W912QR26BA021_Specs_Vol2-0000.pdf
PDF 5 MB Posted
- Attached to
- Renovation/Repair of Bldg 27 at DSCC, OH
- Solicitation number
- W912QR26BA021
About this file
Summary of W912QR26BA021_Specs_Vol2-0000.pdf
This is a certified final design specification document (Volume 2 of 2, covering Divisions 21-33) for the wet pipe sprinkler system and general plumbing requirements for the DSSC DLA Repair Building 27 renovation project at Columbus, OH under solicitation W912QR26BA021. The project is a Design-Bid-Build contract with a 15-year maintenance disposition requirement following construction completion.
The fire protection specifications (Section 21 13 13) require a complete wet pipe sprinkler system compliant with NFPA 13 and NFPA 24, with hydraulic design based on a water flow test conducted July 23, 2025 (65 psi static, 45 psi residual, 3,470 gpm flow). The contractor must perform additional fire hydrant flow testing per NFPA 291 prior to shop drawing submission. All piping, fittings, valves, sprinklers, and components must be listed by UL, FM, or equivalent NRTL. Key submittal requirements include shop drawings, product data, hydraulic calculations, and test procedures, all requiring review and stamping by a NICET Level IV Qualified Fire Protection Engineer (QFPE). The system must include seismic bracing per NFPA 13 Section B (Seismic Design Category B), with minimum 4-inch underground piping at 3-foot minimum cover depth. Sprinklers must provide 100 percent coverage including electrical and mechanical equipment rooms, with pendent sprinklers featuring K-factor 5.6, upright sprinklers K-factor 8.0, and all sprinklers being quick-response type with appropriate finish treatments. Pre-Government and final Government functional performance testing are required, with training for fire department and operations personnel mandated over two separate 4-hour sessions. The plumbing specifications (Section 22 00 00) establish requirements for all potable water, hot water, and drainage systems, requiring materials certified for NSF/ANSI/CAN 61 compliance and lead-free applications. Water heaters must be Energy Star labeled with adjustable temperature controls, expansion tanks rated for 200°F and 150 psi, and thermostatic mixing valves per ASSE 1017 installed downstream of heaters. All piping installations must comply with ICC International Plumbing Code, with specific material standards for copper (ASTM B88), PVC/CPVC, steel (ASTM A53), and cast iron soil pipe per ASTM A888 or CISPI 301. Backflow prevention assemblies must conform to ASSE 1013 for reduced pressure principle devices, with forward flow testing required at system demand including all hose streams.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For DSSC DLA Repair Building 27 Columbus, OH
P2: 519087
Design-Bid-Build
Specifications - Vol 2 of 2(Div 21 - 33) Certified Final Design
06 August 2026
W912QR26BA021
RRS-A: 200A Disposition: Maintain for 15 yrs after construction.
W912QR26BA021_Specs_Vol2-0000
100% Certified Final
P2# 519087 - DSSC DLA Repair Building 27
Columbus, OH
PROJECT SPECIFICATIONS
Divisions covered by this seal
Divisions covered by this seal
00 22
01 23
Architectural
Ernesto Egoavil, R.A.
DLR Group
Mechanical, Plumbing
Michael Nickoson, P.E.
CMTA
Divisions covered by this seal
Divisions covered by this seal
03 26
05 28
Structural
Ryan Robley, P.E.
DLR Group
Electrical
Jeff Evers, P.E.
CMTA
Columbus, OH
Divisions covered by this seal
Fire Protection
Nicholas Stephenson
MES Group Inc.
SECTION 21 13 13
WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
08/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B16.1 (2020) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250
ASME B16.3 (2021) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.4 (2021) Gray Iron Threaded Fittings;
Classes 125 and 250
ASME B16.21 (2021) Nonmetallic Flat Gaskets for Pipe Flanges
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C104/A21.4 (2022) Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water
AWWA C110/A21.10 (2021) Ductile-Iron and Gray-Iron Fittings
AWWA C111/A21.11 (2023) Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings
AWWA C203 (2020) Coal-Tar Protective Coatings and Linings for Steel Water Pipelines - Enamel and Tape - Hot-Applied
ASTM INTERNATIONAL (ASTM)
ASTM A47/A47M (1999; R 2022; E 2022) Standard Specification for Ferritic Malleable Iron Castings
ASTM A53/A53M (2024) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A135/A135M (2021) Standard Specification for Electric-Resistance-Welded Steel Pipe
ASTM A153/A153M (2023) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
SECTION 21 13 13 Page 1
ASTM A183 (2014; R 2020) Standard Specification for Carbon Steel Track Bolts and Nuts
ASTM A536 (2024) Standard Specification for Ductile Iron Castings
FM GLOBAL (FM)
FM 1637 (2010) Flexible Sprinkler Hose with Threaded End Fittings
FM APP GUIDE (updated on-line) Approval Guide https://www.approvalguide.com/
INTELLIGENCE COMMUNITY STANDARD (ICS)
ICS 705-1 (2010) Physical and Technical Security Standard for Sensitive Compartmented Information Facilities
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS
INDUSTRY (MSS)
MSS SP-71 (2018) Gray Iron Swing Check Valves, Flanged and Threaded Ends
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 13 (2025; TIA 24-1; TIA 24-2; TIA 24-3)
Standard for the Installation of Sprinkler Systems
NFPA 13R (2025) Standard for the Installation of Sprinkler Systems in Low-Rise Residential Occupancies
NFPA 24 (2025) Standard for the Installation of Private Fire Service Mains and Their Appurtenances
NFPA 101 (2024) Life Safety Code
NFPA 291 (2025) Recommended Practice for Fire Flow Testing and Marking of Hydrants
NFPA 1963 (2019) Standard for Fire Hose Connections
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES
(NICET)
NICET 1014-7 (2012) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field Code 003) Subfield of Automatic Sprinkler System Layout
UL SOLUTIONS (UL)
UL 193 (2016) UL Standard for Safety Alarm Valves
SECTION 21 13 13 Page 2 for Fire-Protection Service
UL 199 (2020) UL Standard for Safety Automatic Sprinklers for Fire-Protection Service
UL 262 (2004; Reprint Jul 2023) Gate Valves for Fire-Protection Service
UL 312 (2022) UL Standard for Safety Check Valves for Fire-Protection Service
UL 405 (2013; Bul. 2020) UL Standard for Safety Fire Department Connection Devices
UL 668 (2004; Reprint Oct 2021) UL Standard for Safety Hose Valves for Fire-Protection Service
UL 2443 (2015; Reprint May 2020) UL Standard for Safety Flexible Sprinkler Hose with Fitings for Fire Protection Service
UL Fire Prot Dir UL Product IQ (updated online) at https://productiq.ulprospector.com/en
1.2 SYSTEM DESCRIPTION
Provide wet pipe sprinkler system(s) in areas indicated on the drawings .
Except as modified herein, the system must meet the requirements of NFPA 13 .
Pipe sizes which are not indicated on the Contract drawings must be determined by hydraulic calculations.
1.2.1 Hydraulic Design
1.2.1.1 Basis for Calculations
A waterflow test was performed on 7-23-2025 at 3990 E Broad St and resulted in a static pressure of 65 psi with a residual pressure of 45 psi while flowing 3470 gpm. Perform a fire hydrant flow test prior to shop drawing submittal in accordance with NFPA 291 . Results must include hydrant elevations relative to the building and hydrant number/identifiers for the tested hydrants, including which were flowed, which had a gauge.
This information must be presented in a tabular form if multiple hydrants were flowed. The results must be included with the hydraulic calculations. Hydraulic calculations must be based on flow test noted in this paragraph, unless approved by Contracting Officer. Hydraulic calculations must be based upon the Hazen-Williams formula with a "C" value noted in NFPA 13 for piping, ..
1.2.1.2 Hydraulic Calculations
<OLG>
<OLI>Water supply curves and system requirements must be plotted on semi-logarithmic graph (N^1.85) paper so as to present a summary of the complete hydraulic calculation.</OLI>
<OLI>Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, minimum discharge pressures and minimum flows. Elevations of hydraulic reference points (nodes) must be indicated.</OLI>
SECTION 21 13 13 Page 3
<OLI>Documentation must identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe.</OLI>
<OLI>Where the sprinkler system is supplied by interconnected risers, the sprinkler system must be hydraulically calculated using the hydraulically most demanding single riser. The calculations must not assume the simultaneous use of more than one riser.</OLI>
<OLI>All calculations must include the backflow preventer manufacturer's stated friction loss at the design flow or 8 psi for double check backflow preventer, whichever is greater.</OLI>
<OLI>All calculations must be performed back to the actual location of the flow test, taking into account the direction of flow in the service main at the test location.</OLI>
<OLI>For gridded systems, calculations must show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. A flow diagram indicating the quantity and direction of flows must be included.</OLI>
</OLG>
1.2.1.3 Design Criteria
Hydraulically design the system to discharge a minimum density as indicated on the drawings. Hydraulic calculations must be in accordance with the Area/Density Method of NFPA 13 . Add an allowance for exterior hose streams of 250 gpm to the sprinkler system demand at the fire hydrant shown on the drawings closest to the point where the water service enters the building . An allowance for interior hose stations of 100 gpm must be added to the sprinkler system demand.
1.2.2 Sprinkler Coverage
Sprinklers must be uniformly spaced on branch lines. Provide coverage throughout 100 percent of the area noted on the Contract drawings. This includes, but is not limited to, telephone rooms, electrical equipment rooms (regardless of the fire resistance rating of the enclosure), boiler rooms, switchgear rooms, transformer rooms, attached electrical vaults and other electrical and mechanical spaces. Coverage per sprinkler must be in accordance with NFPA 13 . Provide sprinklers below all obstructions in accordance with NFPA 13 . Exceptions are as follows:
<OLG>
<OLI>Sprinklers may be omitted from small rooms which are exempted for specific occupancies in accordance with NFPA 101 .</OLI>
<OLI>Facilities that are designed in accordance with NFPA 13R.</OLI>
</OLG>
1.2.3 Qualified Fire Protection Engineer (QFPE)
An individual who is a licensed professional engineer (P.E.) who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveying (NCEES) and has relevant fire protection engineering experience. Services of the QFPE must include:
<OLG>
<OLI>Reviewing SD-02, SD-03, and SD-05 submittal packages for completeness
SECTION 21 13 13 Page 4 and compliance with the provisions of this specification. Working (shop) drawings and calculations must be prepared by, or prepared under the immediate supervision of, the QFPE. The QFPE must affix their professional engineering stamp with signature to the shop drawings, calculations, and material data sheets, indicating approval prior to submitting the shop drawings to the DFPE.</OLI>
<OLI>Provide a letter documenting that the SD-02, SD-03, and SD-05 submittal package has been reviewed and noting all outstanding comments.</OLI>
<OLI>Performing in-progress construction surveillance prior to installation of ceilings (rough-in inspection).</OLI>
<OLI>Witnessing pre-Government and final Government functional performance testing and performing a final installation review.</OLI>
<OLI>Signing applicable certificates under SD-07.</OLI>
</OLG>
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Partial submittals and submittals not fully complying with NFPA 13 and this specification section must be returned disapproved without review.
SD-02, SD-03 and SD-05 must be submitted simultaneously.
Shop drawings (SD-02), product data (SD-03) and calculations (SD-05) must be prepared by the designer and combined and submitted as one complete package. The QFPE must review the SD-02/SD-03/SD-05 submittal package for completeness and compliance with the Contract provisions prior to submission to the Government. The QFPE must provide a Letter of Confirmation that they have reviewed the submittal package for compliance with the contract provisions. This letter must include their professional engineer stamp and signature. Partial submittals and submittals not reviewed by the QFPE must be returned disapproved without review.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Qualified Fire Protection Engineer (QFPE) ; G, Sprinkler System Designer ; G, Sprinkler System Installer ; G, SD-02 Shop Drawings
Shop Drawing ; G, SD-03 Product Data
Pipe ; G, Fittings ; G, SECTION 21 13 13 Page 5
Valves , including gate, check, butterfly, and globe; G, Alarm Valves ; G, Relief Valves ; G, Sprinklers ; G, Pipe Hangers and Supports ; G, Sprinkler Alarm Switch ; G, Valve Supervisory (Tamper) Switch ; G, Fire Department Connection ; G, Backflow Prevention Assembly ; G, Air Vent ; G, Hose Valve ; G, Nameplates ; G, SD-05 Design Data
Seismic Bracing ; G, Load calculations for sizing of seismic bracing
Hydraulic Calculations ; G, SD-06 Test Reports
Test Procedures ; G, SD-07 Certificates
Verification of Compliant Installation ; G, Request for Government Final Test ; G, SD-10 Operation and Maintenance Data
Operating and Maintenance (O&M) Instructions ; G, Spare Parts Data; G, SD-11 Closeout Submittals
As-built drawings
1.4 QUALITY ASSURANCE
1.4.1 Preconstruction Submittals
Within 36 days of contract award but no less than 14 days prior to commencing work on site, the prime Contractor must submit the following for review and approval. SD-02, SD-03 and SD-05 submittals received prior to the review and approval of the qualifications will be returned Disapproved Without Review.
SECTION 21 13 13 Page 6
1.4.1.1 Shop Drawing
4 copies of the shop drawings, no later than 28 days prior to the start of system installation. Working drawings conforming to the requirements prescribed in NFPA 13 and must be no smaller than the Contract Drawings.
Each set of drawings must include the following:
<OLG>
<OLI>A descriptive index with drawings listed in sequence by number. A legend sheet identifying device symbols, nomenclature, and conventions used in the package.</OLI>
<OLI>Floor plans drawn to a scale not less than 1/8-inch equals 1-foot clearly showing locations of devices, equipment, risers, and other details required to clearly describe the proposed arrangement.</OLI>
<OLI>Actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; from walls to branch lines; from sprinkler feed mains, cross mains and branch lines to finished floor and roof or ceiling. A detail must show the dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.</OLI>
<OLI>Longitudinal and transverse building sections showing typical branch line and cross main pipe routing, elevation of each typical sprinkler above finished floor and elevation of "cloud" or false ceilings in relation to the building ceilings.</OLI>
<OLI>Plan and elevation views which establish that the equipment will fit the allotted spaces with clearance for installation and maintenance.</OLI>
<OLI>Riser layout drawings drawn to a scale of not less than 1/2-inch equals 1-foot to show details of each system component, clearances between each other and from other equipment and construction in the room.</OLI>
<OLI>Details of each type of riser assembly, pipe hanger, sway bracing for earthquake protection, and restraint of underground water main at point-of-entry into the building, and electrical devices and interconnecting wiring. The dimension from the edge of vertical piping to the nearest adjacent wall(s) must be indicated on the drawings when vertical piping is located in stairs or other portions of the means of egress.</OLI>
<OLI>Details of each type of pipe hanger, seismic bracing/restraint and related components.</OLI>
1.4.1.2 Product Data
4 copies of annotated catalog data to show the specific model, type, and size of each item. Catalog cuts must also indicate the NRTL listing. The data must be highlighted to show model, size, options, and other pertinent information, that are intended for consideration. Data must be adequate to demonstrate compliance with all contract requirements. Product data for all equipment must be combined into a single submittal.
1.4.1.3 Hydraulic Calculations
Calculations must be as outlined in NFPA 13 except that calculations must be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings.
Calculations must include isometric diagram indicating hydraulic nodes and
SECTION 21 13 13 Page 7 pipe segments.
1.4.1.4 Operating and Maintenance (O&M) Instructions
Submit in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA as supplemented and modified by this specification section.
Provide six manuals and one pdf version on electronic media. The manuals must include the manufacturer's name, model number, parts list, list of parts and tools that should be kept in stock by the owner for routine maintenance, troubleshooting guide, and recommended service organization (including address and telephone number) for each item of equipment.
Submit spare parts data for each different item of material and equipment specified. The data must include a complete list of parts and supplies, and a list of parts recommended by the manufacturer to be replaced after 1-year and 3 years of service. Include a list of special tools and test equipment required for maintenance and testing of the products supplied.
1.4.2 Qualifications
1.4.2.1 Sprinkler System Designer
The sprinkler system designer must be certified as a Level IV Technician by National Institute for Certification in Engineering Technologies (NICET) in the Water-Based Systems Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 .
1.4.2.2 Sprinkler System Installer
The sprinkler system installer must be regularly engaged in the installation of the type and complexity of system specified in the contract documents, and must have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.
1.4.3 Regulatory Requirements
Equipment and material must be listed or approved. Listed or approved, as used in this Section, means listed, labeled or approved by a Nationally Recognized Testing Laboratory (NRTL) such as UL Fire Prot Dir or FM APP GUIDE. The omission of these terms under the description of an item or equipment described must not be construed as waiving this requirement. All listings or approvals by testing laboratories must be from an existing ANSI or UL published standard. The recommended practices stated in the manufacturer's literature or documentation are mandatory requirements.
1.5 DELIVERY, STORAGE, AND HANDLING
Protect all equipment delivered and placed in storage from the weather, excessive humidity and temperature variations, dirt and dust, or other contaminants. All pipes must be either capped or plugged until installed.
1.6 EXTRA MATERIALS
Spare sprinklers and wrench(es) must be provided as spare parts in accordance with NFPA 13 .
SECTION 21 13 13 Page 8
PART 2 PRODUCTS
2.1 MATERIALS AND EQUIPMENT
2.1.1 Standard Products
Provide materials, equipment, and devices listed for fire protection service when so required by NFPA 13 or this specification. Select material from one manufacturer, where possible, and not a combination of manufacturers, for a classification of material. Material and equipment must be standard products of a manufacturer regularly engaged in the manufacture of the products for at least 2 years prior to bid.
2.1.2 Nameplates
Major components of equipment must have the manufacturer's name, address, type or style, model or serial number, catalog number, date of installation, installing Contractor's name and address, and the contract number provided on a new name plate permanently affixed to the item or equipment. Nameplates must be etched metal or plastic, permanently attached by screws to control units, panels or adjacent walls.
2.1.3 Identification and Marking
Pipe and fitting markings must include name or identifying symbol of manufacturer and nominal size. Pipe must be marked with ASTM designation. Valves and equipment markings must have name or identifying symbol of manufacturer, specific model number, nominal size, name of device, arrow indicating direction of flow, and position of installation (horizontal or vertical), except if valve can be installed in either position. Markings must be included on the body casting or on an etched or stamped metal nameplate permanently on the valve or cover plate.
2.1.4 Pressure Ratings
Valves, fittings, couplings, alarm switches, and similar devices must be rated for the maximum working pressures that can be experienced in the system, but in no case less than 175 psi.
2.2 UNDERGROUND PIPING COMPONENTS
2.2.1 Pipe
Pipe must comply with NFPA 24 . Minimum pipe size is 4 inches. Piping more than 5 feet outside the building walls must comply with Section 33 11 00 WATER UTILITY DISTRIBUTION PIPING. A continuous section of welded stainless steel fire water service piping from a point outside the building perimeter to a flanged fitting at least 1-foot above the finished floor within the building is acceptable.
2.2.2 Fittings and Gaskets
Fittings must be ductile-iron conforming to AWWA C110/A21.10 with cement mortar lining conforming to AWWA C104/A21.4 . Gaskets must be suitable in design and size for the pipe with which such gaskets are to be used.
Gaskets for ductile-iron pipe joints must conform to AWWA C111/A21.11 .
SECTION 21 13 13 Page 9
2.2.3 Gate Valve
Installation must comply with NFPA 24 . Gate valves for use with indicator post must conform to UL 262 .
2.2.4 Valve Boxes
Except where indicator posts are provided, for each buried valve, provide a cast-iron, ductile-iron, or plastic valve box of a suitable size.
Plastic boxes must be constructed of acrylonitrile-butadiene-styrene (ABS) or inorganic fiber-reinforced black polyolefin. Provide cast-iron, ductile-iron, or plastic cover for valve box with the word "WATER" cast on the cover. The minimum box shaft diameter must be 5.25 inches. Coat cast-iron and ductile-iron boxes with bituminous paint applied to a minimum dry-film thickness of 10 mils.
2.2.5 Buried Utility Warning and Identification Tape
Provide detectable aluminum foil plastic backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape must be detectable by an electronic detection instrument. Provide tape, 3 inches minimum width, color coded for the utility involved with warning and identification imprinted in bold block letters continuously and repeatedly over the entire tape length.
Warning and identification must read "CAUTION BURIED WATER PIPING BELOW" or similar wording. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material.
2.3 ABOVEGROUND PIPING COMPONENTS
2.3.1 Steel Piping Components
2.3.1.1 Steel Pipe
Except as modified herein, steel pipe must be black as permitted by NFPA 13 and conform to the applicable provisions of ASTM A53/A53M, ASTM A135/A135M or ASTM A153/A153M .
Steel pipe must be minimum Schedule 40 for sizes 2 inches and less; and minimum Schedule 10 for sizes larger than 2 inches. Steel piping with wall thickness less than Schedule 40 must not be threaded. Grooved pipe must be cut-grooved.
2.3.1.2 Fittings
Fittings must be welded, threaded, or grooved-end type. Threaded fittings must be cast-iron conforming to ASME B16.4 , malleable-iron conforming to ASME B16.3 or ductile-iron conforming to ASTM A536. Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe, steel press fittings and field welded fittings are not permitted. Fittings, mechanical couplings, and rubber gaskets must be supplied by the same manufacturer. Threaded fittings must use Teflon tape or manufacturer's approved joint compound. Saddle tees using rubber gasketed fittings are permitted only when connecting to existing piping for additions or modifications. Saddle tees must use a connection method that completely wraps around the pipe. Reducing couplings are not permitted except as allowed by NFPA 13 .
SECTION 21 13 13 Page 10
2.3.1.3 Grooved Mechanical Joints and Fittings
Joints and fittings must be designed for not less than 175 psi service and the product of the same manufacturer. Field welded fittings must not be used. Fitting and coupling housing must be malleable-iron conforming to ASTM A47/A47M, Grade 32510; ductile-iron conforming to ASTM A536, Grade 65-45-12. Rubber gasketed grooved-end pipe and fittings with mechanical couplings are permitted in pipe sizes 2 inches and larger. Gasket must be the flush type that fills the entire cavity between the fitting and the pipe. Nuts and bolts must be heat-treated steel conforming to ASTM A183 and must be cadmium-plated or zinc-electroplated.
2.3.1.4 Flanges
Flanges must conform to NFPA 13 and ASME B16.1 . Gaskets must be non-asbestos compressed material in accordance with ASME B16.21 , 1/16-inch thick, and full face or self-centering flat ring type.
2.3.2 Flexible Sprinkler Hose
Flexible sprinkler hose must comply with UL 2443 and FM 1637 .
2.3.3 Pipe Hangers and Supports
Provide galvanized pipe hangers, supports and seismic bracing in accordance with NFPA 13 . Design and install seismic protection in accordance with the requirements of NFPA 13 section titled "Protection of Piping Against Damage Where Subject to Earthquakes for Seismic Design Category "B".
2.3.4 Valves
Provide valves of types approved for fire service. Valves must open by counterclockwise rotation.
2.3.4.1 Control Valve
Manually operated sprinkler control/gate valve must be outside stem and yoke (OS&Y) type or butterfly type as indicated on the drawings and must be listed.
2.3.4.2 Check Valves
Check valves must comply with UL 312 . Check valves 4 inches and larger must be of the swing type, have a clear waterway and meet the requirements of MSS SP-71 , for Type 3 or 4. Inspection plate must be provided on valves larger than 6 inches.
2.3.4.3 Hose Valve
Valve must comply with UL 668 .
2.3.5 Alarm Valves
Provide variable pressure type alarm check valve, standard trim piping, pressure gauges, bypass, retarding chamber, testing valves, and main drain, and other components as required for a fully operational system.
Alarm valves must comply with UL 193 .
SECTION 21 13 13 Page 11
2.4 ALARM INITIATING AND SUPERVISORY DEVICES
2.4.1 Sprinkler Alarm Switch
Vane or pressure-type flow switch(es). Connection of switch must be by the fire alarm installer. Vane type alarm actuating devices must have mechanical diaphragm controlled retard device adjustable from 10 to 60 seconds and must instantly recycle.
2.4.2 Valve Supervisory (Tamper) Switch
Switch must be integral to the control valve or suitable for mounting to the type of control valve to be supervised open. The switch must be tamper resistant and contain SPDT (Form C) contacts arranged to transfer upon removal of the housing cover or closure of the valve of more than two rotations of the valve stem.
2.5 FIRE DEPARTMENT CONNECTION
Fire department connection must be projecting type with cast-brass body, matching wall escutcheon lettered "Auto Spkr" with a chromium-plated finish. The connection must have individual self-closing clappers, caps with drip drains and chains. Female inlets must have 2 1/2-inch diameter American National Fire Hose Connection Screw Threads (NH) per NFPA 1963 .
Comply with UL 405 .
2.6 SPRINKLERS
Sprinklers must comply with UL 199 and NFPA 13 . Sprinklers with internal O-rings are not acceptable. Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters must have temperature classification in accordance with NFPA 13 . Extended coverage sprinklers are permitted for loading docks, residential occupancies and high-piled storage applications only.
2.6.1 Pendent Sprinkler
Pendent sprinkler must be quick-response type with nominal K-factor of 5.6.
Pendent sprinklers must have a polished chrome finish. Assembly must include an integral escutcheon.
2.6.2 Upright Sprinkler
Upright sprinkler must be brass quick-response type and have a nominal K-factor of 8.0.
2.6.3 Sidewall Sprinkler
Sidewall sprinkler must be the quick-response type. Sidewall sprinkler must have a nominal K-factor of 8.0. Sidewall sprinkler must have a polished-chrome finish.
2.6.4 Concealed Sprinkler
Concealed sprinkler must be chrome-plated quick-response type and have a nominal K-factor of 5.6. Coverplate must be chrome.
SECTION 21 13 13 Page 12
2.7 ACCESSORIES
2.7.1 Sprinkler Cabinet
Provide spare sprinklers in accordance with NFPA 13 and must be placed in a suitable metal or plastic cabinet of sufficient size to accommodate all the spare sprinklers and wrenches in designated locations. Spare sprinklers must be representative of, and in proportion to, the number of each type and temperature rating of the sprinklers installed as required by NFPA 13 . At least one wrench of each type required must be provided.
2.7.2 Pendent Sprinkler Escutcheon
Escutcheon must be one-piece metallic type with a depth of less than 3/4-inch and suitable for installation on pendent sprinklers. The escutcheon must have a factory finish that matches the pendent sprinkler.
2.7.3 Pipe Escutcheon
Provide split hinge metal plates for piping entering walls, floors, and ceilings in exposed spaces. Provide polished stainless steel plates or chromium-plated finish on copper alloy plates in finished spaces. Provide paint finish on metal plates in unfinished spaces.
2.7.4 Sprinkler Guard
Listed guard must be a steel wire cage designed to encase the sprinkler and protect it from mechanical damage. Guards must be provided on sprinklers located as indicated.
2.7.5 Relief Valve
Relief valves must be listed and installed at the riser in accordance with
NFPA 13 .
2.7.6 Air Vent
Air vents must be of the automatic type and piped to drain to the building exterior.
2.7.7 Identification Sign
Valve identification sign must be minimum 6 inches wide by 2 inches high with enamel baked finish on minimum 18 gage steel or 0.024-inch aluminum with red letters on a white background or white letters on red background. Wording of sign must include, but not be limited to "main drain", "auxiliary drain", "inspector's test", "alarm test", "alarm line", and similar wording as required to identify operational components. Where there is more than one sprinkler system, signage must include specific details as to the respective system.
PART 3 EXECUTION
3.1 VERIFYING ACTUAL FIELD CONDITIONS
Before commencing work, examine all adjoining work on which the contractor's work that is dependent for perfect workmanship according to the intent of this specification section, and report to the Contracting Officer's Representative a condition that prevents performance of first
SECTION 21 13 13 Page 13 class work. No "waiver of responsibility" for incomplete, inadequate or defective adjoining work will be considered unless notice has been filed before submittal of a proposal.
3.2 INSTALLATION
The installation must be in accordance with the applicable provisions of NFPA 13 , NFPA 24 and publications referenced therein. Locate sprinklers in a consistent pattern with ceiling grid, lights, and air supply diffusers. Install sprinkler system over and under ducts, piping and platforms when such equipment can negatively affect or disrupt the sprinkler discharge pattern and coverage.
<OLG>
<OLI>Piping offsets, fittings, and other accessories required must be furnished to provide a complete installation and to eliminate interference with other construction.</OLI>
<OLI>Wherever the contractor's work interconnects with work of other trades the Contractor must coordinate with other Contractors to insure all Contractors have the information necessary so that they may properly install all necessary connections and equipment. Identify all work items needing access (dampers and similar equipment) that are concealed above hung ceilings by permanent color coded pins/tabs in the ceiling directly below the item.</OLI>
<OLI>Provide required supports and hangers for piping, conduit, and equipment so that loading will not exceed allowable loadings of structure.
Submittal of a bid must be a deemed representation that the contractor submitting such bid has ascertained allowable loadings and has included in his estimates the costs associated in furnishing required supports.</OLI>
</OLG>
3.2.1 Waste Removal
At the conclusion of each day's work, clean up and stockpile on site all waste, debris, and trash which may have accumulated during the day as a result of work by the contractor and of his presence on the job.
Sidewalks and streets adjoining the property must be kept broom clean and free of waste, debris, trash and obstructions caused by work of the contractor, which will affect the condition and safety of streets, walks, utilities, and property.
3.3 UNDERGROUND PIPING INSTALLATION
The fire protection water main must be laid, and joints anchored, in accordance with NFPA 24 . Minimum depth of cover must be 3 feet or the frost line, whichever is deeper. The supply line must terminate inside the building with a flanged piece, the bottom of which must be set not less than 1-foot above the finished floor. A blind flange must be installed temporarily on top of the flanged piece to prevent the entrance of foreign matter into the supply line. A concrete thrust block must be provided at the elbow where the pipe turns up toward the floor. In addition, joints must be anchored in accordance with NFPA 24 . Buried steel components must be provided with a corrosion protective coating in accordance with AWWA C203. Piping more than 5 feet outside the building walls must meet the requirements of Section 33 11 00 WATER UTILITY
DISTRIBUTION PIPING.
SECTION 21 13 13 Page 14
3.4 ABOVEGROUND PIPING INSTALLATION
The methods of fabrication and installation of the aboveground piping must fully comply with the requirements and recommended practices of NFPA 13 and this specification section.
3.4.1 Protection of Piping Against Earthquake Damage
Seismic restraint is required.
3.4.2 Piping in Exposed Areas
Install exposed piping without diminishing exit access widths, corridors or equipment access. Exposed horizontal piping, including drain piping, must be installed to provide maximum headroom.
3.4.3 Piping in Finished Areas
In areas with suspended or dropped ceilings and in areas with concealed spaces above the ceiling, piping must be concealed above ceilings. Piping must be inspected, hydrostatically tested and approved before being concealed. Risers and similar vertical runs of piping in finished areas must be concealed.
3.4.4 Pendent Sprinklers
<OLG>
<OLI>Drop nipples to pendent sprinklers must consist of minimum 1-inch pipe with a reducing coupling into which the sprinkler must be threaded.</OLI>
<OLI>Where sprinklers are installed below suspended or dropped ceilings, drop nipples must be cut such that sprinkler ceiling plates or escutcheons are of a uniform depth throughout the finished space. The outlet of the reducing coupling must not extend below the underside of the ceiling.</OLI>
<OLI>Recessed pendent sprinklers must be installed such that the distance from the sprinkler deflector to the underside of the ceiling must not exceed the manufacturer's listed range and must be of uniform depth throughout the finished area.</OLI>
<OLI>Pendent sprinklers in suspended ceilings must be located in the center of the tile (plus or minus 2 inches).</OLI>
<OLI>Dry pendent sprinklers must be of the required length to permit the sprinkler to be threaded directly into a branch line tee.</OLI>
<OLI>Where the maximum static or flowing pressure, whichever is greater at the sprinkler, applied other than through the fire department connection, exceeds 100 psi and a branch line above the ceiling supplies sprinklers in a pendent position below the ceiling, the cumulative horizontal length of an unsupported armover to a sprinkler or sprinkler drop must not exceed 12 inches for steel pipe and 6 inches for copper tube.</OLI>
</OLG>
3.4.5 Upright Sprinklers
Riser nipples or "sprigs" to upright sprinklers must contain no fittings between the branch line tee and the reducing coupling at the sprinkler.
SECTION 21 13 13 Page 15
3.4.6 Pipe Joints
Pipe joints must conform to NFPA 13 , except as modified herein. Not more than four threads must show after joint is made up. Welded joints will be permitted, only if welding operations are performed as required by NFPA 13 at the Contractor's fabrication shop, not at the project construction site. Flanged joints must be provided where indicated or required by NFPA 13 . Grooved pipe and fittings must be prepared in accordance with the manufacturer's latest published specification according to pipe material, wall thickness and size. Grooved couplings, fittings and grooving tools must be products of the same manufacturer. For copper tubing, pipe and groove dimensions must comply with the tolerances specified by the coupling manufacturer. The diameter of grooves made in the field must be measured using a "go/no-go" gauge, vernier or dial caliper, narrow-land micrometer, or other method specifically approved by the coupling manufacturer for the intended application. Groove width and dimension of groove from end of pipe must be measured and recorded for each change in grooving tool setup to verify compliance with coupling manufacturer's tolerances.
3.4.7 Reducers
Reductions in pipe sizes must be made with one-piece tapered reducing fittings. When standard fittings of the required size are not manufactured, single bushings of the face or hex type will be permitted.
Where used, face bushings must be installed with the outer face flush with the face of the fitting opening being reduced. Bushings cannot be used in elbow fittings, in more than one outlet of a tee, in more than two outlets of a cross, or where the reduction in size is less than 1/2-inch.
3.4.8 Pipe Penetrations
<OLG>
<OLI>Cutting structural members for passage of pipes or for pipe-hanger fastenings will not be permitted. Pipes that must penetrate concrete or masonry walls or concrete floors must be core-drilled and provided with pipe sleeves. Each sleeve must be Schedule 40 galvanized steel, ductile-iron or cast-iron pipe and extend through its respective wall or floor and be cut flush with each wall surface. Sleeves must provide required clearance between the pipe and the sleeve per NFPA 13 . The space between the sleeve and the pipe must be firmly packed with mineral wool insulation.</OLI>
<OLI>Where pipes and sleeves penetrate fire walls, fire partitions, or floors, pipes/sleeves must be firestopped in accordance with Section 07 84 00
FIRESTOPPING.</OLI>
<OLI>In penetrations that are not fire-rated or not a floor penetration, the space between the sleeve and the pipe must be sealed at both ends with plastic waterproof cement that will dry to a firm but pliable mass or with a mechanically adjustable segmented elastomer seal.</OLI>
<OLI>All penetrations through the boundary of rooms/areas identified as secure space area must meet ICS 705-1 .</OLI>
</OLG>
3.4.9 Escutcheons
Escutcheons must be provided for pipe penetration in finished areas of ceilings, floors and walls. Escutcheons must be securely fastened to the pipe at surfaces through which piping passes.
SECTION 21 13 13 Page 16
3.4.10 Drains
<OLG>
<OLI>Main drain piping must be provided to discharge at a safe point outside the building, no more than 2 feet above finished grade. Provide a concrete splash block at drain outlet. Discharge to the exterior must not interfere with exiting from the facility. Water discharge or runoff must not cross the path of egress from the building.</OLI>
<OLI>Auxiliary drains must be provided as required by NFPA 13 . Auxiliary drains are permitted to discharge to a floor drain if the drain is sized to accommodate full flow (min 40 gpm). Discharge to service sinks or similar plumbing fixtures is not permitted.</OLI>
</OLG>
3.4.11 Installation of Fire Department Connection
Connection must be mounted on the exterior wall approximately 3 feet above finished grade. The piping between the connection and the check valve must be provided with an automatic drip in accordance with NFPA 13 and piped to drain to the outside or a floor drain within the same room.
3.4.12 Identification Signs
Signs must be affixed to each control valve, inspector test valve, main drain, auxiliary drain, test valve, and similar valves as appropriate or as required by NFPA 13 . Main drain test results must be etched into main drain identification sign. Hydraulic design data must be etched into the nameplates and permanently affixed to each sprinkler riser as specified in NFPA 13 . Provide labeling on the surfaces of all feed and cross mains to show the pipe function (e.g., "Sprinkler System", "Fire Department Connection", "Standpipe") and normal valve position (e.g. "Normally Open", "Normally Closed"). For pipe sizes 4-inch and larger provide white painted stenciled letters and arrows, a minimum of 2 inches in height and visible from at least two sides when viewed from the floor. For pipe sizes less than 4-inch, provide white painted stenciled letters and arrows, a minimum of 0.75-inch in height and visible from the floor.
3.5 ELECTRICAL
Except as modified herein, electric equipment and wiring must be in accordance with Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM. Alarm signal wiring connected to the building fire alarm control system must be by the fire alarm installer.
3.6 PAINTING
Color code mark piping red.
3.7 FIELD QUALITY CONTROL
3.7.1 Test Procedures
Submit detailed test procedures, prepared and signed by the NICET Level III or IV Fire Sprinkler Technician, and the representative of the installing company, and reviewed by the QFPE days prior to performing system tests.
Detailed test procedures must list all components of the installed system. Test procedures must include sequence of testing, time estimate for each test, and sample test data forms. The test data forms must be in a check-off format (pass/fail with space to add applicable test data;
similar to the forms in NFPA 13 ). The test procedures and accompanying
SECTION 21 13 13 Page 17 test data forms must be used for the pre-Government testing and the Government final testing.
<OLG>
<OLI>Provide space to identify the date and time of each test. Provide space to identify the names and signatures of the individuals conducting and witnessing each test.</OLI>
</OLG>
3.7.2 Pre-Government Testing
3.7.2.1 Verification of Compliant Installation
Conduct inspections and tests to ensure that equipment is functioning properly. Tests must meet the requirements of paragraph entitled "Minimum System Tests" and "System Acceptance" as noted in NFPA 13 . The Contractor and QFPE must be in attendance at the pre-Government testing to make necessary adjustments. After inspection and testing is complete, provide a signed Verification of Compliant Installation letter by the QFPE that the installation is complete, compliant with the specification and fully operable. The letter must include the names and titles of the witnesses to the pre-Government tests. Provide all completion documentation as required by NFPA 13 and the test reports noted below.
<OLG>
<OLI> NFPA 13 Aboveground Material and Test Certificate</OLI>
<OLI> NFPA 13 Underground Material and Test Certificate</OLI>
</OLG>
3.7.2.2 Request for Government Final Test
When the verification of compliant installation has been completed, submit a formal request for Government final test to the Designated Fire Protection Engineer (DFPE). Government final testing will not be scheduled until the DFPE has received copies of the request for Government final testing and Verification of Compliant Installation letter with all required reports. Government final testing will not be performed until after the connections to the building fire alarm system have been completed and tested to confirm communications are fully functional.
Submit request for test at least 15 calendar days prior to the requested test date.
3.7.3 Correction of Deficiencies
If equipment was found to be defective or non-compliant with contract requirements, perform corrective actions and repeat the tests. Tests must be conducted and repeated if necessary until the system has been demonstrated to comply with all contract requirements.
3.7.4 Government Final Tests
The tests must be performed in accordance with the approved test procedures in the presence of the DFPE. Furnish instruments and personnel required for the tests. The following must be provided at the job site for Government Final Testing:
<OLG>
<OLI>The manufacturer's technical representative.</OLI>
<OLI>b. The contractor's Qualified Fire Protection Engineer (QFPE).</OLI>
<OLI>Marked-up red line drawings of the system as actually installed.</OLI>
</OLG>
SECTION 21 13 13 Page 18
Government Final Tests will be witnessed by the DOR, Designated Fire Protection Engineer. At this time, all required tests noted in the paragraph "Minimum System Tests" must be repeated at their discretion.
3.8 MINIMUM SYSTEM TESTS
The system, including the underground water mains, and the aboveground piping and system components, must be tested to ensure that equipment and components function as intended. The underground and aboveground interior piping systems and attached appurtenances subjected to system working pressure must be tested in accordance with NFPA 13 and NFPA 24 .
3.8.1 Underground Piping
3.8.1.1 Flushing
Underground piping must be flushed at a minimum of 10 fps in accordance with NFPA 24 .
3.8.1.2 Hydrostatic Test
New underground piping must be hydrostatically tested in accordance with
NFPA 24 .
3.8.2 Aboveground Piping
3.8.2.1 Hydrostatic Test
Aboveground piping must be hydrostatically tested in accordance with NFPA 13 . There must be no drop in gauge pressure or visible leakage when the system is subjected to the hydrostatic test. The test pressure must be read from a gauge located at the low elevation point of the system or portion being tested.
3.8.2.2 Backflow Prevention Assembly Forward Flow Test
Each backflow prevention assembly must be tested at system flow demand, including all applicable hose streams, as specified in NFPA 13 . The Contractor must provide all equipment and instruments necessary to conduct a complete forward flow test, including 2.5-inch diameter hoses, playpipe nozzles or flow diffusers, calibrated pressure gauges, and pitot tube gauge. The Contractor must provide all necessary supports to safely secure hoses and nozzles during the test. At the system demand flow, the pressure readings and pressure drop (friction loss) across the assembly must be recorded. A metal placard must be provided on the backflow prevention assembly that lists the pressure readings both upstream and downstream of the assembly, total pressure drop, and the system test flow rate determined during the preliminary testing. The pressure drop must be compared to the manufacturer's data and the readings observed during the final inspections and tests.
3.8.3 Main Drain Flow Test
Following flushing of the underground piping, a main drain test must be made to verify the adequacy of the water supply. Static and residual pressures must be recorded on the certificate specified in paragraph
SUBMITTALS.
SECTION 21 13 13 Page 19
3.9 SYSTEM ACCEPTANCE
Following acceptance of the system, as-built drawings and O&M manuals must be delivered to the Contracting Officer for review and acceptance. Submit six sets of detailed as-built drawings. The drawings must show the system as installed, including deviations from both the project drawings and the approved shop drawings. These drawings must be submitted within two weeks after the final acceptance test of the system. At least one set of as-built (marked-up) drawings must be provided at the time of, or prior to the final acceptance test.
<OLG>
<OLI>Provide one set of full size paper as-built drawings and schematics.
The drawings must be prepared electronically and sized no less than the contract drawings.
<OLI>Provide operating and maintenance (O&M) instructions .</OLI>
</OLG>
3.10 ONSITE TRAINING
Conduct a training course for the responding fire department and operating and maintenance personnel as designated by the Contracting Officer.
Training must be performed on two separate days (to accommodate different shifts of Fire Department personnel) for a period of 4 hours of normal working time and must start after the system is functionally complete and after the final acceptance test. The on-site training must cover all of the items contained in the approved Operating and Maintenance Instructions.
-- End of Section --
SECTION 21 13 13 Page 20
SECTION 22 00 00
PLUMBING, GENERAL PURPOSE
05/24, CHG 1: 11/24
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI Z21.10.1/CSA 4.1 (2019; R 2024) Gas Water Heaters Vol. I, Storage Water Heaters with Input Ratings of 75,000 Btu Per Hour or Less
ANSI Z21.10.3/CSA 4.3 (2019; R 2024) Gas-Fired Water Heaters Vol.III, Storage Water Heaters With Input Ratings Above 75,000 Btu Per Hour, Circulating and Instantaneous
ANSI Z21.22/CSA 4.4 (2015; R 2020) Relief Valves for Hot Water Supply Systems
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 90.1 - IP (2019) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASHRAE 146 (2020) Method of Testing and Rating Pool Heaters (ANSI Approved)
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME A112.1.2 (2012; R 2017; R 2022) Air Gaps in Plumbing Systems (For Plumbing Fixtures and Water-Connected Receptors)
ASME A112.6.3 (2022) Floor Drains
ASME A112.14.1 (2003; R 2017; R 2022) Backwater Valves
ASME B1.20.1 (2013; R 2018) Pipe Threads, General Purpose (Inch)
ASME B16.3 (2021) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.4 (2021) Gray Iron Threaded Fittings;
Classes 125 and 250
ASME B16.5 (2020) Pipe Flanges and Flanged Fittings
SECTION 22 00 00 Page 1
NPS 1/2 Through NPS 24 Metric/Inch Standard
ASME B16.12 (2019) Cast Iron Threaded Drainage Fittings
ASME B16.15 (2024) Cast Copper Alloy Threaded Fittings Classes 125 and 250
ASME B16.18 (2021) Cast Copper Alloy Solder Joint Pressure Fittings
ASME B16.21 (2021) Nonmetallic Flat Gaskets for Pipe Flanges
ASME B16.22 (2021) Wrought Copper and Copper Alloy Solder Joint Pressure Fittings
ASME B16.23 (2021) Cast Copper Alloy Solder Joint Drainage Fittings - DWV
ASME B16.24 (2022) Cast Copper Alloy Pipe Flanges, Flanged Fittings, and Valves Classes 150, 300, 600, 900, 1500, and 2500
ASME B16.29 (2022) Wrought Copper and Wrought Copper Alloy Solder-Joint Drainage Fittings - DWV
ASME B16.34 (2021) Valves - Flanged, Threaded and Welding End
ASME B16.39 (2020) Standard for Malleable Iron Threaded Pipe Unions; Classes 150, 250, and 300
ASME B16.50 (2021) Wrought Copper and Copper Alloy Braze-Joint Pressure Fittings
ASME B16.51 (2013) Copper and Copper Alloy Press-Connect Pressure Fittings
ASME B31.1 (2024) Power Piping
ASME B31.9 (2020) Building Services Piping
ASME B40.100 (2022) Pressure Gauges and Gauge Attachments
ASME BPVC SEC IV (2017) BPVC Section IV-Rules for…