PRE-PROPOSAL CONFERENCE
10 July 2018
SolicitationW912L7-18-R-7002
Replace KC-135 Maintenance Hangar &
Shops
PROJECT NO.PSXE999132
ConstructionLocation:
134th Air Refueling
Wing Louisville,Tennessee (TN)
INTRODUCTION
Randal Halbrooks: Procurement Contracting Officer (USPFO- TN)
CMSgt Richard Lusby: Administrative Contracting Officer (134th
ARW)
Maj David Barrett: Deputy Base Civil Engineer, Contracting Officer Representative (134thARW)
Lt Col Brian Austin: Base Civil Engineer/Commander (134th
ARW)
52,000 sf hangar Includes:
28,000 Maintenance Hangar Area 19,400 General Purpose Shop Area 4,600 Corrosion Control Are 5,400 Avionics Shop Area
LEED Silver
Base + Options 1-14 730 Days after NTP
Contract Line Item Number (CLIN) Structure:
Base = CLIN 0001
Options = CLIN 0002 - 0015
Project is being solicited as an Unrestricted action The Contract will be awarded using Tradeoff
Source Selection Procedures resulting in the Best Value to the Government
Evaluation Factors – Technical,Past/Present Performance,Small Business Participation and Price
Subcontracting Plan – Large business only
Website - https://www.fbo.gov
Solicitation &Amendments
Exhibits
Questions & Answers (Q&A)Document
Check Regularly & Refresh Web Page
Specifications, Supplements, & Plans/Drawings https://www.fbo.gov/
The Government intends to award without discussions and there may not be a chance for discussions, corrections, or revised proposals.
Offerors are strongly cautioned to carefully read all the requirements of the solicitation and comply accordingly.
Evaluation Factors for Award are detailed in RFP section 00120
Carefully review section 00120 when preparing proposal
Comply with section 00100 and 00110 requirements
Failure to furnish a complete proposal may result in elimination from consideration
Best value is defined as an award based on the greatest overall benefit in response to the requirement. Award is based on price and other non-cost related factors.
Award in this process does not necessarily mean the lowest price wins
Evaluation Factors and Relative Importance
• Factor 1 is slightly more important than Factor 2
• Sub-factor 1, Demonstrated Experience and Key Personnel (slightly more important than sub-factor 2)
• Sub-element 1, Demonstrated Experience (slightly more important thansub-element 2)
• Sub-element 2, Key Personnel
• Sub-factor 2, Technical Approach Plan and Construction Schedule
• Sub-element 1, Technical Approach Plan (slightly more important than sub-element 2)
• Sub-element 2, Construction Schedule
Factor 1, Technical Merit
• Factor 2 is slightly less important than Factor 1Factor 2, Past/Present Performance
Factor 3, Small Business Participation
• Factor 3 is significantly less important than Factor 2
• (Both large and small business)
• Not rated
• Price evaluation will determine if the proposed prices are fair and reasonablePrice
Evaluation Factors and Relative Importance
• Large Businesses only
• Offerors are encouraged to review AFARs Appendix DD for how the subcontracting plan will be scored.
• To be acceptable, subcontracting plans must address all requirements in AFARS
Appendix DD, DD-301.
• Also see Exhibit GSmall Business
Subcontracting Plan
Section 00110 of the RFP Details the Required Information and Format of the Proposal
Proposal
3 VOLUMES (1 CD/DVD for eachvolume)
Volume 1 – Price Proposal & Pro forma docs – includes Subcontracting Plan (1 original, 1 hard copy)
Volume 2 (1 original, 4 hard copies) Part 1:Technical Proposal Part 2:Past/Present Performance Info
Volume 3- Small Business Participation Plan (1 original, 2 hard copies)
1. Basis of Estimate
2. Section 00110 – Introductory Page. Refer to paragraph 2.5.1.2 for details
3. Offer- SF 1442, Offeror portion,Blocks 14 to 20c
4. Section 00010, pricing
5. Original Bid Bond and Power of Attorney
6. Section 00600 – Representations & Certifications
1. Complete Reps & Certs on the web at https://www.sam.gov/portal/public/SAM/
2. Complete & return Reps & Certs in Section 00600
7. Executed JointVenture Agreement (if applicable)
8. Subcontracting Plan (large businesses only) https://www.sam.gov/portal/public/SAM/
Sub-Factor 1, sub-elements 1 and 2 Max No. ofPages
Demonstrated Experience 3 single pages for each project
Key Personnel 3 single pages for each key personnel resume
Sub-Factor 2, sub-elements 1 and 2 Max No. ofPages
Technical Approach Plan 2 pages per topic (items a through h)
Construction Schedule Schedule isn’t subject to page limits but narratives are limited to 5 pages
Demonstrated Experience
•Min of 2 max of 5 completed or currently well underway projects.
•Turn over no more than 8 years preceding this solicitation
• Letters of Commitments from subcontractors, ExhibitD •Exhibit A •Project Manager, Site Superintendent, Quality Control
Manager and Safety Manager
• Section 01000 for minqualifications •Exhibit B
• Letter of commitments from subcontractors, ExhibitD
Key Personnel
•Will be incorporated into the contract •Complete all topics listed
Technical Approach Plan
•Gantt chart •Estimated NTP date •Within period of performance in 52.211-10
Construction Schedule
Submission Requirements
Technical Ratings:
Utilizes CombinedTechnical/Risk Rating
Method Descriptions
COLOR RATING ADJECTIVAL RATING
Blue Outstanding
Purple Good
Green Acceptable
Yellow Marginal
Red Unacceptable
VOLUME 2
PAST/PRESENT PERFORMANCE INFORMATION
• Current/on-going performance complete to 50% or greater
• Within 8 years preceding this solicitation
• Performance Relevancy Questionnaire, Exhibit A. No more than 5
• Reference Package, Exhibit C
• JVs and Formal Teaming Agreements: each company shall complete Exhibit A and obtain Exhibit C
• Consider the currency and the relevancy
• Final CPARS in lieu of references packages
• Key Personnel may be evaluated
• Gov may use: PPIRS, FAPIIS, eSRS, interviews or personal business experience
Past/Present Performance
Exhibit A - Part 1- Performance Relevancy Questionnaire Use Exhibit Format Complete no more than five (5) forms for Relevant Contracts
Quality > Quantity Completed or Substantially Completed (50%) in the last eight (8) years Send Questionnaires for the Exhibit A Projects to your references Do this Early! – Must be received by the Contracting office by the solicitation close date
Exhibit A - Part 2 – Provide the following one (1) time:
Describe compliance with FAR 52.219-8, Utilization of SmallBusinesses (2A)
2B – 2E 2E has a limit of four (4) pages
Exhibit C – Reference Questionnaire Package Linked to Exhibit A – Part 1
If you do not have relevant past/present performance and are using the experience of key personnel, predecessor companies orsubcontractors, ensure you clearly state this in the proposal .
In order to consider the work of subs and teaming partners not currently employed by proposing contractor, the subcontractor must complete Exhibit B - Information and Consent form
Adjectival Rating Description
Very Relevant Essentially the same scope
Relevant Similar scope
Somewhat Relevant Some aspects are similar
Not relevant Little or none similarities
Adjectival Rating Description
Substantial Confidence Based on the recent/relevant performance record- high expectation that the offeror will successfully perform
Satisfactory Confidence Based on the recent/relevant performance record- reasonable expectation that the offeror will successfully perform
Neutral Confidence No recent/relevant performance record is available
Limited Confidence Based on the recent/relevant performance record- low expectation that the offeror will successfully perform
No Confidence Based on the recent/relevant performance record- no expectation that the offeror will successfully perform
VOLUME 3
Small Business Participation Plan
Offerors shall use Exhibit F
Offerors shall identify to extent to which all listed categories in the solicitation will be utilized
Goals are an estimated percentage of total contract dollars (total proposed amount including options)
This is not a subcontracting plan and it is required from both, small businesses and large businesses
Min goals for each category are identified in Section 00120 of the solicitation
Small Business
Participation Plan
VOLUME 3
Small Business Participation Plan
COLOR RATING ADJECTIVAL RATING
Blue Outstanding
Purple Good
Green Acceptable
Yellow Marginal
Red Unacceptable
• Award is contemplated to be made without discussions. Do not anticipate a chance to make corrections or changes
• Your first proposal will probably be your ONLY proposal
• Read the solicitation requirements carefully
• Consider using Sections 00110 and 00120 to “rate” yourself before submitting the proposal- Is it complete??
When using a subcontractor to obtain/enhance relevancy provide Subcontractor Information and Consent For m (Exhibit B) and provide a Letter of Commitment (Exhibit D) or it will not be considered
Submit a complete proposal in accordance with instructions – use formats provided.
Prime Contractors are responsible for coordination among the divisions with subcontractors
All amendments will be posted on the FBO web site
After closing, no information will be available untilaward
Award will be posted to the web
Page 2 of SF 1442, acknowledge all amendments.
• See Section 00100 paragraph 3 for details
• Questions and RFIs are due NLT seventh working day prior to closing
• Answers to questions should be posted not later than five working days prior to closing
• Do not call technical personnel or A&E directly
• Amendments will be only issued only if there is a change in the solicitation, specifications or plans
• All questions and answers will be posted on https://www.fbo.gov/
• If there are necessary addendums,they will be issued by an amendment and posted
• Check web site regularly and don’t forget to refresh web page https://www.fob.gov/
• https://www.fbo.gov
• https://www.acquisition.gov/
• www.sam.gov/
• http://www.wdol.gov/dba.aspx https://www.fbo.gov/ https://www.acquisition.gov/ http://www.sam.gov/ http://www.wdol.gov/dba.aspx
• Proposal Due 2:00 PM EST on July 24,
• Proposal MUST be signed by Officer of your Company
• No Facsimile
• Send CD/DVDs & Paper Submissions to:
ATTN: CMSgt Richard Lusby Contracting Office 123 Briscoe Drive Louisville, TN 37777
2:00 p.m.EST 24 July 2018
DON’T FORGET TO HAVE REFERENCES SENT IN
BYTHISTIME & DATE
| Slide Number 1 |
| Slide Number 2 |
| INTRODUCTION |
| Slide Number 4 |
| Slide Number 5 |
| Project is being solicited as an Unrestricted action |
| Website - https://www.fbo.gov |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Evaluation Factors and Relative Importance |
| Evaluation Factors and Relative Importance |
| Section 00110 of the RFP Details the Required Information and Format of the Proposal |
| Slide Number 15 |
| Slide Number 16 |
| Submission Requirements |
| Technical Ratings: |
| VOLUME 2 |
PAST/PRESENT PERFORMANCE INFORMATION
| Exhibit A - Part 1- Performance Relevancy Questionnaire |
| Slide Number 21 |
| Slide Number 22 |
| VOLUME 3 |
Small Business Participation Plan
| Slide Number 24 |
| Slide Number 25 |
| Slide Number 26 |
| Slide Number 27 |
| Page 2 of SF 1442, acknowledge all amendments. |
| Slide Number 29 |
| Slide Number 30 |
| Slide Number 31 |
| Proposal Due 2:00 PM EST on July 24, 2018 |