190067_ATT10_Submittal_Register.pdf

PDF 171 KB Posted

Attached to
Tinker AFB MACBOA WWYK190067 Repair Fire Suppression System B2136
Solicitation number
WWYK190067
Issued by

About this file

The Submittal Register is a comprehensive document for the Tinker Air Force Base MACB Project WWYK190067 to Repair Fire Suppression System in Hangar B2136. The register details 191 specific submittal requirements across multiple specification sections including demolition, wall panels, firestopping, sprinkler systems, electrical systems, fire alarm systems, and concrete work. Each line item specifies the specification section, submittal description, item to be submitted, paragraph reference, and classification (Government or Architect/Engineer review), with most items marked as requiring Government (G) review.

Key specification sections include 02 41 00 (Demolition), 07 42 63 (Wall Panels), 21 13 13 and 21 13 16 (Wet and Dry Pipe Sprinkler Systems), 23 09 00 (HVAC Controls), 26 20 00 (Electrical Systems), and 28 31 76 (Fire Alarm Systems). Submittals range from preconstruction documents, shop drawings, product data, samples, test reports, certificates, to operation and maintenance manuals and closeout documentation. The project is located at Tinker Air Force Base in Oklahoma, with an estimated price range between $5 million and $10 million, and is restricted to Tinker MACB Office of Acquisition (MACBOA) holders.

View the file

Other files

File Type Posted
OK20250049- REV 4-19SEP2025-WD.pdf PDF
Solicitation Amendment FA813725R00120003 SF 30.pdf PDF
SOW Revision 1- 25 Aug.pdf PDF
Solicitation Amendment FA813725R00120002 SF 30.pdf PDF
WWYK190067_GOVT RESPONSE TO RFI 02 COR.pdf PDF
Solicitation Amendment FA813725R00120001 SF 30.pdf PDF
Solicitation Amendment - FA813725R00120001.pdf PDF
OK20250049- REV 1-14MAR2025-WD.pdf PDF
190067_ATT9_SOW-Rev 1.pdf PDF
190067_GOVT RESPONSE TO RFI 1 SECOND VISIT SIGNED COR.pdf PDF
190067_ATT8_Liquidated_Damages_CO Signed.pdf PDF
Solicitation - FA813725R0012.pdf PDF
WWYK190067-Sign Visit Sign in Sheet- 23 Jan.pdf PDF
190067_ATT11_Revised _Drawings.pdf PDF
Revised SOW.pdf PDF
WWYK190067-Site Visit Sign in Sheet- 17 April.pdf PDF
190067ATT 12.a.iiiFCSpecs.pdf PDF
00 70 00.pdf PDF
01 50 00.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 42 00.pdf PDF
TinkerGenReqSpecsNov22ChLog.pdf PDF
00 71 00.pdf PDF
01 33 00.pdf PDF
00 80 05.pdf PDF
01 33 16.00 10.pdf PDF
01 45 00.00 10.pdf PDF
00 72 00.pdf PDF
01 78 00.pdf PDF
00 80 00.pdf PDF
190067_Drawings.zip ZIP file
190067 PREBID RFI GOVERNMENT RESPONSE_7APR COR.pdf PDF
01 32 16.00 20.pdf PDF
01 78 23.pdf PDF
190067_ATT10_Submittal Register.pdf PDF
WWYK190067 SITE VISIT PICTURES.pdf PDF
Wage Determination.pdf PDF
190067_ATT9_SOW.pdf PDF
190067_ATT11_IFC_Drawings.pdf PDF
190067_ATT3_Green Statement_Signed.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line Activity

Transmittal

# Specification Section SD # Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth Date RCD

From CONTR

Date FWD To Other

Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date RCD From APPR Authority Remarks

1 02 41 00 1 Preconstruction Submittals Demolition Plan 1.2.2 G 2 02 41 00 1 Preconstruction Submittals Existing Conditions 1.9 3 02 41 00 7 Certificates Notification 1.7 G 4 07 42 63 1 Preconstruction Submittals Qualification of Manufacturer 1.5.1 G 5 07 42 63 2 Shop Drawings Wall Panel Assemblies G 6 07 42 63 2 Shop Drawings Flashing and Accessories G 7 07 42 63 2 Shop Drawings Anchorage Systems G 8 07 42 63 3 Product Data Manufacturer's catalog data 9 07 42 63 3 Product Data Factory Color Finish G

10 07 42 63 3 Product Data Pressure Sensitive Tape G 11 07 42 63 3 Product Data Sealants and Caulking 2.3.2.1 G 12 07 42 63 3 Product Data Enamel Repair Paint G 13 07 42 63 3 Product Data Aluminized Steel Repair Paint G 14 07 42 63 3 Product Data Accessories G 15 07 42 63 4 Samples Wall Panel Assemblies 16 07 42 63 4 Samples manufacturer's color charts and chips 17 07 42 63 6 Test Reports Factory Color Finish 18 07 42 63 7 Certificates Fasteners G 19 07 42 63 7 Certificates Enamel Repair Paint G

20 07 42 63 7 Certificates wall system assembly wind load and fire rating classification listings

21 07 42 63 8 Manufacturer's Instructions Installation of Wall Panels 22 07 42 63 11 Closeout Submittals Warranty G 23 07 84 00 2 Shop Drawings Firestopping System 2.1 G 24 07 84 00 3 Product Data Firestopping Materials 2.2 G 25 07 84 00 6 Test Reports Inspection 3.3 G 26 07 84 00 7 Certificates Inspector Qualifications 1.5.2 G 27 07 84 00 7 Certificates Firestopping Materials 2.2 G 28 07 84 00 7 Certificates Installer Qualifications 1.5.1 G 29 21 13 13 1 Preconstruction Submittals Qualified Fire Protection Engineer (QFPE) 1.2.3 G 30 21 13 13 1 Preconstruction Submittals Sprinkler System Designer 1.4.2.1 G 31 21 13 13 1 Preconstruction Submittals Sprinkler System Installer 1.4.2.2 G 32 21 13 13 2 Shop Drawings Shop Drawing 1.4.1.1 G 33 21 13 13 3 Product Data Pipe 2.2.1.1 G 34 21 13 13 3 Product Data Fittings 2.2.1.2 G 35 21 13 13 3 Product Data Valves 2.2.4 G 36 21 13 13 3 Product Data Alarm Valves 2.2.5 G 37 21 13 13 3 Product Data Relief Valves 2.6.5 G 38 21 13 13 3 Product Data Sprinklers 2.5 G 39 21 13 13 3 Product Data Pipe Hangers and Supports 2.2.3 G 40 21 13 13 3 Product Data Sprinkler Alarm Switch 2.3.1 G 41 21 13 13 3 Product Data Valve Supervisory (Tamper) Switch 2.3.2 G 42 21 13 13 3 Product Data Fire Department Connection 2.4 G 43 21 13 13 3 Product Data Air Vent 2.6.6 G 44 21 13 13 3 Product Data Hose Valve 2.2.4.3 G

APPROVING AUTHORITY

(d)

CONTRACTOR

SCHEDULE DATES

CONTRACTOR

ACTION

TITLE: WWYK190067

SUBMITTAL REGISTER

JOB NAME: REPAIR FIRE SUPPRESSION SYSTEM, MAIN HANGAR B2136

LOCATION: TINKER AIR FORCE BASE, OKLAHOMA

CONTRACT NO:

CONTRACTOR:

Activity

Transmittal

# Specification Section SD # Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth Date RCD

From CONTR

Date FWD To Other

Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date RCD From APPR Authority Remarks

APPROVING AUTHORITY

(d)

CONTRACTOR

SCHEDULE DATES

CONTRACTOR

ACTION

TITLE: WWYK190067

SUBMITTAL REGISTER

JOB NAME: REPAIR FIRE SUPPRESSION SYSTEM, MAIN HANGAR B2136

LOCATION: TINKER AIR FORCE BASE, OKLAHOMA

CONTRACT NO:

CONTRACTOR:

45 21 13 13 3 Product Data Nameplates 2.1.2 G 46 21 13 13 5 Design Data Hydraulic Calculations 1.2.1.2 G 47 21 13 13 6 Test Reports Test Procedures 3.6.1 G 48 21 13 13 7 Certificates Verification of Compliant Installation 3.6.2.1 G 49 21 13 13 7 Certificates Request for Government Final Test 3.6.2.2 G

50 21 13 13 10 Operation and Maintenance Data Operating and Maintenance (O&M) Instructions 3.8 G

51 21 13 13 10 Operation and Maintenance Data Spare Parts 1.6 G 52 21 13 13 11 Closeout Submittals As-built drawings 3.8 53 21 13 13 11 Closeout Submittals Coordinated Submittal 1.3.1 54 21 13 16 1 Preconstruction Submittals Qualified Fire Protection Engineer (QFPE) 1.2.3 G 55 21 13 16 1 Preconstruction Submittals Sprinkler System Designer 1.4.2.1 G 56 21 13 16 1 Preconstruction Submittals Sprinkler System Installer 1.4.2.2 G

57 21 13 16 1 Preconstruction Submittals Nitrogen Generation System Commissioning Technician 1.4.2.3 G

58 21 13 16 2 Shop Drawings Shop Drawing 1.4.1.1 G 59 21 13 16 3 Product Data Pipe 2.2.1.1 G 60 21 13 16 3 Product Data Fittings 2.2.1.2 G 61 21 13 16 3 Product Data Valves 2.2.3 G 62 21 13 16 3 Product Data Relief Valves 2.7.4 G 63 21 13 16 3 Product Data Sprinklers 2.6 G 64 21 13 16 3 Product Data Pipe Hangers and Supports 2.2.2 G 65 21 13 16 3 Product Data Sprinkler Alarm Switch 2.5.1 G 66 21 13 16 3 Product Data Valve Supervisory (Tamper) Switch 2.5.3 G

67 21 13 16 3 Product Data High/Low-Nitrogen Pressure Supervisory Switch 2.5.2 G

68 21 13 16 3 Product Data Nitrogen Generation System 1.4.2.3 G 69 21 13 16 3 Product Data Nameplates 2.1.2 G 70 21 13 16 3 Product Data Dry Pipe Valve 2.3 G 71 21 13 16 5 Design Data Hydraulic Calculations 1.2.1.2 G 72 21 13 16 6 Test Reports Test Procedures 3.6.1 G 73 21 13 16 7 Certificates Verification of Compliant Installation 3.6.2.1 G 74 21 13 16 7 Certificates Request for Government Final Test 3.6.2.2 G

75 21 13 16 10 Operation and Maintenance Data Operating and Maintenance (O&M) Instructions 3.8 G

76 21 13 16 10 Operation and Maintenance Data Spare Parts 1.6 G 77 21 13 16 11 Closeout Submittals As-built drawings 3.8 78 23 09 00 2 Shop Drawings DDC Contractor Design Drawings 3.3 G 79 23 09 00 2 Shop Drawings Draft As-Built Drawings 3.3 G 80 23 09 00 2 Shop Drawings Final As-Built Drawings 3.3 G 81 23 09 00 3 Product Data Programming Software 1.8.3 G 82 23 09 00 3 Product Data Controller Application Programs 1.8.4 G 83 23 09 00 3 Product Data Configuration Software 1.8.1 G 84 23 09 00 3 Product Data Controller Configuration Settings 1.8.2 G 85 23 09 00 3 Product Data Manufacturer's Product Data 2.2 G 86 23 09 00 6 Test Reports Existing Conditions Report 3.1.1 G

Activity

Transmittal

# Specification Section SD # Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth Date RCD

From CONTR

Date FWD To Other

Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date RCD From APPR Authority Remarks

APPROVING AUTHORITY

(d)

CONTRACTOR

SCHEDULE DATES

CONTRACTOR

ACTION

TITLE: WWYK190067

SUBMITTAL REGISTER

JOB NAME: REPAIR FIRE SUPPRESSION SYSTEM, MAIN HANGAR B2136

LOCATION: TINKER AIR FORCE BASE, OKLAHOMA

CONTRACT NO:

CONTRACTOR:

87 23 09 00 6 Test Reports Start-Up Testing Report 3.5.2 G 88 23 09 00 6 Test Reports PVT Procedures 3.6.1 G 89 23 09 00 6 Test Reports PVT Report 3.6.3 G

90 23 09 00 6 Test Reports Pre-Construction Quality Control (QC) Checklist 1.9.1 G

91 23 09 00 6 Test Reports Post-Construction Quality Control (QC) Checklist 1.9.2 G

92 23 09 00 10 Operation and Maintenance Data Operation and Maintenance (O&M) Instructions 3.7 G

93 23 09 00 10 Operation and Maintenance Data Training Documentation 3.9.1 G 94 23 09 00 11 Closeout Submittals Enclosure Keys 2.5 G 95 23 09 00 11 Closeout Submittals Password Summary Report 3.2.6.1 G 96 23 09 00 11 Closeout Submittals Closeout Quality Control (QC) Checklist 1.9.3 G 97 23 81 00 3 Product Data Spare Parts 3.7.1 98 23 81 00 3 Product Data Posted Instructions 3.4 99 23 81 00 3 Product Data Coil Corrosion Protection 2.5.1

100 23 81 00 3 Product Data System Performance Tests 3.6 101 23 81 00 3 Product Data Training 3.4 G 102 23 81 00 3 Product Data Inventory 1.4 103 23 81 00 3 Product Data Supplied Products 2.1 104 23 81 00 3 Product Data Manufacturer's Standard Catalog Data 2.2 G 105 23 81 00 3 Product Data Refrigerant Piping & Insulation 2.4.1 G 106 23 81 00 3 Product Data Condensate Drain Piping & Insulation 2.4.2 G 107 23 81 00 6 Test Reports Refrigerant Tests, Charging, and Start-Up 3.5 G 108 23 81 00 6 Test Reports System Performance Tests 3.6 G 109 23 81 00 7 Certificates Service Organizations 3.7.2 110 23 81 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.4 G 111 23 81 00 11 Closeout Submittals Ozone Depleting Substances 2.2.2.3 S 112 26 05 73 1 Preconstruction Submittals Field Examination Plan 3.1 G 113 26 05 73 1 Preconstruction Submittals Arc Flash Label Formats 3.2.9 G 114 26 05 73 6 Test Reports Field Examination 3.1.1 115 26 05 73 7 Certificates System Analyzer 1.4.1 G 116 26 05 73 11 Closeout Submittals Model Files 3.3 G 117 26 05 73 11 Closeout Submittals Load Flow Study 3.2.4 G 118 26 05 73 11 Closeout Submittals Fault Current Study 3.2.5 G 119 26 05 73 11 Closeout Submittals System Coordination Study 3.2.6 G 120 26 05 73 11 Closeout Submittals Arc Flash Hazard Study 3.2.7 G 121 26 20 00 2 Shop Drawings Panelboards 2.1 G 122 26 20 00 3 Product Data Receptacles 2.9 G 123 26 20 00 3 Product Data Circuit Breakers 2.10.3 G 124 26 20 00 3 Product Data Switches 2.8 G 125 26 20 00 3 Product Data Surge Protective Devices 2.17 G 126 26 20 00 6 Test Reports 600-volt Wiring Test 3.5.2 G 127 26 20 00 6 Test Reports Ground-fault Receptacle Test 3.5.3 G 128 26 20 00 10 Operation and Maintenance Data Electrical Systems 1.5.1 G

Activity

Transmittal

# Specification Section SD # Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth Date RCD

From CONTR

Date FWD To Other

Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date RCD From APPR Authority Remarks

APPROVING AUTHORITY

(d)

CONTRACTOR

SCHEDULE DATES

CONTRACTOR

ACTION

TITLE: WWYK190067

SUBMITTAL REGISTER

JOB NAME: REPAIR FIRE SUPPRESSION SYSTEM, MAIN HANGAR B2136

LOCATION: TINKER AIR FORCE BASE, OKLAHOMA

CONTRACT NO:

CONTRACTOR:

129 28 31 76 1 Preconstruction Submittals Qualified Fire Protection Engineer (QFPE) 1.3.2 G 130 28 31 76 1 Preconstruction Submittals Fire alarm system designer 1.8.2.1 G 131 28 31 76 1 Preconstruction Submittals Supervisor 1.8.2.2 G 132 28 31 76 1 Preconstruction Submittals Technician 1.8.2.3 G 133 28 31 76 1 Preconstruction Submittals Installer 1.8.2.4 G 134 28 31 76 1 Preconstruction Submittals Test Technician 1.8.2.5 G

135 28 31 76 1 Preconstruction Submittals Fire Alarm System Site-Specific Software Acknowledgement 1.7 G

136 28 31 76 2 Shop Drawings Nameplates 1.8.1.3 G 137 28 31 76 2 Shop Drawings Instructions 2.2.4 G 138 28 31 76 2 Shop Drawings Wiring Diagrams 1.8.1.4 G 139 28 31 76 2 Shop Drawings System Layout 1.8.1.5 G 140 28 31 76 2 Shop Drawings Notification Appliances 1.8.1.6 G 141 28 31 76 2 Shop Drawings Initiating devices 1.8.1.7 G 142 28 31 76 2 Shop Drawings Amplifiers 1.8.1.8 G 143 28 31 76 2 Shop Drawings Battery Power 1.8.1.9 G 144 28 31 76 2 Shop Drawings Voltage Drop Calculations 1.8.1.10 G

145 28 31 76 3 Product Data Fire Alarm and Mass Notification Control Unit

(FMCU) 2.3 G

146 28 31 76 3 Product Data Local Operating Console (LOC) 1.4.3 G 147 28 31 76 3 Product Data Amplifiers 1.8.1.8 G 148 28 31 76 3 Product Data Tone Generators 2.5 G 149 28 31 76 3 Product Data Digitalized voice generators 2.5 G 150 28 31 76 3 Product Data Manual Stations 2.8 G 151 28 31 76 3 Product Data Flame Detectors 2.7 G 152 28 31 76 3 Product Data Smoke Detectors 2.9 G 153 28 31 76 3 Product Data Duct Smoke Detectors 2.9.2 G 154 28 31 76 3 Product Data Addressable Interface Devices 2.1 G 155 28 31 76 3 Product Data Addressable Control Modules 2.11 G 156 28 31 76 3 Product Data Isolation Modules 2.12 G 157 28 31 76 3 Product Data Notification Appliances 1.8.1.6 G 158 28 31 76 3 Product Data Textual Display Signs 2.13.3 G 159 28 31 76 3 Product Data Batteries 2.15.1 G 160 28 31 76 3 Product Data Battery Chargers 2.15.2 G

161 28 31 76 3 Product Data Supplemental Notification Appliance Circuit Panels 2.15.1.1 G

162 28 31 76 3 Product Data Auxiliary Power Supply Panels 2.15.1.1 G 163 28 31 76 3 Product Data Surge Protective Devices 2.16 G 164 28 31 76 3 Product Data Alarm Wiring 2.16 G 165 28 31 76 3 Product Data Back Boxes and Conduit 3.3.4 G 166 28 31 76 3 Product Data Ceiling Bridges 3.2.8 G 167 28 31 76 3 Product Data Terminal Cabinets 3.3.2 G 168 28 31 76 3 Product Data Automatic Fire Alarm Transmitters 2.19 G 169 28 31 76 3 Product Data Radio Transmitter and Interface Panels 2.19.1 G 170 28 31 76 3 Product Data Document Storage Cabinet 3.13.3 G

Activity

Transmittal

# Specification Section SD # Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth Date RCD

From CONTR

Date FWD To Other

Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date RCD From APPR Authority Remarks

APPROVING AUTHORITY

(d)

CONTRACTOR

SCHEDULE DATES

CONTRACTOR

ACTION

TITLE: WWYK190067

SUBMITTAL REGISTER

JOB NAME: REPAIR FIRE SUPPRESSION SYSTEM, MAIN HANGAR B2136

LOCATION: TINKER AIR FORCE BASE, OKLAHOMA

CONTRACT NO:

CONTRACTOR:

171 28 31 76 6 Test Reports Test Procedures 3.9.1 G 172 28 31 76 7 Certificates Verification of Compliant Installation 3.9.2.1 G 173 28 31 76 7 Certificates Request for Government Final Test 3.9.2.2 G

174 28 31 76 10 Operation and Maintenance Data Operation and Maintenance (O&M) Instructions 3.11 G

175 28 31 76 10 Operation and Maintenance Data Instruction of Government Employees 3.12 G 176 28 31 76 11 Closeout Submittals As-Built Drawings 1.8.1.13 177 28 31 76 11 Closeout Submittals Spare Parts 1.10.1 178 32 11 20 3 Product Data Equipment and Tools 1.5 G 179 32 11 20 6 Test Reports Initial Tests 2.2.1 G 180 32 11 20 6 Test Reports In-Place Tests 3.8.1 G 181 32 13 13.06 3 Product Data Curing Materials 2.1.6 182 32 13 13.06 3 Product Data Epoxy Resin 2.1.9 183 32 13 13.06 3 Product Data Epoxy Resin 2.1.9 184 32 13 13.06 3 Product Data Cementitious Materials 2.1.1 G 185 32 13 13.06 3 Product Data Cementitious Materials 2.1.1 G 186 32 13 13.06 3 Product Data Dowel Bars 2.1.5.1 187 32 13 13.06 3 Product Data Joint Material 188 32 13 13.06 5 Design Data Mix Design Report 2.2.2 G 189 32 13 13.06 6 Test Reports Concrete Slump Tests 190 32 13 13.06 6 Test Reports Compressive Strength 3.7.2 191 32 13 13.06 6 Test Reports Air Content 3.7.3