This document contains a Request for Information (RFI) and details regarding a related federal construction contract opportunity. The RFI outlines questions and answers pertaining to an upcoming construction project, including the availability of as-built drawings, HVAC ductwork requirements, asbestos and lead reports, and use of on-site restroom facilities. The federal contract opportunity is a Solicitation for a five-year Indefinite Delivery-Indefinite Quantity Multiple Award Task Order Contract to provide construction services for the National Guard in Missouri, with individual task orders ranging from $2,000 to $6 million. The contract has a total small business set-aside with a NAICS code of 236220/237990 and will result in five awards to share an ordering capacity of $25 million.

SEED #1 RFI's

View the file

Other files

File Type Posted
Amendment_5.pdf PDF
RFI_dated_2_MAR_2019.docx DOCX document
Exterior_photos_of_bldg_59.docx DOCX document
Bldg_59_Roof.pdf PDF
Exterior_photos_of_bldg_59.docx DOCX document
Bldg_59_Roof.pdf PDF
RFI_dated_2_MAR_2019.docx DOCX document
SEED__2_-_2nd_Sign_in_Sheet.pdf PDF
SEED__1_-_2nd_Sign_in_Sheet.pdf PDF
AF3064.pdf PDF
Amendment_4.pdf PDF
RFI's_dated_28_FEB_2019.docx DOCX document
MATOC_2019_Preproposal_Conference_Slides.pptx PPTX presentation
SOW_LTUY172059_-_Repair_Bldg_59_Rev27FEB19.docx DOCX document
Meeting_Minutes_St_Joseph_SEED_2.docx DOCX document
59_Flr_Plan.pdf PDF
Attendance_sheet_SEED__2.pdf PDF
Bldg_20_Details.pdf PDF
RFI_questions_and_answers_from_site_visit.docx DOCX document
AATTCP302W.pdf PDF
Amendment_3.pdf PDF
AATTCM302-AW.pdf PDF
QA_for_MATOC.docx DOCX document
Attendance_Sheet_SEED__1.pdf PDF
Air_Guard_Bldg_59_&_290_LBP_ACM_report.pdf PDF
Meeting_Minutes_Jefferson_Barracks_SEED_1.docx DOCX document
AATTCA501-AW.pdf PDF
Meeting_Minutes_Jefferson_Barracks_SEED_1.docx DOCX document
AATTCE401W.pdf PDF
AATTCA201-AW.pdf PDF
Second_site_visit_docx.pdf PDF
Second_site_visit_docx.pdf PDF
Amendment_2.pdf PDF
W912NS19R0001_Amendment_1.pdf PDF
Exhibit_D-1._Proposal_Form_(SEED__1).pdf PDF
Exhibit_D-2._Proposal_Form_(SEED__2).pdf PDF
Exhibit_B_-_SUBCONTRACTOR_INFORMATION_AND_CONSENT_FORM.doc DOC document
Exhibit_C_-_PAST_PERFORMANCE_REFERENCE_QUESTIONNAIRE.doc DOC document
Exhibit_D-2._Proposal_Form_(SEED__2).pdf PDF
Attachment_2_Plans_and_Specifications_(SEED_Project__2)_(1).pdf PDF
Attachment_4_Wage_Determination_SEED_2.pdf PDF
Attachment_5_Section__01000.pdf PDF
Exhibit_D-1._Proposal_Form_(SEED__1).pdf PDF
Attachment_3_Wage_Determination_SEED_1.pdf PDF
Attachment_1_Plans_and_Specifications_(SEED_Project__1)_(2).pdf PDF
Exhibit_A_-_PERFORMANCE_RELEVANCY_QUESTIONNAIRE.doc DOC document
MATOC_SOLICITATION_6FEB2019.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI

SEED #1

1. Are CADD files available for as-builts?

Answer: There is an AutoCad dwg file showing the floor plan for this project which can be provided. However it is only a simple architectural floor plan showing the layout. There are no as-built drawings showing existing equipment and construction details. Contractors shall

2. HVAC ductwork office (new), balance HVAC?

Answer: There is an existing supply air duct in the vicinity of the new office. Return air register and duct capability will need to be provided. Determine size of return air ductwork and balance system as best as possible. Facility is rather small.

3. Asbestos and Lead – report available?

Answer: Yes the report from August 13, 2018 is available.

4. Roof Leak in kitchen?

Answer: Civil Engineering will attempt to locate and fix the leak.

5. Closet option has comm backboard. Relocate?

Answer: No. Leave backboard as is.

6. Will Porta-Johns or use of Facilities in the Building be available?

Answer: Restroom in bldg. 59 is available for use, on the condition it is maintained clean. Restrooms in bldg. 50 and 41 are also available for use, should bldg. 59 be inaccessible due to conflicts because of work in progress.

7. At the site visit there was mention of a duress system – Strike this – there will be none.