This is a set of architectural construction plans and phasing documents for the renovation/repair of Building 27 at Defense Supply Center Columbus (DSCC), Wright-Patterson Air Force Base, Ohio, under U.S. Army Corps of Engineers solicitation W912QR26BA021. The project involves comprehensive renovation of an athletic/fitness facility including locker rooms, mechanical systems, HVAC, electrical, plumbing, fire protection, and structural work. The work is organized into five distinct phases designed to maintain continuous facility operations during Phases 1-4, with only a maximum 14-calendar-day full facility shutdown during Phase 5. Phase 1 includes complete renovation of all locker rooms, construction of a new mechanical room, and installation of all MEP stub-outs and main distribution pathways. Phases 2-4 may occur in any order with government approval and will complete architectural finishes, branch ductwork, piping, power, lighting, and controls installations. Phase 5 requires removal of existing air handling units and fans, complete replacement of the 750 kVA electrical service transformer, water heater replacement, exterior EIFS installation and envelope work, vestibule demolition and replacement, and final mechanical system connections.

The plans specify that the contractor must submit a detailed phasing and sequencing plan within 30 days of Notice to Proceed (NTP) addressing dust/debris/abatement control, egress plans, equipment movement, mechanical/electrical routing, shutdown coordination, and temporary partitions. Critical requirements include maintaining restroom operations during all phases except Phase 5, providing designated haul routes for demolition and material removal, daily cleaning to limit dust migration, and negative air/HEPA filtration during Phase 1 and 5 demolition work. The contractor must coordinate all disruptions of utility services, fire protection/alarm systems, and security systems at least 14 days in advance and provide continuous fire watch if any life safety systems are offline. Testing, Adjusting, and Balancing (TAB) activities must be performed in a fully occupied facility and coordinated with government and facility management to avoid shutdowns and minimize disruption. All final commissioning, system integration, and training shall occur only after Phase 5 completion.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION LAYDOWN AREA

PROPOSED

LAYDOWN AREA.

PROJECT SITE

VICINITY MAP

PROJECT SITE

MAP ENLARGEMENT

CONSTRUCTION

LAYDOWN AREA.

JOHN GLENN COLUMBUS

INTERNATIONAL AIRPORT

CONSTRUCTION ACCESS ROUTE

AREA OF

CONSTRUCTION.

PROJECT SITE

ACCESS

GATE

PROPOSED

HAUL ROUTE

US Army Corps of Engineers ®

SHEET ID

U S

AR

M

Y C

O R

PS

O

F

EN

G

IN

EE

R

S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

N

3 5 7 9 11 13 15 17 19

L

J

G

E

C

A

D

AT

E

US Army Corps of Engineers ®

SOLICITATION NO.:

CONTRACT NO.:

ISSUE DATE:

VOLUME:

M

AR

K D

ES

C

R

IP

TI

O

N

Fi le

P at h:

Pl ot D at e:

2 4 6 8 10 12 14 16 18 20

P

M

K

H

F

D

B

Au to de sk

D oc s:

//2

5-

6-

D

LA

D

SC

C

B ld g.

R

E

PF

R em od /2

5-

6-

_D

LA

D

SC

C

B ld g.

R

E

PF

R em od _A

R _2

4.

rv t

4/

/2

5:

:4

PM

G-001

C O

VE

R

S H

EE

T

C O

LU

M

BU

S, O H

IO

LO

U

IS

VI

LL

E, K

Y E.

E.

E.

E.

E.

B.

M ar ch

3, D

SC

C D

LA

R

EP

AI

R B

U

IL

D

IN

G

-2

-0

LOUISVILLE, KY

March 13, 2026

COLUMBUS, OHIO

DSCC DLA REPAIR BUILDING 27

100% CERTIFIED FINAL

25-25126-00 P2# 519087

D FINAL

03/13/2026

06 August 2026

W912QR26BA021

W

2Q R

BA

1_

Pl an s-

US Army Corps of Engineers ®

SHEET ID

U S

AR

M

Y C

O R

PS

O

F

EN

G

IN

EE

R

S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

N

3 5 7 9 11 13 15 17 19

L

J

G

E

C

A

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

2 4 6 8 10 12 14 16 18 20

P

M

K

H

F

D

B

Au to de sk

D oc s:

//2

5-

6-

D

LA

D

SC

C

B ld g.

R

E

PF

R em od /2

5-

6-

_D

LA

D

SC

C

B ld g.

R

E

PF

R em od _A

R _2

4.

rv t

4/

/2

5:

:5

PM

GI001

SH

EE

T

IN

D

EX

C O

LU

M

BU

S, O H

IO

LO

U

IS

VI

LL

E, K

Y E.

E.

E.

E.

A.

B.

E.

B.

M ar ch

3, 0%

C

ER

TI

FI

ED

F

IN

AL

D

SC

C D

LA

R

EP

AI

R B

U

IL

D

IN

G

-2

-0

.ARCHITECTURAL.

A11.7.1 STAIR AND ELEVATOR DETAILS

A11.7.2 STAIR AND ELEVATOR DETAILS

A-001 GENERAL NOTES, ARCHITECTURAL SYMBOLS & ABBREVIATIONS

AD101 DEMOLITION PLAN OVERALL

AD102 DEMOLITION PLAN - AREA 11N

AD103 DEMOLITION PLAN - AREA 12N

AD104 DEMOLITION PLAN - AREA 13N

AD105 DEMOLITION PLAN - AREA 11S

AD106 DEMOLITION PLAN - AREA 12S

AD107 DEMOLITION PLAN - AREA 13S

AD108 DEMOLITION PLAN - MEZZANINE AREA

AD201 EXTERIOR DEMO ELEVATIONS

A-101 FLOOR PLAN OVERALL

A-102 FLOOR PLAN - AREA 11N

A-103 FLOOR PLAN - AREA 12N

A-104 FLOOR PLAN - AREA 13N

A-105 FLOOR PLAN - AREA 11S

A-106 FLOOR PLAN - AREA 12S

A-107 FLOOR PLAN - AREA 13S

A-108 OVERALL - REFLECTED CEILING PLAN

A-201 EXTERIOR ELEVATIONS

A-401 PARTITION TYPES

A-402 DOOR & WINDOWS FRAME TYPE & SCHEDULE

A-501 DOOR AND FRAME DETAILS

A-502 EXTERIOR DETAILS

.GENERAL.

G-001 COVER SHEET

GI001 SHEET INDEX

GC001 GENERAL PHASING NOTES

GC002 FLOOR PLAN OVERALL PHASING

.STRUCTURAL.

S-001 GENERAL STRUCTURAL NOTES

S-002 GENERAL STRUCTURAL NOTES & SPECIAL INSPECTIONS

S-003 GENERAL STRUCTURAL NOTES, SYMBOLS & ABBREVIATIONS

S-100 STRUCTURAL PLAN - AREA 11N

S-101 STRUCTURAL PLAN - AREA 11S

S-102 STRUCTURAL PLAN - AREA 12N

S-103 STRUCTURAL PLAN - AREA 12S

S-104 STRUCTURAL PLAN - AREA 13N

S-105 STRUCTURAL PLAN - AREA 13S

S-500 STRUCTURAL DETAILS

S-501 STRUCTURAL DETAILS

.MECHANICAL.

M-001 GENERAL INFORMATION - HVAC

MD101 AREA 11-N HVAC DEMOLITION PLAN

MD102 AREA 12-N HVAC DEMOLITION PLAN

MD103 AREA 13-N HVAC DEMOLITION PLAN

MD104 AREA 11-S HVAC DEMOLITION PLAN

MD105 AREA 12-S HVAC DEMOLITION PLAN

MD106 AREA 13-S HVAC DEMOLITION PLAN

MD401 MEZZANINE ENLARGED HVAC DEMOLITION PLAN

M-002 FIRST FLOOR HVAC ZONING PLAN

MH101 AREA 11-N HVAC DUCTWORK PLAN

MH102 AREA 12-N HVAC DUCTWORK PLAN

MH103 AREA 13-N HVAC DUCTWORK PLAN

MH104 AREA 11-S HVAC DUCTWORK PLAN

MH105 AREA 12-S HVAC DUCTWORK PLAN

MH106 AREA 13-S HVAC DUCTWORK PLAN

MH107 BOILER ROOM HVAC DUCTWORK PLAN

MH501 HVAC DETAILS

MH701 HVAC SCHEDULES

MP101 AREA 11-N HVAC PIPING PLAN

MP102 AREA 12-N HVAC PIPING PLAN

MP103 AREA 13-N HVAC PIPING PLAN

MP104 AREA 11-S HVAC PIPING PLAN

MP105 AREA 12-S HVAC PIPING PLAN

MP106 AREA 13-S HVAC PIPING PLAN

MP501 HVAC DETAILS

MP601 HVAC PIPING SCHEMATICS

MP701 HVAC SCHEDULES

M-301 MECHANICAL ROOM SECTION AND ISOMETRIC VIEWS

M-401 MECHANICAL ROOM ENLARGED PLAN

MI801 HVAC SEQUENCE OF OPERATIONS / CONTROLS

MI802 HVAC SEQUENCE OF OPERATIONS / CONTROLS

MI803 HVAC SEQUENCE OF OPERATIONS / CONTROLS

MI804 HVAC SEQUENCE OF OPERATIONS / CONTROLS

.PLUMBING.

P-001 GENERAL INFORMATION - PLUMBING

PD101 LEVEL 01 - AREA 11-N PLUMBING DEMOLITION PLAN

PD102 LEVEL 01 - AREA 12-N PLUMBING DEMOLITION PLAN

PL101 AREA 11-N - PLUMBING PLAN

PL102 AREA 12-N - PLUMBING PLAN

PL104 AREA 11-S - PLUMBING PLAN

PL105 AREA 12-S - PLUMBING PLAN

P-401 ENLARGED PLUMBING PLANS

P-501 PLUMBING DETAILS/SCHEDULES

.FIRE PROTECTION.

FP001 NOTES & LEGENDS - FIRE PROTECTION

FA001 FIRE ALARM LEGEND, NOTES, DIAGRAMS AND ABBREVIATIONS

FP100 FIRE PROTECTION SITE PLAN

FS101 LEVEL 01 - LIFE SAFETY PLAN

FS102 LEVEL 01 - BUILDING CODE ANALYSIS

FS103 LEVEL 01 - BUILDING CODE ANALYSIS

FD101 LEVEL 01 - FIRE PROTECTION DEMOLITION OVERALL FLOOR PLAN

FD201 LEVEL 01 - AREA 12 - FIRE ALARM DEMOLITION PLAN

FH101 LEVEL 01 - FIRE PROTECTION OVERALL HAZARD PLAN

FP101 AREA 12-N FIRE SPRINKLER PLAN

FP102 AREA 12-S FIRE SPRINKLER PLAN

FP103 AREA 13-S FIRE SPRINKLER PLAN

FP104 AREA 10-N FIRE SPRINKLER PLAN

FA201 LEVEL 01 - AREA 12 - FIRE ALARM PLAN

FP501 FIRE PROTECTION DETAILS

FA501 FIRE ALARM DETAILS

FP601 MECHANICAL ROOM 1203 HYDRAULIC CALCS

FP602 MECHANICAL ROOM 1203 HYDRAULIC CALCS

FP603 MOST REMOTE AREA HYDRAULIC CALCS

FP604 MOST REMOTE AREA HYDRAULIC CALCS

FP605 BOILER ROOM HYDRAULIC CALCS

FP606 BOILER ROOM HYDRAULIC CALCS

FP607 BOILER ROOM HYDRAULIC CALCS

.ELECTRICAL.

E-001 GENERAL INFORMATION - ELECTRICAL

ED101 AREA 11-N - ELECTRICAL DEMOLITION PLAN

ED102 AREA 12-N - ELECTRICAL DEMOLITION PLAN

ED103 AREA 13-N - ELECTRICAL DEMOLITION PLAN

ED104 AREA 11-S - ELECTRICAL DEMOLITION PLAN

ED105 AREA 12-S - ELECTRICAL DEMOLITION PLAN

ED106 AREA 13-S - ELECTRICAL DEMOLITION PLAN

ED107 AREA 7-N - ELECTRICAL DEMOLITION PLAN

ED401 ELECTRICAL ENLARGED DEMOLITION PLAN - MEZZANINE

EL101 AREA 11-N - ELECTRICAL LIGHTING PLAN

EL102 AREA 12-N - ELECTRICAL LIGHTING PLAN

EL103 AREA 13-N - ELECTRICAL LIGHTING PLAN

EL104 AREA 11-S - ELECTRICAL LIGHTING PLAN

EL105 AREA 12-S - ELECTRICAL LIGHTING PLAN

EL106 AREA 13-S - ELECTRICAL LIGHTING PLAN

EP201 AREA 11-N - ELECTRICAL POWER SYSTEMS PLAN

EP202 AREA 12-N - ELECTRICAL POWER SYSTEMS PLAN

EP203 AREA 13-N - ELECTRICAL POWER SYSTEMS PLAN

EP204 AREA 11-S - ELECTRICAL POWER SYSTEMS PLAN

EP205 AREA 12-S - ELECTRICAL POWER SYSTEMS PLAN

EP206 AREA 13-S - ELECTRICAL POWER SYSTEMS PLAN

EP207 BOILER ROOM - ELECTRICAL POWER SYSTEMS PLAN

EP208 AREA 7-N - ELECTRICAL POWER SYSTEMS PLAN

E-401 ELECTRICAL ENLARGED PLANS

E-501 ELECTRICAL DETAILS

E-502 ELECTRICAL DETAILS

E-503 ELECTRICAL DETAILS

E-601 ELECTRICAL SINGLE-LINE DIAGRAM - DEMOLITION

E-602 ELECTRICAL SINGLE-LINE DIAGRAM - NEW WORK

E-603 ELECTRICAL PANELBOARD SCHEDULE

HAZARD MITIGATION

HM101 ASBESTOS SAMPLE LOCATION

HM102 LEAD PAINT SAMPLE LOCATION

.INTERIORS.

I-111 INTERIOR DETAILS

I-112 INTERIOR SIGNANGE DETAILS

I-101 ENLARGED LOCKER ROOM PLANS

I-102 ENLARGED LOCKER ROOM FINISH PLANS

I-103 ENLARGED LOCKER ROOM FURNITURE PLANS

I-201 WOMENS LOCKER ROOM INTERIOR ELEVATIONS

I-202 MENS INTERIOR ELEVATIONS

D FINAL

03/13/2026

W

2Q R

BA

1_

Pl an s-

US Army Corps of Engineers ®

SHEET ID

U S

AR

M

Y C

O R

PS

O

F

EN

G

IN

EE

R

S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

N

3 5 7 9 11 13 15 17 19

L

J

G

E

C

A

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

2 4 6 8 10 12 14 16 18 20

P

M

K

H

F

D

B

Au to de sk

D oc s:

//2

5-

6-

D

LA

D

SC

C

B ld g.

R

E

PF

R em od /2

5-

6-

_D

LA

D

SC

C

B ld g.

R

E

PF

R em od _A

R _2

4.

rv t

4/

/2

5:

:5

PM

GC001

G

EN

ER

AL

P H

AS

IN

G N

O

TE

S

C O

LU

M

BU

S, O H

IO

LO

U

IS

VI

LL

E, K

Y E.

E.

E.

E.

A.

B.

E.

B.

M ar ch

3, 0%

C

ER

TI

FI

ED

F

IN

AL

D

SC

C D

LA

R

EP

AI

R B

U

IL

D

IN

G

-2

-0

1.

GENERAL INTENT OF PHASING

1.1. THE PURPOSE OF THE PHASING PLAN IS TO MAINTAIN CONTINUOUS FACILITY OPERATIONS THROUGHOUT CONSTRUCTION, EXCEPT DURING THE TOTAL FACILITY SHUTDOWN OF NO MORE THAN 14 CALENDAR DAYS FOR PHASE 5. THE FACILITY SHALL REMAIN OPERATIONAL WITH NO ADDITIONAL

DISRUPTION IN OPERATIONS DURING PHASES 1 THROUGH 4.

1.2. THE CONTRACTOR SHALL PROVIDE ALL MEANS, METHODS, LABOR, MATERIALS, TEMPORARY PARTITIONS, SIGNAGE, CONTROLS, AND PROTECTION REQUIRED TO EXECUTE THE FIVE (5) PHASES OF

WORK SHOWN ON THE DRAWINGS.

1.3. ONLY ONE (1) PHASE MAY BE FULLY “DOWN” (CLOSED TO OCCUPANTS) AT ANY TIME DURING PHASES 1–4. WORK IN ADDITIONAL PHASES MAY PROCEED ONLY IF THOSE AREAS REMAIN OCCUPIABLE AND THE

GOVERNMENT PROVIDES WRITTEN APPROVAL.

2. SEQUENCING OF WORK / PHASE ORDER

2.1. PHASE 1 SHALL INCLUDE COMPLETE RENOVATION OF ALL LOCKER ROOMS, CONSTRUCTION OF THE NEW MECHANICAL ROOM, AND INSTALLATION OF ALL MECHANICAL, ELECTRICAL, PLUMBING, FIRE

PROTECTION, AND CONTROLS STUB-OUTS NECESSARY TO SUPPORT PHASES 2, 3, AND 4.

2.1.1. THE CONTRACTOR SHALL FOLLOW DESIGNATED HAUL ROUTES FOR DEMOLITION, MATERIAL HANDLING, AND EQUIPMENT MOVEMENT AS INDICATED ON THE DRAWINGS. DAILY CLEANING IS REQUIRED

TO LIMIT DUST MIGRATION.

2.1.2. DURING PHASE 1, THE FACILITY SHALL PROVIDE TEMPORARY CHANGING AND TEMPORARY LOCKER

AREAS FOR OCCUPANTS. RESTROOMS SHALL REMAIN OPERATIONAL DURING PHASE 1 AND ALL

SUBSEQUENT PHASES EXCEPT FOR THE FULL SHUTDOWN DURING PHASE 5.

2.1.3. PHASE 1 SHALL ESTABLISH ALL MAIN DISTRIBUTION PATHS FOR DUCTWORK, HYDRONIC LINES, ELECTRICAL FEEDERS, LOW-VOLTAGE CABLING, AND CONTROLS INFRASTRUCTURE INTO FUTURE PHASES.

SUBSEQUENT PHASES SHALL REQUIRE ONLY BRANCH INSTALLATIONS AND FINAL DEVICE CONNECTIONS.

2.2. PHASES 2, 3, AND 4 MAY OCCUR IN ANY ORDER APPROVED BY THE GOVERNMENT. THE CONTRACTOR SHALL SUBMIT A DETAILED PHASING AND SEQUENCING PLAN INDICATING LOGISTICS, EQUIPMENT PROTECTION, EGRESS ROUTING, TEMPORARY PARTITIONS, AND OPERATIONAL IMPACTS FOR EACH

PROPOSED ORDER OF WORK.

2.3. PHASES 2–4 SHALL COMPLETE ALL ARCHITECTURAL FINISHES, BRANCH DUCTWORK, HYDRONIC PIPING, POWER AND LIGHTING INSTALLATIONS, CONTROLS DEVICES, FIRE PROTECTION ADJUSTMENTS, AND ALL OTHER SYSTEMS REQUIRED FOR THE OCCUPANCY OF THEIR RESPECTIVE AREAS. NO COMPLETED PHASE

SHALL BE REOPENED FOR ROUGH-IN WORK.

2.4. PHASE 5 SHALL BE A COMPLETE FACILITY SHUTDOWN AND SHALL INCLUDE THE FOLLOWING WORK:

REMOVAL OF ALL EXISTING AIR HANDLING UNITS, FANS, AND ASSOCIATED MECHANICAL EQUIPMENT.

COMPLETE REPLACEMENT OF THE 750 kVA ELECTRICAL SERVICE TRANSFORMER.

WATER HEATER REPLACEMENT TO OCCUR DURING PHASE 5 WHEN THE FACILITY IS SHUTDOWN TO

MINIMISE OCCUPANT DISTURBANCE.

EXTERIOR EIFS INSTALLATION AND ENVELOPE WORK MUST OCCUR AT ONE TIME INDEPENDENTLY FROM ALL OTHER 5 PHASES, AS APPROVED BY THE GOVENRMENT WITHOUT INTERFERING WITH OTHER

WORK BEING PERFORMED. IT MUST BE INCLUDED IN THE SEQUENCING PLAN

VESTIBULE DEMOLITION AND REPLACEMENT PER THE CONTRACT DOCUMENTS.

FINAL CONNECTION OF ALL NEW MECHANICAL UNITS TO THE EXISTING CHILLER SYSTEM.

DISCONNECTION AND REMOVAL OF EXISTING MECHANICAL PIPING AND DUCTWORK REQUIRED TO

COMPLETE THE NEW SYSTEM INSTALLATION.

2.4.1. NO SPACES WITHIN THE FACILITY SHALL REMAIN OCCUPIABLE DURING PHASE 5. OCCUPANTS SHALL BE NOTIFIED AND COORDINATED WITH NO LESS THAN 14 DAY NOTICE PRIOR TO THE FULL SHUTDOWN.

2.4.2. THE NEW HVAC SYSTEM CANNOT BE STARTED, TESTED, OR OPERATED UNTIL PHASE 5 IS COMPLETE.

2.4.3. ALL FINAL TESTING, ADJUSTING, BALANCING (TAB), CONTROLS PROGRAMMING, GRAPHICS INTEGRATION, FUNCTIONAL TESTING, AND COMMISSIONING SHALL OCCUR ONLY AFTER COMPLETION OF

PHASE 5.

2.4.4. IF PHASE 5 SHUTDOWN OCCURS DURING WINTER MONTHS, THE CONTRACTOR SHALL PROVIDE TEMPORARY HEAT OR TEMPORARY POWER AS REQUIRED TO PREVENT FREEZING CONDITIONS WITHIN THE FACILITY UNTIL THE TRANSFORMER REPLACEMENT IS COMPLETE. IF THIS OCCURS DURING THE SUMMER THIS WILL NOT BE AN ISSUE AS THE FACILITY WILL HAVE NO POWER AND OCCUPANTS WILL NOT BE IN THE

FACILITY.

3. PHASE COMPLETION REQUIREMENTS

3.1. EACH PHASE SHALL BE FULLY PUNCHED OUT, CLEANED, AND MADE READY FOR OCCUPANCY PRIOR TO

COMMENCEMENT OF THE NEXT PHASE.

3.2. ALL MAIN DISTRIBUTION PATHWAYS FOR DUCTWORK, HYDRONIC PIPING, ELECTRICAL, AND CONTROLS SHALL BE INSTALLED PRIOR TO LEAVING THE EARLIEST FEASIBLE PHASE SO THAT FUTURE

PHASES REQUIRE ONLY BRANCH INSTALLATIONS.

3.3. THE GOVERNMENT MUST APPROVE EACH COMPLETED PHASE PRIOR TO THE CONTRACTOR

ADVANCING TO THE NEXT.

4. MAINTENANCE OF FACILITY OPERATIONS

4.1. FACILITY OPERATIONS SHALL CONTINUE THROUGH PHASES 1–4. TEMPORARY PROTECTION, EGRESS ROUTING, AND SIGNAGE SHALL BE MAINTAINED AT ALL TIMES. NO AREA OUTSIDE THE ACTIVE PHASE MAY BE RENDERED UNUSABLE DUE TO DUST, DEBRIS, ODORS, NOISE, TEMPORARY UTILITIES, OR SAFETY HAZARDS.

4.2. RESTROOMS SHALL REMAIN AVAILABLE DURING ALL PHASES EXCEPT PHASE 5 WHEN THE

TRANSFORMER REPLACEMENT IS OCCURING. WHILE THE FACILITY IS SHUTDOWN ALL MEZZENINE DEMO WORK OF THE AHUS AND OTHER FINISHES SHALL BE COMPLETE. AFTER THE POWER IS RESTORED TO THE FACILITY THE RESTROOM WILL BE MADE AVAILABLE TO THE OCCUPANTS. DURING PHASE 5 ALL WORK OVERHEAD OF THE RESTROOMS WILL BE REQUIRED TO BE COMPLETED DURING THE EVENING DURING NON OPERATIONAL HOURS. TEMPORARY PARTITIONS SHALL BE INSTALLED WHERE REQUIRED TO PROTECT OCCUPANTS.

4.3. OCCUPIED AREAS SHALL REMAIN FREE OF DUST, DEBRIS, ODORS, AND SAFETY HAZARDS. DAILY

CLEANING IS REQUIRED.

5. ACCESS, LOGISTICS, AND DEBRIS REMOVAL

5.1. THE CONTRACTOR SHALL USE DESIGNATED HAUL ROUTES FOR ALL DEMOLITION AND MATERIAL REMOVAL ACTIVITIES. IF THE CONTRACTOR IS NOT OCCUPYING THE ENTIRE PHASE DURING CONSTRUCTION THE CONTRACTOR WILL TAPE OFF THE CONSTRUCTION AREA AS TO ALLOW FOR EQUIPMENT ACCESS FOR THE FACILITY. CONTRACTOR MUST MAINTAIN SAFE ACCESS FOR OCCUPANTS AT ALL TIMES, INCLUDING INSTALLATION OF TEMPORARY PROTECTION WHERE CONSTRUCTION ROUTES INTERSECT WITH OCCUPIED

AREAS.

5.2. FLOOR PROTECTION SHALL BE PROVIDED WHEREVER EQUIPMENT OR MATERIALS ARE TRANSPORTED.

5.3. ALL DEBRIS SHALL BE COVERED OR BAGGED WHEN TRANSPORTED THROUGH OCCUPIED SPACES.

5.4. CONTRACTOR SHALL COORDINATE AND SCHEDULE ANY NECESSARY INTERRUPTIONS WITH THE

GOVERNMENT IN ADVANCE.

5.5. FOR PHASE 1 AND 5 PROVIDE A COMBINATION OF HARD BARRIERS AND PLASTIC BARRIERS AS REQUIRED BY THE GOVERNMENT. FOR DEMOLITION INSIDE PHASES 1 AND 5, THE CONTRACTOR SHALL ESTABLISH NEGATIVE AIR, HEPA FILTRATION, AND SEALED PARTITIONS TO PREVENT AIRBORNE DUST

MOVEMENT TO OCCUPIED AREAS.

5.6 DURING PHASE 1 AND 5, THE CONTRACTOR SHALL PROVIDE CAUTION TAPE BARRIERS ALONG THE HAUL

ROUTES AS WELL AS PROVIDE FLOOR PROTECTION AS NEEDED.

5.7. FOR ASBESTOS OR LEAD ABATEMENT:

ABATEMENT SHALL OCCUR PHASE BY PHASE, MATCHING THE CONSTRUCTION PHASING.

ABATEMENT CONTRACTOR SHALL CONSTRUCT CODE-COMPLIANT CONTAINMENT ROOMS AND ANTE-

CHAMBERS AROUND EACH DOOR/WINDOW/OVERHEAD-DOOR LOCATION BEING ABATED.

DO NOT QUARANTINE AN ENTIRE PHASE FOR A SMALL ABATEMENT AREA UNLESS REQUIRED BY CODE.

CONTRACTOR SHALL PROVIDE UNIT PRICING (LINEAR FOOT/CUBIC YARD) FOR POSSIBLE ADDITIONAL

ABATEMENT QUANTITIES AS REQUIRED BY THE GOVERNMENT.

6.4. AT THE COMPLETION OF EACH ABATEMENT AREA, THE CONTRACTOR SHALL PROVIDE ALL

REQUIRED CLEARANCE TESTING AND DOCUMENTATION BEFORE FINISHING WORK PROCEEDS.

GENERAL PHASING NOTES

6. HVAC, ELECTRICAL, AND CONTROLS COORDINATION.

6.1. MAIN DUCTS, HYDRONIC PIPING, CONTROLS CABLING, AND ELECTRICAL CONDUITS SHALL BE ROUTED

THROUGH PHASE 1 TO SUPPORT PHASES 2 –4 WITHOUT FUTURE RE-ENTRY.

6.2. PANEL TERMINATIONS AND CONTROLS NETWORK CONNECTIONS MAY OCCUR LATER BUT SHALL NOT

REQUIRE REOPENING FINISHED AREAS.

6.3. FINAL SYSTEM INTEGRATION SHALL OCCUR ONLY AFTER COMPLETION OF PHASE 5.

7. PHASE 5 SHUTDOWN REQUIREMENTS.

7.1. CONTRACTOR SHALL COORDINATE THE FULL FACILITY SHUTDOWN REQUIRED FOR TRANSFORMER

REPLACEMENT AND MECHANICAL EQUIPMENT CHANGEOVER.

7.2. TEMPORARY HEAT AND/OR POWER SHALL BE PROVIDED AS NECESSARY TO PROTECT THE FACILITY

FROM FREEZING DURING WINTER MONTHS.

7.3. ALL SYSTEMS SHALL BE REACTIVATED IMMEDIATELY UPON TRANSFORMER INSTALLATION AND

EQUIPMENT CONNECTIONS.

8. FIRE PROTECTION, FIRE WATCH, SECURITY, & SHUTDOWNS.

8.1. ANY IMPAIRMENT TO FIRE ALARM, SPRINKLER, SECURITY, OR EGRESS SYSTEMS MUST BE

COORDINATED A MINIMUM OF 14 DAYS IN ADVANCE.

8.2. IF ANY SYSTEM IS OFFLINE AT ANY TIME, THE CONTRACTOR SHALL PROVIDE A CONTINUOUS FIRE WATCH MEETING ALL APPLICABLE UFC, NFPA, AND INSTALLATION REQUIREMENTS UNTIL THE SYSTEM IS

RESTORED.

8.3. SHUTDOWNS SHALL BE SCHEDULED DURING LOW-OCCUPANCY HOURS (BETWEEN 8:30-11:00 AM AND

12:00 - 2:30 PM.) OR AFTER- HOURS WHEN REQUIRED AND PRE-APPROVED.

8.4. IF PHASE 5 SHUTDOWN OCCURS DURING WINTER MONTHS, THE CONTRACTOR SHALL PROVIDE TEMPORARY HEAT OR TEMPORARY POWER AS REQUIRED TO PREVENT FREEZING CONDITIONS WITHIN THE FACILITY UNTIL THE TRANSFORMER REPLACEMENT IS COMPLETE. IF THIS OCCURS DURING THE SUMMER THIS WILL NOT BE AN ISSUE AS THE FACILITY WILL HAVE NO POWER AND OCCUPANTS WILL NOT BE IN THE

FACILITY.

8.5. CONTRACTOR SHALL MAINTAIN EMERGENCY LIGHTING, EXIT SIGNS, AND TEMPORARY DETECTION AS

REQUIRED.

8.6 CONTRACTOR MUST COORDINATE WITH THE FIRE MARSHAL ’S OFFICE OR RESPONSIBLE AGENCY FOR

ALL FIRE WATCH PLAN APPROVALS AND ANY COSTS ASSOCIATED.

9. GYM EQUIPMENT MOVEMENT & PROTECTION.

9.1. CONTRACTOR SHALL COORDINATE FURNITURE AND EQUIPMENT RELOCATION AND/ OR REMOVAL

FROM THE CONSTRUCTION AREAS AS NECESSARY WITH THE CONTRACTING OFFICER PRIOR TO

MOBILIZATION. THE FACILITY WILL BE RESPONSIBLE OF REMOVING AND/OR RELOCATING ANY FURNITURE AND EQUIPMENT DEEMED NECESSARY TO BE MOVED AS AGREED IN A PRE-MOBILIZATION MEETING.

9.2 THE CONTRACTOR IS RESPONSIBLE FOR PROTECTING, AND SECURING ALL GYM EQUIPMENT, WEIGHTS, TREADMILLS, AND MACHINES LOCATED WITHIN EACH PHASE.

9.3. CONTRACTOR SHALL COORDINATE WITH THE FACILITY TO IDENTIFY EQUIPMENT THAT MUST REMAIN

ACCESSIBLE AND SHALL PROVIDE PROTECTIVE COVERINGS TO ALL EQUIPMENT DURING NEARBY

CONSTRUCTION OPERATIONS.

9.4. EQUIPMENT SHALL NOT BE DAMAGED. ANY DAMAGED EQUIPMENT SHALL BE REPAIRED OR REPLACED

BY THE CONTRACTOR AT NO ADDITIONAL COST.

10. END-OF-PROJECT REQUIREMENTS (AFTER PHASE 5)

10.1. WHEN ALL PHASES ARE COMPLETE, CONTRACTOR SHALL PERFORM:

FULL STARTUP, TESTING, ADJUSTING, AND BALANCING (TAB) OF ALL SYSTEMS.

FULL HVAC CONTROLS CHECKOUT, GRAPHICS VERIFICATION, TRENDING VERIFICATION, AND

SEQUENCE TESTING.

FULL LIGHTING CONTROLS VERIFICATION AND COMMISSIONING.

FINAL CLEANING, FINAL EGRESS SIGNAGE RESET, AND REMOVAL OF ALL TEMPORARY SYSTEMS.

DELIVERY OF ALL O&M MATERIALS, AS-BUILTS, ATTIC STOCK, AND TRAINING.

11. CONTRACTOR PHASING PLAN SUBMITTAL.

11.1. WITHIN 30 DAYS OF NTP, CONTRACTOR SHALL SUBMIT A PHASING EXECUTION PLAN THAT INCLUDES:

DETAILED SEQUENCING AND SCHEDULE FOR EACH PHASE

DUST, DEBRIS, ABATEMENT, AND NOISE CONTROL MEASURES

EGRESS PLANS AND PUBLIC SIGNAGE

EQUIPMENT MOVEMENT PLAN

MECHANICAL/ELECTRICAL ROUTING DIAGRAMS

SHUTDOWN COORDINATION PLAN

TEMPORARY PARTITIONS AND PROTECTION LAYOUTS

THE PHASING PLAN SHALL SPECIFICALLY ADDRESS EXTENDED SHUTDOWN REQUIREMENTS DURING

PHASE 5, INCLUDING COORDINATION OF AIR HANDLER REMOVAL, TRANSFORMER REPLACEMENT,

TEMPORARY HEAT OR POWER REQUIREMENTS, AND RESTROOM ACCESS RESTORATION.

11.2. WORK SHALL NOT BEGIN UNTIL THE GOVERNMENT APPROVES THIS PLAN.

11.3. TESTING, ADJUSTING, AND BALANCING (TAB) ACTIVITIES SHALL BE PERFORMED IN A FULLY OCCUPIED FACILITY AND SHALL BE CAREFULLY COORDINATED WITH THE GOVERNMENT AND FACILITY OCCUPANTS.

THE CONTRACTOR SHALL SUBMIT A TAB SCHEDULE IDENTIFYING PROPOSED DATES, TIMES, AND AFFECTED SPACES FOR REVIEW AND APPROVAL BY THE CONTRACTING OFFICER ’S REPRESENTATIVE (COR) AND FACILITY MANAGEMENT PRIOR TO COMMENCING TAB ACTIVITIES. ALL TAB WORK SHALL BE SEQUENCED AND EXECUTED TO AVOID SHUTDOWNS OF OCCUPIED SPACES, MAINTAIN CONTINUOUS OPERATION OF CRITICAL SYSTEMS, AND MINIMIZE DISRUPTION TO BUILDING OCCUPANTS AND ONGOING OPERATIONS. ANY SYSTEM INTERRUPTIONS, AIRFLOW ADJUSTMENTS, ACCESS TO OCCUPIED AREAS, OR TEMPORARY IMPACTS REQUIRED TO COMPLETE TAB SHALL BE PERFORMED DURING APPROVED OFF-

HOURS OR LOW-OCCUPANCY PERIODS, UNLESS OTHERWISE AUTHORIZED IN WRITING BY THE

GOVERNMENT. THE CONTRACTOR SHALL PROVIDE ADVANCE NOTIFICATION OF TAB ACTIVITIES AND SHALL IMMEDIATELY RESTORE SYSTEMS TO NORMAL OPERATION FOLLOWING TESTING. NO TAB ACTIVITIES THAT NEGATIVELY IMPACT BUILDING OPERATIONS SHALL BE PERFORMED WITHOUT PRIOR GOVERNMENT

COORDINATION AND APPROVAL.

D FINAL

03/13/2026

W

2Q R

BA

1_

Pl an s-

5' - 0"

PHASE 5

PHASE 4

PHASE 2

PHASE 1

PHASE 3

PHASE 5

PHASE 4

PHASE 3

PHASE 2

PHASE 1

US Army Corps of Engineers ®

SHEET ID

U S

AR

M

Y C

O R

PS

O

F

EN

G

IN

EE

R

S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

N

3 5 7 9 11 13 15 17 19

L

J

G

E

C

A

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

2 4 6 8 10 12 14 16 18 20

P

M

K

H

F

D

B

Au to de sk

D oc s:

//2

5-

6-

D

LA

D

SC

C

B ld g.

R

E

PF

R em od /2

5-

6-

_D

LA

D

SC

C

B ld g.

R

E

PF

R em od _A

R _2

4.

rv t

4/

/2

5:

:0

PM

GC002

FL

O

O R

P

LA

N O

VE

R

AL

L

PH

AS

IN

G

C O

LU

M

BU

S, O H

IO

LO

U

IS

VI

LL

E, K

Y E.

E.

E.

E.

A.

B.

E.

B.

M ar ch

3, 0%

C

ER

TI

FI

ED

F

IN

AL

D

SC

C D

LA

R

EP

AI

R B

U

IL

D

IN

G

-2

-0

0 10 20

SCALE: 1/16" = 1'=0"

1/16" = 1'-0"A1 FLOOR PLAN PHASING

LEGEND:

NEW CHILLER ROUGH - IN PRIOR

TO PHASE 5 AND STARTUP.

TRANSFORMER

REPLACEMENT PHASE 5

DEMO HAUL ROUTE

TEMPORARY ACCESS

TO THE BUILDING

DURING PHASE 5

D FINAL

03/13/2026

W

2Q R

BA

1_

Pl an s-

ARCHITECTURAL SYMBOLS

XX/ A11.X

XX. X. XX

CASEWORK ELEVATION

DOOR NUMBER

CURTAIN WALL FRAME TYPE

WALL TYPE

027- XX-XXX

XX/ A11.X XXXX

XX

XX

APC-1

9' - 0"

CEILING TYPE

CEILING HEIGHT

CEILING TYPE

EXTERIOR WINDOW

TYPE

X

GENERAL ARCHITECTURAL NOTES

1.

2.

3.

4.

5.

6.

7.

8.

PARTITION TYPES SHALL BE DESIGNATED ON FLOOR PLANS. SEE

SHEET A-401 FOR TYPES.

PROVISIONS SHALL BE MADE AT ALL FULL HEIGHT NON-BEARING

WALLS FOR 1-INCH VERTICAL MOVEMENT OF THE BUILDING

STRUCTURE WITHOUT TRANSFER OF COMPRESSIVE LOADS TO

WALL.

SEE STRUCTURAL DRAWINGS FOR BRACING OF NON-LOAD

BEARING MASONRY WALLS.

FURNISH AND INSTALL FIRE-TREATED WOOD BLOCKING OR METAL

BACKING PLATE IN METAL STUD PARTITIONS FOR THE PROPER

ANCHORAGE OF ALL WALL ATTACHED ITEMS; I.E. TOILET

ACCESSORIES, CASEWORK, MILLWORK, WALL-MOUNTED

FIXTURES, DOOR STOPS, AND OTHER WALL ATTACHED ITEMS.

GYPSUM BOARD SURFACES SHALL BE ISOLATED WITH CONTROL

JOINTS WHERE SHOWN ON DRAWINGS AND AS DESCRIBED IN THE

SPECIFICATIONS.

EXTEND FURRING CHANNELS AND GYPSUM BOARD UP 4 INCHES

ABOVE FINISHED CEILING ON CMU WALLS.

SCRIBE GYPSUM WALL BOARD OF WALLS AND PARTITIONS TO

IRREGULARITIES OF DECK ABOVE. SEAL TIGHTLY AROUND ALL

PENETRATIONS.

CAREFULLY REMOVE ACOUSTICAL INSULATION ON THE

UNDERSIDE OF THE (E) CONCRETE BARREL VAULT TO

ACCOMMODATE THE ANCHOR AND BRACKET AND RE-

INSTALL/PATCH WITH SIMILAR MATERIAL AFTER ATTACHMENT IS

COMPLETE.

GENERAL SYMBOLS

SIM

ROOM NAME

XXX-XX

DETAIL NUMBER

SHEET NUMBER

CROSS REFERENCE

WALL SECTION

SIMILAR OR TYPICAL

REFERENCE

DETAIL REFERENCE

BUILDING SECTION

SHEET NOTE

COLUMN GRID LINE

ROOM NUMBER/NAME

REVISION NUMBER

EARTH

GRAVEL

SAND

CONCRETE

PRECAST CONCRETE

STEEL

STONE

CONCRETE MASONRY UNIT

BRICK VENEER

LEVEL XX

XXX'-XX" LEVEL ELEVATION

GYM FLOOR

WOOD

(CONTINUOUS BLOCKING)

WOOD

(NON-CONTINUOUS BLOCKING)

WOOD (TRIM/FINISH)

GLASS

SHINGLES

PLYWOOD (LARGE SCALE)

GYPSUM WALL BOARD

BLANKET INSULATION

RIGID INSULATION

SPRAY FOAM INSULATION

MINERAL WOOL INSULATION

PROTECTION BOARD

CARPET (LARGE SCALE)

ACOUSTIC TILE (LARGE SCALE)

TILE (LARGE SCALE)

? REFERENCE KEYNOTE

XX A4.XX BUILDING ELEVATION

A12.X

XX

XX XX

XX

INTERIOR ELEVATION

100'-0"

TYP FF EL=

100'-0"

FINISH FLOOR

ELEVATION

SPOT ELEVATION

X

GENERAL NOTES

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

K.

GENERAL NOTES APPLY TO ALL SHEETS.

DIMENSIONS ARE ACTUAL AND ARE TO FACE OF STUDS, FACE

OF CONCRETE WALLS, FACE OF CMU WALLS, FACE OF FRAMES,

OR CENTERLINE OF COLUMNS, UNLESS NOTED OTHERWISE.

COORDINATE ALL MECHANICAL CHASE SIZES WITH THE

MECHANICAL CONTRACTOR.

ARCHITECTURAL FINISH FLOOR ELEVATION 0'-0" EQUALS

ACTUAL FINISH FLOOR ELEVATION OF EXISTING BUILDING.

COORDINATE WITH MECHANICAL AND ELECTRICAL

CONTRACTORS THE SIZE AND LOCATION OF EQUIPMENT PADS

SHOWN ON PLANS.

CONSTRUCTION DOCUMENTS ARE COMPLEMENTARY. SEE

DRAWING FOR QUANTITIES AND LOCATION OF WORK. SEE

SPECIFICATIONS FOR QUALITIES AND CONDITIONS OF WORK.

WORK: ALL ASPECTS OF THE WORK AND ITEMS NOT

SPECIFICALLY MENTIONED, BUT NECESSARY TO MAKE A

COMPLETE WORKING INSTALLATION, SHALL BE INCLUDED AND

INDICATED IN THE CONTRACTOR'S BID.

SHEET NOTES ONLY APPLY TO PARTICULAR DRAWING OR

SERIES OF DRAWINGS.

NO ASBESTOS OR PCB CONTAINING MATERIALS SHALL BE USED

ON THIS PROJECT.

DO NOT SCALE DRAWINGS. DIMENSIONS NOTED PREVAIL.

NOTIFY ARCHITECT IN CASE OF DISCREPANCY.

HORIZONTAL AND VERTICAL DIMENSIONS ARE MINIMUM

DIMENSIONS. CLEARANCES ARE GIVEN TO FINISH SURFACES.

GC TO VERIFY ALL CLEARANCES. NOTIFY ARCHITECT IN CASE

OF DISCREPANCY.

US Army Corps of Engineers ®

SHEET ID

U S

AR

M

Y C

O R

PS

O

F

EN

G

IN

EE

R

S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

N

3 5 7 9 11 13 15 17 19

L

J

G

E

C

A

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

2 4 6 8 10 12 14 16 18 20

P

M

K

H

F

D

B

Au to de sk

D oc s:

//2

5-

6-

D

LA

D

SC

C

B ld g.

R

E

PF

R em od /2

5-

6-

_D

LA

D

SC

C

B ld g.

R

E

PF

R em od _A

R _2

4.

rv t

4/

/2

5:

:0

PM

A-001

G

EN

ER

AL

N O

TE

S, A R

C H

IT

EC

TU

R

AL

S

YM

BO

LS

AB

BR

EV

IA

TI

O

N S

C O

LU

M

BU

S, O H

IO

LO

U

IS

VI

LL

E, K

Y E.

E.

E.

E.

A.

B.

E.

B.

M ar ch

3, 0%

C

ER

TI

FI

ED

F

IN

AL

D

SC

C D

LA

R

EP

AI

R B

U

IL

D

IN

G

-2

-0

% PERCENT

< LESS THAN

= EQUALS

> GREATER THAN

A/E ARCHITECT/ENGINEER

AB AIR BARRIER

AC ARCHITECTURAL CONCRETE

ACC ADA ACCESSIBLE

ACD ACCESS DOOR

ACM ASBESTOS CONTAINING MATERIAL

ACR ACRYLIC

ACT ACOUSTIC TILE CEILING

ACW ALUMINUM CURTAIN WALL

ADJ ADJUSTABLE

ADJT ADJACENT

ADMIN ADMINISTRATION

ADO AUTOMATIC DOOR OPERATOR

AEC AUTOMATED EXTERNAL DEFIBRILLATORS

AFD ACCORDION-FOLDING FIRE DOOR

AFS ALUMINUM-FRAMED STOREFRONT

AGS ALL-GLASS STOREFRONT

AL ALUMINUM

ALD ALUMINUM DOOR

ALF ALUMINUM FRAME

ALUM ALUMINUM

AP ACCESS PANEL

APC ACOUSTICAL PANEL CEILING

ASPH ASPHALT

ATH ATHLETIC EQUIPMENT

AUTO AUTOMATIC

AVG AVERAGE

AW ALUMINUM WINDOW

AWP ACOUSTIC WALL PANEL

B.O. BOTTOM OF

BCS BABY CHANGING STATION

BD BOARD

BENT BENTONITE WATERPROOFING

BFD BIFOLD DOOR

BL BOLLARD

BLK BLOCK

BLKG BLOCKING

BLKHD BULKHEAD

BM(S) BEAM(S)

BN BENCH

BOT BOTTOM

BRDG BRIDGING

BRG BEARING

BRKT BRACKET

BT BATHTUB

BTWN BETWEEN

CAB CABINET

CB COFFEE BREWER

CBD CHALKBOARD

CCG CERAMIC-COATED GLASS

CCV METAL COLUMN COVER

CEQ CONVEYING EQUIPMENT

CF CUBIC FEET

CFAWP COLD-FLUID APPLIED WATERPROOFING

CFCI CONTRACTOR FURNISHED CONTRACTOR

INSTALLED

CFMF COLD-FORMED METAL FRAMING

CG CLEAR FLOAT GLASS

CG CORNER GUARD

CI CAST IRON

CIG CLEAR INSULATING GLASS

CIP CAST IN PLACE

CJ CONTROL JOINT

CJA CONTROL JOINT ABOVE

CLO CLOSET

CLR CLEAR

CMU CONCRETE MASONRY UNIT

COL COLUMN

COMB COMBINATION

COMM COMMUNICATIONS

COMPR COMPRESSIBLE

CONF CONFERENCE

CONFIG CONFIGURATION

CORR CORRIDOR

CP CEMENT PLASTER

CPT CARPET

CR CHAIR RAIL

CRYS CRYSTALLINE WATERPROOFING

CS COUNTERSINK

CST CAST STONE MASONRY

CSTJ CONSTRUCTION JOINT

CTG CLEAR TEMPERED FLOAT GLASS

CTIG CLEAR TEMPERED INSULATING GLASS

CU COPPER

CU COMBINATION UNIT

CV CONDOM VENDOR

CW CASEWORK

CY CUBIC YARD

CYL CYLINDER

DAMP DAMPPROOFING

DB DECIBEL

DBL DOUBLE

DC DUST COLLECTOR

DCS DIAPER CHANGING STATION

DDF DETENTION DOOR AND FRAME

DDH DETENTION DOOR HARDWARE

DEPR DEPRESS(ION)(ED)

ARCHITECTURAL

ABBREVIATIONS

DEPT DEPARTMENT

DET DETENTION

DF DRINKING FOUNTAIN

DFEC DETENTION FIRE EXTINGUISHER CABINET

DG DOOR GRILLE

DGL DETENTION GUN LOCKER

DIAG DIAGONAL

DM DECORATIVE METAL PANEL

DMP DECORATIVE FORMED METAL PANEL

DPTD DETENTION PAPER TOWEL DISPENSER

DR DOOR

DRH DETENTION ROBE HOOK

DRY CLOTHES DRYER

DSCR DETENTION SHOWER CURTAIN ROD

DSN DOWNSPOUT NOZZLE

DTTD DETENTION TOILET TISSUE DISPENSER

DV DIVIDER

DW DISHWASHER

DWI DETENTION WINDOW

DWL(S) DOWEL(S)

DWR DRAWER

EB EXPANSION BOLT

EE EACH END

EEW EMERGENCY EYE WASH

EEWS EMERGENCY EYE WASH SHOWER

EF ENTRANCE FLOOR MAT

EFF EFFICIENCY

EJ EXPANSION JOINT

ELAS ELASTOMERIC

ELEV ELEVATOR

EMER EMERGENCY

ENCL ENCLOSURE

ENTR ENTRANCE

ERF EPOXY RESIN FLOORING

EUI ENERGY USE INTENSITY

EW EACH WAY

EWC ELECTRIC WATER COOLER

EXP EXPANSION

EXP EXPOSED

F FABRIC

F.O. FACE OF

FAB FABRICATE(D)

FB FACE BRICK

FC FIBER-CEMENT CLADDING

FD FLOOR DRAIN

FDN FOUNDATION

FE FIRE EXTINGUISHER

FEC FIRE EXTINGUISHER CABINET

FH FIRE HYDRANT

FHC FIRE HOSE CABINET

FIG FIGURE

FIX FIXTURE

FLEX FLEXIBLE

FLG FLOORING

FLG FLAGPOLE

FLM FULL LENGTH MIRROR

FLUOR FLUORESCENT

FO FINISH OPENING

FOC FACE OF CONCRETE

FOF FACE OF FINISH

FOM FACE OF MASONRY

FOS FACE OF STUD

FOW FACE OF WALL

FP FIREPROOFING

FP FILLER PANEL

FPG FIRE-PROTECTION-RATED GLAZING

FPS FOLDING AND PORTABLE STAGE

FR FIRE RESISTANT

FRG FIRE-RESISTANCE-RATED GLAZING

FRJ FIRE-RESISTIVE JOINT

FRP FIBERGLASS REINFORCED PANEL

FRT FIRE RESISTANCE TREATED

FS FLOOR SINK

FS FIRE STOPPING

FSS FOLDING SHOWER SEAT

FTG FOOTING

FVC FIRE VALVE CABINET

FWC FABRIC WALLCOVERING

FWC FACILITY WASTE COMPACTOR

FWC FLUSH WOOD DOOR

G GROUT

GA GAUGE

GAL GALLON

GALV GALVANIZED

GB GRAB BAR

GD GARBAGE DISPOSAL

GEN GENERAL

GFA GROSS FLOOR AREA

GFRC GLASS-FIBER REINFORCED CONCRETE

GL GLUE LAMINATED

GL GLASS

GLB GLAZED BRICK

GLM GLASS UNIT MASONRY

GM GROMMET

GMP GUARANTEED MAXIMUM PRICE

GR GUARD RAIL

GR GRADE

GRS GALVANIZED RIGID STEEL

GSB GYPSUM SHAFTLINER BOARD

GSWA GYPSUM BOARD SHAFT WALL ASSEMBLY

GT GLASS TILE

GVP GYPSUM VENEER PLASTER

GWB GYPSUM WALLBOARD

GYP GYPSUM

HC HOLLOW CORE

HCW HEALTHCARE CASEWORK

HD HAND DRYER

HDF HIGH DENSITY FIBERBOARD

HDR HEADER

HDWD HARDWOOD

HDWR HARDWARE

HM HOLLOW METAL

HMD HOLLOW METAL DOOR

HMF HOLLOW METAL FRAME

HR HOUR

HR HANDRAIL

HS HARDWARE SET

HSS HOLLOW STRUCTURAL SHAPE

HVAC HEATING VENTILATING AND AIR

CONDITIONING

IAW IN ACCORDANCE WITH

ICE ICE MAKER

ID INSIDE DIAMETER

IF INSIDE FACE

IIP INSULATING INFILL PANEL GLASS

IJ ISOLATION JOINT

IJS IN JOIST SPACE

INC INCLUDE(ING)

INSUL INSULATION

JAN JANITOR

JBE JOIST BEARING ELEVATION

JBX JUNCTION BOX

JCT JUNCTION

JFB JOINT FILLER BOARD

JST JOIST

JT JOINT

KCJ KEYED CONSTRUCTION JOINT

KD KNOCKDOWN

KH KITCHEN HOOD

KIT KITCHEN

L ANGLE

L LENGTH (LONG)

L LEVEL

LAB LABORATORY

LAM LAMINATED

LAV LAVATORY

LBR LUMBER

LCK LOCKER

LCW LABORATORY CASEWORK

LDE LOADING DOCK EQUIPMENT

LDG LOADING

LF LINEAR FOOT

LFH LABORATORY FUME HOOD

LG LAMINATED GLASS

LIN LINEAR

LINO LINOLEUM

LKR LOCKER

LMC LINEAR METAL CEILING

LOC LOCATION

LONG LONGITUDINAL

LSC LIFE SAFETY CODE

LSS LIBRARY STACK SYSTEM

LTG LIGHTING

LV LOUVER

LVT LUXURY VINYL TILE

MAG MAGNETIC

MAINT MAINTENANCE

MAN MANUAL

MAS MASONRY

MATL MATERIAL

MB MOP BASIN

MBD MARKERBOARD

MBH MOP/BROOM HOLDER

MC MEDICINE CABINET

MCJ MASONRY CONTROL JOINT

MEMB MEMBRANE

MH MANHOLE

MP METAL PANEL

MR/S MIRROR WITH SHELF

MSS METAL STORAGE SHELVING

MTD MOUNTED

MTG MOUNTING

MUL MULLION

MW MICROWAVE

NC NOISE CRITERIA

NFPA NATIONAL FIRE PROTECTION ASSOCIATION

NOM NOMINAL

NSMF NON-STRUCTURAL METAL FRAMING

O to O OUT TO OUT

OA OVERALL

OCCD OVERHEAD COILING COUNTER DOOR

OCD OVERHEAD COILING DOOR

OCG OVERHEAD COILING GRILLE

OFCI OWNER FURNISHED CONTRACTOR

INSTALLED

OFF OFFICE

OFOI OWNER FURNISHED OWNER INSTALLED

OH OPPOSITE HAND

OPG(S) OPENING(S)

OSHA OPERATIONAL SAFETY AND HEALTH

ADMINISTRATION

OTB OPEN TO BELOW

OVFL OVERFLOW

P PAINT

PAC PRECAST ARCHITECTURAL CONCRETE

PAN B PANIC BOLT

PB PARTICLE BOARD

PC PRECAST CONCRETE

PCD PAPER CUP DISPENSER

PCE PARKING CONTROL EQUIPMENT

PCEQ PATIENT CARE EQUIPMENT

PD PANIC DEVICE

PERF PERFORATED

PERP PERPENDICULAR

PFD PANEL FOLDING DOOR

PG PATTERN GLASS

PIC PORTABLE INSTRUMENT CONNECTION

PIG PATTERN INSULATING GLASS

PL PLATE

PL PROPERTY LINE

PL PLASTIC LAMINATE

PLAM PLASTIC LAMINATE

PLBG PLUMBING

PLT INTERIOR PLANTER

PR PAIR

PREFAB PREFABRICATED

PROJ PROJECT(OR) (ION)

PS PROJECTION SCREEN

PSC PRECAST STRUCTURAL CONCRETE

PT POINT

PT POINT OF TANGENCY

PT PORCELAIN TILE

PTD PAPER TOWEL DISPENSER

PTD/R COMBINATION TOWEL

DISPENSER/RECEPTACLE

PTN PARTITION

PTW PASS-THROUGH WINDOW

PVC POLYVINYL CHLORIDE

PWL SOUND POWER LEVEL

QGV QUAD GAS VALVE

QT QUARRY TILE

QTR RND QUARTER ROUND

R RISER

RAD RADIUS

RB RUBBER BASE

RBA RESILIENT BASE AND ACCESSORIES

RC REMOTE CONTROL

RCG REFLECTIVE-COATED GLASS

RCP REFLECTED CEILING PLAN

RD ROOF DRAIN

REF REFERENCE

REFL REFLECTED

REM REMOVABLE

RESIL RESILIENT

RF RESILIENT FLOORING

RF RUBBER FLOOR

RF ROOF(ING)

RFA ROOF ACCESSORIES

RFM RECESSED FLOOR MAT

RFS ROOF SPECIALTIES

RH ROBE HOOK

RI&C ROUGH IN AND CONNECT

RLG RAILING

RWB RESILIENT WALL BASE

S SINK

SAC SOUND ABSORBING CEILING UNITS

SAFF SELF-ADHERING FLEXIBLE FLASHING

SAT SPRAYED ACOUSTIC TREATMENT

SAW SOUND ABSORBING WALL UNITS

SAWP SELF-ADHERING SHEET WATERPROOFING

SB SPLASH BLOCK

SC SOLID CORE

SC SHOWER CURTAIN

SCD SEAT COVER DISPENSER

SCD SOUND CONTROL DOOR

SCH SHOWER CURTAIN HOOK

SCR SHOWER CURTAIN ROD

SCT STRUCTURAL CLAY TILE

SCU STAGE CURTAIN

SD SOAP DISPENSER

SDA SLIDING AUTOMATIC ENTRANCE

SECY SECRETARY

SF SQUARE FEET

SG SPECIALTY GLASS

SG SECURITY GLAZING

SGA SLOPED GLAZING ASSEMBLY

SGL SINGLE

SGV SINGLE GAS VALVE

SH SHOWER

SHG SHEATHING

SHM SECURITY HOLLOW METAL

SHW SHOWER VALVE AND HEAD

SIG SECURITY INSULATING GLAZING

SKY SKYLIGHT

SLNT SEALANT

SM SHEET METAL

SM SQUARE METER(S)

SMF SHEET METAL FLASHING

SND SANITARY NAPKIN DISPOSAL

SNTV SANITARY NAPKIN AND TAMPON VENDOR

SNV SANITARY NAPKIN VENDOR

SO SENSOR OPERATED

SPC SPECIALTY CONSTRUCTION

SPF SPRAY POLYURETHANE FOAM

SPG SPANDREL GLASS

SPIG SPANDREL INSULATING GLASS

SPL SOUND PRESSURE LEVEL

SPP STRUCTURED POLYCARBONATE PANEL

ASSEMBLY

SQ SQUARE

SR SURFACE MOUNTED ELECTRICAL

RACEWAY

SSA STORM SHELTER AREA

SSM SOLID SURFACE MATERIAL

SSS STAINLESS STEEL SHELF

SST STAINLESS STEEL

ST STONE

ST STAIR

ST SEATING

ST STONE TILE

STAG'D STAGGERED

STC SOUND TRANSMISSION CLASS

STC STONE CLADDING

STGR STRINGER

STV STONE VENEER

SUBFL SUBFLOOR

SUL SULPHUR

SURF SURFACE

SUSP SUSPENDED

SVF SHEET VINYL FLOORING

SVF SERVICE FIXTURE

SVG SERVICE FIXTURE GROUP

SW STEEL WINDOW

SWS SHAFT WALL STUD

T TREAD

T CERAMIC TILE

T&G TONGUE AND GROOVE

T.O. TOP OF

TAN TANGENT

TB TOWEL BAR

TB THIN BRICK

TB TILE BASE

TC TRAFFIC COATING

TCP TOILET COMPARTMENT PARTITION

TERR TERRAZZO

TG TINTED FLOAT GLASS

TH THRESHOLD

THK THICK(NESS)

TI TENANT IMPROVEMENT

TIG TINTED INSULATING GLASS

TKB TACKBOARD

TOIL TOILET

TOP TOP OF PAVING

TP TOILET PARTITION

TRANS TRANSVERSE

TS TELESCOPING STANDS

TSD TOILET SEAT COVER DISPENSER

TSKY TUBULAR DAYLIGHTING DEVICE

TT TERRAZZO TILE

TTD TOILET TISSUE DISPENSER

TTG TINTED TEMPERED FLOAT GLASS

TTIG TINTED TEMPERED INSULATING GLASS

TW TACK WALL

UK UNIT KITCHEN

UL UNDERWRITERS LABORATORIES

UND UNDERLAYMENT

UR URINAL

US UTILITY SHELF

UTIL UTILITY

VB VAPOR BARRIER

VB VINYL BASE

VCB VENTED COVE BASE

VCE VEHICLE CHARGING EQUIPMENT

VF VINYL FLOOR

VOC VOLATILE ORGANIC COMPOUND

VOL VOLUME

VP VENEER PLASTER

VR VAPOR RETARDER

VT VINYL TILE

VWC VINYL WALLCOVERING

W/I WITHIN

WB WALL BASE

WC WATER CLOSET

WC WALLCOVERING

WCL WATER CLOSET/LAVATORY COMBINATION

WD WOOD

WDAF WOOD ATHLETIC FLOORING

WDF WOOD FLOORING

WDW WINDOW

WG WIRE GLASS

WI WROUGHT IRON

WOC WALK OFF CARPET

WOM WALK OFF MAT

WR WASTE RECEPTACLE

WR WATER REPELLENT

WRB WEATHER RESISTANT BARRIER

WT WINDOW TREATMENT

WW WARM WHITE

WWF WELDED WIRE FABRIC

YD YARD

D FINAL

03/13/2026

W

2Q R

BA

1_

Pl an s-

COILING DOOR TO BE REPLACED WITH

NEW INSULATED OVERHEAD DOOR

RESTROOM

STORAGE

ROOM

AEROBICS

ROOM

VH

RESTROOM

MECH. ROOM

RAQUETBALL

COURT

RAQUETBALL

COURT

MASSAGE

ROOM

BOXING

TRAINING

ROOM

IT CLOS.

LAUNDRY

ROOM

SPRINKLER

RISE

JANITOR

ROOM

STAIRS

CONFERENCE

ROOM

OFFICE

TRANSFORM.

STORAGE

ROOM

WEIGHT ROOM

SPIN ROOM

MEN'S

SHOWERS

MEN'S

RESTROOM

MEN'S

RESTROOM

WOMEN'S

LOCKER ROOM

WOMEN'S

SHOWERS

SAUNA

WOMEN'S

RESTROOM

ELEC. ROOM

AD201

B1

AD201

L1

WORKOUT

AREA

MEN'S LOCKER

ROOM

BASKETBALL

COURT

AD201G1

AD102

B1

AD103

B1

AD104

B1

AD105

B1

AD106

B1

AD107

B1

ELECTRICAL

CLOSET

SAUNA

A-402

DEMOLITION GENERAL NOTES

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

K.

L.

M.

N.

O.

P.

THE CONTRACTOR SHALL:

COORDINATE ALL DEMOLITION AND PHASING EFFORTS WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). EVERY EFFORT SHALL BE MADE TO MINIMIZE DISRUPTION OF OCCUPANT'S OPERATIONS. EXCESSIVE NOISE OR VIBRATION SHALL BE PRE-APPROVED AND COORDINATED WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). IN ALL CASES, PROVISIONS SHALL BE MADE FOR

USER’S SAFETY.

COORDINATE ANY DISRUPTION OF UTILITY SERVICES WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND AS SPECIFIED.

CONSTRUCT TEMPORARY CONSTRUCTION PARTITIONS WITHIN THE EXISTING BUILDING WHICH OFFER A ONE-HOUR ENCLOSURE TO ISOLATE ANY DEMOLITION/CONSTRUCTION WORK FROM THE GENERAL PUBLIC AND AS DEEMED NECESSARY BY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND CODE OFFICIAL HAVING JURISDICTION. COORDINATE LOCATIONS WITH THE CONTRACTING OFFICER

REPRESENTATIVE (C0R) AND MAINTAIN MEANS OF EGRESS THROUGHOUT THE WORK.

MAINTAIN A SECURE, WEATHER-TIGHT ENCLOSURE AT ALL TIMES.

VERIFY ALL EXISTING CONDITIONS, DIMENSIONS AND ELEVATIONS AND NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) OF ANY DISCREPANCIES.

REMOVE IN THEIR ENTIRETY ALL EXISTING WALLS, DOORS, MILLWORK, PLUMBING FIXTURES, CEILINGS, SOFFITS, WALL FIXTURES, AND OTHER ITEMS, AS REQUIRED TO EXECUTE THE

DEMOLITION/CONSTRUCTION WORK DESCRIBED BY THE DRAWINGS.

PROVIDE PROTECTION FOR ALL EXISTING BUILDING MATERIALS AND EQUIPMENT FROM DAMAGE DUE TO ANY DEMOLITION OR CONSTRUCTION-RELATED INCIDENT PERFORMED UNDER THIS CONTRACT.

REPAIR OR REPLACE ITEMS THAT ARE DAMAGED AS A RESULT OF DEMOLITION OR CONSTRUCTION TO MATCH EXISTING FINISH AND/OR CONDITION.

NO EXISTING MATERIALS SHALL BE REUSED IN ANY INSTANCE. DISPOSE OF EXISTING DEMOLISHED MATERIALS AS PER SPECIFICATIONS.

VERIFY AND MAINTAIN THE LOCATION OF EXISTING POWER, COMMUNICATION AND DATA CABLES TO PREVENT INTERRUPTION OF THEIR SERVICE.

PATCH FLOOR, WALL AND CEILING PENETRATIONS RESULTING FROM REMOVAL OR RE-ROUTING OF NEW OR EXISTING PIPING, DUCTWORK, CONDUIT, AND OTHER ITEMS, AS REQUIRED TO MAINTAIN FIRE- RESISTANCE-RATED SEPARATIONS. FINISH AS REQUIRED FOR NEW OR EXISTING ADJACENT SURFACES.

CAP ALL DISCONNECTED MECHANICAL PIPING LINES WITHIN THE WALL OR FLOOR. PATCH AND FINISH AS REQUIRED TO MATCH NEW OR EXISTING ADJACENT SURFACES.

SEE MECHANICAL AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.

WHERE CMU WALLS ARE INDICATED TO BE REMOVED, PREPARE ADJACENT WALLS TO RECEIVE NEW PATCH/FINISH BY SAWCUTTING AND OR REMOVING CMU IN TOOTH-IN PATTERN BOTH SIDES OF DEMOLITION

FOR CONTRACTOR TO TOOTH-IN NEW CMU PATCHES AS NEEDED.

SEE MECHANICAL, PLUMBING AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.

COORDINATE WITH HAZARDOUS ABATEMENT SHEETS AND REPORT BEFORE ANY DEMOLITION TAKES PLACE.

DEMOLITION NOTES APPLY TO ALL DEMOLITION SHEETS.

US Army Corps of Engineers ®

SHEET ID

U S

AR

M

Y C

O R

PS

O

F

EN

G

IN

EE

R

S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

N

3 5 7 9 11 13 15 17 19

L

J

G

E

C

A

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

2 4 6 8 10 12 14 16 18 20

P

M

K

H

F

D

B

Au to de sk

D oc s:

//2

5-

6-

D

LA

D

SC

C

B ld g.

R

E

PF

R em od /2

5-

6-

_D

LA

D

SC

C

B ld g.

R

E

PF

R em od _A

R _2

4.

rv t

4/

/2

5:

:1

PM

AD101

D

EM

O

LI

TI

O

N P

LA

N

O

VE

R

AL

L

C O

LU

M

BU

S, O H

IO

LO

U

IS

VI

LL

E, K

Y E.

E.

E.

E.

A.

B.

E.

B.

M ar ch

3, 0%

C

ER

TI

FI

ED

F

IN

AL

D

SC

C D

LA

R

EP

AI

R B

U

IL

D

IN

G

-2

-0

1/16" = 1'-0"C1 OVERALL DEMOLITION PLAN, LEVEL 1

0 10 20

SCALE: 1/16" = 1'=0"

GLASS WALL TO BE

REMOVED

D FINAL

03/13/2026

W

2Q R

BA

1_

Pl an s-

DEMOLITION GENERAL NOTES

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

K.

L.

M.

N.

O.

P.

THE CONTRACTOR SHALL:

COORDINATE ALL DEMOLITION AND PHASING EFFORTS WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). EVERY EFFORT SHALL BE MADE TO MINIMIZE DISRUPTION OF OCCUPANT'S OPERATIONS. EXCESSIVE NOISE OR VIBRATION SHALL BE PRE-APPROVED AND COORDINATED WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). IN ALL CASES, PROVISIONS SHALL BE MADE FOR

USER’S SAFETY.

COORDINATE ANY DISRUPTION OF UTILITY SERVICES WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND AS SPECIFIED.

CONSTRUCT TEMPORARY CONSTRUCTION PARTITIONS WITHIN THE EXISTING BUILDING WHICH OFFER A ONE-HOUR ENCLOSURE TO ISOLATE ANY DEMOLITION/CONSTRUCTION WORK FROM THE GENERAL PUBLIC AND AS DEEMED NECESSARY BY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND CODE OFFICIAL HAVING JURISDICTION. COORDINATE LOCATIONS WITH THE CONTRACTING OFFICER

REPRESENTATIVE (C0R) AND MAINTAIN MEANS OF EGRESS THROUGHOUT THE WORK.

MAINTAIN A SECURE, WEATHER-TIGHT ENCLOSURE AT ALL TIMES.

VERIFY ALL EXISTING CONDITIONS, DIMENSIONS AND ELEVATIONS AND NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) OF ANY DISCREPANCIES.

REMOVE IN THEIR ENTIRETY ALL EXISTING WALLS, DOORS, MILLWORK, PLUMBING FIXTURES, CEILINGS, SOFFITS, WALL FIXTURES, AND OTHER ITEMS, AS REQUIRED TO EXECUTE THE

DEMOLITION/CONSTRUCTION WORK DESCRIBED BY THE DRAWINGS.

PROVIDE PROTECTION FOR ALL EXISTING BUILDING MATERIALS AND EQUIPMENT FROM DAMAGE DUE TO ANY DEMOLITION OR CONSTRUCTION-RELATED INCIDENT PERFORMED UNDER THIS CONTRACT.

REPAIR OR REPLACE ITEMS THAT ARE DAMAGED AS A RESULT OF DEMOLITION OR CONSTRUCTION TO MATCH EXISTING FINISH AND/OR CONDITION.

NO EXISTING MATERIALS SHALL BE REUSED IN ANY INSTANCE. DISPOSE OF EXISTING DEMOLISHED MATERIALS AS PER SPECIFICATIONS.

VERIFY AND MAINTAIN THE LOCATION OF EXISTING POWER, COMMUNICATION AND DATA CABLES TO PREVENT INTERRUPTION OF THEIR SERVICE.

PATCH FLOOR, WALL AND CEILING PENETRATIONS RESULTING FROM REMOVAL OR RE-ROUTING OF NEW OR EXISTING PIPING, DUCTWORK, CONDUIT, AND OTHER ITEMS, AS REQUIRED TO MAINTAIN FIRE- RESISTANCE-RATED SEPARATIONS. FINISH AS REQUIRED FOR NEW OR EXISTING ADJACENT SURFACES.

CAP ALL DISCONNECTED MECHANICAL PIPING LINES WITHIN THE WALL OR FLOOR. PATCH AND FINISH AS REQUIRED TO MATCH NEW OR EXISTING ADJACENT SURFACES.

SEE MECHANICAL AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.

WHERE CMU WALLS ARE INDICATED TO BE REMOVED, PREPARE ADJACENT WALLS TO RECEIVE NEW PATCH/FINISH BY SAWCUTTING AND OR REMOVING CMU IN TOOTH-IN PATTERN BOTH SIDES OF DEMOLITION

FOR CONTRACTOR TO TOOTH-IN NEW CMU PATCHES AS NEEDED.

SEE MECHANICAL, PLUMBING AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.

COORDINATE WITH HAZARDOUS ABATEMENT SHEETS AND REPORT BEFORE ANY DEMOLITION TAKES PLACE.

DEMOLITION NOTES APPLY TO ALL DEMOLITION SHEETS.

CONFERENCE

ROOM

RESTROOM

LAUNDRY

ROOM

OFFICE

STORAGE

ROOM

WORKOUT

AREA

STORAGE

ROOM

IT CLOS.

TRANSFORM.

DEMO SHEET NOTES#

TRUE

N

WOMEN'S

LOCKER

MEN'S

LOCKER

MECHANICAL

ROOM

20'-3 3/8"

SAUNA

SAUNA

6'-10"

MEN'S

WOMEN'S

WOMEN MEN

HCSHOWER

MECHROOM

TYP

LOCKERWOMEN'S

P/B/F 24 P/B/F 24

P/ B/

F

P/ B/

F

P/B/F 24P/B/F 24

P/B/F 24 P/B/F 24

AREA NOT IN SCOPE

AREA OF WORK

US Army Corps of Engineers ®

SHEET ID

U S

AR

M

Y C

O R

PS

O

F

EN

G

IN

EE

R

S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

N

3 5 7 9 11 13 15 17 19

L

J

G

E

C

A

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

2 4 6 8 10 12 14 16 18 20

P

M

K

H

F

D

B

KEYPLAN

SCALE: N.T.S.

Au to de sk

D oc s:

//2

5-

6-

D

LA

D

SC

C

B ld g.

R

E

PF

R em od /2

5-

6-

_D

LA

D

SC

C

B ld g.

R

E

PF

R em od _A

R _2

4.

rv t

4/

/2

5:

:1

PM

AD102

D

EM

O

LI

TI

O

N P

LA

N

AR

EA

1N

C O

LU

M

BU

S, O H

IO

LO

U

IS

VI

LL

E, K

Y E.

E.

E.

E.

A.

B.

E.

B.

M ar ch

3, 0%

C

ER

TI

FI

ED

F

IN

AL

D

SC

C D

LA

R

EP

AI

R B

U

IL

D

IN

G

-2

-0

1/8" = 1'-0"B1 OVERALL DEMOLITION PLAN - AREA 11-N

0 5 10

SCALE: 1/8" = 1'=0"

1 EXISTING OVERHEAD COILING DOOR TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING DOOR AND PREPARE OPENING FOR NEW

COMPONENT TO BE INSTALLED AS PER SCHEDULE.

2 EXISTING EXTERIOR DOOR AND FRAME TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING DOOR AND PREPARE OPENING FOR NEW

COMPONENT TO BE INSTALLED AS PER SCHEDULE.

3 EXISTING EXTERIOR WINDOW TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING WINDOW AND PREPARE OPENING FOR NEW

COMPONENT TO BE INSTALLED AS PER SCHEDULE.

4 EXISTING EXTERIOR LOUVER TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING LOUVER AND PREPARE OPENING TO BE FILLED AS

PER STRUCTURAL DETAILS.

5 EXISTING INTERIOR DOOR AND FRAME TO BE REMOVED.

6 INCREASE ROUGH OPENING SIZE TO ACCOMODATE A NEW PAIR 3-0 DOORS.

7 EXISTING OVERHEAD DOOR TO REMAIN IN PLACE.

8 EXISTING WINDOW TO REMAIN IN PLACE .

9 EXISTING EXTERIOR DOOR TO REMAIN IN PLACE.

10 EXISTING GLASS WALL TO BE REMOVED. REMOVE ALL FASTENERS AND BRACKETS IN PREPARATION TO INSTALL A NEW METAL STUD WALL AS PER PLANS.

CONFIRM WITH OWNER FOR SALVAGED ITEMS.

11 EXISTING WALL AND WALL MOUNTED ITEMS TO BE REMOVED. VERIFY DIMENSIONS ON SITE.

12 EXISTING VIEWING WINDOW INTO RACQUET BALL COURT TO BE REMOVED.

13 EXISTING RACQUET BALL FLOORING TO BE REMOVED TO CONCRETE SLAB. PREPARE CONCRETE SLAB TO RECEIVE NEW FLOORING AS PER FINISH SCHEDULE.

14 EXISTING RACQUET BALL HARD CEILING TO BE REMOVED. RE: MEP DRAWINGS FOR ADDITIONAL INFORMATION.

15 NEW DOOR OPENING FOR NEW ACCESS DOOR TO RACQUET BALL COURT.

16 DIMENSION TO BE VERIFIED IN FIELD. APPROXIMATE BASED ON EXISTING DOCUMENTS.

17 EXISTING SUSPENDED ACCOUSTICAL CEILING SYSTEM TO BE REMOVED.. RE:MEP FOR ADDITIONAL INFORMATION.

18 EXISTING FLOORING TO BE REMOVED TO CONCRETE SLAB. PREPARE EXISTING SLAB FOR NEW FLOORING AS PER FINISH SCHEDULE.

19 EXISTING WALL PADDING TO BE REMOVED.

20 EXISTING MECHANICAL MEZZANINE ABOVE THIS AREA TO BE REMOVED.

21 EXISTING LADDER TO MEZZANINE TO BE REMOVED WITH ALL COMPONENTS, INCLUDING BUT NOT LIMITED TO FASTENERS, BRACKETS, ETC.. REPAIR WALL, PATCH HOLES, REPAIR FLOORING AND REFINISH WALL AND FLOOR TO MATCH ADJACENT.

22 EXISTING ELECTRICAL CLOSET TO REMAIN IN PLACE. PROTECT DURING DEMOLITION.

23 EXISTING FLOORING DECK TO BE REMOVED. JOIST TO REMAIN IN PLACE.

24 REMOVE ALL DEBRIS LEFT OUT FROM MECHANICAL AND ELECTRICAL DEMOLITION WORK LEFT BEHIND INCLUDING BUT NOT LIMITED TO FASTENERS, HANGERS, METAL PANS, ETC.

25 REMOVE EXISTING ACCESS LADDER AND ALL ASSOCIATED HARDWARE. PATCH HOLES AND REPAINT WALLS AS NEEDED. PATCH AND CLEAN UP FLOOR TO

MATCH EXISTING.

26 EXISTING METAL CAGE TO BE REMOVED. PATCH ALL HOLES, AND REPAIR ANY OTHER DAMAGES AROUND THE WINDOW OPENING TO MATCH ADJACENT

WALLS.

27 EXISTING FAN IN CAGE TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING FAN INCLUDING THE CAGE AND PREPARE OPENING TO BE

FILLED AS PER STRUCTURAL DETAILS. RE: MECHANICAL DEMOLITION DRAWINGS FOR ADDITIONAL INFORMATION.

28 REMOVE EXISTING VINYL FLOORING AND PREPARE SUBSTRATE FOR INSTALLATION OF NEW VINYL FLOORING.

29 SAW CUT BRICK BELOW THE EXISTING WINDOW TO EXTEND THE EXISTING OPENING TO THE FLOOR, CLEAN AND PREPARE TO RECEIVE NEW BLOCK NEW HM

DOOR AND FRAME.

D FINAL

03/13/2026

W

2Q R

BA

1_

Pl an s-

B.

C.

D.

E.

F.

G.

H.

I.

J.

K.

L.

M.

N.

O.

P.

THE CONTRACTOR SHALL:

COORDINATE ALL DEMOLITION AND PHASING EFFORTS WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). EVERY EFFORT SHALL BE MADE TO MINIMIZE DISRUPTION OF OCCUPANT'S OPERATIONS. EXCESSIVE NOISE OR VIBRATION SHALL BE PRE-APPROVED AND COORDINATED WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). IN ALL CASES, PROVISIONS SHALL BE MADE FOR

USER’S SAFETY.

COORDINATE ANY DISRUPTION OF UTILITY SERVICES WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND AS SPECIFIED.

CONSTRUCT TEMPORARY CONSTRUCTION PARTITIONS WITHIN THE EXISTING BUILDING WHICH OFFER A ONE-HOUR ENCLOSURE TO ISOLATE ANY DEMOLITION/CONSTRUCTION WORK FROM THE GENERAL PUBLIC AND AS DEEMED NECESSARY BY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND CODE OFFICIAL HAVING JURISDICTION. COORDINATE LOCATIONS WITH THE CONTRACTING OFFICER

REPRESENTATIVE (C0R) AND MAINTAIN MEANS OF EGRESS THROUGHOUT THE WORK.

MAINTAIN A SECURE, WEATHER-TIGHT ENCLOSURE AT ALL TIMES.

VERIFY ALL EXISTING CONDITIONS, DIMENSIONS AND ELEVATIONS AND NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) OF ANY DISCREPANCIES.

REMOVE IN THEIR ENTIRETY ALL EXISTING WALLS, DOORS, MILLWORK, PLUMBING FIXTURES, CEILINGS, SOFFITS, WALL FIXTURES, AND OTHER ITEMS, AS REQUIRED TO EXECUTE THE

DEMOLITION/CONSTRUCTION WORK DESCRIBED BY THE DRAWINGS.

PROVIDE PROTECTION FOR ALL EXISTING BUILDING MATERIALS AND EQUIPMENT FROM DAMAGE DUE TO ANY DEMOLITION OR CONSTRUCTION-RELATED INCIDENT PERFORMED UNDER THIS CONTRACT.

REPAIR OR REPLACE ITEMS THAT ARE DAMAGED AS A RESULT OF DEMOLITION OR CONSTRUCTION TO MATCH EXISTING FINISH AND/OR CONDITION.

NO EXISTING MATERIALS SHALL BE REUSED IN ANY INSTANCE. DISPOSE OF EXISTING DEMOLISHED MATERIALS AS PER SPECIFICATIONS.

VERIFY AND MAINTAIN THE LOCATION OF EXISTING POWER, COMMUNICATION AND DATA CABLES TO PREVENT INTERRUPTION OF THEIR SERVICE.

PATCH FLOOR, WALL AND CEILING PENETRATIONS RESULTING FROM REMOVAL OR RE-ROUTING OF NEW OR EXISTING PIPING, DUCTWORK, CONDUIT, AND OTHER ITEMS, AS REQUIRED TO MAINTAIN FIRE- RESISTANCE-RATED SEPARATIONS. FINISH AS REQUIRED FOR NEW OR EXISTING ADJACENT SURFACES.

CAP ALL DISCONNECTED MECHANICAL PIPING LINES WITHIN THE WALL OR FLOOR. PATCH AND FINISH AS REQUIRED TO MATCH NEW OR EXISTING ADJACENT SURFACES.

SEE MECHANICAL AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.

WHERE CMU WALLS ARE INDICATED TO BE REMOVED, PREPARE ADJACENT WALLS TO RECEIVE NEW PATCH/FINISH BY SAWCUTTING AND OR REMOVING CMU IN TOOTH-IN PATTERN BOTH SIDES OF DEMOLITION

FOR CONTRACTOR TO TOOTH-IN NEW CMU PATCHES AS NEEDED.

SEE MECHANICAL, PLUMBING AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.

COORDINATE WITH HAZARDOUS ABATEMENT SHEETS AND REPORT BEFORE ANY DEMOLITION TAKES PLACE.

DEMOLITION NOTES APPLY TO ALL DEMOLITION SHEETS.

8' - 9 1/2" +/- VIF

BASKETBALL

COURT

MEN'S

RESTROOM

MEN'S

SHOWERS

MECH. ROOM

WOMEN'S

RESTROOM

WOMEN'S

SHOWERS

WOMEN'S

LOCKER ROOM

SPRINKLER

RISE

2 3

32' - 2" +/- VIF

26 26

SAUNA

1212 SAUNA

A-402

DEMO SHEET NOTES#

WOMEN'S

LOCKER

MEN'S

LOCKER

MECHANICAL

ROOM

20'-3 3/8"

SAUNA

SAUNA

6'-10"

MEN'S

WOMEN'S

WOMEN MEN

HCSHOWER

MECHROOM

TYP

LOCKERWOMEN'S

P/B/F 24 P/B/F 24

P/ B/

F

P/ B/

F

P/B/F 24P/B/F 24

P/B/F 24 P/B/F 24

AREA NOT IN SCOPE

AREA OF WORK

WOMEN'S

LOCKER

MEN'S

LOCKER

MECHANICAL

ROOM

20'-3 3/8"

SAUNA

SAUNA

6'-10"

MEN'S

WOMEN'S

WOMEN MEN

HCSHOWER

MECHROOM

TYP

LOCKERWOMEN'S

P/B/F 24 P/B/F 24

P/ B/

F

P/ B/

F

P/B/F 24P/B/F 24

P/B/F 24 P/B/F 24

AREA NOT IN SCOPE

AREA OF WORK

US Army Corps of Engineers ®

SHEET ID

U S

AR

M

Y C

O R

PS

O

F

EN

G

IN

EE

R

S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

AN

SI

D

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

N

3 5 7 9 11 13 15 17 19

L

J

G

E

C

A

D

AT

E M

AR

K

D

ES

C R

IP

TI

O N

Fi le

P at h:

Pl ot D at e:

2 4 6 8 10 12 14 16 18 20

P

M

K

H

F

D

B

Au to de sk

D oc s:

//2

5-

6-

D

LA

D

SC

C

B ld g.

R

E

PF

R em od /2

5-

6-

_D

LA

D

SC

C

B ld g.

R

E

PF

R em od _A

R _2

4.

rv t

4/

/2

5:

:1

PM

AD103

D

EM

O

LI

TI

O

N P

LA

N

AR

EA

2N

C O

LU

M

BU

S, O H

IO

LO

U

IS

VI

LL

E, K

Y E.

E.

E.

E.

A.

B.

E.

B.

M ar ch

3, 0%

C

ER

TI

FI

ED

F

IN

AL

D

SC

C D

LA

R

EP

AI

R B

U

IL

D

IN

G

-2

-0

1/8" = 1'-0"B1 OVERALL DEMOLITION PLAN - AREA 12-N

0 5 10

SCALE: 1/8" = 1'=0"

1 EXISTING OVERHEAD COILING DOOR TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING DOOR AND PREPARE OPENING FOR NEW

COMPONENT TO BE INSTALLED AS PER SCHEDULE.

2 EXISTING EXTERIOR DOOR AND FRAME TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING DOOR AND PREPARE OPENING FOR NEW

COMPONENT TO BE INSTALLED AS PER SCHEDULE.

3 EXISTING EXTERIOR WINDOW TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING WINDOW AND PREPARE OPENING FOR NEW

COMPONENT TO BE INSTALLED AS PER SCHEDULE.

4 EXISTING EXTERIOR LOUVER TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING LOUVER AND PREPARE OPENING TO BE FILLED AS

PER STRUCTURAL DETAILS.

5 EXISTING INTERIOR DOOR AND FRAME TO BE REMOVED.

6 INCREASE ROUGH OPENING SIZE TO ACCOMODATE A NEW PAIR 3-0 DOORS.

7 EXISTING OVERHEAD DOOR TO REMAIN IN PLACE.

8 EXISTING WINDOW TO REMAIN IN PLACE .

9 EXISTING EXTERIOR DOOR TO REMAIN IN PLACE.

10 EXISTING GLASS WALL TO BE REMOVED. REMOVE ALL FASTENERS AND BRACKETS IN PREPARATION TO INSTALL A NEW METAL STUD WALL AS PER PLANS.

CONFIRM WITH OWNER FOR SALVAGED ITEMS.

11 EXISTING WALL AND WALL MOUNTED ITEMS TO BE REMOVED. VERIFY DIMENSIONS ON SITE.

12 EXISTING VIEWING WINDOW INTO RACQUET BALL COURT TO BE REMOVED.

13 EXISTING RACQUET BALL FLOORING TO BE REMOVED TO CONCRETE SLAB. PREPARE CONCRETE SLAB TO RECEIVE NEW FLOORING AS PER FINISH SCHEDULE.

14 EXISTING RACQUET BALL HARD CEILING TO BE REMOVED. RE: MEP DRAWINGS FOR ADDITIONAL INFORMATION.

15 NEW DOOR OPENING FOR NEW ACCESS DOOR TO RACQUET BALL COURT.

16 DIMENSION TO BE VERIFIED IN FIELD. APPROXIMATE BASED ON EXISTING DOCUMENTS.

17 EXISTING SUSPENDED ACCOUSTICAL CEILING SYSTEM TO BE REMOVED.. RE:MEP FOR ADDITIONAL INFORMATION.

18 EXISTING FLOORING TO BE REMOVED TO CONCRETE SLAB.

This is the start of the file's text. The full file is on GovTribe.