View the file

Other files

File Type Posted
Am8_W912PL-12-R-0018.pdf PDF
FI WTP Bidder Site Visit 2_20120621.pdf PDF
Am6_W912PL-12-R-0018.pdf PDF
Am5_W912PL-12-R-0018.pdf PDF
Pre-Bid Site Visit No 2 Agenda_19June2012_W912PL-12-R-0018.pdf PDF
Am4_W912PL-12-R-0018.pdf PDF
Am3_W912PL-12-R-0018.pdf PDF
Civil Site4.zip ZIP file
Civil Site1.zip ZIP file
Civil Site3.zip ZIP file
Civil Site2.zip ZIP file
Ft Irwin WT Plant Industry Day QA Feb 2012.pdf PDF
Ft Irwin WT Plant Industry Day Attendees Feb 2012.pdf PDF
Ft Irwin WT Plant Site Visit Sign-in Sheet June 2012.pdf PDF
Am2_W912PL-12-R-0018.pdf PDF
Am1_W912PL-12-R-0018.pdf PDF
Spec_Vol_12_W912PL-12-R-0018.pdf PDF
Spec_Vol_10_2_W912PL-12-R-0018.pdf PDF
Spec_Vol_15_W912PL-12-R-0018.pdf PDF
Spec_Vol_2_W912PL-12-R-0018.pdf PDF
Spec_Vol_1_W912PL-12-R-0018.PDF PDF
Spec_Vol_16_3_W912PL-12-R-0018.pdf PDF
J A_W912PL-12-R-0018.pdf PDF
Spec_Vol_5_2_W912PL-12-R-0018.pdf PDF
Spec_Vol_14_W912PL-12-R-0018.pdf PDF
DRWGS_W912PL-12-R-0018.pdf PDF
Spec_Vol_7_W912PL-12-R-0018.pdf PDF
Spec_Vol_16_1_W912PL-12-R-0018.pdf PDF
Spec_Vol_10_1_W912PL-12-R-0018.pdf PDF
Spec_Vol_9_W912PL-12-R-0018.pdf PDF
Spec_Vol_5_1_W912PL-12-R-0018.pdf PDF
Spec_Vol_4_W912PL-12-R-0018.pdf PDF
Spec_Vol_5_3_W912PL-12-R-0018.pdf PDF
Spec_Vol_11_2_W912PL-12-R-0018.pdf PDF
Spec_Vol_8_W912PL-12-R-0018.pdf PDF
Spec_Vol_3_W912PL-12-R-0018.pdf PDF
Spec_Vol_17_2_W912PL-12-R-0018.pdf PDF
Spec_Vol_11_1_W912PL-12-R-0018.pdf PDF
Spec_Vol_13_W912PL-12-R-0018.pdf PDF
Spec_Vol_17_1_W912PL-12-R-0018.pdf PDF
Spec_Vol_6_W912PL-12-R-0018.pdf PDF
Spec_Vol_16_2_W912PL-12-R-0018.pdf PDF
23-WTP_SurveyRpt.pdf PDF
05-DWG_Vol_5.pdf PDF
22-WTP_PipeExam.pdf PDF
04-SPEC_Vol_4.pdf PDF
14-EDR_Principles_CDPH_Oct09.pdf PDF
19-TankRpt_JPL-3_Dec07.pdf PDF
09-SPEC_Vol_9.pdf PDF
06-DWG_Vol_6.pdf PDF
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 1

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE 4. REQUISITION/PURCHASE 5. PROJECT NO. (If applicable) 0007 June 22, 2012

6. ISSUED BY CODE W912PL 7. ADMINISTERED BY(If other than item 6)

CODE

USACE-LOS ANGELES DISTRICT

CONTRACTING DIVISION, WEST REGION BRANCH

P.O. BOX 532711

LOS ANGELES, CA 90053-2325

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP code) 9A. AMENDMENT OF SOLICITATION

NO.

W912PL-12-R-0018

9B. DATED (SEE ITEM 11)

May 24, 2012

10A. MODIFICATION OF

CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1_ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A

ITEM 10A

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT ADMINISTRATIVE CHANGES(such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b)

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)

DESIGN AND CONSTRUCTION OF A WATER TREATMENT AND DISTRIBUTION SYSTEM, FORT IRWIN

SAN BERNARDINO COUNTY, CALIFORNIA

Revised and Added Pages: See Attached SF 30 Continuation Page.

Except as provided herein, all terms and conditions of the document reference in item 9A or 10A, as Heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICE (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of contracting officer)

16C. DATE SIGNED

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

SF 30 (Continuation Page)

DESIGN AND CONSTRUCTION OF A WATER TREATMENT AND DISTRIBUTION SYSTEM, FORT

IRWIN

SAN BERNARDINO COUNTY, CALIFORNIA

NOTICE TO ALL BIDDERS

This Amendment forms a part of the Contract Documents and modifies the original Bidding Documents dated May 24, 2012 and subsequent Amendment Nos. 0003 and 0005. This Amendment shall become a part of the Contract Documents to the same extent as though it has been written into the body thereof and bound therein. This Amendment is applicable to the items affected and all bidders are held responsible for the contents herein.

Acknowledgement of receipt of this Amendment shall be so noted in the space provided on the Bid Form. Failure to do so may subject the Bidder to disqualification.

Revised Pages

Specification Section 01 10 10 - 8 Appendix A - 85

Revised Specification Sections

The following revised Appendices, noted as Amendment No. 0007and as listed below, is to replace the original specification sections from the Bid Documents dated May 24, 2012.

Section No. Name of section

APPENDIX F CONNECT IRWIN WELLS – BID OPTIONS 4 AND 5

APPENDIX G NEW WELL, LANGFORD LAKE – BID OPTION 6

FY12 WATER TREATMENT AND DISTRIBUTION SYSTEM SPECIFICATION NO.: 1858

FT. IRWIN, CA

Section 01 10 10 - Page 8 of 78 Amendment No. 0007 of the building and equipment shall be revised, as required, and at no additional cost to the Government where the energy reductions have not been met or the analyses have not been conducted by the Contractor.

3.1.4 The Contractor shall base the selection of solutions and technologies to achieve the above energy performance requirements on life cycle cost analysis. Life Cycle Cost Analyses shall follow the requirements set forth in NIST Handbook 135 Life-Cycle Costing Manual using an automated calculation tool such as BLCC or LCCID. Cyclical and annual maintenance cost values shall come from ASHRAE recommendations or other similar Industry Standard sources.

3.2 The Contractor shall provide Energy Star or FEMP designated products.

The term “Energy Star product” means a product that is rated for energy efficiency under the Energy Star program. The term “FEMP designated product” means a product that is designated under the Federal Energy Management Program of the Department of Energy as being among the highest 25 percent of equivalent products for energy efficiency. In the case of an electric motor of 1 to 500 horsepower, the Contractor shall select only a premium efficient motor unless its design for use in variable speed service requires a deviation to this policy.

3.3 Life Cycle Cost Analysis Documentation

3.3.1 The Contractor shall provide a life cycle cost document outlining criteria used to design the facility. The designer of record shall perform LCCA on major building systems, structural, mechanical, electrical, and energy efficiency measures.

3.3.2 The energy consumption reduction of 40 percent (or 50 percent, if B.O.

9 is awarded) below the consumption of a baseline building shall be achieved by submitting system energy reduction alternatives which are weighed against the system’s life cycle cost. The life cycle cost report shall be limited to facility yearly energy consumption associated with the building envelope, HVAC systems (including computer room HVAC system loads) and facility interior lighting. Facility receptacle and all facility process loads such as computer room equipment and other electrical loads shall be used in sizing the HVAC equipment but then ignored in calculating as these electrical system and process system loads cannot be appreciably improved upon with energy saving alternatives. $0.1353/kwh is the energy unit cost to be used for LCCA.

3.3.3 The Contractor shall calculate the baseline energy consumption value in kBTUH/yr/ft2 based upon utilization of minimum ASHRAE Standard 90.1-2007 building envelope and system values as outlined in ASHRAE Standard 90.1-2007 Appendix “G”. The Contractor shall decrease this baseline energy consumption value by 40 percent, or 50% if B.O. 9 is awarded. Possible energy saving alternatives suggested are building construction, building air infiltration rates, HVAC equipment efficiencies, demand ventilation, lighting power consumption, and lighting efficiencies. Other system energy saving alternatives or suggestions shall be accepted if life cycle cost effective to accept the alternative or alternatives. The life cycle cost period shall be 25 years. The Contractor shall follow procedures outlined in ASHRAE Standard 90.1-2007 Appendix “G” for estimating facility yearly energy consumption values. Methodologies and procedures for the preparation of Life Cycle Cost Analyses shall be in accordance with Title 10 Code of Federal Regulations (CFR), Part 436, Federal Energy Management and Planning Programs, Subpart A, Appendix A - Page 85 of 114

9.3 LIGHTNING PROTECTION

9.3.1 A conventional lightning protection system shall be designed and provided in accordance with NFPA 70 National Electrical Code and NFPA 780 Standard for the Installation of Lightning Protection Systems, UL 96 Lightning Protection Components and UL 96A Installation Requirements for Lightning Protection Systems. Exterior, exposed, down conductors shall not be utilized. The facility structural steel shall be interconnected and used as the lightning protection system down conductor in conformance with NFPA 780.

9.3.2 The lightning protection system shall consist of air terminals, roof conductors, down conductors, ground connections, and grounds, electrically interconnected to form the shortest distance to ground. Secondary conductors shall interconnect with grounded metallic parts within the building.

Interconnections made within side-flash distances shall be at or above the level of the grounded metallic parts. The system furnished shall consist of the standard products of a manufacturer regularly engaged in the production of lightning protection systems and shall be the manufacturer's latest UL approved design.

9.4 SYSTEMS CONTROL AND SCADA/PMS

9.4.1 Supervisory Control and Data Acquisition (SCADA). Current SCADA systems at Ft. Irwin are primarily utilized to monitor the Waste Water Treatment Plant, water storage tanks fill levels and control the wells and booster pumps that supply it. The communication pathways between the various points of the system utilize RF signals. See Figure 1, Section 1 of Appendix “A” Drinking Water Flow Schematic for overall system function. The system shall be RTU based with the capability utilizing of both RF and FOC pathways. RF signals shall be utilized for all sites off WTP site, except pathway from current tanks on hill to WTP. The water treatment plant and each of the wells and booster stations shall have an independent graphic interface for local control. Master system control shall be provided by graphic interface at the Water Treatment Plant Control Building. Water Treatment Plant monitoring and control functions shall be designed based on the processes described in section 1.3 GENERAL DESIGN REQUIREMENTS AND CRITERIA FOR WATER TREATMENT AND DISTRIBUTION SYSTEM. SCADA system architecture shall include fail-over redundancy for the critical Water Treatment Plant processes. The current Waste Water Treatment Plant (WWTP) shall be integrated into the new system as a client node and shall be monitored from new control building location so that alarms at the waste water treatment plant may be seen and acknowledged. The existing software is based on Rockwell Automation Factory Talk (SE Client) and the existing hardware is based on the Control Logic 5000. It shall be at the contractor’s discretion to add to the existing system or install new equipment at the existing equipment sites so as to make the entire system functional. Integration shall pick up the signals from the PLCs at the WWTP, and bring into the new system at the water plant.

Automation of the water treatment facilities to allow unattended operation and off-site control presents a number of management and technological challenges which must be overcome before an approval can be considered. Each facet of the plant facilities and operations must be fully evaluated to determine what on-line monitoring is appropriate, what alarm capabilities must be incorporated into the design and what staffing is necessary. Consideration must be given to the consequences and operational response to treatment challenges, equipment failure and loss of communications or power.

APPENDIX F - Page 1 of 22

APPENDIX - F: CONNECT IRWIN WELLS – BID OPTION 4 AND 5

1. PROJECT DESCRIPTION

1.1. PROJECT SCOPE

This scope includes design and installation of two main components:

Part A – BID OPTION 4 – Connection of existing Well I-9 (Facility 856) to the Langford Lake raw water line. Well I-9 is an existing well constructed in 1988 for use as a water point for dust control with a well pumping rate of 600 gpm. The well is permitted as an industrial supply well. The well has been off-line for some time and will require re-conditioning. For bidding purposes only, the new well pump is anticipated to be 125 HP submersible pump. Contractor is required to: permit the well as community water supply well; conduct a Water Well Condition Assessment, including television survey of the well with closed circuit television (CCTV); recondition the well to allow full production capacity, including chemical treatment and scale removal; install a new well pump; and design and construct a new well pump house, design and install a sodium hypochlorite generation system with storage tank, discharge piping, flow meter, control system, SCADA, and all required valves and appurtenances for a compliant production well. Well shall have airline and gauges installed for monitoring well levels (static, pumping and drawdown). Demolition and salvage is required of existing water point structure and piping, the submersible pump if the pump is found to be unserviceable, the adjacent light structure and control panel, and required utilities and appurtenances for construction of well house. Generator with secondary containment, control system, SCADA, and FE-8 security fencing is also required for the well. The building facade must follow the Master Planning Building Design Guide for Ft. Irwin and requirements listed in this specification. Although this will supply raw water to the new untreated water storage tank at the WTP of Appendix A, chlorine is required for this I- 9 well. System shall be automated to provide from 0.1 mg/l Cl2 to 4 mg/l Cl2 at the range of flows capable by well pump. System shall be connected to existing alarm system and telemetry system for monitoring and in full compliance with federal, state, and local requirements. Contractor shall determine range of pressures to overcome at connection point in the Langford Lake raw water line and design pump capable of maximizing flow rate at given pressure range. For bidding purposes only, the Contractor shall consider the hydraulic grade line (HGL) for the Well I‐2A at the connection point shown in the RFP drawings (through hydraulic modeling) to range from 2,700 to 2,752 ft (depending on the number of booster pumps operating at Langford Lake Booster station). Well pump shall be premium efficiency pump/motor and shall operate within the optimum range of the pump curve (shall not exceed pump curve limits). The Contractor shall test the water quality of Well I-9 for use in design of Water Treatment Plant. The pumproom floor shall be provided with a floor drain discharging to a sump at least twenty-five feet from the well. A valved pump test connection shall be provided downstream of check valve designed for discharge away from pump house to nearby storm drainage system with proper erosion control methods.

Part B – BID OPTION 5 - Well I-2A (Bldg 43) is an existing well with pumping rate of 400 gpm. The well was previously permitted as a public water supply well, but has been out of service since about 2003 due to high nitrates. The well is not currently permitted as a public water supply well. The well is

APPENDIX F - Page 2 of 22 Amendment No. 0007 plumbed into the RO system and to the DO system. The scope of this effort includes permitting the well as an industrial supply well; disconnection of the well from both the RO & DO system (after the construction and acceptance of the new water treatment and distribution system); conducting a Water Well Condition Assessment that will include removal and a condition assessment of the existing vertical turbine pump and bowls; conducting and recording a downhole video survey of the existing well with Closed Circuit Television (CCTV); reconditioning the well to allow full production capacity, including chemical treatment and scale removal; and design and constructing a new well pump, design discharge piping, flow meter, control system, SCADA, and all required valves and appurtenances for a compliant production well. Well shall have airline and gauges installed for monitoring well levels (static, pumping and drawdown). Refurbishing existing well pump house shall include repainting the existing building walls and roof system. The well will discharge to a new adjacent water storage tank (assumed to be 2,500 gallon, for bidding purposes only) via an air gap. A new booster station building shall be designed and constructed along with new variable frequency drive (VFD) high efficiency pumps, valves, flowmeter, SCADA, control system, and all required valves, utilities, and appurtenances to draw supply from the water storage tank and discharge to the to the nearby reclaimed water (REC) purple pipe system. A sodium hypochlorite chlorination system shall be designed and constructed as part of this Bid Option. System shall be automated to provide from 0.1 mg/l Cl2 to 4 mg/lCl2 at the range of flows capable by well pump. System shall be connected to existing alarm system and telemetry system for monitoring and in full compliance with federal, state, and local requirements. The centrifugal pumps shall be sized to provide the maximum well yield and ramp down as required to match pump output to system demand (paced on system pressure). The REC irrigation system currently delivers up to 600 gpm, with current usage of 550 gpm during the summer and 350 gpm during the winter. This well is intended to be used to provide or supplement irrigation water (in the event that the wastewater treatment plant does not meet permit or quantity requirements) or for testing the water system during daylight hours. It is assumed, for bidding purposes only, that the well pump shall be a 75 HP vertical turbine well and two booster pumps shall be 25 HP centrifugal pumps. Hydraulic modeling was conducted for the REC water system to determine the HGL range for the tie-in point for I-2A.

Depending upon the location and intensity of the irrigation demand during the irrigation cycle, the required HGL for the Well I‐2A booster to pump to in the recycled water distribution system was determined to range from 2,671 to 2,730 ft. Contractor shall complete the design for the well pump and booster pump based on actual field conditions. Booster pumps shall be premium efficiency pump/motor and shall operate within the optimum range of the pump curve (shall not exceed pump curve limits). Drainage shall be provided from pump room to discharging to a sump at least twenty-five feet from the well.

A valved pump test connection shall be provided downstream of check valve designed for discharge away from pump house to nearby sanitary sewer system or street discharge with properly sized erosion control measures.

See Appendix F drawings for proposed site layout, information on existing structures and system, as-builts, and examples of new structures required.

See Appendix N for available well, water quality, and pump information.

Reference Appendix A part 1.4 for additional chemical system requirements in addition to design criteria listed below.

Any connections to AC water lines shall include a minimum of ten feet of replacement pipe up and downstream of the connection with new valves. Other possibly corroded, brittle, or tuberculated pipe shall be brought to the

APPENDIX F - Page 3 of 22 Amendment No. 0007 attention of the COR for possible modification to contract for replacement prior to construction of the tie-in. See requirements for Handling and Disposal of Asbestos Transite Pipe below.

1.2 Contractor shall provide for the following, as a minimum, for approval from the C.O.R.:

1. Prepare and submit a Well Condition Assessment Report for wells I- 9 and I-2A

2. Product Data: For each type and size of pump indicated.

3. Design and Shop Drawings: Show the layout and connections for well pumps and specs.

4. Field quality-control report.

5. Well Condition Assessment Plan for Wells I-9 and I-2a

A plan specified that describes the methods disconnection of the pump from the well head, removal of the well head, methods to pull pump from the well. Inspection methods for eductor pipe well casing and screen, casing and well screen maintenance methods and operations, and new pump installation

6. Well Maintenance Plan.

7. Well Maintenance Methods

8. Pump Installation Plan and Diagram

9. Project Photographs before, during, and after work completion, the design –build contractor shall photograph and document each well and installation activities.

10. Analytical Report that contains the results of well and pump decontamination with analytical results of decontamination of the water wells and sample recovery must submitted within ten days before connection to the water system.

11. Tests. Test reports within 48 hours following the conclusion of each test.

12. Qualifications. Documentation of Personnel Qualifications

13. Permits. A copy of all permits, licenses or other legal requirements necessary for the execution of the work shall be furnished 15 working days before commencement of the work.

Submit a Request to RWQCB-Lahontan Region for Change in use to a Public Supply Well for Well I-9 and Change in Use from a Public Supply Well to an Industrial Supply for Well I-2.

1.3 CRITERIA

In addition to the Design Criteria identified in Specification Section 01 10 10 "DESIGN REQUIREMENTS, GENERAL", this portion of the project shall meet the requirements called for in the following documents. The following criteria documents can be obtained from the following Internet address:

http://www.hnd.usace.army.mil/techinfo. The A/E is responsible for obtaining these documents. In the event of any conflict between criterion identified in Specification Section 01 10 10 and/or this appendix and this Request For Proposal (RFP), the requirements noted in the RFP shall govern. The A/E shall bring all such conflicts to the immediate attention of the Contracting Officer’s Representative (COR).

a. Unified Facilities Criteria (UFCs):

UFC 3-230-04A Design: Water Distribution UFC 3-230-10A Design: Water Supply: Water Distribution UFC 3-600-01 Fire Protection Engineering for Facilities UFC 33-20-00 Design: Water Wells

APPENDIX F - Page 4 of 22

b. International Building Code 2009

c. California Department of Public Health

Public Water Systems rules, regulations, environmental regulations and standards, and minimum recommended design criteria.

California Waterworks Standards which are found in California Code of Regulations, Title 22, Division 4, Chapter 16, Sections 64551-64604

d. Recommended Standards for Water Works (Ten States Standards)

e. California Department of Water Resources, Water Well Standards DWR - Well

Standards

f. USEPA Safe Drinking Water Act 42 U.S.C. §300f et seq. (1974)

g. California Office of Administrative Law CCR Titles 22, 17, and 27

h. National Water Works Association (NWWA) C-200

i. AWWA A100

2. DESIGN REQUIREMENTS

2.1. General: The Contractor shall furnish and be responsible for the complete set of documents required to support this project as called for in specification Section 01 10 10 DESIGN REQUIREMENTS, GENERAL, 01 33 16 DESIGN AFTER AWARD, as required by the drawings, and as called for hereinafter. The Government shall have final acceptance authority for the final overall design, materials, finishes and colors used for the project.

The Design Requirements for the Well Condition Assessment Plan should include the following items:

Method for pump and eductor piping removal.

Method for Pump Condition Inspection for electrical and mechanical operation.

Method for Inspection and testing of eductor pipe, Method for video graphic inspection and documentation of the well casing and screen condition.

Method to clean or repair the well casing and screen.

Method for Decontamination of the well piping and pump

Prior to implementation of the Well Condition Assessment Plan, the plan must be submitted to the COR for Technical Review and approval

The design requirements for the Well Condition Assessment Report should include the following results of the Well Condition Assessment Photo documentation such as video graphic well logs to document well restoration efforts Costs associated with replacement or reinstallation of the pump and eductor pipe if the pump and eductor pipe warrant or replacement.

The results of the mechanical and electrical inspection of the pump.

APPENDIX F - Page 5 of 22 Amendment No. 0007

The results of the inspection and cleaning of the well casing and screen. Any associated cost estimates for replacement or repair of well casing and screens The well decontamination process and results of bacteria decontamination of the well.

Any necessary design required to complete this project shall be completed by the Contactor and accomplished in accordance with the intent of the plans and specifications provided. Specifically all water work under this contract shall conform to the requirements set forth in Specification Sections 33 11 00 Water Distribution System, which the Contractor shall edit.

Coordination of all utility work on the project is the responsibility of the Contractor. The Contractor shall confirm the exact location of existing utilities.

The equipment and materials selected shall be high quality, durable and generally easily maintained. The Contractor shall be responsible for the professional quality, code compliance, technical accuracy and coordination of all designs, drawings, specifications and other documents or publications upon which the design and construction are based. The design and construction of this facility shall conform to the drawings, specifications and design requirements issued in this solicitation. In case of a conflict in design requirements, the most stringent requirements govern.

Drawings included in the solicitation are conceptual drawings for location of work and general outline of effort. The Contractor shall design and develop full design drawings.

The products that are to be provided to accomplish this work shall be selected, connected, and generally arranged by someone accomplished in the required skills necessary to complete the work. For instance, placing and connecting of pipelines shall be accomplished by pipe fitters and plumbers as required. Installation and modification for communication and electrical instrumentation and controls shall be accomplished by electricians and instrument/controls technicians.

The requirements for local construction permits for disruptions of possible vehicular traffic and base utility systems, and all other permits shall be obtained by the Contractor based on preconstruction meetings with Government representatives. These areas shall include, but are not limited to: safety;

security; Army personnel; erosion control requirements; California Department of Public Health; as well as other local environmental departments. The Contractor shall be responsible for submitting all applications and paying for all associated permit application fees that are required. These costs shall be included in the Contractor’s Proposal.

No dumpster will be provided on site by the Government. All debris and trash shall be the responsibility of the Contractor to control and police for cleaning up on a continuous basis. All materials shall be disposed of properly and offsite to a proper disposal area.

2.2. Proposed Construction Description

2.2.1. Site Preparation: The Contractor will be responsible for preparing the selected site as necessary for installation of the water lines and appurtenances to the existing water system.

APPENDIX F - Page 6 of 22

2.2.2. Accessibility to the project site shall be the Contractor’s responsibility. Based on the equipment necessary to deliver and install the piping, valves, and appurtenances, the Contractor shall coordinate deliveries with security personnel, keeping the COR informed at all times. Any additional costs for this coordination shall be included in the Contractor’s proposal.

2.2.3. Utility Outages. If the Contractor determines that a utility must be turned off in order to execute work as required herein, he shall notify the COR of such necessity and it must be coordinated with Army personnel. A minimum of 30 days notice in writing for a requested utility outage is required of the Contractor. The Government will attempt to comply with the Contractor’s desire, but if the chosen date is not workable, another mutually agreeable date must be negotiated.

2.2.4. Technical Specifications and Cut Sheets: The Contractor shall adhere to the 01 10 10 DESIGN REQUIREMENTS, GENERAL and this specification appendix. Technical standards that set the minimum allowable quality that the Government expects are listed at the end of this document. These outline specifications listed in this document are required for use by the Contractor for project design. When purchasing and installing equipment, those specification sections shall be followed as necessary to insure the Government of the quality of the component. Cut sheets for equipment shall be utilized to cover the full scope of the work. Government standards will be referenced in the submittals and shop drawings as required to show compliance with a minimum standard.

2.2.5. Design Submittals: Items of work shall be submitted as required in the schedule provided in SECTION 01 33 16 DESIGN AFTER AWARD.

2.4 PERMITTING

The Contractor is responsible for identifying and obtaining all necessary permits and licenses prior to the start of construction. In addition to Environmental Permits, based upon information provided by the COR or Government personnel, the Contractor shall determine when Base specific permits are required, such as digging, communications, and security.

2.5 GOVERNMENT APPROVED SUBMITTALS

The approval of submittals by the Contracting Officer's Representative shall not be construed as a complete check for the functionality of the project, but will indicate only that the equipment is in conformance with the intent of the contract requirements. Approval will not relieve the Contractor of the responsibility for any error which may exist in his development, as the Contractor is responsible for needed additional design and construction of all work.

3. UTILITIES

3.1 General: All water and electrical utilities shall be installed underground. New underground utility lines, including appurtenant structures such as valve boxes, vaults, etc., shall not be located under pavement, road shoulders, or drainage ditches to the maximum extent practicable. It is the Contractor's responsibility to design and construct new utility services to

APPENDIX F - Page 7 of 22 Amendment No. 0007 provide electricity and communications. The contractor shall take great care in areas where sanitary sewage or other utility systems are located.

Construction and installation shall conform to CDPH requirements, as applicable. The Contractor is responsible for making all taps into the existing water, communications, and electrical service. The Contractor shall excavate to expose the line, furnish all materials required to make the cuts, construct vault, meter, and appurtenances, and backfill the line. The Contractor shall notify the Contracting Officer’s Representative (COR) before a utility tie-in is required. The notification shall be a minimum of 30 days prior to the anticipated date that tapping the utility is required. All utility outages shall be conducted after normal working hours or during weekends, unless approved otherwise by C.O.R.

3.2 Existing Utilities: Government supplied drawings and construction documents related to the location of utilities may not represent actual installed conditions. The Contractor shall verify actual locations of all placed utilities and shall coordinate with the Government regarding any future planned utility installations that affect the work. Coordination of all site work on the project, including utility work, is the responsibility of the Contractor. It is the Contractor's responsibility to confirm the specific locations of the existing utilities and to coordinate and construct the connections of the new system to the existing water system. Subsurface investigative work is required per Specification Section 01 10 10 paragraph 4.2.2.

3.3 Device Location: Valve boxes and vaults, electric switches, control boxes, etc., shall be located in locations not in the immediate vicinity of heavy traffic, either foot or vehicular.

3.4 Marking of Utility Lines: Underground utility lines shall be marked with plastic marking tape. The tape shall be manufactured with integral wires, foil backing or other means to enable detection by a metal detector. The tape shall be of a type specifically manufactured for marking and locating underground utilities. The metallic core of the tape shall be encased in a protective jacket or provided with other means to protect it from corrosion.

Warning tapes shall be provided and installed directly above all buried pipes or wires, at a depth of 18-inches below finished grade. Tape color shall be as specified below and shall bear a continuous printed inscription that identifies the specific utility.

Tape Color:

Red: Electric Power Lines, Cables, Conduit and Lighting Cable Orange: Telephone, telegraph, television, police, and fire communications Blue: Potable Water Lines Purple: Reclaimed Water Lines Olive Green: Raw Water Lines Green: Sewer systems Yellow: Gas or other dangerous materials

3.6 Well Pump: The submersible well pump shall be designed and constructed in accordance with AWWA E101, except as hereinafter modified. The pump shall be designed for flanged discharge above the pump base. The pump shall be sized to pump the available well yield. The pump shall be controlled to operate in a pressure range as determined by the contractor’s system analysis with pressure controls located at the ground surface adjacent to the well pump or located in the chlorination building. After the yield tests have been performed on the drilled well, the Contractor shall add the static lift, APPENDIX F - Page 8 of 22 Amendment No. 0007 including draw down from the water in the well, to the highest pressure to overcome at the discharge point on the Langford Lake Basin raw water line from existing Wells L-1, L-2, and L-3, referencing a common point between the static lift and tank overflow elevation, plus all losses in the pump, pump column, and discharge piping to obtain the total pump head. The specified head and capacity shall maximize efficiency at the design point. Pump speed shall not be greater than 1800 rpm.

3.7 Draw Down Gauge and Piping: Draw down gauge and a water-level indicating device shall be provided for the pump installation. The indicating device shall be of the air-line type. The copper tubing shall extend a minimum of twenty (20) feet below the lowest pumping water level. The testing device shall enable measurement of the water level in the well under any condition.

The draw down gauge shall be wall mounted in the location as chosen by the Contracting Officer’s Representative.

3.8 Booster pumps: Two booster pumps shall be designed and constructed in accordance with AWWA. The pumps shall be sized to pump the yield rate of the well pump. The pump shall be controlled to operate in a pressure range as determined by the contractor’s system analysis with pressure controls located at the ground surface adjacent to the well pump or located in the chlorination building. The Contractor shall add the static head to the highest pressure to overcome at the discharge point on the reclaimed water line irrigation system, referencing a common point between the static lift and tank overflow elevation, plus all losses in the pump, pump column, and discharge piping to obtain the total pump head. The specified pump shall maximize efficiency at design point. Pump speed shall not be greater than 1800 rpm.

3.9 Pressure: Pressure gauge shall be installed and calibrated in pounds per square inch in not more than 2-pound increments from zero to a minimum of fifteen (15) psi above the pump shutoff head with an accuracy of reading within one pound of the correct reading. Pressure transmitter shall be provided to provide trending data to SCADA system.

3.10. Air-Release Valve: An air-release valve with the necessary pipe connections shall be provided to permit the automatic escape of air from the discharge column when the pump is started. A suitable guard and strainer shall be provided on each air valve to prevent foreign material from being drawn into the pump. The location of the valve and piping shall be as shown on the drawings.

3.11. Control Equipment: Motor starters shall be soft start starters. Each motor shall be furnished with an automatically operated starter which shall conform to the adopted standards and recommended practices of the National Electrical Manufacturers Association Industrial Control Standard No. ICS 1.

Starter shall be housed in a NEMA Size 2, drip proof enclosure, and shall be provided with manual-reset thermal overload protection. A separate thermal overload shall be provided for each ungrounded-conductor. Automatic control shall be provided with the pumps being started and stopped by means of automatic controls which shall operate the motor through a magnetic starter and pilot circuit. For VFDs, these shall match pump output to system demand (paced on system pressure).

3.12 Valves: In addition to valves required as shown on drawings, valves shall be installed at intervals not greater than 5,000 feet in long supply lines, 1,200 feed in main distribution loops or feeders, and 500 feet within

APPENDIX F - Page 9 of 22 Amendment No. 0007 the distribution system. Valves shall be installed inside valve boxes or vaults only. Valve connections shall be as required for the piping in which they are installed. Gate valves shall be resilient-seat type.

3.13 Water Meters: Well water meters shall be billing grade, having a local odometer style totalizer. The water meters will also require remote pulsar with Form "C" contacts to provide volume pulses to the building automation system (minimum pulse duration of 0.5 SEC). The number of US gallons per minute represented by the pulse shall be stamped on the local totalizer tag or on the pulsar body. The meter shall provide local readings and a remote pulsar signal which shall be capable of interfacing to the Building Automation System. Any constant multiplier required to convert the local odometer readings to US gallons per minute shall be clearly stamped to the right of the odometer reading.

3.14 Water Distribution Lines. Water lines shall be installed parallel to streets and roads, but not under roadway pavements, except for crossings.

Piping for water service and distribution lines shall be C901/C906 high density polyethylene (HDPE) or C900/C905 polyvinyl chloride (PVC) except where use dictates otherwise. All water piping shall be size of the waterlines indicated on the drawings. All service lines shall be connected using full circle clamp type saddles in accordance with CH2M HILL design standards..

3.15 Waterline and Sewer line Separation. Water pipe shall not be laid closer horizontally than ten (10) feet from a sewer except where the bottom of the water pipe will be at least eighteen (18) inches above the top of the sewer pipe, in which case the water pipe shall not be laid closer horizontally than six (6) feet from the sewer. Where water lines cross under gravity-flow sewer lines, the sewer pipe, for a distance of at least ten (10) feet each side of the crossing, shall be fully encased in concrete or shall be made of pressure pipe with no joint located within three (3) feet horizontally of the crossing. Water lines shall in all cases cross above sewage force mains or inverted siphons and shall be not less than 24 inches above the sewer main. Joints in the sewer main, closer horizontally than three (3) feet to the crossing, shall be encased in concrete. Water lines shall not be laid in the same trench with sewer lines, gas lines, fuel lines, or electric wiring. Copper tubing shall not be installed in the same trench with ferrous piping materials. Where nonferrous metallic pipe, e.g. copper tubing, crosses any ferrous piping material, a minimum vertical separation of eighteen (18) inches shall be maintained between pipes.

3.16 Restraint. Thrust blocking shall be provided in accordance with UFC 3- 230-10A; ETL 1110-3-446 Revision of Thrust Block Criteria in UFC 3-230-10A, Appendix C, and the UFGS water lines specification.

3.17 Disinfection. All water lines and wells shall be effectively sterilized with chlorine solution and tested to meet the bacteriological safety requirements in accordance with AWWA Standards and as specifically required by state and local drinking water regulations before placing them in service.

4. CIVIL/SITE:

4.1 Design Criteria. This portion of the project shall be in accordance with the Design Criteria identified in Specification Section 01 10 10 "DESIGN

REQUIREMENTS, GENERAL”.

APPENDIX F - Page 10 of 22

4.2 Project Location: Work on this project is to be performed at locations indicated on the drawings.

4.3 Survey: The Contractor shall provide a detailed Topographical Survey and Subsurface Utility Investigation in accordance with the survey and utility investigation criteria identified in Specification Section 01 10 10, “DESIGN REQUIREMENTS, GENERAL”. The Contractor shall verify actual locations of all placed utilities and shall coordinate with the Government regarding any future utility installations that affect the work. The Contractor shall survey and stake-out the project boundaries as indicated on the drawings and described herein before starting work.

4.4 Demolition and Removal: All demolition and debris removal shall be in accordance with the demolition and removal criteria identified in Specification Section 01 10 10, “DESIGN REQUIREMENTS, GENERAL”.

4.5 Security Fence. Perimeter security fencing shall enclose the new Well House at Well I-9 on all sides. Security fencing and gates shall be in accordance with MIL-HDB-1013/10. Fencing shall by Type FE8 (chain-link fence with 3 strand barbed-wire on double outrigger). Fence fabric shall be 6 feet high and 9 gauge wire. For added security, the fence fabric shall be supported at the top by a reinforcing wire in lieu of a top rail. Clear zones shall be provided on both sides of the perimeter security fencing in accordance with ATTP 3-39.32 Physical Security. One gate with minimum 12 feet width shall be provided.

4.6 Force Protection Design: A 33 feet (10 meter) minimum physical security setback is required between the facility’s perimeter security fence and the new well house including the generator.

4.7 Secondary Containment: The concrete secondary containment for the new generator shall be designed in accordance with UFC 3-250-01FA

4.8 Grading and Storm Drainage: The specific project sites are relatively flat. Any required site grading shall provide positive drainage away from project site. The storm water runoff after final construction shall be the same as before the start of construction and shall continue to flow at the same rate and direction prior to utility and well house construction. Areas within 5 feet outside of tanks, concrete slabs, other permanent structures shall be constructed true-to-grade, shaped to drain, and shall be maintained free of trash and debris until final inspection has been completed and the work has been accepted.

Storm drainage design shall be in accordance with storm drainage criteria identified in Specification Section 01 10 10, “DESIGN REQUIREMENTS, GENERAL”.

4.9 Erosion and Sediment Control: The Contractor shall provide for erosion protection and sediment control in accordance with criteria identified in Specification Section 01 10 10, “DESIGN REQUIREMENTS, GENERAL”. In addition, the Contractor shall provide for onsite control suitable with best management practices identified as acceptable by regulatory agencies in California for the anticipated work in this project. Each project worksite shall be visited and the areas of impact shall be estimated by the Contractor at that time based on this Scope of Work.

4.9.1. Silt Fence shall be used as appropriate.

APPENDIX F - Page 11 of 22

4.9.2. Erosion control measures shall be in place prior to performing land disturbing activities.

4.9.3. Erosion and sedimentation control measures shall be implemented to retain sediment within the boundaries of the project sites and prevent erosion of soils during all phases of construction.

4.9.4. All disturbed pervious areas shall be returned to native, pre-construction conditions immediately after completion of work in that area.

5. GEOTECHNICAL CONSIDERATIONS

Test pits excavated for other projects at Fort Irwin have encountered layers of cemented or weathered rock. Therefore, difficult excavation should be anticipated for installation of buried water lines.

It shall be the Contractor's responsibility to perform a subsurface investigation (e.g. borings and/or test pits at representative locations) along the proposed buried pipeline alignment to assess excavation difficulty and to collect soil samples for cathodic protection testing. The Contractor shall complete the design for the pipeline using Contractor-developed data.

The Contractor shall be responsible for obtaining all required drilling and excavation permits for the investigations.

6. Architectural Features:

For Well I-9, the new facility will house well and pump equipment, an exterior generator with secondary containment for fuel spill, and a security fence. The building footprint is approximately 20ft x 30ft and shall be constructed similar to existing Langford Lake well houses, except where stated otherwise herein. Refer to Appendix G drawings for information only as-built drawings of existing Langford Lake well house. There is a separate room required for the chlorination system, this room is corrosive requiring a non corrosive door and door frame.

For Well I-2A the new facility will house booster pump equipment and a chlorine room. The building footprint is approximately 20ft x 30ft and shall be constructed similar to existing Langford Lake well houses, except where stated otherwise herein. Refer to Appendix G drawings and for information only as-built drawings of existing Langford Lake well house.

6.1 Exterior Architectural: Well I-9, Pump I-2A

• Building Foundation Walls: Concrete.

• Building Walls: Concrete masonry units CMU with stucco finish. Factory finish metal wall panels with a stucco or precast concrete appearance is an acceptable alternative design. Wherever possible, finish grade will slope up against walls, using native soil or rock. Use of concrete form liners, varying stucco colors and textures, will help reduce the visual height of the buildings and emphasize the horizontal.

APPENDIX F - Page 12 of 22 Amendment No. 0007

• Roofs: Single slope, with factory finished standing seam metal roof panels with concealed fasteners. Provide R-15 insulated for roof. Provide gutter and downspout drainage to splash blocks.

• Roof Hatches: Manufactured steel fabrication with furnished operable hardware, weatherproof with roof flange/curb, color to match metal roof panels. A 5ft by 5 ft hatch opening is required over the well. Coordinate structural opening.

• Doors: Painted or factory finished galvanized steel, generally; factory finished insulated metal doors and frames. Provide double door for direct access to the well. Door hardware includes 3 pair hinges, astragal, mortise lock set, flush bolts and two door holders/stop.

• Doors to chlorine rooms: Door and frames with corrosion proof PVC construction with stainless steel hinges.

• Louvers: Factory finished aluminum.

• Exposed Structural Metal and Miscellaneous Metal: Painted.

• Colors: In accordance with the Fort Irwin "Installation Design Standards and "Supplemental instructions”. Refer to Appendix K.

6.2 Interior Materials: Well I-9

• Floors: Concrete, with skid resist epoxy coating.

• Perimeter Walls: Painted CMU below factory finished metal liner panels.

• Ceilings: Exposed metal building insulated roof system with finished liner panel.

• Structural Framing: Painted steel.

• Doors and Frames: Painted steel.

6.3 Interior Materials: Well House and Booster Pump House for Well I-2A

• Prep for Existing metal surfaces: Remove as much loose and peeling paint by scraping, wirebrush or power-washing the surface. Feather-sand rough edges smooth until they blend with bare surface. De-gloss old metal surfaces with light sanding and clean with mineral spirits. If old film is in poor condition, it should be removed with paint remover. If metal has rusted, that too must be removed. Prime all bare spots with oil-based metal primer.

• Prep for Existing masonry surfaces: Removal all dirt, dust, etc. by sweeping or vacuum cleaning. Remove grease, oil, floor compound and wax by chemical cleaning. Scrape carefully to remove deteriorated coatings. If remaining coating is glossy or very hard, sand it lightly for good adhesion of subsequent coatings. The surface must be thoroughly dry before coating.

• Floors: Paint with clear floor hardener or sealer, as appropriate.

• Perimeter Walls: Paint steel or CMU, as applicable.

• Ceilings: Paint metal roof.

• Structural Framing: Paint steel.

• Doors and Frames: Paint steel.

• Colors: In accordance with the Fort Irwin "Installation Design Standards and "Supplemental instructions”. Refer to Appendix K.

APPENDIX F - Page 13 of 22 Amendment No. 0007

7. STRUCTURAL

7.1 General. A new well house with chlorination room shall be constructed at the I-9 site. The building shall be constructed of 8” concrete masonry and shall be founded on a minimum 6” thick concrete monolithic slab. A steel framed structure with factory finish metal wall panels with a stucco or precast concrete appearance is an acceptable alternative design.

This is the start of the file's text. The full file is on GovTribe.