190067_ATT10_Submittal Register.pdf

PDF 461 KB Posted

Attached to
Tinker AFB MACBOA WWYK190067 Repair Fire Suppression System B2136
Solicitation number
WWYK190067
Issued by

About this file

This is a submittal register for contract WWYK190067 "Repair Fire Suppression System, Main Hangar B2136" at Tinker Air Force Base, Oklahoma. The document details 245 required submittals across multiple specification sections, including preconstruction submittals, shop drawings, product data, test reports, certificates, operation and maintenance data, and closeout submittals.

Key submittal requirements include Quality Control Plans, Health and Safety Plans, Construction Schedules, Product Data for fire suppression system components (valves, pipes, sprinklers, etc.), Shop Drawings for system layout and installation details, Test Reports for system performance verification, Operation and Maintenance Manuals, and As-Built Drawings. Many submittals require Government (G) approval. Notable timing requirements include FAA Form 7460-1 which must be submitted by the 5th day of the month with 45 days processing time, and Monthly Debris Management Reports due the first week of each month during construction. The register tracks submission dates, review actions, and approval status through multiple review stages.

View the file

Other files

File Type Posted
OK20250049- REV 4-19SEP2025-WD.pdf PDF
SOW Revision 1- 25 Aug.pdf PDF
Solicitation Amendment FA813725R00120003 SF 30.pdf PDF
Solicitation Amendment FA813725R00120002 SF 30.pdf PDF
WWYK190067_GOVT RESPONSE TO RFI 02 COR.pdf PDF
190067_ATT9_SOW-Rev 1.pdf PDF
190067_GOVT RESPONSE TO RFI 1 SECOND VISIT SIGNED COR.pdf PDF
Solicitation Amendment FA813725R00120001 SF 30.pdf PDF
Solicitation Amendment - FA813725R00120001.pdf PDF
OK20250049- REV 1-14MAR2025-WD.pdf PDF
Solicitation - FA813725R0012.pdf PDF
190067_ATT8_Liquidated_Damages_CO Signed.pdf PDF
WWYK190067-Site Visit Sign in Sheet- 17 April.pdf PDF
WWYK190067-Sign Visit Sign in Sheet- 23 Jan.pdf PDF
190067_ATT10_Submittal_Register.pdf PDF
190067_ATT11_Revised _Drawings.pdf PDF
Revised SOW.pdf PDF
190067ATT 12.a.iiiFCSpecs.pdf PDF
00 70 00.pdf PDF
01 50 00.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
01 42 00.pdf PDF
190067 PREBID RFI GOVERNMENT RESPONSE_7APR COR.pdf PDF
01 32 16.00 20.pdf PDF
01 78 23.pdf PDF
TinkerGenReqSpecsNov22ChLog.pdf PDF
00 71 00.pdf PDF
01 33 00.pdf PDF
00 80 05.pdf PDF
01 33 16.00 10.pdf PDF
01 45 00.00 10.pdf PDF
00 72 00.pdf PDF
01 78 00.pdf PDF
00 80 00.pdf PDF
190067_Drawings.zip ZIP file
190067_ATT3_Green Statement_Signed.pdf PDF
WWYK190067 SITE VISIT PICTURES.pdf PDF
Wage Determination.pdf PDF
190067_ATT9_SOW.pdf PDF
190067_ATT11_IFC_Drawings.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

1 00 70 00 01 Preconstruction Submittals Entry Access List 1.6 G

2 00 70 00 01 Preconstruction Submittals Key Issue Receipt 1.3.12.1

3 00 70 00 06 Test Reports Pre-Construction Testing Record 1.3.11 G

4 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G

5 00 70 00 11 Closeout Submittals Key Return Receipt 1.3.12.1

6 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G

7 00 71 00 01 Preconstruction Submittals Internal Combustion Engines Plan 1.3.5 G

8 00 71 00 01 Preconstruction Submittals Entry Authority List 1.5.2

9 00 71 00 01 Preconstruction Submittals Vehicle Entry Authority List 1.5.2 G

10 00 71 00 01 Preconstruction Submittals Equipment and Material Storage 1.5 G

11 00 71 00 01 Preconstruction Submittals Contractor Offices and Plants 1.5 G

12 00 71 00 01 Preconstruction Submittals Designated Waste and Disposal Areas 1.5 G

13 00 71 00 01 Preconstruction Submittals Construction Phasing Plan 1.5 G

14 00 71 00 01 Preconstruction Submittals Airfield Construction Waiver 1.5 G

15 00 71 00 01 Preconstruction Submittals FAA Form 7460-1 1.5.3 G

Must be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing.

16 00 71 00 07 Certificates Safety Meetings 1.3

17 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4

18 00 72 00 01 Preconstruction Submittals Restoration Plan 1.3.2 G

19 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G 20 00 72 00 01 Preconstruction Submittals Water System Construction Permit 1.3.3.6 G

21 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization

1.4 G

22 00 72 00 01 Preconstruction Submittals Spray Painting Plan 1.9 G

23 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training

1.1

24 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement

1.3.10 G

25 00 72 00 07 Certificates Monthly Hazardous Material Usage Report

1.4 G

26 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets

1.4 Provide only one. Reference specification for additional information

27 00 72 00 11 Closeout Submittals Notice of Termination (ODEQ Form 640-572)

1.3.3.2 G

28 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G

29 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction

30 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G 31 01 32 16.00 20 07 Certificates Monthly Updates 1.4 32 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 33 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G 34 01 33 16.00 10 11 Closeout Submittals DD Form 1354 3.8.5 A 35 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G 36 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G

WWYK190067

REPAIR FIRE SUPPRESSION SYSTEM, MAIN HANGAR B2136

TINKER AIR FORCE BASE, OKLAHOMA

TBD

TBD

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES

APPROVING AUTHORITY

TITLE:

SUBMITTAL REGISTER

JOB NAME:

LOCATION:

CONTRACT NO:

CONTRACTOR:

Submittal Register_v3_03/07/22

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES

APPROVING AUTHORITY

37 01 50 00 01 Preconstruction Submittals Photographic Record 1.3

38 01 78 00 03 Product Data Warranty Letter 1.7.1

39 01 78 00 03 Product Data Warranty Tags 1.7.3

40 01 78 00 03 Product Data Spare Parts Data 1.5

41 01 78 00 08 Manufacturer's Instructions Instructions 1.7.1

42 01 78 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.4 G

43 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G

44 01 78 00 11 Closeout Submittals Record Drawings 3.3 G

45 01 78 00 11 Closeout Submittals DD FORM 1354 3.6 G

46 01 78 00 11 Closeout Submittals Checklist for DD FORM 1354 3.6 G

47 01 78 23 10 Operation and Maintenance Data Operation and Maintenance Data 1.2 G

48 01 78 23 10 Operation and Maintenance Data O&M Database 1.3 G

49 01 78 23 10 Operation and Maintenance Data Training Plan 3.1.1 G

50 01 78 23 10 Operation and Maintenance Data Training Content 3.1.2 G

51 01 78 23 10 Operation and Maintenance Data Training Outline 3.1.3 G

52 01 78 23 11 Closeout Submittals Validation of Training Completion 3.1.6 G

53 SOW 07 Certificates Contract Progress Report(s) 2.4 G

54 SOW 01 Preconstruction Submittals B3001 Visitor Badge Issue Receipt 1.3.7

55 SOW 11 Closeout Submittals B3001 Visitor Badge Return Receipt 1.3.7

56 02 41 00 1 Preconstruction Submittals Demolition Plan 1.2.2 G

57 02 41 00 1 Preconstruction Submittals Existing Conditions 1.9

58 02 41 00 7 Certificates Notification 1.7 G

59 07 42 63 1 Preconstruction Submittals Qualification of Manufacturer 1.5.1 G

60 07 42 63 2 Shop Drawings Wall Panel Assemblies G

61 07 42 63 2 Shop Drawings Flashing and Accessories G

62 07 42 63 2 Shop Drawings Anchorage Systems G

63 07 42 63 3 Product Data Manufacturer's catalog data

64 07 42 63 3 Product Data Factory Color Finish G

65 07 42 63 3 Product Data Pressure Sensitive Tape G

66 07 42 63 3 Product Data Sealants and Caulking 2.3.2.1 G

67 07 42 63 3 Product Data Enamel Repair Paint G

68 07 42 63 3 Product Data Aluminized Steel Repair Paint G

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES

APPROVING AUTHORITY

69 07 42 63 3 Product Data Accessories G

70 07 42 63 4 Samples Wall Panel Assemblies

71 07 42 63 4 Samples manufacturer's color charts and chips

72 07 42 63 6 Test Reports Factory Color Finish

73 07 42 63 7 Certificates Fasteners G Provide 1st week of each month during construction

74 07 42 63 7 Certificates Enamel Repair Paint G

75 07 42 63 7 Certificates wall system assembly wind load and fire rating classification listings

76 07 42 63 8 Manufacturer's Instructions Installation of Wall Panels Provide within 10 days of NTP.

77 07 42 63 11 Closeout Submittals Warranty G Provide within 10 days of NTP.

78 07 84 00 2 Shop Drawings Firestopping System 2.1 G Provide 1st week of each month during construction, or as directed by CO

79 07 84 00 3 Product Data Firestopping Materials 2.2 G Provide weekly with the Contract Progress Report

80 07 84 00 6 Test Reports Inspection 3.3 G

81 07 84 00 7 Certificates Inspector Qualifications 1.5.2 G

82 07 84 00 7 Certificates Firestopping Materials 2.2 G

83 07 84 00 7 Certificates Installer Qualifications 1.5.1 G

84 21 13 13 1 Preconstruction Submittals Qualified Fire Protection Engineer

(QFPE)

1.2.3 G

85 21 13 13 1 Preconstruction Submittals Sprinkler System Designer 1.4.2.1 G

86 21 13 13 1 Preconstruction Submittals Sprinkler System Installer 1.4.2.2 G

87 21 13 13 2 Shop Drawings Shop Drawing 1.4.1.1 G

88 21 13 13 3 Product Data Pipe 2.2.1.1 G

89 21 13 13 3 Product Data Fittings 2.2.1.2 G

90 21 13 13 3 Product Data Valves 2.2.4 G

91 21 13 13 3 Product Data Alarm Valves 2.2.5 G

92 21 13 13 3 Product Data Relief Valves 2.6.5 G

93 21 13 13 3 Product Data Sprinklers 2.5 G

94 21 13 13 3 Product Data Pipe Hangers and Supports 2.2.3 G

95 21 13 13 3 Product Data Sprinkler Alarm Switch 2.3.1 G

96 21 13 13 3 Product Data Valve Supervisory (Tamper) Switch 2.3.2 G

97 21 13 13 3 Product Data Fire Department Connection 2.4 G Provide weekly with the Contract Progress Report

98 21 13 13 3 Product Data Air Vent 2.6.6 G

99 21 13 13 3 Product Data Hose Valve 2.2.4.3 G

100 21 13 13 3 Product Data Nameplates 2.1.2 G

101 21 13 13 5 Design Data Hydraulic Calculations 1.2.1.2 G

102 21 13 13 6 Test Reports Test Procedures 3.6.1 G

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES

APPROVING AUTHORITY

103 21 13 13 7 Certificates Verification of Compliant Installation 3.6.2.1 G

104 21 13 13 7 Certificates Request for Government Final Test 3.6.2.2 G Provide (2) electronic sets (optical media) and (1) hard copy

105 21 13 13 10 Operation and Maintenance Data Operating and Maintenance (O&M) Instructions

3.8 G

Provide (2) electronic sets (optical media) and

(2) hard copies

106 21 13 13 10 Operation and Maintenance Data Spare Parts 1.6 G Provide (2) electronic sets (optical media) and (1) hard copy

107 21 13 13 11 Closeout Submittals As-built drawings 3.8

108 drty7 21 13 13 11 Closeout Submittals Coordinated Submittal 1.3.1

109 21 13 16 1 Preconstruction Submittals Qualified Fire Protection Engineer

(QFPE)

1.2.3 G

110 21 13 16 1 Preconstruction Submittals Sprinkler System Designer 1.4.2.1 G

111 21 13 16 1 Preconstruction Submittals Sprinkler System Installer 1.4.2.2 G Provide 30 days prior to scheduled Training

112 21 13 16 1 Preconstruction Submittals Nitrogen Generation System Commissioning Technician

1.4.2.3 G

113 21 13 16 2 Shop Drawings Shop Drawing 1.4.1.1 G Provide 30 days prior to scheduled Final Inspection

114 21 13 16 3 Product Data Pipe 2.2.1.1 G Provide 14 days prior to scheduled Training

115 21 13 16 3 Product Data Fittings 2.2.1.2 G Provide 14 days prior to scheduled Training

116 21 13 16 3 Product Data Valves 2.2.3 G

117 21 13 16 3 Product Data Relief Valves 2.7.4 G

118 21 13 16 3 Product Data Sprinklers 2.6 G Provide weekly throughout life of contract. Utilize AF Form 3065, Contract Progress Report (or equal)

119 21 13 16 3 Product Data Pipe Hangers and Supports 2.2.2 G

120 21 13 16 3 Product Data Sprinkler Alarm Switch 2.5.1 G

121 21 13 16 3 Product Data Valve Supervisory (Tamper) Switch 2.5.3 G

122 21 13 16 3 Product Data High/Low-Nitrogen Pressure Supervisory Switch

2.5.2 G

123 21 13 16 3 Product Data Nitrogen Generation System 1.4.2.3 G

124 21 13 16 3 Product Data Nameplates 2.1.2 G

125 21 13 16 3 Product Data Dry Pipe Valve 2.3 G

126 21 13 16 5 Design Data Hydraulic Calculations 1.2.1.2 G

127 21 13 16 6 Test Reports Test Procedures 3.6.1 G

128 21 13 16 7 Certificates Verification of Compliant Installation 3.6.2.1 G

129 21 13 16 7 Certificates Request for Government Final Test 3.6.2.2 G

130 21 13 16 10 Operation and Maintenance Data Operating and Maintenance (O&M) Instructions

3.8 G

131 21 13 16 10 Operation and Maintenance Data Spare Parts 1.6 G

132 21 13 16 11 Closeout Submittals As-built drawings 3.8

133 23 09 00 2 Shop Drawings DDC Contractor Design Drawings 3.3 G

134 23 09 00 2 Shop Drawings Draft As-Built Drawings 3.3 G

135 23 09 00 2 Shop Drawings Final As-Built Drawings 3.3 G

136 23 09 00 3 Product Data Programming Software 1.8.3 G

137 23 09 00 3 Product Data Controller Application Programs 1.8.4 G

138 23 09 00 3 Product Data Configuration Software 1.8.1 G

139 23 09 00 3 Product Data Controller Configuration Settings 1.8.2 G

140 23 09 00 3 Product Data Manufacturer's Product Data 2.2 G

141 23 09 00 6 Test Reports Existing Conditions Report 3.1.1 G

142 23 09 00 6 Test Reports Start-Up Testing Report 3.5.2 G

143 23 09 00 6 Test Reports PVT Procedures 3.6.1 G

144 23 09 00 6 Test Reports PVT Report 3.6.3 G

145 23 09 00 6 Test Reports Pre-Construction Quality Control (QC) Checklist

1.9.1 G

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES

APPROVING AUTHORITY

146 23 09 00 6 Test Reports Post-Construction Quality Control (QC) Checklist

1.9.2 G

147 23 09 00 10 Operation and Maintenance Data Operation and Maintenance (O&M) Instructions

3.7 G

148 23 09 00 10 Operation and Maintenance Data Training Documentation 3.9.1 G

149 23 09 00 11 Closeout Submittals Enclosure Keys 2.5 G

150 23 09 00 11 Closeout Submittals Password Summary Report 3.2.6.1 G

151 23 09 00 11 Closeout Submittals Closeout Quality Control (QC) Checklist 1.9.3 G

152 23 81 00 3 Product Data Spare Parts 3.7.1

153 23 81 00 3 Product Data Posted Instructions 3.4

154 23 81 00 3 Product Data Coil Corrosion Protection 2.5.1

155 23 81 00 3 Product Data System Performance Tests 3.6

156 23 81 00 3 Product Data Training 3.4 G

157 23 81 00 3 Product Data Inventory 1.4

158 23 81 00 3 Product Data Supplied Products 2.1

159 23 81 00 3 Product Data Manufacturer's Standard Catalog Data 2.2 G

160 23 81 00 3 Product Data Refrigerant Piping & Insulation 2.4.1 G

161 23 81 00 3 Product Data Condensate Drain Piping & Insulation 2.4.2 G

162 23 81 00 6 Test Reports Refrigerant Tests, Charging, and Start-Up 3.5 G

163 23 81 00 6 Test Reports System Performance Tests 3.6 G

164 23 81 00 7 Certificates Service Organizations 3.7.2

165 23 81 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.4 G

166 23 81 00 11 Closeout Submittals Ozone Depleting Substances 2.2.2.3 S

167 26 05 73 1 Preconstruction Submittals Field Examination Plan 3.1 G

168 26 05 73 1 Preconstruction Submittals Arc Flash Label Formats 3.2.9 G

169 26 05 73 6 Test Reports Field Examination 3.1.1

170 26 05 73 7 Certificates System Analyzer 1.4.1 G

171 26 05 73 11 Closeout Submittals Model Files 3.3 G

172 26 05 73 11 Closeout Submittals Load Flow Study 3.2.4 G

173 26 05 73 11 Closeout Submittals Fault Current Study 3.2.5 G

174 26 05 73 11 Closeout Submittals System Coordination Study 3.2.6 G

175 26 05 73 11 Closeout Submittals Arc Flash Hazard Study 3.2.7 G

176 26 20 00 2 Shop Drawings Panelboards 2.1 G

177 26 20 00 3 Product Data Receptacles 2.9 G

178 26 20 00 3 Product Data Circuit Breakers 2.10.3 G

179 26 20 00 3 Product Data Switches 2.8 G

180 26 20 00 3 Product Data Surge Protective Devices 2.17 G

181 26 20 00 6 Test Reports 600-volt Wiring Test 3.5.2 G

182 26 20 00 6 Test Reports Ground-fault Receptacle Test 3.5.3 G

183 26 20 00 10 Operation and Maintenance Data Electrical Systems 1.5.1 G

184 28 31 76 1 Preconstruction Submittals Qualified Fire Protection Engineer

(QFPE)

1.3.2 G

185 28 31 76 1 Preconstruction Submittals Fire alarm system designer 1.8.2.1 G

186 28 31 76 1 Preconstruction Submittals Supervisor 1.8.2.2 G

187 28 31 76 1 Preconstruction Submittals Technician 1.8.2.3 G

188 28 31 76 1 Preconstruction Submittals Installer 1.8.2.4 G

189 28 31 76 1 Preconstruction Submittals Test Technician 1.8.2.5 G

190 28 31 76 1 Preconstruction Submittals Fire Alarm System Site-Specific Software Acknowledgement

1.7 G

191 28 31 76 2 Shop Drawings Nameplates 1.8.1.3 G

192 28 31 76 2 Shop Drawings Instructions 2.2.4 G

193 28 31 76 2 Shop Drawings Wiring Diagrams 1.8.1.4 G

194 28 31 76 2 Shop Drawings System Layout 1.8.1.5 G

Acti vity

Transm ittal #

Specification Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval Needed

By

Material Needed

By Action Code

Date Of Action

Date FWD to APPR / Auth

Date RCD From

CONTR

Date FWD To Other Revwr

Date RCD From Other Reviewer

Action Code

Date Of Action

Mailed To CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES

APPROVING AUTHORITY

195 28 31 76 2 Shop Drawings Notification Appliances 1.8.1.6 G

196 28 31 76 2 Shop Drawings Initiating devices 1.8.1.7 G

197 28 31 76 2 Shop Drawings Amplifiers 1.8.1.8 G

198 28 31 76 2 Shop Drawings Battery Power 1.8.1.9 G

199 28 31 76 2 Shop Drawings Voltage Drop Calculations 1.8.1.10 G

200 28 31 76 3 Product Data Fire Alarm and Mass Notification Control Unit (FMCU)

2.3 G

201 28 31 76 3 Product Data Local Operating Console (LOC) 1.4.3 G

202 28 31 76 3 Product Data Amplifiers 1.8.1.8 G

203 28 31 76 3 Product Data Tone Generators 2.5 G

204 28 31 76 3 Product Data Digitalized voice generators 2.5 G

205 28 31 76 3 Product Data Manual Stations 2.7 G

206 28 31 76 3 Product Data Smoke Detectors 2.8 G

207 28 31 76 3 Product Data Duct Smoke Detectors 2.8.2 G

208 28 31 76 3 Product Data Addressable Interface Devices 2.9 G

209 28 31 76 3 Product Data Addressable Control Modules 2.1 G

210 28 31 76 3 Product Data Isolation Modules 2.11 G

211 28 31 76 3 Product Data Notification Appliances 1.8.1.6 G

212 28 31 76 3 Product Data Textual Display Signs 2.12.3 G

213 28 31 76 3 Product Data Batteries 2.14.1 G

214 28 31 76 3 Product Data Battery Chargers 2.14.2 G

215 28 31 76 3 Product Data Supplemental Notification Appliance Circuit Panels

2.14.1.1 G

216 28 31 76 3 Product Data Auxiliary Power Supply Panels 2.14.1.1 G

217 28 31 76 3 Product Data Surge Protective Devices 2.15 G

218 28 31 76 3 Product Data Alarm Wiring 2.15 G

219 28 31 76 3 Product Data Back Boxes and Conduit 3.3.4 G

220 28 31 76 3 Product Data Ceiling Bridges 3.2.8 G

221 28 31 76 3 Product Data Terminal Cabinets 3.3.2 G

222 28 31 76 3 Product Data Automatic Fire Alarm Transmitters 2.18 G

223 28 31 76 3 Product Data Radio Transmitter and Interface Panels 2.18.1 G

224 28 31 76 3 Product Data Document Storage Cabinet 3.13.3 G

225 28 31 76 6 Test Reports Test Procedures 3.9.1 G

226 28 31 76 7 Certificates Verification of Compliant Installation 3.9.2.1 G

227 28 31 76 7 Certificates Request for Government Final Test 3.9.2.2 G

228 28 31 76 10 Operation and Maintenance Data Operation and Maintenance (O&M) Instructions

3.11 G

229 28 31 76 10 Operation and Maintenance Data Instruction of Government Employees 3.12 G

230 28 31 76 11 Closeout Submittals As-Built Drawings 1.8.1.13

231 28 31 76 11 Closeout Submittals Spare Parts 1.10.1

232 32 11 20 3 Product Data Equipment and Tools 1.5 G

233 32 11 20 6 Test Reports Initial Tests 2.2.1 G

234 32 11 20 6 Test Reports In-Place Tests 3.8.1 G

235 32 13 13.06 3 Product Data Curing Materials 2.1.6

236 32 13 13.06 3 Product Data Epoxy Resin 2.1.9

237 32 13 13.06 3 Product Data Epoxy Resin 2.1.9

238 32 13 13.06 3 Product Data Cementitious Materials 2.1.1 G

239 32 13 13.06 3 Product Data Cementitious Materials 2.1.1 G

240 32 13 13.06 3 Product Data Dowel Bars 2.1.5.1

241 32 13 13.06 3 Product Data Joint Material

242 32 13 13.06 5 Design Data Mix Design Report 2.2.2 G

243 32 13 13.06 6 Test Reports Concrete Slump Tests

244 32 13 13.06 6 Test Reports Compressive Strength 3.7.2

245 32 13 13.06 6 Test Reports Air Content 3.7.3