in submittal schedule, unless an earlier date has been agreed to by all affected parties, and is of the benefit to the project.

a. Send submittals in electronic format via email to Architect.

7. Schedule submittals to expedite the Project, and coordinate submission of related items.

Massena, New York

Administrative Requirements 013000 - 9

8. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.

9. Provide space for Contractor and Architect review stamps.

10. When revised for resubmission, identify all changes made since previous submission.

B. Product Data Procedures:

1. Submit only information required by individual specification sections.

2. Collect required information into a single submittal.

3. Submit concurrently with related shop drawing submittal.

4. Do not submit (Material) Safety Data Sheets for materials or products.

C. Shop Drawing Procedures:

1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting Contract Documents and coordinating related work.

2. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.

D. Samples Procedures:

1. Transmit related items together as single package.

2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.

3. Provide physical samples boards when submitting for color selection. Digital color samples can vary between equipment and will not be reviewed.

3.12 SUBMITTAL REVIEW

A. Submittals for Review: Architect will review each submittal, and approve, or take other appropriate action.

B. Submittals for Information: Architect will acknowledge receipt and review. See below for actions to be taken.

C. Architect's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.

D. Architect's and consultants' actions on items submitted for review:

Massena, New York

Administrative Requirements 013000 - 10

1. Authorizing purchasing, fabrication, delivery, and installation:

a. "Approved".

b. "Approved as Noted".

1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.

2. Not Authorizing fabrication, delivery, and installation:

a. "Revise and Resubmit".

1) Resubmit revised item, with review notations acknowledged and incorporated.

b. "Rejected".

1) Submit item complying with requirements of Contract Documents.

END OF SECTION 013000

Massena, New York

Quality Requirements 014000 - 1

SECTION 014000 - QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Submittals.

B. Quality assurance.

C. References and standards.

D. Testing and inspection agencies and services.

E. Control of installation.

F. Mock-ups.

G. Tolerances.

H. Manufacturers' field services.

I. Defect Assessment.

1.2 REFERENCE STANDARDS

A. IAS AC89 - Accreditation Criteria for Testing Laboratories 2020.

1.3 SUBMITTALS

A. See Section 013000 - Administrative Requirements, for submittal procedures.

B. Test Reports: After each test/inspection, promptly submit two electronic copies of report to Architect and to Contractor.

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location in the Project.

g. Type of test/inspection.

Massena, New York

Quality Requirements 014000 - 2

h. Date of test/inspection.

i. Results of test/inspection.

j. Compliance with Contract Documents.

k. When requested by Architect, provide interpretation of results.

2. Test report submittals are for Architect's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents, or for Owner's information.

C. Certificates: When specified in individual specification sections, submit certification by the manufacturer and Contractor or installation/application subcontractor to Architect, in quantities specified for Product Data.

1. Indicate material or product complies with or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

2. Certificates may be recent or previous test results on material or product, but must be acceptable to Architect.

D. Erection Drawings: Submit drawings for Architect's benefit as contract administrator or for Owner.

1. Submit for information for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents.

2. Data indicating inappropriate or unacceptable Work may be subject to action by Architect or Owner.

1.4 QUALITY ASSURANCE

A. Testing Agency Qualifications:

1. Prior to start of work, submit agency name, address, and telephone number, and names of full time registered Engineer and responsible officer.

2. Submit copy of report of laboratory facilities inspection made by NIST Construction Materials Reference Laboratory during most recent inspection, with memorandum of remedies of any deficiencies reported by the inspection.

3. Qualification Statement: Provide documentation showing testing laboratory is accredited under IAS AC89.

Massena, New York

Quality Requirements 014000 - 3

1.5 REFERENCES AND STANDARDS

A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Comply with reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.

C. Obtain copies of standards where required by product specification sections.

D. Should specified reference standards conflict with Contract Documents, request clarification from Architect before proceeding.

E. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Architect shall be altered from Contract Documents by mention or inference otherwise in any reference document.

1.6 TESTING AND INSPECTION AGENCIES AND SERVICES

A. Owner will employ services of an independent testing agency to perform specified testing.

Contractor is responsible for coordination and scheduling with 3rd party testing agency.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

PART 2 - PRODUCTS - NOT USED

PART 3 - EXECUTION

3.1 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Architect before proceeding.

D. Comply with specified standards as minimum quality for the work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have work performed by persons qualified to produce required and specified quality.

Massena, New York

Quality Requirements 014000 - 4

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

3.2 MOCK-UPS

A. Before installing portions of the Work where mock-ups are required, for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work. The purpose of mock-up is to demonstrate the proposed range of aesthetic effects and workmanship.

B. Accepted mock-ups establish the standard of quality the Architect will use to judge the Work.

C. Integrated Exterior Mock-ups: Construct integrated exterior mock-up as indicated on drawings.

Coordinate installation of exterior envelope materials and products as required in individual Specification Sections. Provide adequate supporting structure for mock-up materials as necessary.

D. Room Mock-ups: Construct room mock-ups as indicated on drawings. Coordinate installation of materials, products, and assemblies as required in specification sections; finish according to requirements. Provide required lighting and any supplemental lighting where required to enable Architect to evaluate quality of the mock-up.

E. Notify Architect fifteen (15) working days in advance of dates and times when mock-ups will be constructed.

F. Provide supervisory personnel who will oversee mock-up construction. Provide workers that will be employed during the construction at Project.

G. Tests shall be performed under provisions identified in this section and identified in the respective product specification sections.

H. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

I. Obtain Architect's approval of mock-ups before starting work, fabrication, or construction.

1. Architect will issue written comments within seven (7) working days of initial review and each subsequent follow up review of each mock-up.

2. Make corrections as necessary until Architect's approval is issued.

J. Architect will use accepted mock-ups as a comparison standard for the remaining Work.

Massena, New York

Quality Requirements 014000 - 5

K. Where mock-up has been accepted by Architect and is specified in product specification sections to be removed, protect mock-up throughout construction, remove mock-up and clear area when directed to do so by Architect.

L. Where possible salvage and recycle the demolished mock-up materials.

3.3 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from Architect before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

3.4 TESTING AND INSPECTION

A. Testing Agency Duties:

1. Test samples of mixes submitted by Contractor.

2. Provide qualified personnel at site. Cooperate with Architect and Contractor in performance of services.

3. Perform specified sampling and testing of products in accordance with specified standards.

4. Ascertain compliance of materials and mixes with requirements of Contract Documents.

5. Promptly notify Architect and Contractor of observed irregularities or non-compliance of Work or products.

6. Perform additional tests and inspections required by Architect.

7. Submit reports of all tests/inspections specified.

B. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

C. Contractor Responsibilities:

Massena, New York

Quality Requirements 014000 - 6

1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

4. Notify Architect and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

6. Arrange with Owner's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

D. Re-testing required because of non-compliance with specified requirements shall be performed by the same agency on instructions by Architect.

E. Re-testing required because of non-compliance with specified requirements shall be paid for by Contractor.

3.5 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust, and balance equipment, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

3.6 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not complying with specified requirements.

Massena, New York

Quality Requirements 014000 - 7

B. If, in the opinion of Owner, it is not practical to remove and replace the work, Owner will direct an appropriate remedy or adjust payment.

END OF SECTION 014000

EISENHOWER LOCK VISITORS' CENTER March 2022

References 014200 - 1

SECTION 014200 - REFERENCES

PART 1 - GENERAL

1.1 DEFINITIONS

A. General: Basic Contract definitions are included in the Conditions of the Contract.

B. Agent: Special Inspector

C. "Approved": When used to convey Architect's action on Contractor's submittals, applications, and requests, "approved" is limited to Architect's duties and responsibilities as stated in the

Conditions of the Contract.

“Architect”: Aubertine and Currier Architects, Engineers & Land Surveyors, PLLC

D. "Directed": A command or instruction by Architect. Other terms including "requested," "authorized," "selected," "approved," "required," and "permitted" have the same meaning as

"directed."

E. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including "shown,"

"noted," "scheduled," and "specified" have the same meaning as "indicated."

F. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.

G. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

H. "Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

I. "Provide": Furnish and install, complete and ready for the intended use.

J. "Installer": Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name.

K. “Engineer of Record”: Aubertine and Currier Architects, Engineers & Land Surveyors, PLLC

EISENHOWER LOCK VISITORS' CENTER March 2022

References 014200 - 2

L. "Experienced": When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

M. "Project Site": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built.

1.2 INDUSTRY STANDARDS

A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with standards in effect as of date of the Contract Documents, unless otherwise indicated.

C. Conflicting Requirements: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Architect for a decision before proceeding.

1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.

D. Copies of Standards: Each entity engaged in construction on Project must be familiar with industry standards applicable to its construction activity. Copies of applicable standards are not bound with the Contract Documents.

1. Where copies of standards are needed to perform a required construction activity, obtain copies directly from publication source and make them available on request.

E. Abbreviations and Acronyms for Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the standards and regulations.

F. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities indicated in Gale

Research's "Encyclopedia of Associations" or in Columbia Books' "National Trade &

Professional Associations of the U.S."

EISENHOWER LOCK VISITORS' CENTER March 2022

References 014200 - 3

G. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities.

H. Code Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities.

I. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities.

J. State Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 014200

EISENHOWER LOCK VISITORS' CENTER March 2022

Special Inspections and Structural Testing 014533-1

SECTION 014533 - SPECIAL INSPECTIONS AND STRUCTURAL TESTING

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Special Inspections and Structural Testing shall be in accordance with Chapter 17 of the New York State Uniform Code (NYSUC).

1.02 DEFINITIONS

A. Registered Design Professional (RDP) for Structures: Licensed Professional Engineer or

Registered Architect whose seal appears in the Construction Drawings. The Registered

Design…

This is the start of the file's text. The full file is on GovTribe.