04-SPEC_Vol_4.pdf
PDF 15 MB Posted
- Attached to
- Design Build, FY 12 Water Treatment and Distribution System, Fort Irwin, San Bernardino County, CA
- Solicitation number
- W912PL-12-R-0018
About this file
draft Specification Vol. 4
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES ARMY
NATIONAL TRAINING CENTER
FORT IRWIN, CALIFORNIA
BIDDING REQUIREMENTS
AND
CONTRACT DOCUMENTS
for the construction of the
FORT IRWIN WATER TREATMENT PLANT (WTP)
Contract No. W4
San Francisco, CA
Copy No.
FORT IRWIN WTP
Pages
*TO BE PROVIDED BY DBO CONTRACTOR
TABLE OF CONTENTS
00 01 10 - 1
VOLUME 1
*PART 1—PROCUREMENT REQUIREMENTS
Request for Quote (RFQ) Instructions to Bidders Bid Form
*PART 2—CONTRACTING REQUIREMENTS
CONTRACTING FORMS
Purchase Order Agreement
PROJECT FORMS
Performance Bond Payment Bond
CONDITIONS OF THE CONTRACT
General Conditions Supplementary Conditions
PART 3—SPECIFICATIONS
DIVISION 1—GENERAL REQUIREMENTS
01 11 00 Summary of Work ....................................................................... 1- 2 01 14 23 Mitigation Measures ................................................................... 1- 2 01 26 00 Contract Modification Procedures .............................................. 1- 5 01 29 00 Payment Procedures .................................................................... 1- 7 Supplement:
Exhibit C, Subcontract Price Schedule ....................................... 1- 1 01 31 13 Project Coordination ................................................................... 1- 4 01 31 19 Project Meetings ......................................................................... 1- 4 01 32 00 Construction Progress Documentation ....................................... 1- 11 01 33 00 Submittal Procedures .................................................................. 1- 10 Supplement:
Transmittal of Supplier’s or Subcontractor’s Submittal ............. 1- 1 01 35 25 Safety Requirements and Protection of Property ........................ 1- 10 01 42 13 Abbreviations and Definitions .................................................... 1- 5
00 01 10 - 2
01 43 33 Manufacturers’ Field Services .................................................... 1- 5 Supplements:
Manufacturer’s Certificate of Compliance ................................. 1- 1 Manufacturer’s Certificate of Proper Installation ....................... 1- 1 Attachment A Outline of Training Session ................................. 1- 2 01 45 10 Special Inspections and Seismic Qualification of Equipment .... 1- 6 Supplement:
Subcontractor’s Statement of Responsibility .............................. 1- 3 01 50 00 Temporary Facilities and Controls ............................................. 1- 9 01 57 13 Temporary Erosion and Sediment Control ................................. 1- 7 01 61 00 Common Product Requirements ................................................. 1- 9 01 61 10 Seismic Anchorage and Bracing ................................................. 1- 5 01 64 00 DBO Contractor-Furnished Products/Equipment ....................... 1- 10 01 77 00 Closeout Procedures ................................................................... 1- 6 01 78 23 Operation and Maintenance Data ............................................... 1- 9 Supplements:
Fort Irwin WTP Electronic Document Requirements ................ 1- 2 O&M Data Sequences and Responsibilities ............................... 1- 1 Fort Irwin WTP Maintenance Summary Form ........................... 1- 4 01 91 14 Equipment Testing and Facility Startup ..................................... 1- 7 Supplements:
Unit Process Startup Form .......................................................... 1- 1 Facility Performance Demonstration/Certification Form ........... 1- 1
VOLUME 2
DIVISION 2—EXISTING CONDITIONS (NOT USED)
DIVISION 3—CONCRETE
03 01 31 Repair of Vertical and Overhead Concrete Surfaces .................. 1- 12 03 01 32 Repair of Horizontal Concrete Surfaces ..................................... 1- 8 03 01 33 Concrete Crack Repair Using Injection ...................................... 1- 10 03 10 00 Concrete Forming and Accessories ............................................ 1- 5 03 15 00 Concrete Joints and Accessories ................................................. 1- 7 03 21 00 Reinforcing Steel ........................................................................ 1- 6 03 30 00 Cast-In-Place Concrete ............................................................... 1- 30 03 39 00 Concrete Curing .......................................................................... 1- 5
00 01 10 - 3
03 62 00 Nonshrink Grouting .................................................................... 1- 6 Supplement:
24-hour Evaluation of Nonshrink Grout Test Form and Grout Testing Procedures ....................................................... 1- 3
DIVISION 4—MASONRY (NOT USED)
DIVISION 5—METALS
05 05 23 Welding ....................................................................................... 1- 5 Supplement:
Welding and Nondestructive Testing Table ............................... 1- 1 05 12 00 Structural Steel Framing ............................................................. 1- 11 05 50 00 Metal Fabrications ...................................................................... 1- 19 05 52 00 Metal Railings ............................................................................. 1- 13 05 53 00 Metal Gratings ............................................................................ 1- 7
DIVISION 6—WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry ......................................................................... 1- 7 06 20 00 Finish Carpentry ......................................................................... 1- 4 06 44 00 Ornamental Woodwork ............................................................... 1- 5 06 82 00 Glass-Fiber-Reinforced Plastic ................................................... 1- 10
DIVISION 7—THERMAL AND MOISTURE PROTECTION
07 14 00 Fluid-Applied Waterproofing ..................................................... 1- 5 07 26 00 Vapor Retarders .......................................................................... 1- 3 07 62 00 Sheet Metal Flashing and Trim ................................................... 1- 5 07 70 01 Roof Specialties and Accessories ............................................... 1- 3 07 84 00 Firestopping ................................................................................ 1- 5 07 92 00 Joint Sealants .............................................................................. 1- 7
DIVISION 8—OPENINGS
08 06 01 Door and Hardware Schedule ..................................................... 1- 1 Supplements:
Door and Hardware Schedule Table ........................................... 1- 4 Door and Frame Types ................................................................ 1- 3
00 01 10 - 4
08 06 50 Window and Relight Schedule.................................................... 1- 1 Supplements:
Window and Relight Schedule Table ......................................... 1- 3 Window and Relight Types ........................................................ 1- 2 08 11 00 Metal Doors and Frames ............................................................. 1- 5 08 14 00 Wood Doors ................................................................................ 1- 5 08 30 00 Specialty Doors ........................................................................... 1- 6 08 45 00 Translucent Wall and Roof Assemblies ...................................... 1- 7 08 51 13 Aluminum Windows ................................................................... 1- 6 08 71 00 Door Hardware............................................................................ 1- 11 08 80 00 Glazing ........................................................................................ 1- 6 08 90 00 Louvers ....................................................................................... 1- 5 Supplement:
Louver Schedule ......................................................................... 1- 4
DIVISION 9—FINISHES
09 06 00 Schedules for Finishes ................................................................ 1- 1 Supplements:
Interior Finish Schedule .............................................................. 1- 4 Exterior Finish Schedule ............................................................. 1- 1 Color List .................................................................................... 1- 3 09 29 00 Gypsum Board ............................................................................ 1- 13 09 30 00 Tiling ........................................................................................... 1- 5 09 51 13 Acoustical Panel Ceilings ........................................................... 1- 5 09 54 00 Fiberglass Reinforced Plastic (FRP) Wall Surfaces ................... 1- 2 09 65 00 Resilient Flooring ....................................................................... 1- 8 09 68 00 Carpeting ..................................................................................... 1- 6 09 90 00 Painting and Coating ................................................................... 1- 26 Supplements:
Paint System Data Sheet (PSDS) ................................................ 1- 1 Paint Product Data Sheet (PDS) ................................................. 1- 1 09 96 35 Chemical-Resistant Coatings for Concrete ................................. 1- 10 Supplement:
Chemical-Resistant Coating Data Sheet (CRCDS) .................... 1- 1 09 97 13 Steel Tank Coatings .................................................................... 1- 12
Paint System Data Sheet (PSDS) ................................................ 1- 2
00 01 10 - 5
DIVISION 10—SPECIALTIES
10 14 00 Signage ........................................................................................ 1- 8 Supplement:
Sign Schedule ............................................................................. 1- 4 10 21 00 Compartments and Cubicles ....................................................... 1- 2 10 28 00 Toilet and Bath Accessories ....................................................... 1- 3 10 44 00 Portable Fire Safety Equipment .................................................. 1- 3 10 51 00 Lockers ........................................................................................ 1- 2 10 80 00 Miscellaneous Specialties ........................................................... 1- 6
DIVISION 11—EQUIPMENT
11 31 00 Appliances .................................................................................. 1- 2
DIVISION 12—FURNISHINGS
12 20 00 Window Treatments .................................................................... 1- 3 12 35 53 Process Analysis Room Casework and Furnishings ................... 1- 18
DIVISION 13—SPECIAL CONSTRUCTION
13 34 19 Metal Building Systems .............................................................. 1- 11
DIVISION 14—CONVEYING EQUIPMENT (NOT USED)
DIVISION 15 (NOT USED)
DIVISION 16 (NOT USED)
DIVISION 17 (NOT USED)
DIVISION 18 (NOT USED)
DIVISION 19 (NOT USED)
DIVISION 20 (NOT USED)
DIVISION 21—FIRE SUPPRESSION
21 13 00 Fire-Suppression Sprinkler Systems .............................................. 1- 5
00 01 10 - 6
DIVISION 22—PLUMBING
22 07 00 Building Mechanical Thermal Insulation ................................... 1- 10 22 10 01 Plumbing Piping and Accessories ............................................... 1- 20 22 30 00 Plumbing Equipment .................................................................. 1- 7 Supplements:
Gas Water Heater (Commercial) Data Sheet .............................. 1- 1 Domestic Water Expansion Tank Data Sheet ............................. 1- 1 Domestic Hot Water Circulating Pump Data Sheet .................... 1- 1 Acid Neutralization Tank Data Sheet ......................................... 1- 1 Backflow Preventers Data Sheet ................................................. 1- 1 22 40 00 Plumbing Fixtures ....................................................................... 1- 13
VOLUME 3
DIVISION 23—HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 05 48 Vibration Isolation and Seismic Control .................................... 1- 11 23 05 93 Testing, Adjusting, and Balancing for HVAC ............................ 1- 6 23 09 00 Instrumentation and Control Devices for HVAC ....................... 1- 12 23 09 13 HVAC Controls, Field Components, and Instruments ............... 1- 4 23 23 00 Refrigerant Piping ....................................................................... 1- 8 23 31 13 Metal Ducts and Accessories ...................................................... 1- 29 Supplement:
Ductwork Schedule ..................................................................... 1- 1 23 31 16.16 Thermoset Fiberglass-Reinforced Plastic Ducts and Accessories ............................................................................. 1- 9 23 34 00 HVAC Fans ................................................................................. 1- 14 23 37 00 Air Outlets and Inlets .................................................................. 1- 4 23 77 00 Air Handling Units ...................................................................... 1- 15 23 81 00 Unitary Air-Conditioning Equipment ......................................... 1- 19
DIVISION 24 (NOT USED)
DIVISION 25—INTEGRATED AUTOMATION (NOT USED)
DIVISION 26—ELECTRICAL
26 05 02 Basic Electrical Requirements .................................................... 1- 6 26 05 04 Basic Electrical Materials and Methods ..................................... 1- 16 26 05 05 Conductors .................................................................................. 1- 22 26 05 26 Grounding and Bonding for Electrical Systems ......................... 1- 8
00 01 10 - 7
26 05 33 Raceway and Boxes .................................................................... 1- 29 26 05 70 Electrical Systems Analysis ........................................................ 1- 8 Supplement:
Figure 1: Example Arc Flash Label ............................................ 1- 1 26 08 00 Commissioning of Electrical Systems ........................................ 1- 22 26 14 13 Switchboards ............................................................................... 1- 10 26 20 00 Low-Voltage AC Induction Motors ............................................ 1- 12 26 22 00 Low-Voltage Transformers ......................................................... 1- 3 26 24 16 Panelboards ................................................................................. 1- 8 26 24 19 Low-Voltage Motor Control ....................................................... 1- 13 26 27 26 Wiring Devices ........................................................................... 1- 7 26 29 23 Low-Voltage Adjustable Frequency Drive System .................... 1- 14 26 35 26 Power Factor Correction/Active Harmonic Filtering Equipment ............................................................................... 1- 6 26 42 03 Cathodic Protection - Submerged Metal ..................................... 1- 8 Supplement:
Water Quality for Cathodic Protection ....................................... 1- 2 26 50 00 Interior Lighting .......................................................................... 1- 11 26 56 00 Exterior Lighting ......................................................................... 1- 8 26 57 00 Static Uninterruptible Power Supply .......................................... 1- 9
DIVISION 27—COMMUNICATIONS (NOT USED)
DIVISION 28—ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm ........................................................... 1- 25
DIVISION 29 (NOT USED)
DIVISION 30 (NOT USED)
DIVISION 31—EARTHWORK
31 10 00 Site Clearing ............................................................................... 1- 2 31 23 13 Subgrade Preparation .................................................................. 1- 3 31 23 16 Excavation .................................................................................. 1- 4 31 23 23 Fill and Backfill .......................................................................... 1- 8 31 23 23.15 Trench Backfill ........................................................................... 1- 10 31 32 19.16 Geotextile .................................................................................... 1- 8 31 41 00 Shoring ........................................................................................ 1- 2
00 01 10 - 8
DIVISION 32—EXTERIOR IMPROVEMENTS
32 11 23 Aggregate Base Courses ............................................................. 1- 5 32 12 16 Asphalt Paving ............................................................................ 1- 9 32 13 13 Concrete Paving .......................................................................... 1- 19 32 17 23 Pavement Markings .................................................................... 1- 4 32 31 13 Chain Link Fences and Gates ..................................................... 1- 15
DIVISION 33—UTILITIES
33 05 01 Conveyance Piping—General ..................................................... 1- 6 33 05 01.01 Welded Steel Pipe and Fittings ................................................... 1- 20 33 05 01.09 Polyvinyl Chloride (PVC) Pressure Pipe and Fittings ................ 1- 5 33 05 01.10 High-Density Polyethylene (HDPE) Pressure Pipe and Fittings .................................................................................... 1- 8 33 05 01.12 Gravity Sewer Pipe and Fittings ................................................. 1- 17 33 05 13 Manholes ..................................................................................... 1- 11 33 12 19 Water Utility Distribution Fire Hydrants .................................... 1- 4 33 13 00 Disinfecting of Water Utility Distribution .................................. 1- 6 33 16 13.13 Welded Steel Tank ...................................................................... 1- 14 33 46 23.19 Composite Drainage Net ............................................................. 1- 5 33 47 13.01 Pond and Reservoir Liners—HDPE ........................................... 1- 18 Supplement:
Geomembrane Installer’s Certification of Subsurface Acceptability ........................................................................... 1- 1 33 47 13.07 Pond and Reservoir Liners—Geosynthetic Clay ........................ 1- 8
DIVISION 34—TRANSPORTATION (NOT USED)
DIVISION 35—WATERWAY AND MARINE CONSTRUCTION
35 20 16.27 Fiberglass Reinforced Polyester (FRP) Downward Opening Weir Gates .............................................................................. 1- 7 Supplement:
Slide Gate Schedule .................................................................... 1- 1
DIVISION 36 (NOT USED)
DIVISION 37 (NOT USED)
DIVISION 38 (NOT USED)
00 01 10 - 9
DIVISION 39 (NOT USED)
VOLUME 4
DIVISION 40—PROCESS INTEGRATION
40 05 16 Piping Support Systems .............................................................. 1- 15 40 05 33 Pipe Heat Tracing ....................................................................... 1- 4 40 27 00 Process Piping-General ............................................................... 1- 25 Supplement:
Piping Schedule .......................................................................... 1- 4 40 27 00.01 DS – Cement-Mortar-Lined Ductile Iron Pipe and Fittings ....... 1- 2 40 27 00.02 DS – Carbon Steel Pipe and Fittings-Special Service ................ 1- 2 40 27 00.03 DS – Carbon Steel Pipe and Fittings-General Service ............... 1- 3 40 27 00.08 DS – Stainless Steel Pipe and Fittings-General Service ............. 1- 2 40 27 00.09 DS – Stainless Steel Pipe and Fittings-Special Service .............. 1- 3 40 27 00.10 DS – Polyvinyl Chloride (PVC) Pipe and Fittings ..................... 1- 2 40 27 00.11 DS – Chlorinated Polyvinyl Chloride (CPVC) Pipe and Fittings .................................................................................... 1- 2 40 27 00.13 DS – Copper and Copper Alloy Pipe, Tubing, and Fittings ....... 1- 1 40 27 00.15 DS – Double Wall Containment Piping ...................................... 1- 2 40 27 00.19 Polyvinyl Chloride Drain Waste and Vent (PVC-DWV) Pipe and Fittings ..................................................................... 1- 1 40 27 00.22 DS – High-Density Polyethylene (HDPE) Pipe and Fittings-Gas Service ................................................................ 1- 2 40 27 01 Process Piping Specialties .......................................................... 1- 13 40 27 02 Process Valves and Operators ..................................................... 1- 26 Supplements:
Open-Close Valve Schedule ....................................................... 1- 1 Modulating Valve Schedule ........................................................ 1- 1 Self-Contained Valve Schedule .................................................. 1- 1 Manual and Check Valve Schedule ............................................ 1- 2 40 42 13 Process Piping and Equipment Insulation .................................. 1- 7 40 80 01 Process Piping Leakage Testing ................................................. 1- 4 40 90 00 Instrumentation and Control for Process Systems ...................... 1- 31 40 91 00 Instrumentation and Control Components .................................. 1- 9 Supplements:
Instrument Data Sheets PLC Input/Output List. ............................................................... 1- 28 Panel List .................................................................................... 1- 1
00 01 10 - 10
40 95 80 Local Area Network (LAN) Communication System ................ 1- 13
As-Built Fiber Optic Cable Installation Form ............................ 1- 2
DIVISION 41—MATERIAL PROCESSING AND HANDLING
EQUIPMENT
41 62 23 Forklift Trucks ............................................................................ 1- 3
DIVISION 42—PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
(NOT USED)
DIVISION 43—PROCESS GAS AND LIQUID HANDLING, PURIFICATION,
AND STORAGE EQUIPMENT
43 12 01 Compressed Air Systems ............................................................ 1- 10 43 32 59 Cartridge Filters .......................................................................... 1- 5 43 40 01 High-Density Cross-Linked Polyethylene Storage Tank ............ 1- 9 Supplement:
55TNK088-00: Sodium Hypochlorite Storage Tank Data Sheet ............................................................................... 1- 1 43 40 02 Fiberglass Reinforced Plastic Tanks ........................................... 1- 10 Supplements:
55TNK001-00: Magnesium Chloride Storage Tank Data Sheet ...................................................................... 1- 1 55TNK040-01: Calcium Chloride Storage Tank No. 1 Data Sheet ............................................................ 1- 1 55TNK040-02: Calcium Chloride Storage Tank No. 2 Data Sheet ............................................................ 1- 1 55TNK020-01: Hydrochloric Acid Storage Tank No. 1 Data Sheet ............................................................ 1- 1 55TNK020-02: Hydrochloric Acid Storage Tank No. 2 Data Sheet ............................................................ 1- 1 30TNK071-00: EDR CIP Tank Data Sheet ................................ 1- 1 30TNK051-00: EDR Hydrochloric Acid Day Tank Data Sheet 1- 1 30TNK043-00: ECIP Tank Data Sheet....................................... 1- 1 50TNK360-00: ME Hydrochloric Acid Day Tank Data Sheet .. 1- 1 50TNK370-00: Calcium Chloride Day Tank Data Sheet ........... 1- 1 50TNK036-00: RO CIP Tank Data Sheet .................................. 1- 1 50TNK219-00: Brine Treatment Product Storage Data Sheet ... 1- 1 45TNK023-00: Settled Water Storage Tank Data Sheet ............ 1- 1
00 01 10 - 11
DIVISION 44—POLLUTION CONTROL EQUIPMENT
44 11 78 Air Stripper System .................................................................... 1- 6 44 42 56.02 Horizontal Split-Case Centrifugal Pumps ................................... 1- 5 Supplements:
Untreated Water Feed Pumps Data Sheet ................................... 1- 2 Untreated Water Feed Pumps Induction Motor Data Sheet ............................................................................... 1- 1 44 42 56.04 Submersible Pumps ..................................................................... 1- 6 Supplement:
Process Drain Pumps Data Sheet ................................................ 1- 2 44 42 56.10 Horizontal End Suction Centrifugal Pumps ................................ 1- 6 Supplement:
Brine Treatment Product Pumps Data Sheet .............................. 1- 3 Carbon Dioxide Carrier Water Pumps Data Sheet ..................... 1- 3 Lime Softening Feed Pumps Data Sheet .................................... 1- 3 EDR Hydrochloric Acid Transfer Pump No. 1 Data Sheet ........ 1- 3 EDR Hydrochloric Acid Transfer Pump No. 2 Data Sheet ........ 1- 3 EDR Sodium Hydroxide Transfer Pump Data Sheet .................. 1- 2 Hydrochloric Acid Transfer Pumps Data Sheet ......................... 1- 3 Calcium Chloride Transfer Pumps Data Sheet ........................... 1- 3 RO CIP Pump Data Sheet ........................................................... 1- 3 EDR CIP Pump Data Sheet ......................................................... 1- 3 44 42 56.13 Progressing Cavity Pumps .......................................................... 1- 5 Supplements:
Thickener Feed Pumps No. 1 and No. 2 Data Sheet ................... 1- 2 Lagoon Feed Pumps No. 1 and No. 2 Data Sheet ....................... 1- 2 44 42 56.18 Nonmetallic Sump Pump ............................................................ 1- 10 44 44 13.01 Chemical Metering Pumps .......................................................... 1- 8 Supplements:
30PMP045-01 to -05: ECIP Feed Pump Nos. 1 to 5 Data Sheet ............................................................................... 1- 2 30PMP053-01 to -05: EDR Brine Acid Metering Pump
Nos. 1 to 5 Data Sheet ............................................................ 1- 2 30PMP063-01 to -05: EDR Anti-Scalant Metering Pump Nos. 1 to 5 Data Sheet ............................................................ 1- 2 50PMP090-01 to -03: RO Train Anti-Scalant Metering Pumps Data Sheet ................................................................... 1- 2 50PMP350-01 and -02: ME Anti-Scalant Feed Pump 1 and 2 Data Sheet ............................................................................... 1- 2
00 01 10 - 12
46PMP080-01 and -02: Sodium Bisulfite Metering Pump Nos. 1 and 2 Data Sheet .......................................................... 1- 2 44 44 13.04 Peristaltic Pumps ......................................................................... 1- 8 Supplements:
Hydrochloric Acid Metering Pumps Data Sheet ........................ 1- 1 Magnesium Chloride Metering Pumps Data Sheet ..................... 1- 1 Calcium Chloride Metering Pumps Data Sheet .......................... 1- 1 Sodium Hypochlorite Metering Pumps Data Sheet .................... 1- 1 ME Calcium Chloride Feed Pumps Data Sheet .......................... 1- 1 RO Citric Acid Feed Pump Data Sheet....................................... 1- 1 RO Sodium Hydroxide Feed Pump Data Sheet .......................... 1- 1 ME Hydrochloric Acid Feed Pumps Data Sheet ........................ 1- 1 Settled Water Return Pumps Data Sheet .................................... 1- 1
DIVISION 45—INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT (NOT
USED)
DIVISION 46 (NOT USED)
DIVISION 47 (NOT USED)
DIVISION 48—ELECTRICAL POWER GENERATION (NOT USED)
DIVISION 49 (NOT USED)
VOLUME 5
DRAWINGS – AREAS 01 THROUGH 44
VOLUME 6
DRAWINGS – AREAS 45 THROUGH 95
VOLUME 7
DESIGN DETAILS – SERIES 2000 THROUGH 16000
00 01 10 - 13
VOLUME 8
PROCUREMENT PACKAGE B – EDR MEMBRANE SYSTEM
PROCUREMENT PACKAGE C – MECHANICAL EVAPORATOR SYSTEM
PROCUREMENT PACKAGE D – DIESEL-ENGINE-DRIVEN GENERATOR SET
VOLUME 9
PROCUREMENT PACKAGE E – HYDRATED LIME STORAGE AND FEED SYSTEM
PROCUREMENT PACKAGE F – PRE-ENGINEERED GRAVITY FILTERS
PROCUREMENT PACKAGE G – REVERSE OSMOSIS SYSTEM
VOLUME 10
PROCUREMENT PACKAGE H – CONTACT CLARIFIER AND GRAVITY
THICKENER MECHANISMS
PROCUREMENT PACKAGE I – VERTICAL TURBINE PUMPS
PROCUREMENT PACKAGE J – SODIUM HYPOCHLORITE GENERATION SYSTEM
PROCUREMENT PACKAGE M – CARBON DIOXIDE STORAGE AND FEED SYSTEM
END OF SECTION
PIPING SUPPORT SYSTEMS
40 05 16 - 1
SECTION 40 05 16
PART 1 GENERAL
1.01 REFERENCES
A. The following is a list of standards which may be referenced in this section:
1. ASTM International (ASTM): E84, Standard Test Method for Surface Burning Characteristics of Building Materials.
2. International Code Council(ICC):
a. International Building Code (IBC).
b. International Mechanical Code (IMC).
3. Manufacturers’ Standardization Society (MSS):
a. SP 58, Pipe Hangers and Supports—Materials, Design and
Manufacture.
b. SP 69, Pipe Hangers and Supports—Selection and Application.
c. SP 89, Pipe Hangers and Supports—Fabrication and Installation.
1.02 DEFINITIONS
A. Ferrous Metal: Iron, steel, stainless steel, and alloys with iron as principal component.
B. Wetted or Submerged: Submerged, less than 1 foot above liquid surface, below top of channel wall, under cover or slab of channel or tank, or in other damp locations.
1.03 SUBMITTALS
A. Action Submittals:
1. Drawings of each piping support system to scale shown, locating each support, brace, hanger, guide, component and anchor. Identify support, hanger, guide, brace type, and anchor type by catalog number and shop drawing detail number.
2. Revisions to support systems resulting from changes in related piping system layout or addition of flexible joints. For pipe support revisions provide seismic anchorage and bracing calculations and Drawings in accordance with Section 01 61 10, Seismic Anchorage and Bracing.
B. Informational Submittals: Maintenance information on piping support system.
40 05 16 - 2
1.04 QUALIFICATIONS
A. Modifications to the Piping support systems shown on the Drawings shall be designed and Shop Drawings prepared and sealed by a licensed professional civil or structural engineer in the State of California.
1.05 DESIGN REQUIREMENTS
A. General:
1. Pipe Support Systems shall be designed for:
a. Gravity loads imposed by weight of pipes including the weight of fluid in pipes and insulation.
b. Seismic loads in accordance with IBC 2006.
c. Wind loads in accordance with IBC 2006.
2. Provide piping support systems throughout facility, whether shown or not.
3. Piping systems and pipe connections to equipment shall be properly anchored and supported to prevent undue deflection, vibration, dislocation due to seismic events and line pressures, and stresses on piping, equipment, and structures. Supports and parts thereof shall conform to the requirements of ASME B31.3, Process Piping, MSS SP 58, MSS SP 69, MSS SP 89, and IBC 2006, except as supplemented or modified below. Supports for plumbing piping shall be in accordance with the latest edition of the applicable plumbing code or local administration requirements.
4. Any deviation from the design shall be designed by a licensed civil or structural engineer in the State of California.
B. Pipe Hangers: Pipe hangers shall be capable of supporting the pipe in all conditions operation, allowing free expansion and contraction of the piping, and preventing excessive stress on equipment. Hangers shall have a means of vertical adjustment after erection. Hangers shall be designed to prevent becoming disengaged by any movement of the supported pipe. Hangers subject to shock, seismic disturbances, or thrust imposed by the actuation of safety valves, shall include hydraulic shock suppressors. Hanger rods shall be subject to tensile loading only.
C. Hangers Subject to Horizontal Movements: At hanger locations where lateral or axial movement is anticipated, suitable linkage shall be provided to permit such movement. Where horizontal pipe movement is greater than 1/2 inch, or where the hanger rod deflection from the vertical is greater than 4 degrees from the cold to the hot position of the pipe, the hanger rod and structural attachment shall be offset in such a manner that the rod is vertical in the hot position.
40 05 16 - 3
D. Spring-Type Hangers: Spring-type pipe hangers shall be provided for piping subject to vibration or vertical expansion and contraction, such as engine exhausts and similar piping, Spring-type hangers shall be sized to the manufacturer’s printed recommendations and the loading conditions encountered. Variable spring supports shall be provided with means to limit misalignment, buckling, eccentric loading, or to prevent overstressing of the spring, and with means to indicated at all times the compression of the spring.
Supports shall be capable of accommodating at least four times the maximum travel due to thermal expansion.
E. Thermal Expansion: Wherever expansion and contraction of piping is expected, a sufficient number of expansion loops or joints shall be provided, together with the necessary rolling or sliding supports, anchors, guides, pivots, and restraints permitting the piping to expand and contract freely in directions away from the anchored points. Components shall be structurally suitable to withstand loads imposed.
F. Heat Transmission: Supports, hangers, anchors, and guides shall be so designed and insulated, that excessive heat will not be transmitted to the structure or to other equipment.
G. Riser Supports: Where practical, risers shall be supported on each floor with riser clamps and lugs, independent of the connected horizontal piping.
H. Freestanding Piping: Freestanding pipe connections to equipment such as chemical feeders and pumps shall be firmly attached to steel frames fabricated from angles, channels, or I-beams anchored to the structure. Exterior, freestanding overhead piping shall be supported on fabricated pipe stands consisting of pipe columns anchored to concrete footings, with horizontal, welded steel angles and U-bolts or clamps securing the pipes.
I. Materials of Construction:
1. General: Pipe support assemblies, including framing and hardware, shall be hot-dip galvanized carbon steel construction, unless otherwise indicated.
2. Pipe supports in submerged locations, except in steel reservoirs, shall be Type 316L stainless steel.
3. Pipe supports in chemical containment areas and in the Brine Treatment Facility chemical area shall be nonmetallic.
J. Point Loads: Any meters, valves, heavy equipment, and other point loads on PVC, FRP, and other plastic pipes, shall be supported on both sides, according to manufacturer’s recommendations to avoid undue pipe stresses and failures.
To avoid point loads, all supports on PVC, FRP, and other plastic piping shall be equipped with extra wide pipe saddles or galvanized steel shields.
40 05 16 - 4
K. Noise Reduction: To reduce transmission of noise to piping systems, copper tubes in buildings and structures shall be wrapped with a 2-inch wide strip of rubber fabric or similar, suitable material at each pipe support, bracket, clip, or hanger.
L. Pipe Support Spacing:
1. Supports for piping with the longitudinal axis in approximately a horizontal position shall be spaced to prevent excessive sag, bending, and shear stresses in the piping, with special consideration given where components such as flanges and valves impose concentrated loads. Pipe support spacing shall not exceed the maximum spans in the tables below. For temperatures other than ambient temperatures, or those listed, and for other piping materials or wall thicknesses, the pipe support spacings shall be modified in accordance with the pipe manufacturer’s recommendations. Vertical supports shall be provided to prevent the pipe from being overstressed from the combination of all loading effects.
2. As tabulated, unless indicated otherwise on the Drawings.
3. Single Rod Hanger Supported Pipe Span:
Maximum Support Spacing
(ft)
Steel and
Ductile Iron Pipe Stainless Steel Pipe Copper Tube
Nominal Pipe or Tubing Size
Water Service
Vapor Service
Water Service
Vapor Service
Water Service
Vapor Service
1/2" and smaller 6 8 6 8 5 5
3/4" through 1-1/4" 6 9 6 9 5 7
1-1/2" and 2" 8 12 6 10 8 10
2-1/2" and 3" 10 14 8 12 9 13
4" 10 16 8 14 NA NA
6" through 10" 12 16 10 14 NA NA
12" 10 14 10 12 NA NA
40 05 16 - 5
4. Double Rod Hanger Supported Pipe Span:
Maximum Support Spacing (ft)
Steel and Ductile Iron Pipe
Stainless Steel Pipe
Nominal Pipe Size
Water Service
Vapor Service
Water Service
Vapor Service
8" through 12" 16 20 14 18
5. Stanchion Pipe Support Spacing:
Maximum Support Spacing (ft)
Steel and Ductile Iron Pipe
Stainless Steel Pipe
Copper Tube
Nominal Pipe or Tubing Size
Water Service
Vapor Service
Water Service
Vapor Service
Water Service
Vapor Service
1/2" and smaller 6 8 6 6 5 5
3/4" through 1-1/2" 7 9 6 7 7 7
2" and 2-1/2" 8 12 7 10 8 10
3" 10 12 10 10 13
4" 10 14 10 12 NA NA
6" and 8" 12 16 12 14 NA NA
14" through 18" 10 20 14 16
NA NA
6. Hanger Rod Size:
Minimum Hanger Rod Size
(in)
Carbon Steel, Stainless Steel and Ductile Iron
Pipe Copper Tube and Plastic Pipe
Nominal Pipe or Tubing Size
Single Rod
Double Rod
Single Rod
Double Rod
2" and smaller 3/8 NA 3/8 NA
2-1/2" through 3" 1/2 NA 1/2 NA
4" 5/8 NA 1/2 NA
6" 3/4 NA 5/8 NA
40 05 16 - 6
Minimum Hanger Rod Size
(in)
Carbon Steel, Stainless Steel and Ductile Iron
Pipe Copper Tube and Plastic Pipe
Nominal Pipe or Tubing Size
Single Rod
Double Rod
Single Rod
Double Rod
8" and 10" 7/8 3/4 3/4 NA
12" 7/8 3/4 3/4 5/8
14" NA 7/8 7/8 3/4
16" and 18" NA 7/8 NA NA
7. Support Spacing for Schedule 80 PVC Pipe:
Nominal Pipe Diameter (Inches) Maximum Span
(at 100 Degrees F) (Feet)
1/2 4
3/4 4.5
1 5
1-1/4 5.5
1-1/2 5.75
2 6.25
3 7.5
4 8.25
6 10
8 11
10 12.25
12 13.25
8. Cast Iron Soil Pipe: Hanger rod size same as for ductile iron pipe.
Horizontal pipe support or hanger rod spacing shall not exceed 10 feet.
9. Plastic and Fiberglass Pipe: As recommended by manufacturer for the flow temperature in pipe.
M. Bracing: Provide lateral sway bracing on 10-foot maximum centers or where shown.
40 05 16 - 7
N. Pipe Anchors:
1. Provide on straight runs without provisions for piping expansion.
2. Maximum Spacing: The maximum straight run of piping smaller than
3 inches not bound by anchors shall be as follows:
Pipe Type (Service Temperature)
Anchor Spacing (ft)
Steel (81 - 212 degrees F) 100
Steel (33 - 80 degrees F) 120
Stainless steel (81 - 212 degrees F) 80
Stainless steel (33 - 80 degrees F) 100
Copper (120 - 212 degrees F) 100
Copper (81 - 119 degrees F) 1" and smaller 1-1/2" through 2-1/2"
NR
Copper (33 - 80 degrees F) 1" and smaller 1-1/2" through 2-1/2"
NR
PVC (81 degrees F and higher) 60
PVC (33 - 80 degrees F) 100
Fiberglass 100
3. Direction of design load shall be either perpendicular or parallel to support, or parallel to pipe, whichever produces greatest stress in anchor. Design load shall be as follows:
Pipe Size (inches)
Design Load (Pounds)
1/4 150
1/2 150
3/4 150
1 150
1-1/4 200
1-1/2 300
2 500
40 05 16 - 8
Pipe Size (inches)
Design Load (Pounds)
2-1/2 800
O. Metal Framing Support Systems:
1. Beams: Size such that beam stress does not exceed the allowable stress as dictated by the appropriate design standard and maximum deflection does not exceed 1/240 of span.
2. Column Members: Size in accordance with manufacturer’s recommended method.
3. Support Loads: Include total weight of supported piping full of water, flanges, fittings, valves, and insulation, electrical conduit, as well as weight of support assembly.
4. Maximum Spans:
a. Steel and Ductile Iron Pipe, 3-Inch Diameter and Larger: 10-foot centers, unless otherwise shown.
b. Other Pipelines and Special Situations: May require supplementary hangers and supports.
P. Trapeze Pipe Supports:
1. Trapeze Beam:
a. Allowable Stress: Conform to MSS SP 58. Beam stress based on concentrated load located at midpoint of span.
b. Beam Load: Include total weight of supported piping full of water, flanges, fittings, valves, and insulation, electrical conduit, as well as weight of support assembly.
c. Spacing: As indicated for single rod hangers for smallest pipe being supported.
2. Hanger Rods: Maximum Pipe Size and maximum allowable load based on rod size:
Rod Diameter (Inches)
Maximum Pipe Size (Inches)
Maximum Allowable Load
(Pounds)
3/8 3 520
1/2 4 1,130
5/8 6 1,810
3/4 8-10 2,200
3/4 12 2,400
40 05 16 - 9
Q. Building Structural Attachments:
a. No pipes shall be supported from the metal building systems unless explicitly shown on the Drawings or unless approved in writing by DBO Contractor and coordinated/ approved by metal building manufacturer.
b. Minimum design load for attachments shall be the following:
Pipe Size Load (lbs)
1-1/4" and smaller 150
1-1/2" and 2" 150
2-1/2" 170
3" 210
4" 260
6" 530
8" 760
10" 1,120
12" through 18" 1,200
c. Rating shall be based on an allowable stress of 1/5 of the minimum tensile strength of the material at service temperature.
Castings shall include a casting quality factor of 0.80 of the allowable stress specified.
d. Verify that the concrete used is of sufficient strength to hold concrete inserts at the design load rating specified.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Standard Support Components:
1. Anvil.
2. B-Line.
3. Tolco.
B. Channel Type Support and Framing Systems:
1. Unistrut.
2. Kin-Line.
40 05 16 - 10
3. Power Strut.
4. B-Line.
C. Nonmetallic Support Components:
1. Aickenstrut.
2. CLIC.
2.02 NONMETALLIC CHANNEL FRAMING SYSTEM
A. Glass Fiber Reinforced Composites and Plastic Products: Flame spread rating of 25 or less when tested per ASTM E84.
B. Channel Framing: Glass reinforced plastic manufactured by pultrusion or extrusion to provide proper balance to longitudinal and transverse strength.
C. Vinyl Ester: Premium grade, at least equal to Kopper’s 9300 MPQ in corrosion resistance, and nexus polyester surfacing.
D. Minimum Pull-Out Strength: 1,000 pounds when load is applied to head grooves over a 3/8-inch long section of channel.
E. Pipe Clamps and Hangers: Polyamide 12 nylon.
2.03 COMPONENTS
A. Standard Component Types:
1. Type Definition: Per MSS SP 58.
2. General Service (33 degrees F to 119 degrees F) and Hot Service
(120 degrees F to 450 degrees F):
Item Type
(MSS SP 58) Notes
Horizontal Pipe Attachments (Bare)—General and Hot Service
Clips 24
Rings 6, 11 1
Bands 1
Clamps 3
Hanging Rollers 41, 43
Supporting Rolls 44, 46
Saddles 36, 37, 38
40 05 16 - 11
Item Type
(MSS SP 58) Notes
Horizontal Pipe Attachments (Insulated)—General Service
Clips 26
Bands 1 2
Hanging Rollers 41, 43 2, 3
Supporting Rolls 44, 46 2, 3
Protective Shields 39, 40
Saddles 36, 37, 38 2
Horizontal Pipe Attachments (Insulated)—Hot Service
Bands 1 1, 2
Hanging Rollers 41, 43 2, 3
Protective Shields 39
Supporting Rolls 44, 46 2, 3
Saddles 36, 37, 38 2
Vertical Pipe Attachments—General and Hot Service
Riser Clamps 8, 42
Hanger Rod Fixtures—General and Hot Service
Turnbuckles 13, 15
Swing Eyes 16, 17
Clevises 14
Building Structural Attachments—General and Hot Service
Inserts 18
C-Clamps 19, 23
Beam Clamps 20, 21, 25, 27, 28, 29, 30
Welded Attachments 22, 57, 58
Brackets 33, 34
Notes:
1. Use for piping 2-1/2 inches and smaller.
2. Use rigid insulation insert under hanger.
3. Use insulation shield.
40 05 16 - 12
B. Nonmetallic Pipe Clamps and Hangers:
1. Pipe Size: 1/8 inch through 4 inches.
2. Type: Two-piece, automatic locking, corrosion resistant.
3. Features:
a. Clamping segments anchor to base by nylon hinges at base.
b. Fastening via centrally located oval mounting holes.
4. Structural Attachments: Furnish required factory-fabricated accessories for structural attachments.
C. Intermediate Pipe Guides:
1. Piping 6 Inches and Smaller:
a. Type: Pipe clamp with oversized pipe sleeve to provide minimum
1/8-inch clearance.
b. Manufacturers and Products:
1) Kin-Line, Inc.; Figure 417.
2) Anvil Power Strut; Figure P5932.
2. Piping 8 Inches and Larger:
a. Type: Specially formed U-bolts with double nuts to provide
1/4-inch minimum clearance around pipe.
b. U-Bolt Stock Size:
1) 8-Inch Pipe: 5/8 inch.
2) 10-Inch Pipe: 3/4 inch.
3) 12 Through 16-Inch Pipe: 7/8 inch.
4) 18 Through 30-Inch Pipe: 1 inch.
D. Pipe Alignment Guides:
1. Type:
a. Piping 8 Inches and Smaller: Spider or sleeve type.
b. Piping 10 Inches and Larger: Roller type.
2. Manufacturers:
a. Flexonics.
b. Kin-Line.
E. Pipe Anchors:
1. Type: Anchor chair with U-bolt or bar strap.
2. Manufacturers and Products:
a. Anvil; Figure 198.
b. B-Line; Figure B3147A or B3147B.
2.04 FASTENERS
A. Anchor Bolt Material: Wetted or submerged use Type 316 stainless steel.
40 05 16 - 13
B. Nonmetallic Channel Framing Connections: Vinyl ester glass fiber or polyurethane base composite nuts and bolts.
2.05 FABRICATION
A. Shop Assembly: In accordance with MSS SP 89.
B. Shop Finishing:
1. In accordance with MSS SP 85.
2. Coat ungalvanized steel components with rust inhibitive primer as specified in Section 09 90 00, Painting and Coating.
2.06 SOURCE QUALITY CONTROL
A. Shop Tests: In accordance with MSS SP 89.
PART 3 EXECUTION
3.01 INSTALLATION
A. General:
1. Install support systems in accordance with MSS SP 69 and MSS SP 89, unless shown otherwise.
2. Support piping connections to equipment by pipe support and not by the equipment.
3. Support large or heavy valves, fittings, and appurtenances independently of connected piping.
4. Support no pipe from the pipe above it.
5. Support pipe at changes in direction or in elevation, adjacent to flexible joints and couplings, and where shown.
6. Do not install pipe supports and hangers in equipment access areas or bridge crane runs.
7. Brace hanging pipes against horizontal movement by both longitudinal and lateral sway bracing.
8. Install lateral supports for seismic loads at all changes in direction.
9. Install pipe anchors where required to withstand expansion thrust loads and to direct and control thermal expansion.
10. Repair mounting surfaces to original condition after attachments are made.
B. Standard Pipe Supports:
1. Horizontal Suspended Piping:
a. Single Pipes: Adjustable swivel-ring, splint-ring or clevis hangers.
40 05 16 - 14
b. Grouped Pipes: Trapeze hanger systems.
c. For insulated piping, furnish galvanized steel protection shields, welding insulation saddles, or precut sections of rigid insulation (with vapor barrier) at all hanger locations.
2. Horizontal Piping Supported From Walls:
a. Single Pipes: Wall brackets or wall clips attached to wall with anchors. Clips attached to wall-mounted framing also acceptable.
b. Stacked Piping:
1) Wall-mounted framing system and clips acceptable for piping smaller than 3-inch minimal diameter.
2) Piping clamps that resist axial movement of pipe through support not acceptable.
c. Insulated piping shall have the insulation removed in the vicinity of wall brackets and piping clips to allow only direct pipe wall contact with the support system.
3. Horizontal Piping Supported From Floors:
a. Stanchion Type:
1) Pedestal type; adjustable with stanchion, saddle, and anchoring flange.
2) Use yoked saddles for piping whose centerline elevation is 18 inches or greater above the floor and for all exterior installations.
3) Provide neoprene waffle isolation pad under anchoring flanges, adjacent to equipment or where otherwise required to provide vibration isolation.
b. Floor-Mounted Channel Supports:
1) Use for piping smaller than 3-inch nominal diameter running along floors and in trenches at piping elevations lower than can be accommodated using pedestal pipe supports.
2) Attach channel framing to floors with anchor bolts.
3) Attach pipe to channel with clips or pipe clamps.
c. Concrete Cradles:
1) Use for piping larger than 3-inch along floor and in trenches at piping elevations lower than can be accommodated using stanchion type.
4. Vertical Pipe:
a. Support with wall brackets and base elbow or riser clamps on floor penetrations.
b. Insulated piping shall have the insulation removed in the vicinity of wall brackets and riser clamps, to allow only direct wall contact with the support system.
5. Standard Attachments:
a. To Concrete Ceilings: Concrete inserts.
b. To Steel Beams: I-beam clamp or welded attachments.
40 05 16 - 15
c. To Concrete Walls: Concrete inserts or brackets or clip angles with anchor bolts.
C. Intermediate and Pipe Alignment Guides:
1. Provide pipe alignment guides (or pipe supports that provide the same function) at all expansion joints and loops.
2. Guide piping on each side of an expansion joint or loop at 4 and 14 pipe diameters from each joint or loop.
3. Install intermediate guides on metal framing support systems not carrying a pipe anchor or alignment guide.
D. Accessories:
1. Insulation Shield: Install on insulated nonsteel piping. Oversize rollers and supports.
2. Welding Insulation Saddle: Install on insulated steel pipe. Oversize rollers and supports.
3. Vibration Isolation Pad: Install under base flange of pedestal type pipe supports adjacent to equipment, and where required to isolate vibration.
4. Dielectric Barrier:
a. Install between carbon steel members and copper or stainless steel pipe.
b. Install between stainless steel supports and nonstainless steel ferrous metal piping.
5. Electrical Isolation: Install 1/4-inch by 3-inch neoprene rubber wrap between submerged metal pipe and oversized clamps.
3.02 FIELD FINISHING
A. Paint atmospheric exposed surfaces of black and hot-dip galvanized steel components as specified in Section 09 90 00, Painting and Coating.
PIPE HEAT TRACING
40 05 33 - 1
SECTION 40 05 33
PART 1 GENERAL
1.01 REFERENCES
A. The following is a list of standards which may be referenced in this section:
1. Factory Mutual.
2. Institute of Electrical and Electronics engineers, Inc (IEEE): 515, Testing, Design, Installation and Maintenance of Electrical Resistance Heat Tracing for Industrial Applications.
3. National Electrical Manufacturers’ Association (NEMA): 250, Enclosures for Electrical Equipment (1000 Volts Maximum).
4. Underwriters Laboratories, Inc. (UL).
1.02 SUBMITTALS
A. Action Submittals:
1. Manufacturer’s descriptive literature.
2. Plastic Pipe Installations: Output adjustment factors for heating tape for the services indicated.
3. Pipe heat loss calculations for each pipe size to be heat traced.
PART 2 PRODUCTS
2.01 SYSTEM DESIGN REQUIREMENTS
A. Design Heating Load:
1. Heating load to be calculated based upon a 50 degree F delta, 20 mph wind if pipes are located outdoors, insulation as…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .