JA - SCO (HVAC Chillers - Brand Name) - B1600 (Clean).pdf
PDF 178 KB Posted
- Attached to
- Scott AFB B1600 Renovation
- Solicitation number
- W912QR20R0087
About this file
This justification and approval document outlines the use of brand name specifications for Trane HVAC chillers in a construction contract for renovations at Scott Air Force Base. The Air Force Civil Engineering Command conducted market research and determined that Trane chillers will provide efficiencies in maintenance support and costs. All facilities at Scott Air Force Base currently use Trane chillers. The renovations will replace the existing Trane chillers with new ones of the same brand in order to standardize equipment and realize lifecycle cost savings. The construction contract solicitation will include the brand name specifications and is planned for award as a full and open competition using fiscal year 2021 funds. The estimated cost for the chiller equipment is approximately $XXXXXX.
The related federal contract opportunity is a solicitation for the renovation of Building 1600 at Scott Air Force Base. The project scope includes complete interior and exterior renovations and replacement of all mechanical, electrical, plumbing and communications systems. The solicitation will be a firm-fixed-price contract with a magnitude between $100-250 million. The North American Industry Classification System code is 236220. Proposals will be evaluated using a tradeoff best value approach. The solicitation will be posted at beta.sam.gov and have a contract duration of 1260 calendar days.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JUSTIFICATION AND APPROVAL
FOR OTHER THAN FULL AND OPEN COMPETITION
1. Contracting Agency: U.S. Army Corps of Engineers (USACE), Louisville District, Post Office Box 59, Louisville, Kentucky 40201-0059.
2. Description of Action: This justification and approval (J&A) is being prepared for the use of a brand name item, Trane HVAC Chillers, in the firm fixed price construction contract for the Air Mobility Command Headquarters Renovation project at Scott Air Force Base, Illinois.
The government will not purchase the Trane equipment directly, but rather brand name specifications will be included in the design bid build solicitation that will lead to a new firm fixed price (FFP) construction contract. The construction contract is planned to be awarded under a full and open solicitation, using FY21 Sustainment, Restoration and Modernization (SRM) funding.
3. Description of Supplies/Services: The chillers selected for use on the Air Mobility Command Headquarters Renovation project at Scott Air Force Base, Illinois are Trane chillers. The Trane Chillers Brand Name Specifications will be included in the Design Bid Build Solicitation. Trane has offices around the world, with an office in Fenton, MO. The estimated total cost for the equipment is approximately XXXXXX.
4. Authority Cited: 10 United States Code (U.S.C.) 2304(c)(1), as implemented by Federal Acquisition Regulation (FAR) 6.302-1(a)(2) “Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements.” This authority is applicable to brand name justifications in accordance with FAR 6.302-1(c)(1).
5. Reason for Authority Cited: As described at FAR 6.302-1(a)(2), when the supplies or services required by the agency are available only from one responsible source and no other types of supplies or services will satisfy agency requirements, full and open competition need not be provided for. This J&A applies that ‘Only One Responsible Source’ authority using the application of FAR 6.302-1(b)(4), which states that “[w]hen the agency head has determined in accordance with the agency’s standardization program that only specified makes and models of technical equipment and parts will satisfy the agency’s needs for additional units or replacement items, and only one source is available.”
a) Background: The Air Mobility Command Headquarters Renovation project at Scott Air Force Base is a wholesale renovation and systems replacement project. The scope of the project will consist of a complete renovation to make the 314,000 SF facility current for all applicable criteria, standards, and codes. The scope includes life safety systems, structural systems, architectural and interior systems, interior power and lighting, emergency / alarm systems, plumbing, HVAC, telecommunications systems, ATFP/Seismic upgrades, server racks, floors, walls / ceilings, toilets, and furnishings.
Work will include providing adequate seismic bracing and protection to the existing steel structure. Replacement of the interior partitions to better the suit the current mission within the facility. Replacement of the existing lighting with a more energy efficient system, and replacement of all conduit that will hold the wiring for all communication lines, security system lines, and fire alarm systems. Installation of a fire suppression system to meet updated codes to include any alarm and mass notification systems. All interior and exterior windows will be replaced along with the interior and exterior doors.
The electrical, HVAC, and plumbing systems will be replaced. Site work will include grading of the site and soil removal to accommodate additional pier foundations being installed. Site electrical utilities will include a primary switchgear, transformer, and grounding system. A generator will be included to ensure emergency power for the facility.
The facility currently uses Trane chillers; as do all other facilities located on Scott Air Force Base. The intent is to replace the existing Trane chillers with new chillers of the same brand.
b) Justification:
(1) FAR 6.302-1(b)(4) permits use of the Only One Responsible Source authority when the agency head has determined in accordance with the agency's standardization program that only specified makes and models of technical equipment and parts will satisfy the agency's needs for additional units or replacement items, and only one source is available.
(2) In a memorandum signed on 22 June 2017, the Under Secretary of the Air Force appointed the Deputy under Secretary of the Air Force, Management and Deputy Chief Management Officer as the AF Category Management Accountable Official. On 14 July 2017, the Deputy under Secretary of the Air Force, Management and Deputy Chief Management Officer, appointed the Civil Engineer Center Director (AFCEC/CL) as the Air Force Category Manager for the Facilities and Construction Category. On 16 May 2019, the AFCEC/CL directed the mandatory standardization of HVAC chiller systems and delegated manufacturer selection to the AFCEC Operations Director (AFCEC/CO).
(3) On 3 May 2019, the AFCEC/CO executed a memorandum, Subject: HVAC Chiller System Standardization, Single Manufacturer Selection, which set forth the AFCEC/CL intent to standardize HVAC chiller systems to a single manufacturer at the installation level. The memorandum explained that standardization of all HVAC chiller systems allows the Air Force to significantly reduce the total cost of ownership which includes the initial procurement, subsequent maintenance, and associated training costs to operate the system over its lifecycle. The memorandum went on to provide guidance for the evaluation, recommendation, and subsequent approval of a single manufacturer for HVAC chiller systems at each installation and stated that Base Civil Engineers (BCEs) were to request and provide justification for the recommended single HVAC chiller manufacturer. The memorandum concluded with a requirement to repeat the analysis after five years from the date of AFCEC/CO approval for a single manufacturer. The purpose of this secondary analysis is to document the installation's progress in standardizing HVAC chiller systems, consider any changes in the decision facts, and confirm no external factors exist that may drive a reconsideration of the approved single manufacturer.
(4) On 10 May 2019, the AFCEC/CL signed a memorandum, Subject: Mandatory Standardization of HVAC Chiller Systems. The memorandum directed the mandatory standardization of HVAC chiller systems to a single manufacturer at the installation level and reiterated the process laid out in the above referenced 3 May 2019 guidance. The memorandum also delegated the AFCEC/CL’s approval authority to the AFCEC/CO for the selection of a single manufacturer for HVAC chiller systems.
(5) In a memorandum dated 10 September 2019, Subject: HVAC Chiller System Standardization, Single Manufacturer Selection, the AFCEC/CO approved the selection of specific brands as the single manufacturer for various installations, including Scott Air Force Base. This memorandum specifies Trane Inc. as the selected manufacturer for this installation. This selection, supported by the other memorandums summarized above, satisfies the FAR 6.302-1(b)(4) application of the ‘Only One Responsible Source authority,’ as the Agency Head (delegee) has determined in accordance with the agency's standardization program that only specified makes and models of technical equipment and parts will satisfy the agency's needs for additional units or replacement items, and only one source is available.
c) Impact: If this J&A is not approved, USACE will be unable to implement the Air Force’s standardization decision for Air Mobility Command Headquarters Renovation project at Scott Air Force Base. If the HVAC equipment at this installation is not standardized, the Air Force will not be able to realize the efficiencies and reduction of costs that have been targeted in its category management analysis. Anticipated advantages include reduced training costs for Air Force maintenance personnel, efficiencies in obtaining and storing spare parts, and decreased disruption to mission by rapid resolution of any HVAC system failures. If Trane chillers are not utilized in this facility, the Air Force will be required to expend significant resources in additional training for maintenance personnel or in contracts for outside maintenance personnel to perform work on the non-Trane systems, and it would not be able to fully realize the benefits of its standardization decision in gaining efficiencies, decreasing disruptions, and achieving less system down time.
d) Alternatives: The standardization determination executed by the Air Force compels USACE to include the base-specific requirement in the solicitation for the Air Mobility Command Headquarters Renovation. There is no alternative product that meets the AF’s need to standardize this equipment. The only alternative available would be to purchase the HVAC equipment separately and provide it to the construction contractor as government furnished equipment (GFE). This alternative would still involve the purchase of the Trane equipment on a sole source basis. Further, the effort associated with purchasing, storing, equipment warranty, conveying and managing the GFE was determined to both be inefficient and uneconomical. No other feasible alternative were identified.
6. Efforts to Obtain Competition: A technical review and evaluation was conducted of the Chillers for the all of the Air Force, per Installation, by the Air Force Civil Engineering Command (AFCEC). AFCEC determined TRANE would be the official sole-source provider of Chillers for Scott AFB to provide efficiencies in maintenance support and in savings of training time and money for their maintenance staff.
A Notice of Intent to Sole Source was posted on 09 September 2020 on the beta.sam.gov website. To date, no other sources have written to express interest. If prior to issuance of the solicitation, responses are received expressing interest, the justification will be amended.
7. Actions to Increase Competition: In order to achieve the benefits of the Air Force’s standardization decision competition must be limited. This is a finite requirement with no future needs, and therefore there are no actions to increase future competition.
8. Market Research: A technical review and evaluation was conducted of the Chillers for all of the Air Force, per Installation, by the Air Force Civil Engineering Command (AFCEC).
AFCEC determined TRANE would be the official sole-source provider of Chillers for Scott AFB to provide efficiencies in maintenance support and in savings of training time and money for their maintenance staff.
A Notice of Intent to Sole Source was posted on 09 September 2020 on the beta.sam.gov website. To date, no other sources have written to express interest. If prior to issuance of the solicitation, responses are received expressing interest, the justification will be amended.
9. Interested Sources: A Notice of Intent to Sole Source was posted on 09 September 2020 the beta.sam.gov website. To date, no other sources have written to express interest. If prior to issuance of the solicitation, responses are received expressing interest, the justification will be amended.
10. Other Factors: None
11. Technical Certification: I certify that the supporting data under my cognizance, which are included in the Justification and Approval, are accurate and complete to the best of my knowledge and belief.
File details come from the government source that posted it. Updated .