WWYK190067_GOVT RESPONSE TO RFI 02 COR.pdf

PDF 193 KB Posted

Attached to
Tinker AFB MACBOA WWYK190067 Repair Fire Suppression System B2136
Solicitation number
WWYK190067
Issued by

About this file

This document is a Pre-Bid Request for Information (RFI) response memorandum for Project WWYK190067, a fire suppression system repair at Tinker Air Force Base, Oklahoma. The document addresses three specific contractor inquiries related to project phasing, duct detectors, and communication loop wiring requirements. Key responses include: (1) Clarifying that the contractor is responsible for developing a final phasing plan incorporating user requirements, with each project phase not exceeding six weeks, (2) Confirming that existing duct smoke detectors will be demolished and replaced with new detectors compatible with the new Fire Alarm/Mass Notification system, and (3) Specifying that the design requires a Class B wiring configuration contrary to the contractor's assumption of a Class A installation.

The memorandum provides contact information for key project personnel, including the Project Manager (Bash Jimoh), Construction Inspector (Adam Gibson), CSAG Program Manager (Joshua Wheeler), and Contracting Officer Representative (Matthew Morris). The project is restricted to Tinker AFB MAC BOA (Multiple Award Construction Bundle) holders, with a small business set-aside, and an estimated project value between $5,000,000 and $10,000,000. The solicitation indicates a mandatory site visit was conducted on 23 January 2025, with Request for Information (RFI) submissions due by 30 January 2025.

View the file

Other files

File Type Posted
OK20250049- REV 4-19SEP2025-WD.pdf PDF
SOW Revision 1- 25 Aug.pdf PDF
Solicitation Amendment FA813725R00120003 SF 30.pdf PDF
Solicitation Amendment FA813725R00120002 SF 30.pdf PDF
190067_GOVT RESPONSE TO RFI 1 SECOND VISIT SIGNED COR.pdf PDF
190067_ATT9_SOW-Rev 1.pdf PDF
OK20250049- REV 1-14MAR2025-WD.pdf PDF
Solicitation Amendment - FA813725R00120001.pdf PDF
Solicitation Amendment FA813725R00120001 SF 30.pdf PDF
190067_ATT8_Liquidated_Damages_CO Signed.pdf PDF
Solicitation - FA813725R0012.pdf PDF
Revised SOW.pdf PDF
190067_ATT11_Revised _Drawings.pdf PDF
WWYK190067-Site Visit Sign in Sheet- 17 April.pdf PDF
WWYK190067-Sign Visit Sign in Sheet- 23 Jan.pdf PDF
190067_ATT10_Submittal_Register.pdf PDF
190067ATT 12.a.iiiFCSpecs.pdf PDF
01 50 00.pdf PDF
190067_Drawings.zip ZIP file
00 80 00.pdf PDF
01 78 00.pdf PDF
00 72 00.pdf PDF
01 42 00.pdf PDF
01 78 23.pdf PDF
01 32 16.00 20.pdf PDF
190067 PREBID RFI GOVERNMENT RESPONSE_7APR COR.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
00 70 00.pdf PDF
00 71 00.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
00 80 05.pdf PDF
TinkerGenReqSpecsNov22ChLog.pdf PDF
01 45 00.00 10.pdf PDF
190067_ATT9_SOW.pdf PDF
190067_ATT10_Submittal Register.pdf PDF
190067_ATT3_Green Statement_Signed.pdf PDF
190067_ATT11_IFC_Drawings.pdf PDF
WWYK190067 SITE VISIT PICTURES.pdf PDF
Wage Determination.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 72 AIR BASE WING (AFMC)

TINKER AIR FORCE BASE OKLAHOMA

29 MAY 25

MEMORANDUM FOR AFSC/PZIOC (ATTN: Rachel Silva)

THROUGH: 72 ABW/CENM

FROM: 72 ABW/CEED

Tepa Companies

SUBJECT: Pre-Bid RFI Responses Project: WWYK190067, REPAIR FIRE SUPPRESSION SYSTEM, B2136

Reference: Memo, 15 MAY 2025, Pre-Bid RFIs, WWYK190067, REPAIR FIRE SUPPRESSION

SYSTEM, B2136

1. This office reviewed the referenced RFIs for the subject project and provided answers below. Please forward to the contractor(s) for their use in preparing proposals

(1) Request for information. Changes in the SOW and drawings are made to the phases of the project. All the language is for the installation and removal of the suppression system. No mention of the fire detection system that must be installed at the same time. Given current requirements to notify the owner for pretest, final testing, and notice to demo after the final acceptance of each phase will only leave the contractor 3 weeks for installation.

Government Response: Per G-002 phasing plan, General Note 2 - NOT ALL

ASPECTS OF THE SCOPE OF WORK ARE EXPLICITLY DESCRIBED IN THIS

PLAN. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO INCLUDE ALL

WORK THAT IS REQUIRED IN THE FINAL PHASING PLAN. As the scope of the project is focused on the fire suppression systems, so the phasing plan is also focused on the fire suppression systems. Per General Note 1 – THE PHASING PLAN

PRESENTED IS A SUGGESTED PHASING PLAN ONLY. THE CONTRACTOR

SHALL DEVELOP A FINAL PHASING PLAN THAT INCORPORATES THE USER

REQUIREMENTS AND SHALL BE COORDINATED WITH AND APPROVED BY THE

USER AND GOVERNMENT PRIOR TO IMPLEMENTATION. Contractor is to propose a schedule as necessary to accomplish required work within the required time frame (no more than six weeks per phase per General Note 6.) in their proposal.

(2) Request for information. The drawings do not reflect duct detectors currently installed in the hangar.

Government Response: Multiple duct smoke detectors are indicated on the third floor fire alarm demolition sheets FD105 and FD106. Existing duct smoke detectors are to be demolished and new duct smoke detectors, compatible with the new Fire alarm/Mass Notification system, installed.

(3) Request for information. The communication loop for all detronics must be a class A installation. So, as each new phase is started, the contractor will have to go to the previous phase to repull new wire. It has been a requirement by Tinker FD that if you touch or change anything with a test system, that it be retested. Therefore, the previous phase will also have to be retested, all within their 6 week time frame.

Government Response: Our design requires Class B wiring configuration provided in accordance with 28 31 76, 1.6.1.a and as indicated on FA/MNS riser diagram on sheet FA-602. Please provide the reference requiring the communication loop for all detronics to be a class A installation.

2. The points of contact for this project are:

a. Bash Jimoh, Project Manager. PH: 582-4828

b. Adam Gibson, Construction Inspector. PH: 736-5028

c. Joshua Wheeler, CSAG Program Manager. PH: 582-4826

d. Matthew Morris, Contracting Officer Representative (COR). PH: 736-7081

BASH JIMOH MATTHEW MORRIS

Project Manager Electrical Engineer/COR 72d Civil Engineering Directorate (Tepa) 72d Civil Engineering Directorate

0 Attachment(s):

cc:

Project folder

2025-05-29T10:09:38-0500
MORRIS.MATTHEW.K.1385757456
2025-05-29T10:12:30-0500
JIMOH.BASHIRU.BABATUNDE.1399499174

File details come from the government source that posted it. Updated .