Fort Peck Powerhouse 1 Cubicle Room 15kV Switchgear Replacement Project

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W9128F25RA008
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Fort Peck, Montana 59223, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers, Engineering District Omaha, is soliciting proposals for the replacement of 15kV switchgear and associated electrical infrastructure at the Fort Peck Powerhouse 1 Cubicle Room. The scope of work includes replacing existing switchgear, installing new generator and tie breakers in the Cubicle Room, adding new outdoor circuit breakers in the switchyard, installing two 15kV/12MVA reactors, replacing cable trays, updating lighting distribution panelboards and transformers, installing warning lights, and evaluating the existing lighting system. This is a firm-fixed-price solicitation (W9128F25RA008) issued as a Best Value Tradeoff unrestricted Request for Proposals with no set-aside designations. Evaluation will prioritize past performance as the most important factor, followed by technical approach, personnel qualifications and experience, small business participation (minimum 20% required), and price. The proposal due date is October 21, 2025, at 2:00 p.m. local time, with mandatory site visits conducted on August 5, 2025, and September 9, 2025, for which contractors must register with Irene Whitmer at Irene.E.Whitmer@usace.army.mil.

The project is estimated at greater than $10,000,000 and involves a 730-calendar-day performance period, including a 30-day mobilization period following notice to proceed. Work must be completed with a specific operational window from September 15 through November 15, emphasizing minimal powerhouse outage duration during installation and commissioning. The contract includes 23 line items covering equipment removal, installation, concrete work, control board modifications, spare parts procurement, documentation, testing, commissioning, and training activities. No incumbent contractors are identified in the solicitation materials. The place of performance is Fort Peck, Montana, at the Fort Peck Dam facility, with inspection and acceptance occurring at the destination in Omaha, Nebraska. All offerors must be registered in the System for Award Management (SAM.gov) and submit electronic proposals with comprehensive documentation addressing technical requirements, personnel qualifications, past performance history, and small business participation plans.

Notice text

11 versions

Update #11 · Latest ·

UPDATE:  Amendment 0007 was issued on 17 October 2025.  Please see three (3) corresponding documents.

UPDATE:  Amendment 0006 was issued on 3 October 2025.  Please see four (4) corresponding documents.

UPDATE:  Amendment 0005 was issued on 1 October 2025.  Please see four (4) corresponding documents.

UPDATE:  Amendment 0004 was issued on 22 September 2025.  Please see seven (7) corresponding documents. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 9 September 2025 has been posted in the attachments. 

UPDATE:  Amendment 0003 was issued on 27 August 2025.  Please see four (4) corresponding documents. 

UPDATE: A follow-on site visit is scheduled for September 9, 2025 at 10:00 am. Contractors interested in seeing the site need to make a reservation with Irene Whitmer by e-mail at Irene.E.Whitmer@usace.army.mil. Contractors are to meet at the Powerhouse.

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #10 ·

UPDATE:  Amendment 0006 was issued on 3 October 2025.  Please see four (4) corresponding documents.

UPDATE:  Amendment 0005 was issued on 1 October 2025.  Please see four (4) corresponding documents.

UPDATE:  Amendment 0004 was issued on 22 September 2025.  Please see seven (7) corresponding documents. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 9 September 2025 has been posted in the attachments. 

UPDATE:  Amendment 0003 was issued on 27 August 2025.  Please see four (4) corresponding documents. 

UPDATE: A follow-on site visit is scheduled for September 9, 2025 at 10:00 am. Contractors interested in seeing the site need to make a reservation with Irene Whitmer by e-mail at Irene.E.Whitmer@usace.army.mil. Contractors are to meet at the Powerhouse.

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #9 ·

UPDATE:  Amendment 0005 was issued on 1 October 2025.  Please see four (4) corresponding documents.

UPDATE:  Amendment 0004 was issued on 22 September 2025.  Please see seven (7) corresponding documents. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 9 September 2025 has been posted in the attachments. 

UPDATE:  Amendment 0003 was issued on 27 August 2025.  Please see four (4) corresponding documents. 

UPDATE: A follow-on site visit is scheduled for September 9, 2025 at 10:00 am. Contractors interested in seeing the site need to make a reservation with Irene Whitmer by e-mail at Irene.E.Whitmer@usace.army.mil. Contractors are to meet at the Powerhouse.

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #8 ·

UPDATE:  Amendment 0004 was issued on 22 September 2025.  Please see seven (7) corresponding documents. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 9 September 2025 has been posted in the attachments. 

UPDATE:  Amendment 0003 was issued on 27 August 2025.  Please see four (4) corresponding documents. 

UPDATE: A follow-on site visit is scheduled for September 9, 2025 at 10:00 am. Contractors interested in seeing the site need to make a reservation with Irene Whitmer by e-mail at Irene.E.Whitmer@usace.army.mil. Contractors are to meet at the Powerhouse.

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #7 ·

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 9 September 2025 has been posted in the attachments. 

UPDATE:  Amendment 0003 was issued on 27 August 2025.  Please see four (4) corresponding documents. 

UPDATE: A follow-on site visit is scheduled for September 9, 2025 at 10:00 am. Contractors interested in seeing the site need to make a reservation with Irene Whitmer by e-mail at Irene.E.Whitmer@usace.army.mil. Contractors are to meet at the Powerhouse.

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #6 ·

UPDATE:  Amendment 0003 was issued on 27 August 2025.  Please see four (4) corresponding documents. 

UPDATE: A follow-on site visit is scheduled for September 9, 2025 at 10:00 am. Contractors interested in seeing the site need to make a reservation with Irene Whitmer by e-mail at Irene.E.Whitmer@usace.army.mil. Contractors are to meet at the Powerhouse.

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #5 ·

UPDATE: A follow-on site visit is scheduled for September 9, 2025 at 10:00 am. Contractors interested in seeing the site need to make a reservation with Irene Whitmer by e-mail at Irene.E.Whitmer@usace.army.mil. Contractors are to meet at the Powerhouse.

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #4 ·

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #3 ·

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #2 ·

UPDATE:  Amendment 0001 was issued on 31 July 2025.  Please see four (4) corresponding documents. 

Original Solicitation issued on 21 July 2025. 

Update #1 ·

Please see attached documents. 

Files

File Type Posted
Amend 0007_W9128F25RA0080007 SF 30.pdf PDF
Amend 0007_ W9128F25RA0080007.pdf PDF
Amend 0007_Transformer KV7A Information.pdf PDF
Amend 0006_W9128F25RA008_Narrative.pdf PDF
Amend 0006_W9128F25RA0080006 SF 30.pdf PDF
Amend 0006_W9128F25RA0080006.pdf PDF
Amend 0006_02 82 00.pdf PDF
Amend 0005_Div 00 22 00_FP PH1 15kV Switchgear_(Clean).pdf PDF
Amend 0005_Solicitation Amendment_W9128F25RA0080005.pdf PDF
Amend 0005_Div 00 22 00_FP PH1 15kV Switchgear_(Redlined).pdf PDF
Amend 0005_Solicitation Amendment_W9128F25RA0080005 SF 30.pdf PDF
Amend 0004_26 25 00.00 26.pdf PDF
Amend 0004_E-601.pdf PDF
Amend 0004_E-501.pdf PDF
Amend 0004_E-103.pdf PDF
Amend 0004_W9128F25RA008_Narrative.pdf PDF
Amend 0004_W9128F25RA0080004 SF 30.pdf PDF
Amend 0004_W9128F25RA0080004.pdf PDF
Site Visit 2_KTR SignIn Sheet_9 Sep 2025_FP PH1 Cubile Room Swgr Upgrade.pdf PDF
Amend 0003_26 05 00.00 26.pdf PDF
Amend 0003_W9128F25RA0080003_FP PH1 Switchgear.pdf PDF
Amend 0003_W9128F25RA0080003- Narrative.pdf PDF
Amend 0003_W9128F25RA0080003 SF 30_FP PH1 Switchgear.pdf PDF
Amend 0002_W9128F25RA0080002 SF 30_FP PH1 Switchgear.pdf PDF
Amend 0002_W9128F25RA0080002_FP PH1 Switchgear.pdf PDF
Site Visit_KTR SignIn Sheet_5 Aug 2025_FP PH1 Cubile Room Switchgear.pdf PDF
Amend 0001_W9128F25RA0080001_FP PH1 Switchgear.pdf PDF
Amend 0001_Div 00 22 00_FP PH1 15kV Switchgear_(Redlined).pdf PDF
Amend 0001_W9128F25RA0080001 SF 30_FP PH1 Switchgear.pdf PDF
Amend 0001_Div 00 22 00_FP PH1 15kV Switchgear_(Clean).pdf PDF
02-Div 00 22 00_FP PH1 15kV Switchgear.pdf PDF
05- FP Cubicle Room 15kV Switchgear Contract Drawings_Final_4_of_5.pdf PDF
05- FP Cubicle Room 15kV Switchgear Contract Drawings_Final_3_of_5.pdf PDF
06- W9128F25RA008 FP PH1 Cubicle Room Switchgear Upgrade Specs.pdf PDF
02-Div 00 22 00_FP PH1 15kV Switchgear.pdf PDF
05- FP Cubicle Room 15kV Switchgear Contract Drawings_Final_5_of_5.pdf PDF
05- FP Cubicle Room 15kV Switchgear Contract Drawings_Final_2_of_5.pdf PDF
01-Solicitation - W9128F25RA008 FP PH1 15kV Switchgear Upgrade.pdf PDF
04- Fort Peck Cubicle Room 15kV Switchgear Reference Drawings_Final Submittal.pdf PDF
05- FP Cubicle Room 15kV Switchgear Contract Drawings_Final_1_of_5.pdf PDF
03- DBA WD MT20250076 18 July 2025.pdf PDF
Show all 41

Notice history

Notice Type Posted
Fort Peck Powerhouse 1 Cubicle Room 15kV Switchgear Replacement Project Award Award Notice
This notice Latest solicitation Solicitation
Fort Peck Powerhouse 1 Cubicle Room 15kV Switchgear Replacement Project Pre-Solicitation
Fort Peck Powerhouse 1 Cubicle Room 15kV Switchgear Replacement Project Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Tenkiller Hydropower Excitation System Replacement Gore, Oklahoma, United States · NAICS 237990 ENDIST Tulsa No set-aside
FTG247 Replace UPS at IDT1, Fort Greely, Alaska Fort Greely, Alaska 99731, United States · NAICS 237130 ENDIST Alaska Total Small Business
LLA Navigation Lock Switchgear Pomeroy, Washington 99347, United States · NAICS 238210 ENDIST Walla Walla Total Small Business
Dike B Generator Installation, Mansfield Hollow Dam, Mansfield Center, CT Mansfield Center, Connecticut, United States · NAICS 238290 ENDIST New England Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors