Amend 0004_W9128F25RA008_Narrative.pdf
PDF 134 KB Posted
- Solicitation number
- W9128F25RA008
About this file
This document is an amendment (Amendment No. 0004) to a solicitation for a construction project issued by the U.S. Army Corps of Engineers, Omaha District. The project involves a Powerhouse 1 Cubicle Room 15kV Switchgear Upgrade at Fort Peck, Montana, with Solicitation No. W9128F25RA008. The amendment modifies specifications and drawings, including reissuing two existing drawings (Sheet E-103 and Sheet E-601) with a September 2025 revision date and adding a new drawing (Sheet E-501 for Cable Tray Lengths).
Key dates include a solicitation issue date of 21 July 2025, with proposals due by 2:00 p.m. local time on 07 October 2025. Prospective offerors are required to provide a receipt acknowledgement with the SF1442 form. Electronic proposal submissions should follow guidelines in Section 00 22 00, and all other original specification conditions remain unchanged. The amendment is part of the proposing documents and applies to the ongoing construction project for electrical infrastructure upgrades.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Am #0004 - 2 (Continuation SF 30)
22 SEP 2025
Solicitation No. W9128F25RA008
Date of Issue: 21 JUL 2025 Date of Receiving Proposals: 07 OCT 2025
SUBJECT: Amendment No. 0004 to specification and drawings for Construction of
POWERHOUSE 1 CUBICLE ROOM 15KV SWITCHGEAR UPGRADE, FORT PECK, MONTANA
TO: Prospective Offerors and Others Concerned
1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).
a. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment.
Pages or Sections Deleted Pages or Sections Substituted or Added N/A 26 25 00.00 26 Am-0004
b. Drawings (Reissued). The following drawings are revised with latest revision date of SEP 2025 and reissued with this amendment.
(1) Sheet E-103, Switchyard 1 Lower Level Buses Plan View Install
(2) Sheet E-601, Plant 1 One Line Diagram Install
c. Drawings (New). The following new drawings are hereby added to the contract drawings and are issued with this amendment.
(1) Sheet E-501, Cable Tray Lengths
2. This amendment is a part of the proposing documents, and a receipt acknowledgement shall be provided with the SF1442. All other conditions and requirements of the specifications remain unchanged.
3. Electronic Proposal/Email. See Section 00 22 00 for how to submit electronic proposals.
4. Electric Offers will be received until 2:00 p.m., local time at place of receiving proposals, 07 OCT 2025, as stated in the Request For Proposal.
Attachments:
Spec Pages listed in 1.a. above Dwgs. listed in 1.b. and 1.c. above
U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901
22 SEP 2025
JNS/2179
File details come from the government source that posted it. Updated .