W912L718R7002_Amendment_1.pdf

PDF 133 KB Posted

Attached to
Replace KC-135 Maintenance Hangar and Shops
Solicitation number
W912L7-18-R-7002
Issued by

About this file

Amendment 1

View the file

Other files

File Type Posted
Question_103&116.pdf PDF
Question_97-115.pdf PDF
Question_76-96.pdf PDF
Question_65-75.pdf PDF
Question_49-64.pdf PDF
Question_34-48.pdf PDF
Question_15.pdf PDF
Question_16-33.pdf PDF
Question_1-15.pdf PDF
Geotechnical.pdf PDF
Asbestos_Survey-Sample.pdf PDF
Asbestos_Management_Plan.PDF PDF
400hz_cutsheet.pdf PDF
Pre-Proposal_Conference_Sign_in_Sheet_W912L718R7002.pdf PDF
Pre-Proposal_Conference_Slides_W912L718R7002.pdf PDF
Preproposal_minutes_W912L718R7002.pdf PDF
Exhibit_F_-_Small_Business_Participation_Plan_Format.docx DOCX document
Exhibit_D_-_Letter_of_Commitment.docx DOCX document
J_and_A_Brand_Name_Advantor_18-7005_18R7001.pdf PDF
McGheeTyKC135_B-3_combined_vol_2.pdf PDF
McGhee_Tyson_B3_Vol1_March_2018.pdf PDF
Exhibit_B_-_Subcontractor_Information_and_Consent_Form.doc DOC document
Exhibit_A_-_Performance_Relevancy_Questionnaire_Specialized_Experience.docx DOCX document
J_and_A_Brand_Name_Simplex_18-7002_18R7002.pdf PDF
Exhibit_C_-_Past_Performance_Questionnaire_Package.doc DOC document
J_and_A_Brand_Name_Schneider_DDC_18-7003_18R7002.pdf PDF
Exhibit_G_-_Subcontracting_Plan_Format.docx DOCX document
Division_01_SECTION_01000.pdf PDF
McGhee_Tyson_B3_Vol2_March_2018.pdf PDF
McGheeTyKC135_B-3_combined_vol_1.pdf PDF
McGhee_Tyson_B3_Vol3_March_2018.pdf PDF
W912L718R7002.pdf PDF
J_and_A_Brand_Name_HEF_18-7004_18R7002.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F7X3188099AW01 PSXE999132

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0001 has been issued to change the proposal due date from 24 July 2018 to 1 August 2018, 2PM EST. All questions must be submitted no later than 25 July 2018, 3PM EST.

The follow ing have been provide on FBO.GOV: Geotechnical Report, Asbestos Management Plan, Asbestos Survey Sample, 400hz cut sheet All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Jul-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912L7-18-R-7002

X 9B. DATED (SEE ITEM 11)

22-Jun-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Jul-2018

CODE

134TH TN AIR NATIONAL GUARD

134 MSC CONTRACTING OFFICE - WAWF W912L7

240 BRISCOE DRIVE

LOUISVILLE TN 37777-6227

W912L7 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912L7-18-R-7002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 24-Jul-2018 02:00 PM to 01-Aug-2018 02:00 PM.

(End of Summary of Changes)