15. Question: A pre-bid substitution request for liquid membrane vapor permeable air barrier was received.
15. Answer: Proposals shall be based on the contract plans and specifications as posted. After award, the awarded General Contractor (GC) may submit a substitution request, but only per the substitution request process as defined in the Division 1 Specification Section (01 33 00) describing that process.