This is a set of architectural construction plans and phasing documents for the renovation/repair of Building 27 at Defense Supply Center Columbus (DSCC), Wright-Patterson Air Force Base, Ohio, under U.S. Army Corps of Engineers solicitation W912QR26BA021. The project involves comprehensive renovation of an athletic/fitness facility including locker rooms, mechanical systems, HVAC, electrical, plumbing, fire protection, and structural work. The work is organized into five distinct phases designed to maintain continuous facility operations during Phases 1-4, with only a maximum 14-calendar-day full facility shutdown during Phase 5. Phase 1 includes complete renovation of all locker rooms, construction of a new mechanical room, and installation of all MEP stub-outs and main distribution pathways. Phases 2-4 may occur in any order with government approval and will complete architectural finishes, branch ductwork, piping, power, lighting, and controls installations. Phase 5 requires removal of existing air handling units and fans, complete replacement of the 750 kVA electrical service transformer, water heater replacement, exterior EIFS installation and envelope work, vestibule demolition and replacement, and final mechanical system connections.
The plans specify that the contractor must submit a detailed phasing and sequencing plan within 30 days of Notice to Proceed (NTP) addressing dust/debris/abatement control, egress plans, equipment movement, mechanical/electrical routing, shutdown coordination, and temporary partitions. Critical requirements include maintaining restroom operations during all phases except Phase 5, providing designated haul routes for demolition and material removal, daily cleaning to limit dust migration, and negative air/HEPA filtration during Phase 1 and 5 demolition work. The contractor must coordinate all disruptions of utility services, fire protection/alarm systems, and security systems at least 14 days in advance and provide continuous fire watch if any life safety systems are offline. Testing, Adjusting, and Balancing (TAB) activities must be performed in a fully occupied facility and coordinated with government and facility management to avoid shutdowns and minimize disruption. All final commissioning, system integration, and training shall occur only after Phase 5 completion.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION LAYDOWN AREA
PROPOSED
LAYDOWN AREA.
PROJECT SITE
VICINITY MAP
PROJECT SITE
MAP ENLARGEMENT
CONSTRUCTION
LAYDOWN AREA.
JOHN GLENN COLUMBUS
INTERNATIONAL AIRPORT
CONSTRUCTION ACCESS ROUTE
AREA OF
CONSTRUCTION.
PROJECT SITE
ACCESS
GATE
PROPOSED
HAUL ROUTE
US Army Corps of Engineers ®
SHEET ID
U S
AR
M
Y C
O R
PS
O
F
EN
G
IN
EE
R
S
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
SU
BM
IT
TE
D B
Y:
SI
ZE
C H
EC
KE
D B
Y:
AN
SI
D
IS
SU
E D
AT
E:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
N
3 5 7 9 11 13 15 17 19
L
J
G
E
C
A
D
AT
E
US Army Corps of Engineers ®
SOLICITATION NO.:
CONTRACT NO.:
ISSUE DATE:
VOLUME:
M
AR
K D
ES
C
R
IP
TI
O
N
Fi le
P at h:
Pl ot D at e:
2 4 6 8 10 12 14 16 18 20
P
M
K
H
F
D
B
Au to de sk
D oc s:
//2
5-
6-
D
LA
D
SC
C
B ld g.
R
E
PF
R em od /2
5-
6-
_D
LA
D
SC
C
B ld g.
R
E
PF
R em od _A
R _2
4.
rv t
4/
/2
5:
:4
PM
G-001
C O
VE
R
S H
EE
T
C O
LU
M
BU
S, O H
IO
LO
U
IS
VI
LL
E, K
Y E.
E.
E.
E.
E.
B.
M ar ch
3, D
SC
C D
LA
R
EP
AI
R B
U
IL
D
IN
G
-2
-0
LOUISVILLE, KY
March 13, 2026
COLUMBUS, OHIO
DSCC DLA REPAIR BUILDING 27
100% CERTIFIED FINAL
25-25126-00 P2# 519087
D FINAL
03/13/2026
06 August 2026
W912QR26BA021
W
2Q R
BA
1_
Pl an s-
US Army Corps of Engineers ®
SHEET ID
U S
AR
M
Y C
O R
PS
O
F
EN
G
IN
EE
R
S
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
SU
BM
IT
TE
D B
Y:
SI
ZE
C H
EC
KE
D B
Y:
AN
SI
D
IS
SU
E D
AT
E:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
N
3 5 7 9 11 13 15 17 19
L
J
G
E
C
A
D
AT
E M
AR
K
D
ES
C R
IP
TI
O N
Fi le
P at h:
Pl ot D at e:
2 4 6 8 10 12 14 16 18 20
P
M
K
H
F
D
B
Au to de sk
D oc s:
//2
5-
6-
D
LA
D
SC
C
B ld g.
R
E
PF
R em od /2
5-
6-
_D
LA
D
SC
C
B ld g.
R
E
PF
R em od _A
R _2
4.
rv t
4/
/2
5:
:5
PM
GI001
SH
EE
T
IN
D
EX
C O
LU
M
BU
S, O H
IO
LO
U
IS
VI
LL
E, K
Y E.
E.
E.
E.
A.
B.
E.
B.
M ar ch
3, 0%
C
ER
TI
FI
ED
F
IN
AL
D
SC
C D
LA
R
EP
AI
R B
U
IL
D
IN
G
-2
-0
.ARCHITECTURAL.
A11.7.1 STAIR AND ELEVATOR DETAILS
A11.7.2 STAIR AND ELEVATOR DETAILS
A-001 GENERAL NOTES, ARCHITECTURAL SYMBOLS & ABBREVIATIONS
AD101 DEMOLITION PLAN OVERALL
AD102 DEMOLITION PLAN - AREA 11N
AD103 DEMOLITION PLAN - AREA 12N
AD104 DEMOLITION PLAN - AREA 13N
AD105 DEMOLITION PLAN - AREA 11S
AD106 DEMOLITION PLAN - AREA 12S
AD107 DEMOLITION PLAN - AREA 13S
AD108 DEMOLITION PLAN - MEZZANINE AREA
AD201 EXTERIOR DEMO ELEVATIONS
A-101 FLOOR PLAN OVERALL
A-102 FLOOR PLAN - AREA 11N
A-103 FLOOR PLAN - AREA 12N
A-104 FLOOR PLAN - AREA 13N
A-105 FLOOR PLAN - AREA 11S
A-106 FLOOR PLAN - AREA 12S
A-107 FLOOR PLAN - AREA 13S
A-108 OVERALL - REFLECTED CEILING PLAN
A-201 EXTERIOR ELEVATIONS
A-401 PARTITION TYPES
A-402 DOOR & WINDOWS FRAME TYPE & SCHEDULE
A-501 DOOR AND FRAME DETAILS
A-502 EXTERIOR DETAILS
.GENERAL.
G-001 COVER SHEET
GI001 SHEET INDEX
GC001 GENERAL PHASING NOTES
GC002 FLOOR PLAN OVERALL PHASING
.STRUCTURAL.
S-001 GENERAL STRUCTURAL NOTES
S-002 GENERAL STRUCTURAL NOTES & SPECIAL INSPECTIONS
S-003 GENERAL STRUCTURAL NOTES, SYMBOLS & ABBREVIATIONS
S-100 STRUCTURAL PLAN - AREA 11N
S-101 STRUCTURAL PLAN - AREA 11S
S-102 STRUCTURAL PLAN - AREA 12N
S-103 STRUCTURAL PLAN - AREA 12S
S-104 STRUCTURAL PLAN - AREA 13N
S-105 STRUCTURAL PLAN - AREA 13S
S-500 STRUCTURAL DETAILS
S-501 STRUCTURAL DETAILS
.MECHANICAL.
M-001 GENERAL INFORMATION - HVAC
MD101 AREA 11-N HVAC DEMOLITION PLAN
MD102 AREA 12-N HVAC DEMOLITION PLAN
MD103 AREA 13-N HVAC DEMOLITION PLAN
MD104 AREA 11-S HVAC DEMOLITION PLAN
MD105 AREA 12-S HVAC DEMOLITION PLAN
MD106 AREA 13-S HVAC DEMOLITION PLAN
MD401 MEZZANINE ENLARGED HVAC DEMOLITION PLAN
M-002 FIRST FLOOR HVAC ZONING PLAN
MH101 AREA 11-N HVAC DUCTWORK PLAN
MH102 AREA 12-N HVAC DUCTWORK PLAN
MH103 AREA 13-N HVAC DUCTWORK PLAN
MH104 AREA 11-S HVAC DUCTWORK PLAN
MH105 AREA 12-S HVAC DUCTWORK PLAN
MH106 AREA 13-S HVAC DUCTWORK PLAN
MH107 BOILER ROOM HVAC DUCTWORK PLAN
MH501 HVAC DETAILS
MH701 HVAC SCHEDULES
MP101 AREA 11-N HVAC PIPING PLAN
MP102 AREA 12-N HVAC PIPING PLAN
MP103 AREA 13-N HVAC PIPING PLAN
MP104 AREA 11-S HVAC PIPING PLAN
MP105 AREA 12-S HVAC PIPING PLAN
MP106 AREA 13-S HVAC PIPING PLAN
MP501 HVAC DETAILS
MP601 HVAC PIPING SCHEMATICS
MP701 HVAC SCHEDULES
M-301 MECHANICAL ROOM SECTION AND ISOMETRIC VIEWS
M-401 MECHANICAL ROOM ENLARGED PLAN
MI801 HVAC SEQUENCE OF OPERATIONS / CONTROLS
MI802 HVAC SEQUENCE OF OPERATIONS / CONTROLS
MI803 HVAC SEQUENCE OF OPERATIONS / CONTROLS
MI804 HVAC SEQUENCE OF OPERATIONS / CONTROLS
.PLUMBING.
P-001 GENERAL INFORMATION - PLUMBING
PD101 LEVEL 01 - AREA 11-N PLUMBING DEMOLITION PLAN
PD102 LEVEL 01 - AREA 12-N PLUMBING DEMOLITION PLAN
PL101 AREA 11-N - PLUMBING PLAN
PL102 AREA 12-N - PLUMBING PLAN
PL104 AREA 11-S - PLUMBING PLAN
PL105 AREA 12-S - PLUMBING PLAN
P-401 ENLARGED PLUMBING PLANS
P-501 PLUMBING DETAILS/SCHEDULES
.FIRE PROTECTION.
FP001 NOTES & LEGENDS - FIRE PROTECTION
FA001 FIRE ALARM LEGEND, NOTES, DIAGRAMS AND ABBREVIATIONS
FP100 FIRE PROTECTION SITE PLAN
FS101 LEVEL 01 - LIFE SAFETY PLAN
FS102 LEVEL 01 - BUILDING CODE ANALYSIS
FS103 LEVEL 01 - BUILDING CODE ANALYSIS
FD101 LEVEL 01 - FIRE PROTECTION DEMOLITION OVERALL FLOOR PLAN
FD201 LEVEL 01 - AREA 12 - FIRE ALARM DEMOLITION PLAN
FH101 LEVEL 01 - FIRE PROTECTION OVERALL HAZARD PLAN
FP101 AREA 12-N FIRE SPRINKLER PLAN
FP102 AREA 12-S FIRE SPRINKLER PLAN
FP103 AREA 13-S FIRE SPRINKLER PLAN
FP104 AREA 10-N FIRE SPRINKLER PLAN
FA201 LEVEL 01 - AREA 12 - FIRE ALARM PLAN
FP501 FIRE PROTECTION DETAILS
FA501 FIRE ALARM DETAILS
FP601 MECHANICAL ROOM 1203 HYDRAULIC CALCS
FP602 MECHANICAL ROOM 1203 HYDRAULIC CALCS
FP603 MOST REMOTE AREA HYDRAULIC CALCS
FP604 MOST REMOTE AREA HYDRAULIC CALCS
FP605 BOILER ROOM HYDRAULIC CALCS
FP606 BOILER ROOM HYDRAULIC CALCS
FP607 BOILER ROOM HYDRAULIC CALCS
.ELECTRICAL.
E-001 GENERAL INFORMATION - ELECTRICAL
ED101 AREA 11-N - ELECTRICAL DEMOLITION PLAN
ED102 AREA 12-N - ELECTRICAL DEMOLITION PLAN
ED103 AREA 13-N - ELECTRICAL DEMOLITION PLAN
ED104 AREA 11-S - ELECTRICAL DEMOLITION PLAN
ED105 AREA 12-S - ELECTRICAL DEMOLITION PLAN
ED106 AREA 13-S - ELECTRICAL DEMOLITION PLAN
ED107 AREA 7-N - ELECTRICAL DEMOLITION PLAN
ED401 ELECTRICAL ENLARGED DEMOLITION PLAN - MEZZANINE
EL101 AREA 11-N - ELECTRICAL LIGHTING PLAN
EL102 AREA 12-N - ELECTRICAL LIGHTING PLAN
EL103 AREA 13-N - ELECTRICAL LIGHTING PLAN
EL104 AREA 11-S - ELECTRICAL LIGHTING PLAN
EL105 AREA 12-S - ELECTRICAL LIGHTING PLAN
EL106 AREA 13-S - ELECTRICAL LIGHTING PLAN
EP201 AREA 11-N - ELECTRICAL POWER SYSTEMS PLAN
EP202 AREA 12-N - ELECTRICAL POWER SYSTEMS PLAN
EP203 AREA 13-N - ELECTRICAL POWER SYSTEMS PLAN
EP204 AREA 11-S - ELECTRICAL POWER SYSTEMS PLAN
EP205 AREA 12-S - ELECTRICAL POWER SYSTEMS PLAN
EP206 AREA 13-S - ELECTRICAL POWER SYSTEMS PLAN
EP207 BOILER ROOM - ELECTRICAL POWER SYSTEMS PLAN
EP208 AREA 7-N - ELECTRICAL POWER SYSTEMS PLAN
E-401 ELECTRICAL ENLARGED PLANS
E-501 ELECTRICAL DETAILS
E-502 ELECTRICAL DETAILS
E-503 ELECTRICAL DETAILS
E-601 ELECTRICAL SINGLE-LINE DIAGRAM - DEMOLITION
E-602 ELECTRICAL SINGLE-LINE DIAGRAM - NEW WORK
E-603 ELECTRICAL PANELBOARD SCHEDULE
HAZARD MITIGATION
HM101 ASBESTOS SAMPLE LOCATION
HM102 LEAD PAINT SAMPLE LOCATION
.INTERIORS.
I-111 INTERIOR DETAILS
I-112 INTERIOR SIGNANGE DETAILS
I-101 ENLARGED LOCKER ROOM PLANS
I-102 ENLARGED LOCKER ROOM FINISH PLANS
I-103 ENLARGED LOCKER ROOM FURNITURE PLANS
I-201 WOMENS LOCKER ROOM INTERIOR ELEVATIONS
I-202 MENS INTERIOR ELEVATIONS
D FINAL
03/13/2026
W
2Q R
BA
1_
Pl an s-
US Army Corps of Engineers ®
SHEET ID
U S
AR
M
Y C
O R
PS
O
F
EN
G
IN
EE
R
S
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
SU
BM
IT
TE
D B
Y:
SI
ZE
C H
EC
KE
D B
Y:
AN
SI
D
IS
SU
E D
AT
E:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
N
3 5 7 9 11 13 15 17 19
L
J
G
E
C
A
D
AT
E M
AR
K
D
ES
C R
IP
TI
O N
Fi le
P at h:
Pl ot D at e:
2 4 6 8 10 12 14 16 18 20
P
M
K
H
F
D
B
Au to de sk
D oc s:
//2
5-
6-
D
LA
D
SC
C
B ld g.
R
E
PF
R em od /2
5-
6-
_D
LA
D
SC
C
B ld g.
R
E
PF
R em od _A
R _2
4.
rv t
4/
/2
5:
:5
PM
GC001
G
EN
ER
AL
P H
AS
IN
G N
O
TE
S
C O
LU
M
BU
S, O H
IO
LO
U
IS
VI
LL
E, K
Y E.
E.
E.
E.
A.
B.
E.
B.
M ar ch
3, 0%
C
ER
TI
FI
ED
F
IN
AL
D
SC
C D
LA
R
EP
AI
R B
U
IL
D
IN
G
-2
-0
1.
GENERAL INTENT OF PHASING
1.1. THE PURPOSE OF THE PHASING PLAN IS TO MAINTAIN CONTINUOUS FACILITY OPERATIONS THROUGHOUT CONSTRUCTION, EXCEPT DURING THE TOTAL FACILITY SHUTDOWN OF NO MORE THAN 14 CALENDAR DAYS FOR PHASE 5. THE FACILITY SHALL REMAIN OPERATIONAL WITH NO ADDITIONAL
DISRUPTION IN OPERATIONS DURING PHASES 1 THROUGH 4.
1.2. THE CONTRACTOR SHALL PROVIDE ALL MEANS, METHODS, LABOR, MATERIALS, TEMPORARY PARTITIONS, SIGNAGE, CONTROLS, AND PROTECTION REQUIRED TO EXECUTE THE FIVE (5) PHASES OF
WORK SHOWN ON THE DRAWINGS.
1.3. ONLY ONE (1) PHASE MAY BE FULLY “DOWN” (CLOSED TO OCCUPANTS) AT ANY TIME DURING PHASES 1–4. WORK IN ADDITIONAL PHASES MAY PROCEED ONLY IF THOSE AREAS REMAIN OCCUPIABLE AND THE
GOVERNMENT PROVIDES WRITTEN APPROVAL.
2. SEQUENCING OF WORK / PHASE ORDER
2.1. PHASE 1 SHALL INCLUDE COMPLETE RENOVATION OF ALL LOCKER ROOMS, CONSTRUCTION OF THE NEW MECHANICAL ROOM, AND INSTALLATION OF ALL MECHANICAL, ELECTRICAL, PLUMBING, FIRE
PROTECTION, AND CONTROLS STUB-OUTS NECESSARY TO SUPPORT PHASES 2, 3, AND 4.
2.1.1. THE CONTRACTOR SHALL FOLLOW DESIGNATED HAUL ROUTES FOR DEMOLITION, MATERIAL HANDLING, AND EQUIPMENT MOVEMENT AS INDICATED ON THE DRAWINGS. DAILY CLEANING IS REQUIRED
TO LIMIT DUST MIGRATION.
2.1.2. DURING PHASE 1, THE FACILITY SHALL PROVIDE TEMPORARY CHANGING AND TEMPORARY LOCKER
AREAS FOR OCCUPANTS. RESTROOMS SHALL REMAIN OPERATIONAL DURING PHASE 1 AND ALL
SUBSEQUENT PHASES EXCEPT FOR THE FULL SHUTDOWN DURING PHASE 5.
2.1.3. PHASE 1 SHALL ESTABLISH ALL MAIN DISTRIBUTION PATHS FOR DUCTWORK, HYDRONIC LINES, ELECTRICAL FEEDERS, LOW-VOLTAGE CABLING, AND CONTROLS INFRASTRUCTURE INTO FUTURE PHASES.
SUBSEQUENT PHASES SHALL REQUIRE ONLY BRANCH INSTALLATIONS AND FINAL DEVICE CONNECTIONS.
2.2. PHASES 2, 3, AND 4 MAY OCCUR IN ANY ORDER APPROVED BY THE GOVERNMENT. THE CONTRACTOR SHALL SUBMIT A DETAILED PHASING AND SEQUENCING PLAN INDICATING LOGISTICS, EQUIPMENT PROTECTION, EGRESS ROUTING, TEMPORARY PARTITIONS, AND OPERATIONAL IMPACTS FOR EACH
PROPOSED ORDER OF WORK.
2.3. PHASES 2–4 SHALL COMPLETE ALL ARCHITECTURAL FINISHES, BRANCH DUCTWORK, HYDRONIC PIPING, POWER AND LIGHTING INSTALLATIONS, CONTROLS DEVICES, FIRE PROTECTION ADJUSTMENTS, AND ALL OTHER SYSTEMS REQUIRED FOR THE OCCUPANCY OF THEIR RESPECTIVE AREAS. NO COMPLETED PHASE
SHALL BE REOPENED FOR ROUGH-IN WORK.
2.4. PHASE 5 SHALL BE A COMPLETE FACILITY SHUTDOWN AND SHALL INCLUDE THE FOLLOWING WORK:
REMOVAL OF ALL EXISTING AIR HANDLING UNITS, FANS, AND ASSOCIATED MECHANICAL EQUIPMENT.
COMPLETE REPLACEMENT OF THE 750 kVA ELECTRICAL SERVICE TRANSFORMER.
WATER HEATER REPLACEMENT TO OCCUR DURING PHASE 5 WHEN THE FACILITY IS SHUTDOWN TO
MINIMISE OCCUPANT DISTURBANCE.
EXTERIOR EIFS INSTALLATION AND ENVELOPE WORK MUST OCCUR AT ONE TIME INDEPENDENTLY FROM ALL OTHER 5 PHASES, AS APPROVED BY THE GOVENRMENT WITHOUT INTERFERING WITH OTHER
WORK BEING PERFORMED. IT MUST BE INCLUDED IN THE SEQUENCING PLAN
VESTIBULE DEMOLITION AND REPLACEMENT PER THE CONTRACT DOCUMENTS.
FINAL CONNECTION OF ALL NEW MECHANICAL UNITS TO THE EXISTING CHILLER SYSTEM.
DISCONNECTION AND REMOVAL OF EXISTING MECHANICAL PIPING AND DUCTWORK REQUIRED TO
COMPLETE THE NEW SYSTEM INSTALLATION.
2.4.1. NO SPACES WITHIN THE FACILITY SHALL REMAIN OCCUPIABLE DURING PHASE 5. OCCUPANTS SHALL BE NOTIFIED AND COORDINATED WITH NO LESS THAN 14 DAY NOTICE PRIOR TO THE FULL SHUTDOWN.
2.4.2. THE NEW HVAC SYSTEM CANNOT BE STARTED, TESTED, OR OPERATED UNTIL PHASE 5 IS COMPLETE.
2.4.3. ALL FINAL TESTING, ADJUSTING, BALANCING (TAB), CONTROLS PROGRAMMING, GRAPHICS INTEGRATION, FUNCTIONAL TESTING, AND COMMISSIONING SHALL OCCUR ONLY AFTER COMPLETION OF
PHASE 5.
2.4.4. IF PHASE 5 SHUTDOWN OCCURS DURING WINTER MONTHS, THE CONTRACTOR SHALL PROVIDE TEMPORARY HEAT OR TEMPORARY POWER AS REQUIRED TO PREVENT FREEZING CONDITIONS WITHIN THE FACILITY UNTIL THE TRANSFORMER REPLACEMENT IS COMPLETE. IF THIS OCCURS DURING THE SUMMER THIS WILL NOT BE AN ISSUE AS THE FACILITY WILL HAVE NO POWER AND OCCUPANTS WILL NOT BE IN THE
FACILITY.
3. PHASE COMPLETION REQUIREMENTS
3.1. EACH PHASE SHALL BE FULLY PUNCHED OUT, CLEANED, AND MADE READY FOR OCCUPANCY PRIOR TO
COMMENCEMENT OF THE NEXT PHASE.
3.2. ALL MAIN DISTRIBUTION PATHWAYS FOR DUCTWORK, HYDRONIC PIPING, ELECTRICAL, AND CONTROLS SHALL BE INSTALLED PRIOR TO LEAVING THE EARLIEST FEASIBLE PHASE SO THAT FUTURE
PHASES REQUIRE ONLY BRANCH INSTALLATIONS.
3.3. THE GOVERNMENT MUST APPROVE EACH COMPLETED PHASE PRIOR TO THE CONTRACTOR
ADVANCING TO THE NEXT.
4. MAINTENANCE OF FACILITY OPERATIONS
4.1. FACILITY OPERATIONS SHALL CONTINUE THROUGH PHASES 1–4. TEMPORARY PROTECTION, EGRESS ROUTING, AND SIGNAGE SHALL BE MAINTAINED AT ALL TIMES. NO AREA OUTSIDE THE ACTIVE PHASE MAY BE RENDERED UNUSABLE DUE TO DUST, DEBRIS, ODORS, NOISE, TEMPORARY UTILITIES, OR SAFETY HAZARDS.
4.2. RESTROOMS SHALL REMAIN AVAILABLE DURING ALL PHASES EXCEPT PHASE 5 WHEN THE
TRANSFORMER REPLACEMENT IS OCCURING. WHILE THE FACILITY IS SHUTDOWN ALL MEZZENINE DEMO WORK OF THE AHUS AND OTHER FINISHES SHALL BE COMPLETE. AFTER THE POWER IS RESTORED TO THE FACILITY THE RESTROOM WILL BE MADE AVAILABLE TO THE OCCUPANTS. DURING PHASE 5 ALL WORK OVERHEAD OF THE RESTROOMS WILL BE REQUIRED TO BE COMPLETED DURING THE EVENING DURING NON OPERATIONAL HOURS. TEMPORARY PARTITIONS SHALL BE INSTALLED WHERE REQUIRED TO PROTECT OCCUPANTS.
4.3. OCCUPIED AREAS SHALL REMAIN FREE OF DUST, DEBRIS, ODORS, AND SAFETY HAZARDS. DAILY
CLEANING IS REQUIRED.
5. ACCESS, LOGISTICS, AND DEBRIS REMOVAL
5.1. THE CONTRACTOR SHALL USE DESIGNATED HAUL ROUTES FOR ALL DEMOLITION AND MATERIAL REMOVAL ACTIVITIES. IF THE CONTRACTOR IS NOT OCCUPYING THE ENTIRE PHASE DURING CONSTRUCTION THE CONTRACTOR WILL TAPE OFF THE CONSTRUCTION AREA AS TO ALLOW FOR EQUIPMENT ACCESS FOR THE FACILITY. CONTRACTOR MUST MAINTAIN SAFE ACCESS FOR OCCUPANTS AT ALL TIMES, INCLUDING INSTALLATION OF TEMPORARY PROTECTION WHERE CONSTRUCTION ROUTES INTERSECT WITH OCCUPIED
AREAS.
5.2. FLOOR PROTECTION SHALL BE PROVIDED WHEREVER EQUIPMENT OR MATERIALS ARE TRANSPORTED.
5.3. ALL DEBRIS SHALL BE COVERED OR BAGGED WHEN TRANSPORTED THROUGH OCCUPIED SPACES.
5.4. CONTRACTOR SHALL COORDINATE AND SCHEDULE ANY NECESSARY INTERRUPTIONS WITH THE
GOVERNMENT IN ADVANCE.
5.5. FOR PHASE 1 AND 5 PROVIDE A COMBINATION OF HARD BARRIERS AND PLASTIC BARRIERS AS REQUIRED BY THE GOVERNMENT. FOR DEMOLITION INSIDE PHASES 1 AND 5, THE CONTRACTOR SHALL ESTABLISH NEGATIVE AIR, HEPA FILTRATION, AND SEALED PARTITIONS TO PREVENT AIRBORNE DUST
MOVEMENT TO OCCUPIED AREAS.
5.6 DURING PHASE 1 AND 5, THE CONTRACTOR SHALL PROVIDE CAUTION TAPE BARRIERS ALONG THE HAUL
ROUTES AS WELL AS PROVIDE FLOOR PROTECTION AS NEEDED.
5.7. FOR ASBESTOS OR LEAD ABATEMENT:
ABATEMENT SHALL OCCUR PHASE BY PHASE, MATCHING THE CONSTRUCTION PHASING.
ABATEMENT CONTRACTOR SHALL CONSTRUCT CODE-COMPLIANT CONTAINMENT ROOMS AND ANTE-
CHAMBERS AROUND EACH DOOR/WINDOW/OVERHEAD-DOOR LOCATION BEING ABATED.
DO NOT QUARANTINE AN ENTIRE PHASE FOR A SMALL ABATEMENT AREA UNLESS REQUIRED BY CODE.
CONTRACTOR SHALL PROVIDE UNIT PRICING (LINEAR FOOT/CUBIC YARD) FOR POSSIBLE ADDITIONAL
ABATEMENT QUANTITIES AS REQUIRED BY THE GOVERNMENT.
6.4. AT THE COMPLETION OF EACH ABATEMENT AREA, THE CONTRACTOR SHALL PROVIDE ALL
REQUIRED CLEARANCE TESTING AND DOCUMENTATION BEFORE FINISHING WORK PROCEEDS.
GENERAL PHASING NOTES
6. HVAC, ELECTRICAL, AND CONTROLS COORDINATION.
6.1. MAIN DUCTS, HYDRONIC PIPING, CONTROLS CABLING, AND ELECTRICAL CONDUITS SHALL BE ROUTED
THROUGH PHASE 1 TO SUPPORT PHASES 2 –4 WITHOUT FUTURE RE-ENTRY.
6.2. PANEL TERMINATIONS AND CONTROLS NETWORK CONNECTIONS MAY OCCUR LATER BUT SHALL NOT
REQUIRE REOPENING FINISHED AREAS.
6.3. FINAL SYSTEM INTEGRATION SHALL OCCUR ONLY AFTER COMPLETION OF PHASE 5.
7. PHASE 5 SHUTDOWN REQUIREMENTS.
7.1. CONTRACTOR SHALL COORDINATE THE FULL FACILITY SHUTDOWN REQUIRED FOR TRANSFORMER
REPLACEMENT AND MECHANICAL EQUIPMENT CHANGEOVER.
7.2. TEMPORARY HEAT AND/OR POWER SHALL BE PROVIDED AS NECESSARY TO PROTECT THE FACILITY
FROM FREEZING DURING WINTER MONTHS.
7.3. ALL SYSTEMS SHALL BE REACTIVATED IMMEDIATELY UPON TRANSFORMER INSTALLATION AND
EQUIPMENT CONNECTIONS.
8. FIRE PROTECTION, FIRE WATCH, SECURITY, & SHUTDOWNS.
8.1. ANY IMPAIRMENT TO FIRE ALARM, SPRINKLER, SECURITY, OR EGRESS SYSTEMS MUST BE
COORDINATED A MINIMUM OF 14 DAYS IN ADVANCE.
8.2. IF ANY SYSTEM IS OFFLINE AT ANY TIME, THE CONTRACTOR SHALL PROVIDE A CONTINUOUS FIRE WATCH MEETING ALL APPLICABLE UFC, NFPA, AND INSTALLATION REQUIREMENTS UNTIL THE SYSTEM IS
RESTORED.
8.3. SHUTDOWNS SHALL BE SCHEDULED DURING LOW-OCCUPANCY HOURS (BETWEEN 8:30-11:00 AM AND
12:00 - 2:30 PM.) OR AFTER- HOURS WHEN REQUIRED AND PRE-APPROVED.
8.4. IF PHASE 5 SHUTDOWN OCCURS DURING WINTER MONTHS, THE CONTRACTOR SHALL PROVIDE TEMPORARY HEAT OR TEMPORARY POWER AS REQUIRED TO PREVENT FREEZING CONDITIONS WITHIN THE FACILITY UNTIL THE TRANSFORMER REPLACEMENT IS COMPLETE. IF THIS OCCURS DURING THE SUMMER THIS WILL NOT BE AN ISSUE AS THE FACILITY WILL HAVE NO POWER AND OCCUPANTS WILL NOT BE IN THE
FACILITY.
8.5. CONTRACTOR SHALL MAINTAIN EMERGENCY LIGHTING, EXIT SIGNS, AND TEMPORARY DETECTION AS
REQUIRED.
8.6 CONTRACTOR MUST COORDINATE WITH THE FIRE MARSHAL ’S OFFICE OR RESPONSIBLE AGENCY FOR
ALL FIRE WATCH PLAN APPROVALS AND ANY COSTS ASSOCIATED.
9. GYM EQUIPMENT MOVEMENT & PROTECTION.
9.1. CONTRACTOR SHALL COORDINATE FURNITURE AND EQUIPMENT RELOCATION AND/ OR REMOVAL
FROM THE CONSTRUCTION AREAS AS NECESSARY WITH THE CONTRACTING OFFICER PRIOR TO
MOBILIZATION. THE FACILITY WILL BE RESPONSIBLE OF REMOVING AND/OR RELOCATING ANY FURNITURE AND EQUIPMENT DEEMED NECESSARY TO BE MOVED AS AGREED IN A PRE-MOBILIZATION MEETING.
9.2 THE CONTRACTOR IS RESPONSIBLE FOR PROTECTING, AND SECURING ALL GYM EQUIPMENT, WEIGHTS, TREADMILLS, AND MACHINES LOCATED WITHIN EACH PHASE.
9.3. CONTRACTOR SHALL COORDINATE WITH THE FACILITY TO IDENTIFY EQUIPMENT THAT MUST REMAIN
ACCESSIBLE AND SHALL PROVIDE PROTECTIVE COVERINGS TO ALL EQUIPMENT DURING NEARBY
CONSTRUCTION OPERATIONS.
9.4. EQUIPMENT SHALL NOT BE DAMAGED. ANY DAMAGED EQUIPMENT SHALL BE REPAIRED OR REPLACED
BY THE CONTRACTOR AT NO ADDITIONAL COST.
10. END-OF-PROJECT REQUIREMENTS (AFTER PHASE 5)
10.1. WHEN ALL PHASES ARE COMPLETE, CONTRACTOR SHALL PERFORM:
FULL STARTUP, TESTING, ADJUSTING, AND BALANCING (TAB) OF ALL SYSTEMS.
FULL HVAC CONTROLS CHECKOUT, GRAPHICS VERIFICATION, TRENDING VERIFICATION, AND
SEQUENCE TESTING.
FULL LIGHTING CONTROLS VERIFICATION AND COMMISSIONING.
FINAL CLEANING, FINAL EGRESS SIGNAGE RESET, AND REMOVAL OF ALL TEMPORARY SYSTEMS.
DELIVERY OF ALL O&M MATERIALS, AS-BUILTS, ATTIC STOCK, AND TRAINING.
11. CONTRACTOR PHASING PLAN SUBMITTAL.
11.1. WITHIN 30 DAYS OF NTP, CONTRACTOR SHALL SUBMIT A PHASING EXECUTION PLAN THAT INCLUDES:
DETAILED SEQUENCING AND SCHEDULE FOR EACH PHASE
DUST, DEBRIS, ABATEMENT, AND NOISE CONTROL MEASURES
EGRESS PLANS AND PUBLIC SIGNAGE
EQUIPMENT MOVEMENT PLAN
MECHANICAL/ELECTRICAL ROUTING DIAGRAMS
SHUTDOWN COORDINATION PLAN
TEMPORARY PARTITIONS AND PROTECTION LAYOUTS
THE PHASING PLAN SHALL SPECIFICALLY ADDRESS EXTENDED SHUTDOWN REQUIREMENTS DURING
PHASE 5, INCLUDING COORDINATION OF AIR HANDLER REMOVAL, TRANSFORMER REPLACEMENT,
TEMPORARY HEAT OR POWER REQUIREMENTS, AND RESTROOM ACCESS RESTORATION.
11.2. WORK SHALL NOT BEGIN UNTIL THE GOVERNMENT APPROVES THIS PLAN.
11.3. TESTING, ADJUSTING, AND BALANCING (TAB) ACTIVITIES SHALL BE PERFORMED IN A FULLY OCCUPIED FACILITY AND SHALL BE CAREFULLY COORDINATED WITH THE GOVERNMENT AND FACILITY OCCUPANTS.
THE CONTRACTOR SHALL SUBMIT A TAB SCHEDULE IDENTIFYING PROPOSED DATES, TIMES, AND AFFECTED SPACES FOR REVIEW AND APPROVAL BY THE CONTRACTING OFFICER ’S REPRESENTATIVE (COR) AND FACILITY MANAGEMENT PRIOR TO COMMENCING TAB ACTIVITIES. ALL TAB WORK SHALL BE SEQUENCED AND EXECUTED TO AVOID SHUTDOWNS OF OCCUPIED SPACES, MAINTAIN CONTINUOUS OPERATION OF CRITICAL SYSTEMS, AND MINIMIZE DISRUPTION TO BUILDING OCCUPANTS AND ONGOING OPERATIONS. ANY SYSTEM INTERRUPTIONS, AIRFLOW ADJUSTMENTS, ACCESS TO OCCUPIED AREAS, OR TEMPORARY IMPACTS REQUIRED TO COMPLETE TAB SHALL BE PERFORMED DURING APPROVED OFF-
HOURS OR LOW-OCCUPANCY PERIODS, UNLESS OTHERWISE AUTHORIZED IN WRITING BY THE
GOVERNMENT. THE CONTRACTOR SHALL PROVIDE ADVANCE NOTIFICATION OF TAB ACTIVITIES AND SHALL IMMEDIATELY RESTORE SYSTEMS TO NORMAL OPERATION FOLLOWING TESTING. NO TAB ACTIVITIES THAT NEGATIVELY IMPACT BUILDING OPERATIONS SHALL BE PERFORMED WITHOUT PRIOR GOVERNMENT
COORDINATION AND APPROVAL.
D FINAL
03/13/2026
W
2Q R
BA
1_
Pl an s-
5' - 0"
PHASE 5
PHASE 4
PHASE 2
PHASE 1
PHASE 3
PHASE 5
PHASE 4
PHASE 3
PHASE 2
PHASE 1
US Army Corps of Engineers ®
SHEET ID
U S
AR
M
Y C
O R
PS
O
F
EN
G
IN
EE
R
S
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
SU
BM
IT
TE
D B
Y:
SI
ZE
C H
EC
KE
D B
Y:
AN
SI
D
IS
SU
E D
AT
E:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
N
3 5 7 9 11 13 15 17 19
L
J
G
E
C
A
D
AT
E M
AR
K
D
ES
C R
IP
TI
O N
Fi le
P at h:
Pl ot D at e:
2 4 6 8 10 12 14 16 18 20
P
M
K
H
F
D
B
Au to de sk
D oc s:
//2
5-
6-
D
LA
D
SC
C
B ld g.
R
E
PF
R em od /2
5-
6-
_D
LA
D
SC
C
B ld g.
R
E
PF
R em od _A
R _2
4.
rv t
4/
/2
5:
:0
PM
GC002
FL
O
O R
P
LA
N O
VE
R
AL
L
PH
AS
IN
G
C O
LU
M
BU
S, O H
IO
LO
U
IS
VI
LL
E, K
Y E.
E.
E.
E.
A.
B.
E.
B.
M ar ch
3, 0%
C
ER
TI
FI
ED
F
IN
AL
D
SC
C D
LA
R
EP
AI
R B
U
IL
D
IN
G
-2
-0
0 10 20
SCALE: 1/16" = 1'=0"
1/16" = 1'-0"A1 FLOOR PLAN PHASING
LEGEND:
NEW CHILLER ROUGH - IN PRIOR
TO PHASE 5 AND STARTUP.
TRANSFORMER
REPLACEMENT PHASE 5
DEMO HAUL ROUTE
TEMPORARY ACCESS
TO THE BUILDING
DURING PHASE 5
D FINAL
03/13/2026
W
2Q R
BA
1_
Pl an s-
ARCHITECTURAL SYMBOLS
XX/ A11.X
XX. X. XX
CASEWORK ELEVATION
DOOR NUMBER
CURTAIN WALL FRAME TYPE
WALL TYPE
027- XX-XXX
XX/ A11.X XXXX
XX
XX
APC-1
9' - 0"
CEILING TYPE
CEILING HEIGHT
CEILING TYPE
EXTERIOR WINDOW
TYPE
X
GENERAL ARCHITECTURAL NOTES
1.
2.
3.
4.
5.
6.
7.
8.
PARTITION TYPES SHALL BE DESIGNATED ON FLOOR PLANS. SEE
SHEET A-401 FOR TYPES.
PROVISIONS SHALL BE MADE AT ALL FULL HEIGHT NON-BEARING
WALLS FOR 1-INCH VERTICAL MOVEMENT OF THE BUILDING
STRUCTURE WITHOUT TRANSFER OF COMPRESSIVE LOADS TO
WALL.
SEE STRUCTURAL DRAWINGS FOR BRACING OF NON-LOAD
BEARING MASONRY WALLS.
FURNISH AND INSTALL FIRE-TREATED WOOD BLOCKING OR METAL
BACKING PLATE IN METAL STUD PARTITIONS FOR THE PROPER
ANCHORAGE OF ALL WALL ATTACHED ITEMS; I.E. TOILET
ACCESSORIES, CASEWORK, MILLWORK, WALL-MOUNTED
FIXTURES, DOOR STOPS, AND OTHER WALL ATTACHED ITEMS.
GYPSUM BOARD SURFACES SHALL BE ISOLATED WITH CONTROL
JOINTS WHERE SHOWN ON DRAWINGS AND AS DESCRIBED IN THE
SPECIFICATIONS.
EXTEND FURRING CHANNELS AND GYPSUM BOARD UP 4 INCHES
ABOVE FINISHED CEILING ON CMU WALLS.
SCRIBE GYPSUM WALL BOARD OF WALLS AND PARTITIONS TO
IRREGULARITIES OF DECK ABOVE. SEAL TIGHTLY AROUND ALL
PENETRATIONS.
CAREFULLY REMOVE ACOUSTICAL INSULATION ON THE
UNDERSIDE OF THE (E) CONCRETE BARREL VAULT TO
ACCOMMODATE THE ANCHOR AND BRACKET AND RE-
INSTALL/PATCH WITH SIMILAR MATERIAL AFTER ATTACHMENT IS
COMPLETE.
GENERAL SYMBOLS
SIM
ROOM NAME
XXX-XX
DETAIL NUMBER
SHEET NUMBER
CROSS REFERENCE
WALL SECTION
SIMILAR OR TYPICAL
REFERENCE
DETAIL REFERENCE
BUILDING SECTION
SHEET NOTE
COLUMN GRID LINE
ROOM NUMBER/NAME
REVISION NUMBER
EARTH
GRAVEL
SAND
CONCRETE
PRECAST CONCRETE
STEEL
STONE
CONCRETE MASONRY UNIT
BRICK VENEER
LEVEL XX
XXX'-XX" LEVEL ELEVATION
GYM FLOOR
WOOD
(CONTINUOUS BLOCKING)
WOOD
(NON-CONTINUOUS BLOCKING)
WOOD (TRIM/FINISH)
GLASS
SHINGLES
PLYWOOD (LARGE SCALE)
GYPSUM WALL BOARD
BLANKET INSULATION
RIGID INSULATION
SPRAY FOAM INSULATION
MINERAL WOOL INSULATION
PROTECTION BOARD
CARPET (LARGE SCALE)
ACOUSTIC TILE (LARGE SCALE)
TILE (LARGE SCALE)
? REFERENCE KEYNOTE
XX A4.XX BUILDING ELEVATION
A12.X
XX
XX XX
XX
INTERIOR ELEVATION
100'-0"
TYP FF EL=
100'-0"
FINISH FLOOR
ELEVATION
SPOT ELEVATION
X
GENERAL NOTES
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
GENERAL NOTES APPLY TO ALL SHEETS.
DIMENSIONS ARE ACTUAL AND ARE TO FACE OF STUDS, FACE
OF CONCRETE WALLS, FACE OF CMU WALLS, FACE OF FRAMES,
OR CENTERLINE OF COLUMNS, UNLESS NOTED OTHERWISE.
COORDINATE ALL MECHANICAL CHASE SIZES WITH THE
MECHANICAL CONTRACTOR.
ARCHITECTURAL FINISH FLOOR ELEVATION 0'-0" EQUALS
ACTUAL FINISH FLOOR ELEVATION OF EXISTING BUILDING.
COORDINATE WITH MECHANICAL AND ELECTRICAL
CONTRACTORS THE SIZE AND LOCATION OF EQUIPMENT PADS
SHOWN ON PLANS.
CONSTRUCTION DOCUMENTS ARE COMPLEMENTARY. SEE
DRAWING FOR QUANTITIES AND LOCATION OF WORK. SEE
SPECIFICATIONS FOR QUALITIES AND CONDITIONS OF WORK.
WORK: ALL ASPECTS OF THE WORK AND ITEMS NOT
SPECIFICALLY MENTIONED, BUT NECESSARY TO MAKE A
COMPLETE WORKING INSTALLATION, SHALL BE INCLUDED AND
INDICATED IN THE CONTRACTOR'S BID.
SHEET NOTES ONLY APPLY TO PARTICULAR DRAWING OR
SERIES OF DRAWINGS.
NO ASBESTOS OR PCB CONTAINING MATERIALS SHALL BE USED
ON THIS PROJECT.
DO NOT SCALE DRAWINGS. DIMENSIONS NOTED PREVAIL.
NOTIFY ARCHITECT IN CASE OF DISCREPANCY.
HORIZONTAL AND VERTICAL DIMENSIONS ARE MINIMUM
DIMENSIONS. CLEARANCES ARE GIVEN TO FINISH SURFACES.
GC TO VERIFY ALL CLEARANCES. NOTIFY ARCHITECT IN CASE
OF DISCREPANCY.
US Army Corps of Engineers ®
SHEET ID
U S
AR
M
Y C
O R
PS
O
F
EN
G
IN
EE
R
S
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
SU
BM
IT
TE
D B
Y:
SI
ZE
C H
EC
KE
D B
Y:
AN
SI
D
IS
SU
E D
AT
E:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
N
3 5 7 9 11 13 15 17 19
L
J
G
E
C
A
D
AT
E M
AR
K
D
ES
C R
IP
TI
O N
Fi le
P at h:
Pl ot D at e:
2 4 6 8 10 12 14 16 18 20
P
M
K
H
F
D
B
Au to de sk
D oc s:
//2
5-
6-
D
LA
D
SC
C
B ld g.
R
E
PF
R em od /2
5-
6-
_D
LA
D
SC
C
B ld g.
R
E
PF
R em od _A
R _2
4.
rv t
4/
/2
5:
:0
PM
A-001
G
EN
ER
AL
N O
TE
S, A R
C H
IT
EC
TU
R
AL
S
YM
BO
LS
AB
BR
EV
IA
TI
O
N S
C O
LU
M
BU
S, O H
IO
LO
U
IS
VI
LL
E, K
Y E.
E.
E.
E.
A.
B.
E.
B.
M ar ch
3, 0%
C
ER
TI
FI
ED
F
IN
AL
D
SC
C D
LA
R
EP
AI
R B
U
IL
D
IN
G
-2
-0
% PERCENT
< LESS THAN
= EQUALS
> GREATER THAN
A/E ARCHITECT/ENGINEER
AB AIR BARRIER
AC ARCHITECTURAL CONCRETE
ACC ADA ACCESSIBLE
ACD ACCESS DOOR
ACM ASBESTOS CONTAINING MATERIAL
ACR ACRYLIC
ACT ACOUSTIC TILE CEILING
ACW ALUMINUM CURTAIN WALL
ADJ ADJUSTABLE
ADJT ADJACENT
ADMIN ADMINISTRATION
ADO AUTOMATIC DOOR OPERATOR
AEC AUTOMATED EXTERNAL DEFIBRILLATORS
AFD ACCORDION-FOLDING FIRE DOOR
AFS ALUMINUM-FRAMED STOREFRONT
AGS ALL-GLASS STOREFRONT
AL ALUMINUM
ALD ALUMINUM DOOR
ALF ALUMINUM FRAME
ALUM ALUMINUM
AP ACCESS PANEL
APC ACOUSTICAL PANEL CEILING
ASPH ASPHALT
ATH ATHLETIC EQUIPMENT
AUTO AUTOMATIC
AVG AVERAGE
AW ALUMINUM WINDOW
AWP ACOUSTIC WALL PANEL
B.O. BOTTOM OF
BCS BABY CHANGING STATION
BD BOARD
BENT BENTONITE WATERPROOFING
BFD BIFOLD DOOR
BL BOLLARD
BLK BLOCK
BLKG BLOCKING
BLKHD BULKHEAD
BM(S) BEAM(S)
BN BENCH
BOT BOTTOM
BRDG BRIDGING
BRG BEARING
BRKT BRACKET
BT BATHTUB
BTWN BETWEEN
CAB CABINET
CB COFFEE BREWER
CBD CHALKBOARD
CCG CERAMIC-COATED GLASS
CCV METAL COLUMN COVER
CEQ CONVEYING EQUIPMENT
CF CUBIC FEET
CFAWP COLD-FLUID APPLIED WATERPROOFING
CFCI CONTRACTOR FURNISHED CONTRACTOR
INSTALLED
CFMF COLD-FORMED METAL FRAMING
CG CLEAR FLOAT GLASS
CG CORNER GUARD
CI CAST IRON
CIG CLEAR INSULATING GLASS
CIP CAST IN PLACE
CJ CONTROL JOINT
CJA CONTROL JOINT ABOVE
CLO CLOSET
CLR CLEAR
CMU CONCRETE MASONRY UNIT
COL COLUMN
COMB COMBINATION
COMM COMMUNICATIONS
COMPR COMPRESSIBLE
CONF CONFERENCE
CONFIG CONFIGURATION
CORR CORRIDOR
CP CEMENT PLASTER
CPT CARPET
CR CHAIR RAIL
CRYS CRYSTALLINE WATERPROOFING
CS COUNTERSINK
CST CAST STONE MASONRY
CSTJ CONSTRUCTION JOINT
CTG CLEAR TEMPERED FLOAT GLASS
CTIG CLEAR TEMPERED INSULATING GLASS
CU COPPER
CU COMBINATION UNIT
CV CONDOM VENDOR
CW CASEWORK
CY CUBIC YARD
CYL CYLINDER
DAMP DAMPPROOFING
DB DECIBEL
DBL DOUBLE
DC DUST COLLECTOR
DCS DIAPER CHANGING STATION
DDF DETENTION DOOR AND FRAME
DDH DETENTION DOOR HARDWARE
DEPR DEPRESS(ION)(ED)
ARCHITECTURAL
ABBREVIATIONS
DEPT DEPARTMENT
DET DETENTION
DF DRINKING FOUNTAIN
DFEC DETENTION FIRE EXTINGUISHER CABINET
DG DOOR GRILLE
DGL DETENTION GUN LOCKER
DIAG DIAGONAL
DM DECORATIVE METAL PANEL
DMP DECORATIVE FORMED METAL PANEL
DPTD DETENTION PAPER TOWEL DISPENSER
DR DOOR
DRH DETENTION ROBE HOOK
DRY CLOTHES DRYER
DSCR DETENTION SHOWER CURTAIN ROD
DSN DOWNSPOUT NOZZLE
DTTD DETENTION TOILET TISSUE DISPENSER
DV DIVIDER
DW DISHWASHER
DWI DETENTION WINDOW
DWL(S) DOWEL(S)
DWR DRAWER
EB EXPANSION BOLT
EE EACH END
EEW EMERGENCY EYE WASH
EEWS EMERGENCY EYE WASH SHOWER
EF ENTRANCE FLOOR MAT
EFF EFFICIENCY
EJ EXPANSION JOINT
ELAS ELASTOMERIC
ELEV ELEVATOR
EMER EMERGENCY
ENCL ENCLOSURE
ENTR ENTRANCE
ERF EPOXY RESIN FLOORING
EUI ENERGY USE INTENSITY
EW EACH WAY
EWC ELECTRIC WATER COOLER
EXP EXPANSION
EXP EXPOSED
F FABRIC
F.O. FACE OF
FAB FABRICATE(D)
FB FACE BRICK
FC FIBER-CEMENT CLADDING
FD FLOOR DRAIN
FDN FOUNDATION
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FH FIRE HYDRANT
FHC FIRE HOSE CABINET
FIG FIGURE
FIX FIXTURE
FLEX FLEXIBLE
FLG FLOORING
FLG FLAGPOLE
FLM FULL LENGTH MIRROR
FLUOR FLUORESCENT
FO FINISH OPENING
FOC FACE OF CONCRETE
FOF FACE OF FINISH
FOM FACE OF MASONRY
FOS FACE OF STUD
FOW FACE OF WALL
FP FIREPROOFING
FP FILLER PANEL
FPG FIRE-PROTECTION-RATED GLAZING
FPS FOLDING AND PORTABLE STAGE
FR FIRE RESISTANT
FRG FIRE-RESISTANCE-RATED GLAZING
FRJ FIRE-RESISTIVE JOINT
FRP FIBERGLASS REINFORCED PANEL
FRT FIRE RESISTANCE TREATED
FS FLOOR SINK
FS FIRE STOPPING
FSS FOLDING SHOWER SEAT
FTG FOOTING
FVC FIRE VALVE CABINET
FWC FABRIC WALLCOVERING
FWC FACILITY WASTE COMPACTOR
FWC FLUSH WOOD DOOR
G GROUT
GA GAUGE
GAL GALLON
GALV GALVANIZED
GB GRAB BAR
GD GARBAGE DISPOSAL
GEN GENERAL
GFA GROSS FLOOR AREA
GFRC GLASS-FIBER REINFORCED CONCRETE
GL GLUE LAMINATED
GL GLASS
GLB GLAZED BRICK
GLM GLASS UNIT MASONRY
GM GROMMET
GMP GUARANTEED MAXIMUM PRICE
GR GUARD RAIL
GR GRADE
GRS GALVANIZED RIGID STEEL
GSB GYPSUM SHAFTLINER BOARD
GSWA GYPSUM BOARD SHAFT WALL ASSEMBLY
GT GLASS TILE
GVP GYPSUM VENEER PLASTER
GWB GYPSUM WALLBOARD
GYP GYPSUM
HC HOLLOW CORE
HCW HEALTHCARE CASEWORK
HD HAND DRYER
HDF HIGH DENSITY FIBERBOARD
HDR HEADER
HDWD HARDWOOD
HDWR HARDWARE
HM HOLLOW METAL
HMD HOLLOW METAL DOOR
HMF HOLLOW METAL FRAME
HR HOUR
HR HANDRAIL
HS HARDWARE SET
HSS HOLLOW STRUCTURAL SHAPE
HVAC HEATING VENTILATING AND AIR
CONDITIONING
IAW IN ACCORDANCE WITH
ICE ICE MAKER
ID INSIDE DIAMETER
IF INSIDE FACE
IIP INSULATING INFILL PANEL GLASS
IJ ISOLATION JOINT
IJS IN JOIST SPACE
INC INCLUDE(ING)
INSUL INSULATION
JAN JANITOR
JBE JOIST BEARING ELEVATION
JBX JUNCTION BOX
JCT JUNCTION
JFB JOINT FILLER BOARD
JST JOIST
JT JOINT
KCJ KEYED CONSTRUCTION JOINT
KD KNOCKDOWN
KH KITCHEN HOOD
KIT KITCHEN
L ANGLE
L LENGTH (LONG)
L LEVEL
LAB LABORATORY
LAM LAMINATED
LAV LAVATORY
LBR LUMBER
LCK LOCKER
LCW LABORATORY CASEWORK
LDE LOADING DOCK EQUIPMENT
LDG LOADING
LF LINEAR FOOT
LFH LABORATORY FUME HOOD
LG LAMINATED GLASS
LIN LINEAR
LINO LINOLEUM
LKR LOCKER
LMC LINEAR METAL CEILING
LOC LOCATION
LONG LONGITUDINAL
LSC LIFE SAFETY CODE
LSS LIBRARY STACK SYSTEM
LTG LIGHTING
LV LOUVER
LVT LUXURY VINYL TILE
MAG MAGNETIC
MAINT MAINTENANCE
MAN MANUAL
MAS MASONRY
MATL MATERIAL
MB MOP BASIN
MBD MARKERBOARD
MBH MOP/BROOM HOLDER
MC MEDICINE CABINET
MCJ MASONRY CONTROL JOINT
MEMB MEMBRANE
MH MANHOLE
MP METAL PANEL
MR/S MIRROR WITH SHELF
MSS METAL STORAGE SHELVING
MTD MOUNTED
MTG MOUNTING
MUL MULLION
MW MICROWAVE
NC NOISE CRITERIA
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
NOM NOMINAL
NSMF NON-STRUCTURAL METAL FRAMING
O to O OUT TO OUT
OA OVERALL
OCCD OVERHEAD COILING COUNTER DOOR
OCD OVERHEAD COILING DOOR
OCG OVERHEAD COILING GRILLE
OFCI OWNER FURNISHED CONTRACTOR
INSTALLED
OFF OFFICE
OFOI OWNER FURNISHED OWNER INSTALLED
OH OPPOSITE HAND
OPG(S) OPENING(S)
OSHA OPERATIONAL SAFETY AND HEALTH
ADMINISTRATION
OTB OPEN TO BELOW
OVFL OVERFLOW
P PAINT
PAC PRECAST ARCHITECTURAL CONCRETE
PAN B PANIC BOLT
PB PARTICLE BOARD
PC PRECAST CONCRETE
PCD PAPER CUP DISPENSER
PCE PARKING CONTROL EQUIPMENT
PCEQ PATIENT CARE EQUIPMENT
PD PANIC DEVICE
PERF PERFORATED
PERP PERPENDICULAR
PFD PANEL FOLDING DOOR
PG PATTERN GLASS
PIC PORTABLE INSTRUMENT CONNECTION
PIG PATTERN INSULATING GLASS
PL PLATE
PL PROPERTY LINE
PL PLASTIC LAMINATE
PLAM PLASTIC LAMINATE
PLBG PLUMBING
PLT INTERIOR PLANTER
PR PAIR
PREFAB PREFABRICATED
PROJ PROJECT(OR) (ION)
PS PROJECTION SCREEN
PSC PRECAST STRUCTURAL CONCRETE
PT POINT
PT POINT OF TANGENCY
PT PORCELAIN TILE
PTD PAPER TOWEL DISPENSER
PTD/R COMBINATION TOWEL
DISPENSER/RECEPTACLE
PTN PARTITION
PTW PASS-THROUGH WINDOW
PVC POLYVINYL CHLORIDE
PWL SOUND POWER LEVEL
QGV QUAD GAS VALVE
QT QUARRY TILE
QTR RND QUARTER ROUND
R RISER
RAD RADIUS
RB RUBBER BASE
RBA RESILIENT BASE AND ACCESSORIES
RC REMOTE CONTROL
RCG REFLECTIVE-COATED GLASS
RCP REFLECTED CEILING PLAN
RD ROOF DRAIN
REF REFERENCE
REFL REFLECTED
REM REMOVABLE
RESIL RESILIENT
RF RESILIENT FLOORING
RF RUBBER FLOOR
RF ROOF(ING)
RFA ROOF ACCESSORIES
RFM RECESSED FLOOR MAT
RFS ROOF SPECIALTIES
RH ROBE HOOK
RI&C ROUGH IN AND CONNECT
RLG RAILING
RWB RESILIENT WALL BASE
S SINK
SAC SOUND ABSORBING CEILING UNITS
SAFF SELF-ADHERING FLEXIBLE FLASHING
SAT SPRAYED ACOUSTIC TREATMENT
SAW SOUND ABSORBING WALL UNITS
SAWP SELF-ADHERING SHEET WATERPROOFING
SB SPLASH BLOCK
SC SOLID CORE
SC SHOWER CURTAIN
SCD SEAT COVER DISPENSER
SCD SOUND CONTROL DOOR
SCH SHOWER CURTAIN HOOK
SCR SHOWER CURTAIN ROD
SCT STRUCTURAL CLAY TILE
SCU STAGE CURTAIN
SD SOAP DISPENSER
SDA SLIDING AUTOMATIC ENTRANCE
SECY SECRETARY
SF SQUARE FEET
SG SPECIALTY GLASS
SG SECURITY GLAZING
SGA SLOPED GLAZING ASSEMBLY
SGL SINGLE
SGV SINGLE GAS VALVE
SH SHOWER
SHG SHEATHING
SHM SECURITY HOLLOW METAL
SHW SHOWER VALVE AND HEAD
SIG SECURITY INSULATING GLAZING
SKY SKYLIGHT
SLNT SEALANT
SM SHEET METAL
SM SQUARE METER(S)
SMF SHEET METAL FLASHING
SND SANITARY NAPKIN DISPOSAL
SNTV SANITARY NAPKIN AND TAMPON VENDOR
SNV SANITARY NAPKIN VENDOR
SO SENSOR OPERATED
SPC SPECIALTY CONSTRUCTION
SPF SPRAY POLYURETHANE FOAM
SPG SPANDREL GLASS
SPIG SPANDREL INSULATING GLASS
SPL SOUND PRESSURE LEVEL
SPP STRUCTURED POLYCARBONATE PANEL
ASSEMBLY
SQ SQUARE
SR SURFACE MOUNTED ELECTRICAL
RACEWAY
SSA STORM SHELTER AREA
SSM SOLID SURFACE MATERIAL
SSS STAINLESS STEEL SHELF
SST STAINLESS STEEL
ST STONE
ST STAIR
ST SEATING
ST STONE TILE
STAG'D STAGGERED
STC SOUND TRANSMISSION CLASS
STC STONE CLADDING
STGR STRINGER
STV STONE VENEER
SUBFL SUBFLOOR
SUL SULPHUR
SURF SURFACE
SUSP SUSPENDED
SVF SHEET VINYL FLOORING
SVF SERVICE FIXTURE
SVG SERVICE FIXTURE GROUP
SW STEEL WINDOW
SWS SHAFT WALL STUD
T TREAD
T CERAMIC TILE
T&G TONGUE AND GROOVE
T.O. TOP OF
TAN TANGENT
TB TOWEL BAR
TB THIN BRICK
TB TILE BASE
TC TRAFFIC COATING
TCP TOILET COMPARTMENT PARTITION
TERR TERRAZZO
TG TINTED FLOAT GLASS
TH THRESHOLD
THK THICK(NESS)
TI TENANT IMPROVEMENT
TIG TINTED INSULATING GLASS
TKB TACKBOARD
TOIL TOILET
TOP TOP OF PAVING
TP TOILET PARTITION
TRANS TRANSVERSE
TS TELESCOPING STANDS
TSD TOILET SEAT COVER DISPENSER
TSKY TUBULAR DAYLIGHTING DEVICE
TT TERRAZZO TILE
TTD TOILET TISSUE DISPENSER
TTG TINTED TEMPERED FLOAT GLASS
TTIG TINTED TEMPERED INSULATING GLASS
TW TACK WALL
UK UNIT KITCHEN
UL UNDERWRITERS LABORATORIES
UND UNDERLAYMENT
UR URINAL
US UTILITY SHELF
UTIL UTILITY
VB VAPOR BARRIER
VB VINYL BASE
VCB VENTED COVE BASE
VCE VEHICLE CHARGING EQUIPMENT
VF VINYL FLOOR
VOC VOLATILE ORGANIC COMPOUND
VOL VOLUME
VP VENEER PLASTER
VR VAPOR RETARDER
VT VINYL TILE
VWC VINYL WALLCOVERING
W/I WITHIN
WB WALL BASE
WC WATER CLOSET
WC WALLCOVERING
WCL WATER CLOSET/LAVATORY COMBINATION
WD WOOD
WDAF WOOD ATHLETIC FLOORING
WDF WOOD FLOORING
WDW WINDOW
WG WIRE GLASS
WI WROUGHT IRON
WOC WALK OFF CARPET
WOM WALK OFF MAT
WR WASTE RECEPTACLE
WR WATER REPELLENT
WRB WEATHER RESISTANT BARRIER
WT WINDOW TREATMENT
WW WARM WHITE
WWF WELDED WIRE FABRIC
YD YARD
D FINAL
03/13/2026
W
2Q R
BA
1_
Pl an s-
COILING DOOR TO BE REPLACED WITH
NEW INSULATED OVERHEAD DOOR
RESTROOM
STORAGE
ROOM
AEROBICS
ROOM
VH
RESTROOM
MECH. ROOM
RAQUETBALL
COURT
RAQUETBALL
COURT
MASSAGE
ROOM
BOXING
TRAINING
ROOM
IT CLOS.
LAUNDRY
ROOM
SPRINKLER
RISE
JANITOR
ROOM
STAIRS
CONFERENCE
ROOM
OFFICE
TRANSFORM.
STORAGE
ROOM
WEIGHT ROOM
SPIN ROOM
MEN'S
SHOWERS
MEN'S
RESTROOM
MEN'S
RESTROOM
WOMEN'S
LOCKER ROOM
WOMEN'S
SHOWERS
SAUNA
WOMEN'S
RESTROOM
ELEC. ROOM
AD201
B1
AD201
L1
WORKOUT
AREA
MEN'S LOCKER
ROOM
BASKETBALL
COURT
AD201G1
AD102
B1
AD103
B1
AD104
B1
AD105
B1
AD106
B1
AD107
B1
ELECTRICAL
CLOSET
SAUNA
A-402
DEMOLITION GENERAL NOTES
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
THE CONTRACTOR SHALL:
COORDINATE ALL DEMOLITION AND PHASING EFFORTS WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). EVERY EFFORT SHALL BE MADE TO MINIMIZE DISRUPTION OF OCCUPANT'S OPERATIONS. EXCESSIVE NOISE OR VIBRATION SHALL BE PRE-APPROVED AND COORDINATED WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). IN ALL CASES, PROVISIONS SHALL BE MADE FOR
USER’S SAFETY.
COORDINATE ANY DISRUPTION OF UTILITY SERVICES WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND AS SPECIFIED.
CONSTRUCT TEMPORARY CONSTRUCTION PARTITIONS WITHIN THE EXISTING BUILDING WHICH OFFER A ONE-HOUR ENCLOSURE TO ISOLATE ANY DEMOLITION/CONSTRUCTION WORK FROM THE GENERAL PUBLIC AND AS DEEMED NECESSARY BY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND CODE OFFICIAL HAVING JURISDICTION. COORDINATE LOCATIONS WITH THE CONTRACTING OFFICER
REPRESENTATIVE (C0R) AND MAINTAIN MEANS OF EGRESS THROUGHOUT THE WORK.
MAINTAIN A SECURE, WEATHER-TIGHT ENCLOSURE AT ALL TIMES.
VERIFY ALL EXISTING CONDITIONS, DIMENSIONS AND ELEVATIONS AND NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) OF ANY DISCREPANCIES.
REMOVE IN THEIR ENTIRETY ALL EXISTING WALLS, DOORS, MILLWORK, PLUMBING FIXTURES, CEILINGS, SOFFITS, WALL FIXTURES, AND OTHER ITEMS, AS REQUIRED TO EXECUTE THE
DEMOLITION/CONSTRUCTION WORK DESCRIBED BY THE DRAWINGS.
PROVIDE PROTECTION FOR ALL EXISTING BUILDING MATERIALS AND EQUIPMENT FROM DAMAGE DUE TO ANY DEMOLITION OR CONSTRUCTION-RELATED INCIDENT PERFORMED UNDER THIS CONTRACT.
REPAIR OR REPLACE ITEMS THAT ARE DAMAGED AS A RESULT OF DEMOLITION OR CONSTRUCTION TO MATCH EXISTING FINISH AND/OR CONDITION.
NO EXISTING MATERIALS SHALL BE REUSED IN ANY INSTANCE. DISPOSE OF EXISTING DEMOLISHED MATERIALS AS PER SPECIFICATIONS.
VERIFY AND MAINTAIN THE LOCATION OF EXISTING POWER, COMMUNICATION AND DATA CABLES TO PREVENT INTERRUPTION OF THEIR SERVICE.
PATCH FLOOR, WALL AND CEILING PENETRATIONS RESULTING FROM REMOVAL OR RE-ROUTING OF NEW OR EXISTING PIPING, DUCTWORK, CONDUIT, AND OTHER ITEMS, AS REQUIRED TO MAINTAIN FIRE- RESISTANCE-RATED SEPARATIONS. FINISH AS REQUIRED FOR NEW OR EXISTING ADJACENT SURFACES.
CAP ALL DISCONNECTED MECHANICAL PIPING LINES WITHIN THE WALL OR FLOOR. PATCH AND FINISH AS REQUIRED TO MATCH NEW OR EXISTING ADJACENT SURFACES.
SEE MECHANICAL AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.
WHERE CMU WALLS ARE INDICATED TO BE REMOVED, PREPARE ADJACENT WALLS TO RECEIVE NEW PATCH/FINISH BY SAWCUTTING AND OR REMOVING CMU IN TOOTH-IN PATTERN BOTH SIDES OF DEMOLITION
FOR CONTRACTOR TO TOOTH-IN NEW CMU PATCHES AS NEEDED.
SEE MECHANICAL, PLUMBING AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.
COORDINATE WITH HAZARDOUS ABATEMENT SHEETS AND REPORT BEFORE ANY DEMOLITION TAKES PLACE.
DEMOLITION NOTES APPLY TO ALL DEMOLITION SHEETS.
US Army Corps of Engineers ®
SHEET ID
U S
AR
M
Y C
O R
PS
O
F
EN
G
IN
EE
R
S
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
SU
BM
IT
TE
D B
Y:
SI
ZE
C H
EC
KE
D B
Y:
AN
SI
D
IS
SU
E D
AT
E:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
N
3 5 7 9 11 13 15 17 19
L
J
G
E
C
A
D
AT
E M
AR
K
D
ES
C R
IP
TI
O N
Fi le
P at h:
Pl ot D at e:
2 4 6 8 10 12 14 16 18 20
P
M
K
H
F
D
B
Au to de sk
D oc s:
//2
5-
6-
D
LA
D
SC
C
B ld g.
R
E
PF
R em od /2
5-
6-
_D
LA
D
SC
C
B ld g.
R
E
PF
R em od _A
R _2
4.
rv t
4/
/2
5:
:1
PM
AD101
D
EM
O
LI
TI
O
N P
LA
N
O
VE
R
AL
L
C O
LU
M
BU
S, O H
IO
LO
U
IS
VI
LL
E, K
Y E.
E.
E.
E.
A.
B.
E.
B.
M ar ch
3, 0%
C
ER
TI
FI
ED
F
IN
AL
D
SC
C D
LA
R
EP
AI
R B
U
IL
D
IN
G
-2
-0
1/16" = 1'-0"C1 OVERALL DEMOLITION PLAN, LEVEL 1
0 10 20
SCALE: 1/16" = 1'=0"
GLASS WALL TO BE
REMOVED
D FINAL
03/13/2026
W
2Q R
BA
1_
Pl an s-
DEMOLITION GENERAL NOTES
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
THE CONTRACTOR SHALL:
COORDINATE ALL DEMOLITION AND PHASING EFFORTS WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). EVERY EFFORT SHALL BE MADE TO MINIMIZE DISRUPTION OF OCCUPANT'S OPERATIONS. EXCESSIVE NOISE OR VIBRATION SHALL BE PRE-APPROVED AND COORDINATED WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). IN ALL CASES, PROVISIONS SHALL BE MADE FOR
USER’S SAFETY.
COORDINATE ANY DISRUPTION OF UTILITY SERVICES WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND AS SPECIFIED.
CONSTRUCT TEMPORARY CONSTRUCTION PARTITIONS WITHIN THE EXISTING BUILDING WHICH OFFER A ONE-HOUR ENCLOSURE TO ISOLATE ANY DEMOLITION/CONSTRUCTION WORK FROM THE GENERAL PUBLIC AND AS DEEMED NECESSARY BY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND CODE OFFICIAL HAVING JURISDICTION. COORDINATE LOCATIONS WITH THE CONTRACTING OFFICER
REPRESENTATIVE (C0R) AND MAINTAIN MEANS OF EGRESS THROUGHOUT THE WORK.
MAINTAIN A SECURE, WEATHER-TIGHT ENCLOSURE AT ALL TIMES.
VERIFY ALL EXISTING CONDITIONS, DIMENSIONS AND ELEVATIONS AND NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) OF ANY DISCREPANCIES.
REMOVE IN THEIR ENTIRETY ALL EXISTING WALLS, DOORS, MILLWORK, PLUMBING FIXTURES, CEILINGS, SOFFITS, WALL FIXTURES, AND OTHER ITEMS, AS REQUIRED TO EXECUTE THE
DEMOLITION/CONSTRUCTION WORK DESCRIBED BY THE DRAWINGS.
PROVIDE PROTECTION FOR ALL EXISTING BUILDING MATERIALS AND EQUIPMENT FROM DAMAGE DUE TO ANY DEMOLITION OR CONSTRUCTION-RELATED INCIDENT PERFORMED UNDER THIS CONTRACT.
REPAIR OR REPLACE ITEMS THAT ARE DAMAGED AS A RESULT OF DEMOLITION OR CONSTRUCTION TO MATCH EXISTING FINISH AND/OR CONDITION.
NO EXISTING MATERIALS SHALL BE REUSED IN ANY INSTANCE. DISPOSE OF EXISTING DEMOLISHED MATERIALS AS PER SPECIFICATIONS.
VERIFY AND MAINTAIN THE LOCATION OF EXISTING POWER, COMMUNICATION AND DATA CABLES TO PREVENT INTERRUPTION OF THEIR SERVICE.
PATCH FLOOR, WALL AND CEILING PENETRATIONS RESULTING FROM REMOVAL OR RE-ROUTING OF NEW OR EXISTING PIPING, DUCTWORK, CONDUIT, AND OTHER ITEMS, AS REQUIRED TO MAINTAIN FIRE- RESISTANCE-RATED SEPARATIONS. FINISH AS REQUIRED FOR NEW OR EXISTING ADJACENT SURFACES.
CAP ALL DISCONNECTED MECHANICAL PIPING LINES WITHIN THE WALL OR FLOOR. PATCH AND FINISH AS REQUIRED TO MATCH NEW OR EXISTING ADJACENT SURFACES.
SEE MECHANICAL AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.
WHERE CMU WALLS ARE INDICATED TO BE REMOVED, PREPARE ADJACENT WALLS TO RECEIVE NEW PATCH/FINISH BY SAWCUTTING AND OR REMOVING CMU IN TOOTH-IN PATTERN BOTH SIDES OF DEMOLITION
FOR CONTRACTOR TO TOOTH-IN NEW CMU PATCHES AS NEEDED.
SEE MECHANICAL, PLUMBING AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.
COORDINATE WITH HAZARDOUS ABATEMENT SHEETS AND REPORT BEFORE ANY DEMOLITION TAKES PLACE.
DEMOLITION NOTES APPLY TO ALL DEMOLITION SHEETS.
CONFERENCE
ROOM
RESTROOM
LAUNDRY
ROOM
OFFICE
STORAGE
ROOM
WORKOUT
AREA
STORAGE
ROOM
IT CLOS.
TRANSFORM.
DEMO SHEET NOTES#
TRUE
N
WOMEN'S
LOCKER
MEN'S
LOCKER
MECHANICAL
ROOM
20'-3 3/8"
SAUNA
SAUNA
6'-10"
MEN'S
WOMEN'S
WOMEN MEN
HCSHOWER
MECHROOM
TYP
LOCKERWOMEN'S
P/B/F 24 P/B/F 24
P/ B/
F
P/ B/
F
P/B/F 24P/B/F 24
P/B/F 24 P/B/F 24
AREA NOT IN SCOPE
AREA OF WORK
US Army Corps of Engineers ®
SHEET ID
U S
AR
M
Y C
O R
PS
O
F
EN
G
IN
EE
R
S
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
SU
BM
IT
TE
D B
Y:
SI
ZE
C H
EC
KE
D B
Y:
AN
SI
D
IS
SU
E D
AT
E:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
N
3 5 7 9 11 13 15 17 19
L
J
G
E
C
A
D
AT
E M
AR
K
D
ES
C R
IP
TI
O N
Fi le
P at h:
Pl ot D at e:
2 4 6 8 10 12 14 16 18 20
P
M
K
H
F
D
B
KEYPLAN
SCALE: N.T.S.
Au to de sk
D oc s:
//2
5-
6-
D
LA
D
SC
C
B ld g.
R
E
PF
R em od /2
5-
6-
_D
LA
D
SC
C
B ld g.
R
E
PF
R em od _A
R _2
4.
rv t
4/
/2
5:
:1
PM
AD102
D
EM
O
LI
TI
O
N P
LA
N
AR
EA
1N
C O
LU
M
BU
S, O H
IO
LO
U
IS
VI
LL
E, K
Y E.
E.
E.
E.
A.
B.
E.
B.
M ar ch
3, 0%
C
ER
TI
FI
ED
F
IN
AL
D
SC
C D
LA
R
EP
AI
R B
U
IL
D
IN
G
-2
-0
1/8" = 1'-0"B1 OVERALL DEMOLITION PLAN - AREA 11-N
0 5 10
SCALE: 1/8" = 1'=0"
1 EXISTING OVERHEAD COILING DOOR TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING DOOR AND PREPARE OPENING FOR NEW
COMPONENT TO BE INSTALLED AS PER SCHEDULE.
2 EXISTING EXTERIOR DOOR AND FRAME TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING DOOR AND PREPARE OPENING FOR NEW
COMPONENT TO BE INSTALLED AS PER SCHEDULE.
3 EXISTING EXTERIOR WINDOW TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING WINDOW AND PREPARE OPENING FOR NEW
COMPONENT TO BE INSTALLED AS PER SCHEDULE.
4 EXISTING EXTERIOR LOUVER TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING LOUVER AND PREPARE OPENING TO BE FILLED AS
PER STRUCTURAL DETAILS.
5 EXISTING INTERIOR DOOR AND FRAME TO BE REMOVED.
6 INCREASE ROUGH OPENING SIZE TO ACCOMODATE A NEW PAIR 3-0 DOORS.
7 EXISTING OVERHEAD DOOR TO REMAIN IN PLACE.
8 EXISTING WINDOW TO REMAIN IN PLACE .
9 EXISTING EXTERIOR DOOR TO REMAIN IN PLACE.
10 EXISTING GLASS WALL TO BE REMOVED. REMOVE ALL FASTENERS AND BRACKETS IN PREPARATION TO INSTALL A NEW METAL STUD WALL AS PER PLANS.
CONFIRM WITH OWNER FOR SALVAGED ITEMS.
11 EXISTING WALL AND WALL MOUNTED ITEMS TO BE REMOVED. VERIFY DIMENSIONS ON SITE.
12 EXISTING VIEWING WINDOW INTO RACQUET BALL COURT TO BE REMOVED.
13 EXISTING RACQUET BALL FLOORING TO BE REMOVED TO CONCRETE SLAB. PREPARE CONCRETE SLAB TO RECEIVE NEW FLOORING AS PER FINISH SCHEDULE.
14 EXISTING RACQUET BALL HARD CEILING TO BE REMOVED. RE: MEP DRAWINGS FOR ADDITIONAL INFORMATION.
15 NEW DOOR OPENING FOR NEW ACCESS DOOR TO RACQUET BALL COURT.
16 DIMENSION TO BE VERIFIED IN FIELD. APPROXIMATE BASED ON EXISTING DOCUMENTS.
17 EXISTING SUSPENDED ACCOUSTICAL CEILING SYSTEM TO BE REMOVED.. RE:MEP FOR ADDITIONAL INFORMATION.
18 EXISTING FLOORING TO BE REMOVED TO CONCRETE SLAB. PREPARE EXISTING SLAB FOR NEW FLOORING AS PER FINISH SCHEDULE.
19 EXISTING WALL PADDING TO BE REMOVED.
20 EXISTING MECHANICAL MEZZANINE ABOVE THIS AREA TO BE REMOVED.
21 EXISTING LADDER TO MEZZANINE TO BE REMOVED WITH ALL COMPONENTS, INCLUDING BUT NOT LIMITED TO FASTENERS, BRACKETS, ETC.. REPAIR WALL, PATCH HOLES, REPAIR FLOORING AND REFINISH WALL AND FLOOR TO MATCH ADJACENT.
22 EXISTING ELECTRICAL CLOSET TO REMAIN IN PLACE. PROTECT DURING DEMOLITION.
23 EXISTING FLOORING DECK TO BE REMOVED. JOIST TO REMAIN IN PLACE.
24 REMOVE ALL DEBRIS LEFT OUT FROM MECHANICAL AND ELECTRICAL DEMOLITION WORK LEFT BEHIND INCLUDING BUT NOT LIMITED TO FASTENERS, HANGERS, METAL PANS, ETC.
25 REMOVE EXISTING ACCESS LADDER AND ALL ASSOCIATED HARDWARE. PATCH HOLES AND REPAINT WALLS AS NEEDED. PATCH AND CLEAN UP FLOOR TO
MATCH EXISTING.
26 EXISTING METAL CAGE TO BE REMOVED. PATCH ALL HOLES, AND REPAIR ANY OTHER DAMAGES AROUND THE WINDOW OPENING TO MATCH ADJACENT
WALLS.
27 EXISTING FAN IN CAGE TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING FAN INCLUDING THE CAGE AND PREPARE OPENING TO BE
FILLED AS PER STRUCTURAL DETAILS. RE: MECHANICAL DEMOLITION DRAWINGS FOR ADDITIONAL INFORMATION.
28 REMOVE EXISTING VINYL FLOORING AND PREPARE SUBSTRATE FOR INSTALLATION OF NEW VINYL FLOORING.
29 SAW CUT BRICK BELOW THE EXISTING WINDOW TO EXTEND THE EXISTING OPENING TO THE FLOOR, CLEAN AND PREPARE TO RECEIVE NEW BLOCK NEW HM
DOOR AND FRAME.
D FINAL
03/13/2026
W
2Q R
BA
1_
Pl an s-
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
THE CONTRACTOR SHALL:
COORDINATE ALL DEMOLITION AND PHASING EFFORTS WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). EVERY EFFORT SHALL BE MADE TO MINIMIZE DISRUPTION OF OCCUPANT'S OPERATIONS. EXCESSIVE NOISE OR VIBRATION SHALL BE PRE-APPROVED AND COORDINATED WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R). IN ALL CASES, PROVISIONS SHALL BE MADE FOR
USER’S SAFETY.
COORDINATE ANY DISRUPTION OF UTILITY SERVICES WITH THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND AS SPECIFIED.
CONSTRUCT TEMPORARY CONSTRUCTION PARTITIONS WITHIN THE EXISTING BUILDING WHICH OFFER A ONE-HOUR ENCLOSURE TO ISOLATE ANY DEMOLITION/CONSTRUCTION WORK FROM THE GENERAL PUBLIC AND AS DEEMED NECESSARY BY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) AND CODE OFFICIAL HAVING JURISDICTION. COORDINATE LOCATIONS WITH THE CONTRACTING OFFICER
REPRESENTATIVE (C0R) AND MAINTAIN MEANS OF EGRESS THROUGHOUT THE WORK.
MAINTAIN A SECURE, WEATHER-TIGHT ENCLOSURE AT ALL TIMES.
VERIFY ALL EXISTING CONDITIONS, DIMENSIONS AND ELEVATIONS AND NOTIFY THE CONTRACTING OFFICER REPRESENTATIVE (C0R) OF ANY DISCREPANCIES.
REMOVE IN THEIR ENTIRETY ALL EXISTING WALLS, DOORS, MILLWORK, PLUMBING FIXTURES, CEILINGS, SOFFITS, WALL FIXTURES, AND OTHER ITEMS, AS REQUIRED TO EXECUTE THE
DEMOLITION/CONSTRUCTION WORK DESCRIBED BY THE DRAWINGS.
PROVIDE PROTECTION FOR ALL EXISTING BUILDING MATERIALS AND EQUIPMENT FROM DAMAGE DUE TO ANY DEMOLITION OR CONSTRUCTION-RELATED INCIDENT PERFORMED UNDER THIS CONTRACT.
REPAIR OR REPLACE ITEMS THAT ARE DAMAGED AS A RESULT OF DEMOLITION OR CONSTRUCTION TO MATCH EXISTING FINISH AND/OR CONDITION.
NO EXISTING MATERIALS SHALL BE REUSED IN ANY INSTANCE. DISPOSE OF EXISTING DEMOLISHED MATERIALS AS PER SPECIFICATIONS.
VERIFY AND MAINTAIN THE LOCATION OF EXISTING POWER, COMMUNICATION AND DATA CABLES TO PREVENT INTERRUPTION OF THEIR SERVICE.
PATCH FLOOR, WALL AND CEILING PENETRATIONS RESULTING FROM REMOVAL OR RE-ROUTING OF NEW OR EXISTING PIPING, DUCTWORK, CONDUIT, AND OTHER ITEMS, AS REQUIRED TO MAINTAIN FIRE- RESISTANCE-RATED SEPARATIONS. FINISH AS REQUIRED FOR NEW OR EXISTING ADJACENT SURFACES.
CAP ALL DISCONNECTED MECHANICAL PIPING LINES WITHIN THE WALL OR FLOOR. PATCH AND FINISH AS REQUIRED TO MATCH NEW OR EXISTING ADJACENT SURFACES.
SEE MECHANICAL AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.
WHERE CMU WALLS ARE INDICATED TO BE REMOVED, PREPARE ADJACENT WALLS TO RECEIVE NEW PATCH/FINISH BY SAWCUTTING AND OR REMOVING CMU IN TOOTH-IN PATTERN BOTH SIDES OF DEMOLITION
FOR CONTRACTOR TO TOOTH-IN NEW CMU PATCHES AS NEEDED.
SEE MECHANICAL, PLUMBING AND ELECTRICAL DRAWINGS AND NOTES FOR FURTHER SEQUENCING AND SCOPE OF WORK.
COORDINATE WITH HAZARDOUS ABATEMENT SHEETS AND REPORT BEFORE ANY DEMOLITION TAKES PLACE.
DEMOLITION NOTES APPLY TO ALL DEMOLITION SHEETS.
8' - 9 1/2" +/- VIF
BASKETBALL
COURT
MEN'S
RESTROOM
MEN'S
SHOWERS
MECH. ROOM
WOMEN'S
RESTROOM
WOMEN'S
SHOWERS
WOMEN'S
LOCKER ROOM
SPRINKLER
RISE
2 3
32' - 2" +/- VIF
26 26
SAUNA
1212 SAUNA
A-402
DEMO SHEET NOTES#
WOMEN'S
LOCKER
MEN'S
LOCKER
MECHANICAL
ROOM
20'-3 3/8"
SAUNA
SAUNA
6'-10"
MEN'S
WOMEN'S
WOMEN MEN
HCSHOWER
MECHROOM
TYP
LOCKERWOMEN'S
P/B/F 24 P/B/F 24
P/ B/
F
P/ B/
F
P/B/F 24P/B/F 24
P/B/F 24 P/B/F 24
AREA NOT IN SCOPE
AREA OF WORK
WOMEN'S
LOCKER
MEN'S
LOCKER
MECHANICAL
ROOM
20'-3 3/8"
SAUNA
SAUNA
6'-10"
MEN'S
WOMEN'S
WOMEN MEN
HCSHOWER
MECHROOM
TYP
LOCKERWOMEN'S
P/B/F 24 P/B/F 24
P/ B/
F
P/ B/
F
P/B/F 24P/B/F 24
P/B/F 24 P/B/F 24
AREA NOT IN SCOPE
AREA OF WORK
US Army Corps of Engineers ®
SHEET ID
U S
AR
M
Y C
O R
PS
O
F
EN
G
IN
EE
R
S
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
SU
BM
IT
TE
D B
Y:
SI
ZE
C H
EC
KE
D B
Y:
AN
SI
D
IS
SU
E D
AT
E:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
N
3 5 7 9 11 13 15 17 19
L
J
G
E
C
A
D
AT
E M
AR
K
D
ES
C R
IP
TI
O N
Fi le
P at h:
Pl ot D at e:
2 4 6 8 10 12 14 16 18 20
P
M
K
H
F
D
B
Au to de sk
D oc s:
//2
5-
6-
D
LA
D
SC
C
B ld g.
R
E
PF
R em od /2
5-
6-
_D
LA
D
SC
C
B ld g.
R
E
PF
R em od _A
R _2
4.
rv t
4/
/2
5:
:1
PM
AD103
D
EM
O
LI
TI
O
N P
LA
N
AR
EA
2N
C O
LU
M
BU
S, O H
IO
LO
U
IS
VI
LL
E, K
Y E.
E.
E.
E.
A.
B.
E.
B.
M ar ch
3, 0%
C
ER
TI
FI
ED
F
IN
AL
D
SC
C D
LA
R
EP
AI
R B
U
IL
D
IN
G
-2
-0
1/8" = 1'-0"B1 OVERALL DEMOLITION PLAN - AREA 12-N
0 5 10
SCALE: 1/8" = 1'=0"
1 EXISTING OVERHEAD COILING DOOR TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING DOOR AND PREPARE OPENING FOR NEW
COMPONENT TO BE INSTALLED AS PER SCHEDULE.
2 EXISTING EXTERIOR DOOR AND FRAME TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING DOOR AND PREPARE OPENING FOR NEW
COMPONENT TO BE INSTALLED AS PER SCHEDULE.
3 EXISTING EXTERIOR WINDOW TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING WINDOW AND PREPARE OPENING FOR NEW
COMPONENT TO BE INSTALLED AS PER SCHEDULE.
4 EXISTING EXTERIOR LOUVER TO BE REMOVED. REMOVE ALL COMPONENTS ASSOCIATED WITH EXISTING LOUVER AND PREPARE OPENING TO BE FILLED AS
PER STRUCTURAL DETAILS.
5 EXISTING INTERIOR DOOR AND FRAME TO BE REMOVED.
6 INCREASE ROUGH OPENING SIZE TO ACCOMODATE A NEW PAIR 3-0 DOORS.
7 EXISTING OVERHEAD DOOR TO REMAIN IN PLACE.
8 EXISTING WINDOW TO REMAIN IN PLACE .
9 EXISTING EXTERIOR DOOR TO REMAIN IN PLACE.
10 EXISTING GLASS WALL TO BE REMOVED. REMOVE ALL FASTENERS AND BRACKETS IN PREPARATION TO INSTALL A NEW METAL STUD WALL AS PER PLANS.
CONFIRM WITH OWNER FOR SALVAGED ITEMS.
11 EXISTING WALL AND WALL MOUNTED ITEMS TO BE REMOVED. VERIFY DIMENSIONS ON SITE.
12 EXISTING VIEWING WINDOW INTO RACQUET BALL COURT TO BE REMOVED.
13 EXISTING RACQUET BALL FLOORING TO BE REMOVED TO CONCRETE SLAB. PREPARE CONCRETE SLAB TO RECEIVE NEW FLOORING AS PER FINISH SCHEDULE.
14 EXISTING RACQUET BALL HARD CEILING TO BE REMOVED. RE: MEP DRAWINGS FOR ADDITIONAL INFORMATION.
15 NEW DOOR OPENING FOR NEW ACCESS DOOR TO RACQUET BALL COURT.
16 DIMENSION TO BE VERIFIED IN FIELD. APPROXIMATE BASED ON EXISTING DOCUMENTS.
17 EXISTING SUSPENDED ACCOUSTICAL CEILING SYSTEM TO BE REMOVED.. RE:MEP FOR ADDITIONAL INFORMATION.
18 EXISTING FLOORING TO BE REMOVED TO CONCRETE SLAB.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .