This document is a Summary Section (01 10 00) for the Wayne County Rouge Valley Sewage Disposal System (RVSDS) SRF Project Plan - Phase 2C/3C, involving multiple jurisdictions including Wayne County, the City of Wayne, Wayne County Parks and Recreation Department, and the Michigan Department of Transportation. The project involves the rehabilitation of approximately 21,000 feet of large diameter sewer along the Middle Rouge River, including Lining Phase A and B in specific river segments, six additional rehabilitation areas along various roads and within Warren Valley Golf Course, and grouting at multiple locations along the Lower and Middle Rouge Rivers. The project will include spot rehabilitation of one 24-inch diameter sanitary sewer segment and placement of seven new concrete structures at existing sewer system bends, with an expected timeline of Lining Area B occurring in 2025 and Lining Area A in 2026.
The project will be constructed under a single prime contract with work limited to normal business hours (7:00 a.m. to 6:00 p.m., Monday through Saturday), requiring coordination with Wayne County Parks and Recreation Department and careful management of public spaces, including maintaining pedestrian access during "Saturday in the Park" events. The contractor is responsible for securing staging areas, obtaining necessary permits from various jurisdictions (including Michigan Department of Environment, Great Lakes, and Energy), and protecting the work from potential flooding in the Hines Parkway and along the Rouge Rivers. All bypass pumping and temporary facilities are considered incidental to the project, and the contractor must maintain flow in existing Wayne County Interceptors throughout construction.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SRF #5858
Wayne County – RVSDS SRF Phase 2C/3C SUMMARY SRF #5858 01 10 00 - Page 1 of 5
SECTION 01 10 00 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
A. Project information.
B. Work covered by Contract Documents C. Right-of Way Jurisdiction/Permits D. Type of the Contract.
E. Use of premises.
F. Coordination with Occupants G. Work restrictions.
H. Maintenance of flow and construction sequencing for Phase 2C/3C.
I. Flooding and Protection of the Work J. Specification and Drawing Conventions.
B. Related Sections include the following:
A. Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.3 PROJECT INFORMATION
A. Project Identification: RVSDS SRF Project Plan – Phase 2C/3C A. Phase 2C/3C Project Locations:
a. Lining Phase A - Along the Middle Rouge River between Warrendale Dr and Outer Dr.
b. Lining Phase B - Along the Middle Rouge River between Beech Daly Rd and Telegraph Rd
c. Additional Rehab Areas:
1) Location 1: Along Ann Arbor Rd between Newburgh Rd and Edward Hines
Dr.
2) Location 2: Along Edward Hines Dr just east of Nollar Dr
3) Location 3: Along Edward Hines Dr between Nollar Dr and Beech Daly
4) Location 4: Within Warren Valley Golf Course
5) Location 5: Along Edward Hines Dr just east of Middlebelt Hill parking area
6) Location 6: Along Edward Hines Dr between Telegraph and Warrendale Dr
d. Grouting - Various locations along the Lower Rouge River between Venoy Rd and Military St and various locations along the Middle Rouge River between Plymouth Rd and Ford Rd.
All hereinafter referred to as the Project.
B. Owner: Wayne County, 400 Monroe Street, Suite 400, Detroit, MI 48226 A. Owner's Representative: OHM Advisors, 34000 Plymouth Road, Livonia, MI 48150
SRF #5858 01 10 00 - Page 2 of 5
C. Engineer: OHM Advisors, 34000 Plymouth Road, Livonia, MI 48150 and Wade Trim, 500 Griswold Street, Suite 2500, Detroit, MI 48226. The Contractor shall direct all communication to OHM Advisors.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
A. Phase 2C/3C: The rehabilitation of sanitary sewer pipeline which includes approximately
21,000 feet of large diameter sewer, along with widespread grouting locations, within the RVSDS and along the Middle Rouge River. The project also includes the spot rehabilitation of one 24” diameter sanitary sewer segment and placing seven new concrete structures at existing bends in the sewer system. All bypass pumping shall be in accordance with Section 01 50 00, Temporary Facilities and Controls and the special provision for Temporary Flow Diversion and Bypass Pumping.
1.5 RIGHT-OF-WAY JURISDICTION/PERMITS
A. Local streets in the vicinity of the Project used to access the site are under the jurisdiction of the City of Wayne.
B. The existing and proposed sanitary sewers are under the jurisdiction of Wayne County Department of Public Services.
C. Work on the north side of the Lower Rouge River is under the jurisdiction of the Wayne- Westland School District and the City of Wayne.
D. Work on the south side of the Lower Rouge River is under the jurisdiction of Wayne County Parks and the City of Wayne.
E. Michigan Avenue is under the jurisdiction of the Michigan Department of Transportation.
F. Hines Drive and Hines Parkway are under the jurisdiction of the Wayne County Department of Public Services.
G. Ford Road is under the jurisdiction of the Michigan Department of Transportation.
H. All other roads and streets in the vicinity of the Project are under the jurisdiction of the City of Wayne or Dearborn Heights.
I. The Lower Rouge River is under the jurisdiction of the Michigan Department of Environment, Great Lakes, and Energy (EGLE). The Middle Rouge River is under the jurisdiction of the Michigan Department of Environment, Great Lakes, and Energy (EGLE).
J. Soil erosion and sedimentation control is under the jurisdiction of the Wayne County Department of Environment, Land Resource Management Division.
K. Part 41 Construction Permits for the new work on the sanitary sewer facilities is under the jurisdiction of Michigan Department of Environment, Great Lakes, and Energy (EGLE).
L. The CONTRACTOR shall secure any permits required by the agency having jurisdiction, shall abide by all rules and regulations of each, and shall pay all costs in connection with the permits.
The CONTRACTOR shall pay for all permit and inspection fees as the agencies may charge to ensure compliance with their requirements.
SRF #5858 01 10 00 - Page 3 of 5
1.6 TYPE OF CONTRACT
A. Project will be constructed under a single prime contract.
1.7 USE OF PREMISES
A. General: The majority of the project work site is within the Wayne County Parks and Recreation Department’s Property. Contractor shall limit use of premises for construction operations to areas within the Department’s and the public ROW. Care shall be taken to minimize disturbance of land outside of the necessary construction activities. The Contractor shall coordinate and acquire written approval from the Parks and Recreation Department for any and all staging areas within the Department’s property. If necessary, the Contractor is responsible for securing additional areas along the project route for their operations through discussion with private property owners. The County will not be responsible for providing additional project staging areas. It is the Contractor’s sole responsibility to secure any necessary access easements or approvals from property owners as needed. The County will not be held responsible for the actual availability of an area, or any other private site availability outside of the public ROW or dedicated easements along the project route.
A. Wayne County Parks and Recreation Department: Elizabeth Iszler, Chief of Planning and
Design, Wayne County Department of Public Services Parks Division, 33175 Ann Arbor Trail, Westland, MI 48182.
Phone:734-261-4312 Email: eiszler@waynecounty.com
B. Use of Site: Limit use of premises to areas within the public ROW, Park property, and permanent/temporary easement limits.
A. Limits: Confine construction operations and equipment/material staging within public ROW, approved Park property, and permanent/temporary easement limits. The Contractor is responsible for securing additional staging areas along the project route, or in the general vicinity of project. The County may provide assistance in locating additional areas for staging, but the Contractor is ultimately responsible for securing these areas with the private property owner.
B. Owner Occupancy: Allow for Owner occupancy of Project site and use by the public.
C. Park Property/Public Events: Saturday in the Park occurs every Saturday from May through
September. During Saturday in the Park, Hines Drive is closed from Ann Arbor Trail to Outer Drive for the public to run, walk, or bike safely without vehicle traffic. The contractor shall keep pedestrian facilities open during Saturday in the Park. Should pathway closures be needed during Saturday in the Park, the Contractor shall have approval from the Engineer and Wayne County Parks Department.
D. Driveways and Entrances: Keep driveways and entrances within the project limits clear and available to Owner, residents, the public, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize impacts on driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Sidewalks and Pathways: Keep all pedestrian facilities within the project limits open to the public at all times except where noted on the plans. Should a pedestrian facility need to be closed for completion of the work, follow the project’s traffic control plan.
F. Roadways: No street, road, or section thereof shall be closed to through traffic unless otherwise provided for on the Plans, Specifications, or authorized by the agency with jurisdiction over the roads. Prior to closing a street, road, or section thereof, the Contractor shall provide the Engineer with a copy of a detour plan approved by the agency having jurisdiction over the roads.
G. In the event roads or streets are to be closed, the Contractor shall notify the local fire department, police department, local road authority, ambulance and emergency services, Department of Public Works, public transit authority and public school system daily as to
SRF #5858 01 10 00 - Page 4 of 5 what streets will be partly blocked or closed, the length of time the streets will be blocked or closed and when the streets will be reopened to traffic. The Contractor shall designate one responsible employee to carry out the requirements of this condition.
1.8 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and existing adjacent building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
A. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
B. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.
1.9 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
A. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work to normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Saturday, unless otherwise approved by Wayne County in writing.
A. Sunday Work: No work shall be allowed on Sunday without written approval from Wayne
County.
B. Holiday Work: No work shall occur on Holidays, as defined in the MDOT 2020
Specifications for Construction.
C. Early Morning Hours: No work shall be allowed without written approval Wayne County.
D. Hours for Utility Shutdowns: Not allowed E. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others.
1.10 MAINTENANCE OF FLOW AND CONSTRUCTION SEQUENCING FOR PHASE 2C/3C
A. The CONTRACTOR shall maintain flow in existing Wayne County Interceptors at all times during construction. A suggested construction sequence is provided with the plans for sequencing.
B. All bypass pumping shall be in accordance with Section 01 50 00, Temporary Facilities and Controls. All Temporary Facilities and Controls, pumping and bypassing flow, maintenance of traffic, etc. is incidental to the Project.
C. The CONTRACTOR must complete all work in Lining Area B, including restoration, prior to starting any work in Lining Area A. It is expected that Lining Area B will occur in 2025 and Lining Area A will occur in 2026, alternate schedules may be provided by the CONTRACTOR but shall be approved in writing by the ENGINEER.
1.11 FLOODING AND PROTECTION OF THE WORK
A. The location of the work within Hines Parkway and along the Middle Rouge and Lower Rouge Rivers is prone to periodic flooding. The CONTRACTOR shall at all times protect his work from flooding and be responsible for any damage done by flooding including any dewatering necessary to continue work. Time extensions due to flooding for down time shall be in accordance with the Conditions of the Contract.
SRF #5858 01 10 00 - Page 5 of 5
1.12 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 49-division format and CSI/CSC’s “MasterFormat” numbering system.
A. Section Identification: The Specifications use Section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete because all available Section numbers are not used. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of Sections in the Contract Documents.
B. Division 01: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
B. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
C. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
A. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
B. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
A. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
B. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.
C. Keynoting: Materials and products are identified by reference keynotes referencing
Specification Section numbers found in this Project Manual.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 10 00