Solicitation Amendment No. 0002

View the file

Other files

File Type Posted
EXHIBIT_E_-_Amend_0005.docx DOCX document
Solicitation_No._W912KC-16-R-0002_Amendment_0005.pdf PDF
TSC_Questions-Answers-AMENDED_FINAL-30AUG2016.pdf PDF
M104.pdf PDF
A12-tac2_-_site.dwg DWG drawing
M302.pdf PDF
Appendix_1_to_Specifications_LEED_Checklist_071615.pdf PDF
M401.pdf PDF
TSC_Questions-Answers-VER_FINAL_26AUG2016.pdf PDF
Revised_Spec_TOC_Amend_4.pdf PDF
A12-tac2_-_topo.dwg DWG drawing
Q47-Sketch.pdf PDF
Solicitation_No._W912KC-16-R-0002_Amendment_0004.pdf PDF
Appendix_2_to_Specifciations_01_TAC_Spec_NPDES_Permit_Cover_Ltr.pdf PDF
EXHIBIT_E_-_Amend_0004.docx DOCX document
P501.pdf PDF
TSC_Supplemental_Addendum_Items.pdf PDF
Appendix_3_to_Specifications_Geothermal_Testing_Data.pdf PDF
M504.pdf PDF
Appendix_2_to_Specifications_02_TAC_Spec_NPDES_Permit.pdf PDF
Solicitation_No._W912KC-16-R-0002_Amendment_0003.pdf PDF
TSC_Questions-Answers-VER_2.doc DOC document
EXHIBIT_E_-_Amend_0003.docx DOCX document
EXHIBIT_E_-_Amend_0002.docx DOCX document
Volume_I_Specifications.pdf PDF
Specifications_Division_01.pdf PDF
EXHIBIT_E.docx DOCX document
Solicitation_No._W912KC-16-R-0002.pdf PDF
EXHIBIT_C.doc DOC document
Attachment_1_-_GFP.pdf PDF
TAC_Bid_Drawings.pdf PDF
EXHIBIT_A.doc DOC document
EXHIBIT_D.doc DOC document
Volume_II_Specifications.pdf PDF
EXHIBIT_B.doc DOC document
TSC_Questions-Answers-VER_1.pdf PDF
EXHIBIT_C_-_Amend_0001.doc DOC document
Spec_TOC_with_Tilt-Up_Concrete_Const_Amend1.pdf PDF
420522_TAC_Pre-Bid_Presentation_11Aug2016_ver2.pdf PDF
Spec_03_47_13_Tilt-Up_Concrete_Construction_Amend1.pdf PDF
Volume_II_Specifications_081016.pdf PDF
Site_Visit_Sign_In_Sheet_TAC.pdf PDF
EXHIBIT_E_-_Amend_0001.docx DOCX document
Conference_Slides_11_August_16.pdf PDF
G001_revised_Drawing_Cover_Sheet_06022016_Amend1_.pdf PDF
Solicitation_No._W912KC-16-R-0002_Amendment_0001.pdf PDF
Volume_I_Specifications_081016.pdf PDF
EXHIBIT_D_-_Amend_0001.doc DOC document
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912KC-16-R-0002

USPFO FOR PENNSYLVANIA

ATTN: ANDREA MAGEE

(717)861-8658

FORT INDIANTOWN GAP

ANNVILLE PA

0010892911 420522

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Removal of requirement for Exhibit D. Options, if exercised, w ill be exercised at time of aw ard. The performance period for any/all exercised options shall be the same as the base aw ard period of performance (547 calendar days after issuance of Notice to Proceed).

Acknow ledgement of amendment shall be on Exhibit E.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 21

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Aug-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912KC-16-R-0002

X 9B. DATED (SEE ITEM 11)

27-Jul-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Aug-2016

CODE

USPFO FOR PENNSYLVANIA

ATTENTION: DEPT OF MILITARY AND VETERANS AFF

: P & C, RM#242,

FORT INDIANTOWN GAP PA 17003-5003

W912KC 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912KC

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The following have been modified:

SECTION 10 NOTES

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

SECTION 00100

Section 00100 INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. SCOPE

1.1. You are invited to submit a proposal in response to our Request for Proposal W912KC-16-R-0002 for Project No. 420522 at Fort Indiantown Gap, Annville, Pennsylvania. As a result of this solicitation, the Government intends to award a single Firm Fixed Price (FFP) contract to the responsible offeror whose proposal represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

1.2. This solicitation is set-aside 100% for small businesses.

2. NOTICE OF PRE-PROPOSAL CONFERENCE

2.1. A pre-proposal conference will be conducted on August 11, 2016 at 9:00 AM for the purposes of briefing on the proposal requirements and answering questions regarding this solicitation. This conference will be held at the State Reservation Maintenance Office, Building 11-64, Conference Room, Fort Indiantown Gap, Annville, Pennsylvania . Interested Contractors are highly encouraged to attend the pre-proposal conference. The site visit will be held following the conference.

2.2. Due to security conditions, all offerors must register to attend this conference and site visit. Email the following information for all attendees to: michael.v.brown60.civ@mail.mil; karen.m.finn2.civ@mail.mil; and richard.a.weber8.mil@mail.mil.

Visitor’s Name Last Four Digits of Social Security No.

Driver’s License No., State Issued and Expiration Date Date of Birth Citizenship

2.3. This information must be provided in advance, not later than 2 business days prior to the meeting, in order to ensure access to the military base and conference site and ensure adequate seating for the conference attendees. Even if you have access to the base you must register to ensure adequate seating. The furnishing of the above information is voluntary; however, your failure to furnish all or part of the requested information may result in the Government’s denial of your access to the pre-proposal conference. This information will be provided to the

Base Security Forces who will authorize your entrance to the site.

2.4. You may be required to present the following information upon arrival: (1) Vehicle Registration, (2) Valid Driver’s License, (3) Proof of Insurance for Vehicle, and/or (4) Safety Inspection and Car Rental agreement if applicable. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.

2.5. Information provided at this conference or site visit shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.

2.6. A record of the conference shall be made and furnished to all prospective offerors via posting to:

www.fbo.gov. The record will include minutes of the meeting, including questions (on a non-attribution basis) and answers.

3. FORMAL COMMUNICATION, OFFEROR EXPLANATIONS

3.1. Submit all questions via email to the contracting office at the address shown below. Do NOT contact the A-E or Engineering personnel directly. Doing so will only delay the response to your question.

Subject Line: Reference No. W912KC-16-R-0002.

Email: michael.v.brown60.civ@mail.mil and karen.m.finn2.civ@mail.mil.

INQUIRIES SHALL BE SUBMITTED VIA EMAIL AND INCLUDE THE FOLLOWING INFORMATION:

Date of Proposal Inquiry:

From: ______________________________

Company Name: ___________________________

Phone Number: ____________________________

Email address: _____________________________

Proposal Inquiry: Be specific as to part of solicitation you are questioning.

3.2. Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, or proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach offerors before the submission of their offer.

3.3. The Contracting Officer reserves the right to address questions received after the fifth day prior to solicitation closing with those offers deemed compliant and/or in the competitive range after closing. All questions and requests for information (RFI) must be received NOT LATER THAN the fifth working day prior to closing and will be posted not later than two working days prior to closing. OFFERORS ARE STRONGLY ENCOURAGED

TO SUBMIT QUESTIONS EARLY IN THIS PROCESS.

3.4. Any interpretations made will be in the form of an amendment of the solicitation, drawings, specifications, etc., and will be furnished to all prospective offerors via posting to www.fbo.gov.

3.4.1. Receipt by the offeror must be acknowledged in the space provided on the SF 1442 or by returning a signed copy of the amendment by the time set for receipt of proposals. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding. Questions (on a non-attribution basis) and answers shall be furnished to all prospective offerors via the web site.

3.4.2. For security reasons, all technical and engineering data related to this solicitation will be distributed using the Federal Business Opportunities (www.FedBizOpps.gov or www.fbo.gov) system. FedBizOpps is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Interested bidders/offerors must register with FedBizOpps before accessing the system. FedBizOpps registration requires the following information:

1) Marketing Partner Identification Number (MPIN)

2) DUNS Number and CAGE Code

3) Telephone Number

4) Email address

Registration instructions can be found on the FedBizOpps website at https://www.fbo.gov/?s=getstart. (Please note the registration for access to the secure site takes approximately 15 business days, so plan accordingly.)

3.4.2.2. Interested offerors must be registered in the System for Award Management (SAM). To register go to:

www.sam.gov. You will need your DUNS number to register. Instructions for registering are on the web page.

4. AMENDMENTS PRIOR TO DATE SET FOR RECEIPT OF PROPOSALS

4.1. The right is reserved, as the interest of the Government may require, to revise or amend, the specifications or drawings or both prior to and/or after the date set for receipt of proposals as necessary. Such amendments, if any, will be announced by an amendment or amendments to this Request for Proposal. All information relating to this RFP, including pertinent changes/amendments and information prior to the date set for receipt of proposals will be posted at www.fbo.gov.

4.2. Offerors are strongly cautioned to check this site frequently and to “refresh” their web page to ensure they have the lasted information.

5. HAND CARRIED PROPOSALS/INVITATIONS

5.1. A proposal repository is provided for hand carried proposals and is located at: USPFO For PA, Purchasing and Contracting Office, DMVA, Building 0-48, Room 242, Fort Indiantown Gap, Annville, PA 17003

5.2. Hand carried proposals must be deposited in the repository prior to the time established for receipt of proposals.

5.3. Offerors are cautioned that approval to enter Building 0-48 at Fort Indiantown Gap is restricted and requires passing through a security gate. Persons seeking entrance to deliver a hand carried proposal should request security personnel to contact the Contracting Office at Extension 8687 or Extension 6311. Security personnel may require you to present the following information upon arrival: (1) Vehicle Registration, (2) Valid Driver’s License, (3) Proof of Insurance for Vehicle, and/or (4) Safety Inspection and Car Rental agreement if applicable. Any of the above information furnished by you is protected under the Privacy Act and shall not be released unless permitted by law and/or you have consented to such.. Follow the procedures outlined above in paragraph 2.1.2. for entry.

Delays are probable at the entry point and should be accounted for. Late receipt of proposals due to base entry delays may not be deemed excusable and the Contracting Officer may declare the proposal late and remove it from consideration.

6. WAGE DETERMINATION

6.1. The Construction Wage Rate Requirements formerly known as Davis Bacon Wage Rates are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation is General Decision Number: PA160117, Mod. 08, dated July 15, 2016, Mod. 09, dated July 29, 2016 for Lebanon County, Pennsylvania.

In the event the current prevailing Wage Determination is changed by the Department of Labor prior to the closing date of the solicitation, the most current wage determination is in effect. Should the wage rate change after closing, but prior to award, the updated Wage Determination will be incorporated by amendment and issued to all offerors that have not been eliminated from the competition. If applicable, these offerors/contractors will be given a reasonable opportunity to provide revised proposals solely to amend proposals due to Wage Determination changes.

If the wage determination modification does not change any affected wage rates, then the provisions of FAR 22.404- 5(c)(4) will apply.

6.2. Applicable wage rates can be found at http://wdol.gov/dba.aspx.

7. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

This RFP does not commit the Government to pay costs incurred in preparation and submission of initial and subsequent proposals or for other costs incurred prior to award of a formal contract.

8. REMOVAL OF SECTIONS AT TIME OF AWARD

Sections 00100, 00110, 00120, 00600 and all exhibits will be physically removed as a result of an award, but will be deemed to be incorporated by reference in that award.

9. DISPOSITION OF UNSUCCESSFUL PROPOSALS

In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful proposals. The Government will destroy extra copies of unsuccessful proposals. No destruction certificate will be provided.

10. INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES

It has been determined that all temporary utilities shall be the responsibility of the contractor. The contractor will pay all charges (hook up fees, metering, monthly usage, etc.) resulting from temporary utilities. The offerors shall take this into consideration when computing their offers. (FAR Clause 52.236-14, Availability and Use of Utility Services.) OR It has been determined that all reasonable amounts of (insert), where/if physically available, used in connection with this project will be furnished to contractor without cost. The offerors will take this into consideration when computing its offer. (FAR Clause 52.236-14, Availability and Use of Utility Services)

11. EXCEPTIONS

If the offeror takes exception to any of the requirements specified in this solicitation, the offeror shall clearly identify each such exception and include a complete explanation of why the exception was taken and what benefit accrues to the Government. All exceptions to the solicitation requirements (Sections 00010 through 00800) and supporting rationale shall be included in an addendum to the proposal and clearly labeled "Exceptions". An addendum is only required if the offeror takes exception to any requirement in the solicitation. (The Addendum does not have a page limitation, but shall only include information relevant to exceptions taken to the solicitation requirements.) The Government will assume an offeror takes no exceptions to any solicitation requirement if the offeror does not submit an Addendum identifying exceptions. Offerors are advised that solicitation requirements are not necessarily negotiable and such exceptions may render an offeror's proposal unacceptable and ineligible for award.

12. CLAUSES

12.1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.

12.2. Clauses and provisions in this document may not appear in consecutive order.

13. BRAND NAME REQUIREMENTS

NONE.

SECTION 00110 SUBMISSION REQUIREMENTS AND INSTRUCTIONS

1. PROPOSAL PREPARATION INSTRUCTIONS

1.1. These instructions prescribe the format of proposals, and describe the approach for the development and presentation of the proposal data. They are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of proposals. Carefully review this section prior to commencing proposal preparation. All solicitation amendments must be acknowledged in accordance with Section 00100, FAR Provision 52.215-1, Instruction to Offerors – Competitive Acquisition.

1.2. Offerors are cautioned to strictly comply with all instructions within this solicitation to ensure submission of a complete proposal. Failure to furnish a complete proposal, at the time of proposal submission, may result in the proposal being unacceptable to the Government and eliminated from consideration for award.

2. PROPOSAL CONTENT

2.1. Prospective offerors shall submit the following volumes in two separate packages:

2.1.1. Submit Volume 1, Price proposal (Exhibit E), pro forma documents, in original and (3) three hard copies, in accordance with instructions contained herein.

Volume 2, Part 1 – Technical Capability Proposal, in original, (3) hard copies and one CD.

Subfactor 1 – Experience and Capability (limit resumes to 2 pages each) Subfactor 2- Construction Schedule and Commissioning Approach/timeline (schedule no page limit;

narrative – no more than 5 pages) Subfactor 3 – LEED ( limit resumes to 2 pages each)

Volume 2, Part 2 – Past/Present Performance Information

2.1.2. Although the assessment of Past Performance as a specific evaluation factor is separate and distinct from the Determination of Responsibility required by FAR Part 9, Past Performance information obtained herein will be used during the Government’s responsibility determination. In addition contractors shall submit a single copy of the following information in a sealed envelope with their name on the outside. This information is sought pursuant to FAR 9.105-1 and will be opened and utilized only if the contractor is selected for award.

Information will be used in determining the contractor responsible in accordance with FAR Part 9. If an award is not being offered the envelope will be filed unopened with the original proposal.

2.1.3. Documentation of adequate financial resources: Provide letters of reference from financial institution(s) concerning credit worthiness and from bonding companies indicating capability to bond to, at a minimum, the price proposed.

2.1.4. Offerors are cautioned to carefully review the proposal requirements for these Volumes and ensure a complete proposal is submitted.

2.2. PROPOSAL DUE DATE SCHEDULE

2.2.1. The entire proposal (Volumes 1 and 2 and the CD copy (Vol 2 only) are due by the date and time set for the receipt of proposals shown in Block 13 of the SF 1442. Past performance references should provide questionnaire responses to the Contracting Officer not later than the closing date.

2.3. After compiling all required information, submit original and specified number of copies to the following office: USPFO for PA, Purchasing and Contracting Office, Bldg 0-48, Room 242, Fort Indiantown Gap, Annville, PA 17003. Mark the front of the envelope/box with the following: “PROPOSAL No. W912KC-16-R-0002, DO NOT OPEN--- Competitive Acquisition”.

2.4. PROPOSAL FORMAT

2.4.1. Purpose: These instructions prescribe the format of proposals, and describe the approach for the development and presentation of the proposed data. The proposal shall include all of the information requested in the specific instructions. Failure to include all information requested may adversely affect the evaluation.

2.4.2. A proposal that merely reiterates or promises to accomplish the requirements of the RFP will be considered unacceptable. A proposal that is orderly and sufficiently documented will be easy for the Government to understand and will enable the Government to perform a thorough and fair evaluation.

2.4.3. Offerors are cautioned to submit enough information to enable the evaluation committee to fully ascertain each offeror’s capability to perform all of the requirements contemplated by this solicitation. All commitments made in the proposal may become a part of the resultant contract. The data submitted with each proposal should be complete and concise, but not overly elaborate. Excessive reliance on promotional brochures is discouraged.

2.4.4. Written proposals shall be prepared on standard 8.5 x 11 inch paper (charts may be landscaped but must be on 8.5 x 11 inch paper) and shall be in a legible font size (10 min.). All pages of each proposal shall be appropriately numbered, and identified with the RFP number. For ease of reference, consecutive page numbering with tabs is required. Type size for graphics, charts, diagrams and tables shall be of an appropriate font and size for the application, and must be clearly readable without magnification assistance to the normal eye. Text lines will be no less than single-space. To the maximum extent practicable, proposal submission shall be double sided. Where page limits exist a page is defined as one single side of a page. Double sided pages count as 2 pages. Unless otherwise stated, tabs, indexes and dividers do not count in the page count.

2.4.5. Binding: Elaborate format and binding are neither necessary nor desirable. All binders will be capable of lying flat when opened. Three ring binders are preferred. The cover and spine of each binder will clearly identify the offeror’s name, Project number, RFP number, RFP title and copy number, (e.g. copy 2 of 3). The original for each volume will be clearly identified on the cover and the spine. All binders will allow for easy removal and replacement of pages.

2.4.6. Indexing: Each binder will contain a “Table of Contents” for that volume. The “Table of Contents” will identify major areas, paragraphs and subparagraphs by number and title, as well as by page number and volume locations. Tab indexing will be used to identify Sections as appropriate.

2.4.7. Electronic Copy: Provide one (1) electronic copy of all of the Volume 2 proposal information. Electronic copies shall be submitted on CD/DVD saved in Microsoft Word format or Adobe Acrobat. (“Read Only” files are acceptable).

2.4.10. The offeror shall be held responsible for the validity of all information supplied in his/her proposal, including that provided by potential subcontractors. Should subsequent investigation disclose that the facts and conditions were not as stated, the proposal may be rejected.

2.5. PROPOSAL VOLUME CONTENTS: Each offeror’s proposal shall be submitted as set forth below and all information shall be confined to the appropriate part to facilitate independent evaluation. Proposals, which do not include the requested minimum information, may be eliminated from further consideration for award.

2.5.1. VOLUME 1, PRICE/COST INFORMATION AND PRO FORMA DOCUMENTS

2.5.1.1. Offerors shall provide all price/cost information necessary to provide a meaningful basis for Government's analysis and evaluation of price/cost for the project set forth in Section 00120 of this solicitation. The Government is not, and does not intend on, requesting certified cost or pricing data. Offerors may be required during the evaluation process to provided sufficient price/cost information that will enable the Government to perform a meaningful evaluation.

2.5.1.2. Provide an introductory page to include Cage Code, DUNS Number, Tax Identification Number (TIN), points of contact, authorized negotiators, contact phone, and email addresses. Also, include your business socioeconomic status, e.g. small business, woman-owned small business, HUBZone small business, etc.

2.5.1.3. Offer and Section 00010 – Complete in its entirety the “Offeror” portion of the Standard Form (SF) 1442.

An official having the authority to contractually bind your company must sign the SF 1442 in accordance with FAR

4.102. One copy of the SF 1442 is required to have an original signature. Complete Exhibit E. One copy of Exhibit E is required to have an original signature.

2.5.1.4. Section 00010 – Insert the price/cost associated with the project in the line items on Exhibit E. All line items (CLINs) on Exhibit E must be priced to be considered. CLINs on SF 1442 will be completed at time of award.

2.5.1.5. Representations and Certifications- Section 00600- insert the required certifications and representations and return only those shown in section 00600. Return the entire Section 00600 with your proposal. All other required representations and certifications are to be completed on line in the System for Award Management (SAM) www.sam.gov.

2.5.1.6. All potential offerors are required to register in the System for Award Management. See FAR Provision 52.204-7 System for Award Management.

2.5.1.7. Provide on Exhibit D the number of days after the Notice to Proceed (NTP) is issued that Options 1-14can be exercised and not affect the contract price or performance period given a NTP is issued on or about October 14, 2016. The information provided will be incorporated in any unexercised options at time of contract award and will be used as a basis for exercising option after award (Exhibit D information is provided for informational purposes only and not for evaluation). [Reserved].

2.5.1.8. Joint Venture Requirements - Parties wishing to propose as a joint venture must submit, with the Pro Forma documents, an executed copy of the joint venture agreement. The joint venture agreement shall be executed in accordance with FAR 4.102(d). Each joint venture partner shall submit evidence satisfactory to the Contracting Officer that its Board of Directors has approved its participation in the joint venture or by an instrument of similarly binding character in the case of an unincorporated entity. Offerors are reminded that to obtain an award the awardee, to include a joint venture, must be registered in the System for Award Management (SAM) database. Applicable to set-aside solicitations: Joint Ventures must meet applicable size standards (See FAR Subpart 19.1). Submit with the proposal any size determination for the Joint Venture entity received from the Small Business Administration. A Joint Venture where-in one party is not a small business may be referred to the Small Business Administration ( IAW FAR 19.302 (b)) to determine eligibility. All questions regarding Joint Ventures must be directed to the Small Business Administration (SBA) and not the Contracting Officer.

2.5.2. VOLUME 2, PART 1, OFFEROR TECHNICAL CAPABILITY PROPOSAL

2.5.2.1. Volume 2 Part 1 is comprised of three (3) subfactors. Subfactor 1 Experience and Capability; Subfactor 2 Construction Schedule; Subfactor 3, LEED® Experience and Capability United States Green Building Council (USGBC) LEED® standards

2.5.2.1.1. Government acknowledges that the technical proposal will involve discussion of some of the same projects/contracts discussed in the Past Performance volume. While Past Performance examines how an offeror performed in the past, so as to determine the probability of success on future projects, this subfactor examines the offeror’s experience with complex multidiscipline project management and execution and how the offeror demonstrates an understanding of the contract’s requirements taking this experience into consideration. The Government intends to use Exhibit A Part 1 information in the evaluation of experience for Subfactor 1. A reiteration of the information provided in Exhibit A is neither required nor desired. Offeror should reference this information by providing a short summation of their relevant experience to meet the submission requirements of this subfactor

2.5.2.2. Subfactor 1 Experience and Capability. Demonstrate offerors technical experience and capability to perform a project of this magnitude and complexity. Discuss and provide experience of key construction personnel including, but not limited to, Project Manager, Site Superintendent(s), Quality Assurance Manager (on site), Site engineering personnel. Discuss any previous projects that are similar to this project in terms of scope, size and complexity. Specifically discuss any changed conditions you encountered and how those conditions were resolved.

If no experience so state and indicate in detail how you plan to overcome this lack of experience. The onus is solely on the offeror to indicate in detail how the offeror plans to overcome this lack of experience. (Resumes or experience cut sheets are limited to 2 pages each and are not part of the page count.) In the event the intended person is not part of the offeror’s organization at the time the proposal is submitted then a completed Exhibit B, “Subcontractor/Team/Key Personnel Information and Consent Form” is also required or the information will not be considered.

2.5.2.3. Subfactor 2: Construction Schedule and commissioning approach/timeline is obtained for the purposes of evaluating an offerors understanding of the requirements of the schedule and commissioning. The Schedule itself is not subject to page limits; however any provided narrative to the schedule submission is limited to 5 pages , excluding tabs, and indexes.

2.5.2.3.1. Provide Construction Schedules using a critical path a (Critical Path Method (CPM)) scheduling approach considering a Notice to Proceed date of October 14, 2016 for the schedule. The Construction Schedule is an integrated and networked multi-layered schedule of program/project tasks. It identifies project events, accomplishment, and criteria and the expected dates of each. These dates are based on the calendar dates provided as the starting point and the logical flow of dates provided by calculating the addition of duration of all tasks using typical schedule networking tools. Each major task will be directly traceable to the requirements of the project. The NTP date for the schedule is for the purpose of evaluation only.

2.5.2.3.2. Subfactor 3: Discuss company experience with building to United States Green Building Council (USGBC) LEED® standards. Indicate any previous projects that achieved USGBC LEED® certification, any level of recognition. Additionally, indicate the key construction personnel and demonstrate they have experience and required qualifications in assigned roles with building to USGBC LEED® standards. If no experience so state and indicate in detail how you plan to overcome this lack of experience. The onus is solely on the offeror to indicate in detail how the offeror plans to overcome this lack of experience. (Resumes or experience cut sheets are limited to 2 pages each and are not part of the page count.) In the event the intended person is not part of the offeror’s organization at the time the proposal is submitted then a completed Exhibit B, “Subcontractor/Team/Key Personnel Information and Consent Form” is also required or the information will not be considered.

2.5.3. VOLUME 2, PART 2 OFFEROR PAST/PRESENT PERFORMANCE INFORMATION

2.5.3.1. Volume 2 Part 2 is obtained for the purpose of evaluating Past/Present Performance. Past/Present Performance includes current/on-going performance that is complete to 70% or greater. Volume 2 includes the offeror’s Performance Relevancy Questionnaire, Exhibit A Parts 1 and 2; and any discussion and or additional information, awards, letters, etc. concerning past/present performance the offeror includes. Offerors are cautioned to complete all the questions on the Exhibit A Parts 1 and Part 2. Detailed instructions are included in Exhibit A.

2.5.3.2. Offerors shall use the Reference Package, Exhibit C, to obtain references from past and present clients.

2.5.3.3. Past/Present Performance, which includes current on-going (present) performance that is complete to 70% or greater will be evaluated using the evaluation criteria set forth in Section 00120 of the solicitation. If the offeror represents the combining of two or more companies, joint venture or formal teaming agreement, for the purpose of this RFP, each company shall complete Exhibit As and obtain Exhibit C references. The Government may contact these references and may consider this information as well as information obtained from any other sources when evaluating the offeror's past/present performance.

2.5.3.4. Offerors shall discuss their performance using the Performance Relevancy Questionnaire format, Exhibit A, Part 1. Prepare not more than (3-5) of these documents. Contractors should select their projects carefully because the quality of the contractor’s relevant performance is more important than the quantity of projects submitted.

2.5.3.5. Use the Exhibit A format to provide information that demonstrates a history of performance on contracts that are similar in scope, complexity, and cost magnitude to this project’s plans and specifications. Explain what aspects of the contract you find relevant to the proposed effort and identify how each contract ranks, in terms of relevancy, with respect to the other contracts addressed in proposal.

2.5.3.6. Offerors should consider the currency and relevancy of the past/present performance information to be considered, the performance must have been completed during the past five (5) years. The period begins five (5) years prior to the solicitation release date and includes current performance. Performance that is more current may have greater impact than older performance.

2.5.3.7. In determining relevancy to the solicitation requirement, offerors should consider the similarity of construction methods employed, size, scope, cost magnitude, location, client type (e.g. federal government) and complexity of work performed to those required for the proposed effort. Location should also be considered.

2.5.3.8. Offerors are encouraged to include with their proposal information any problems encountered on the identified contracts and the offeror's correction actions.

2.5.3.9. Offerors lacking relevant present/past performance experience may submit information regarding predecessor companies, key personnel who have relevant experience or subcontractors that will perform major or critical aspects of the requirement if such information is relevant to this acquisition. Such information shall, as a minimum, include:

Name(s) of Predecessor Company/Subcontractor and/or Key Personnel Complete Address Telephone, Fax Number and email address Brief synopsis of the experience- A resume may be submitted for "Key Personnel" Describe relevancy to this project

2.5.3.10 Provide three (3) references, for each Predecessor Company, Subcontractor or Key Personnel. Clearly identify the contractor/individual for whom the reference information concerns.

2.5.3.10.1. Each proposed subcontractor/Teaming Partner must also complete an Exhibit B, “Subcontractor/Team/Key Personnel Information and Consent Form”, to be considered.

2.5.3.11. Past Performance References – REQUIRED – A “Final” Performance Evaluation (Construction) (also referred to as CCASS Evaluation) issued for a project may be included in lieu of sending out reference package for the project. OR Offerors shall prepare and submit to prior client(s) of all the projects listed on your Exhibit A submission a Reference Package (Exhibit C) (Detailed instructions are included in Exhibit C Package). This includes correspondence explaining the requirement to obtain an independent evaluation of prior contract performance, and the Past Performance Questionnaire for use in evaluating Past Performance. Inform references that completed Performance Questionnaire should be returned to the Contracting Officer via email at: michael.v.brown60.civ@mail.mil and karen.m.finn2.civ@mail.mil to arrive not later than the closing date for receipt of proposals. Offeror must not review the Past Performance Questionnaire prior to submission. They are to be submitted by the client/evaluator directly to the Contracting Officer. Offeror's should follow-up and encourage references to get the questionnaires to the Contracting Officer in a timely manner.

2.5.3.12. In assessing past performance, the Government may also consider the past/present performance of the offeror’s key personnel, Project Manager, Quality Control Manager and Site Superintendent, as it relates to previous projects. In the event the intended key personnel for this solicitation’s project do not have demonstrated past performance in the project(s) submitted in the Exhibit A’s, the Government reserves to obtain reference information additional information is required.

2.5.3.12.1. Each key person without prior past performance history demonstrated on the submitted Exhibit A shall provide a summary of experience or a resume. In the event the intended person is not part of the offeror’s organization at the time the proposal is submitted then a completed Exhibit B, “Subcontractor/Team/Key Personnel Information and Consent Form” or Letter of Intent, is also required or the information will not be considered. The Government may seek additional references and reserves the right to use the information provided to obtain additional references.

2.5.3.13. Offerors are advised that the Government may use all data provided by the offeror in this volume and data obtained from any other sources, to include, but not limited to, data independently obtained from other Government or commercial sources; from any other sources available to the Government, to include, but not limited to, the Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases; interviews with Program/Project Managers, Contracting Officers or rely upon personal business experience with the offeror. The Government reserves the rights to obtain and evaluate past performance information from any source it deems appropriate. While the Government may elect to consider data obtained from other sources, the burden of providing current accurate and complete past/present performance information rests with the offeror.

3. DISCUSSIONS

The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer, in his/her sole discretion, later determines them to be necessary or appropriate. Further, the Government reserves the right to create or not to create a competitive range. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

SECTION 00120

SECTION 00120 PROPOSAL EVALUATIONS AND BASIS FOR AWARD

1. GENERAL INFORMATION

1.1. This solicitation is for a Firm Fixed Price Contract. The Government intends to award a single contract to a qualified Small Business Offeror deemed responsible in accordance with the Federal Acquisition Regulation (FAR), whose proposal conforms to all the RFP's requirements and is judged to represent the Best Value to the Government in accordance with the evaluation scheme set out in this solicitation. The award will be made based on the lowest price, technically acceptable source selection process. Best value is expected to result from selection of the technically acceptable proposal with the lowest evaluated price, with appropriate consideration given to the three (3) evaluation factors: Technical, Price, and Past Performance. To arrive at a Best Value decision, the Source Selection Authority will integrate the evaluation of Past/Present Performance, Technical and Price as set out in the solicitation.

In terms of the relative importance of the factors, the Technical factor is somewhat more important than Present/ Past Performance and when combined however, the non-cost factors are approximately equal to the Price Factor.

1.2. To arrive at a Best Value decision this acquisition will utilize the lowest price, technically acceptable process.

1.3. The source selection process will be conducted in accordance with FAR Subpart 15.3, Source Selection procedures. Offers will be evaluated using the criteria listed in “Evaluation Factors for Award.” Noncompliance with the RFP requirements may raise serious questions regarding an offeror’s technical ability, past performance and/or pricing and may be grounds to eliminate the proposal from consideration for contract award. Failure to include all information requested may adversely affect the evaluation. A proposal that merely reiterates or promises to accomplish the requirements of the RFP will be considered unacceptable. A proposal that is orderly and sufficiently documented will be easy for the Government to understand and will enable the Government to perform a thorough and fair evaluation.

1.4. The Contracting Officer will begin the evaluation process by conducting a proposal compliance review for all timely-received proposals for determination of basic proposal adequacy prior to providing the proposals to the evaluators. Failure to provide a complete proposal may result in the proposal being removed from further consideration for award. Failure to address any factor Technical, Past Performance and Price or any technical subfactor shall be grounds for elimination from evaluation and consideration for award.

1.5. Offerors must ensure that no pricing information is displayed in Volume 2, Technical and Past Performance Proposal.

1.6. Although the assessment of Past Performance as a specific evaluation factor is separate and distinct from the Determination of Responsibility required by FAR Part 9, Past Performance information obtained herein will be used during the Government’s responsibility determination. The Government also reserves the right to obtain additional information solely for the purpose of making a responsibility determination from all offerors after receipt of proposals. Requests for responsibility information do not constitute discussions.

1.7. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer, in his/her sole discretion, later determines them to be necessary or appropriate. Further, the Government reserves the right to create or not to create a competitive range.

1.8. ENFORCEABILITY OF PROPOSAL: The proposal must set forth full, accurate and complete information as required by this solicitation. By submission of the offer, the Offeror agrees that all items proposed (if applicable e.g., key personnel, subcontractors, etc.) will be utilized for the duration of the contract and any substitutions shall require prior Contracting Officer's approval.

2. EVALUATION FACTORS FOR AWARD

2.1. The evaluation factors are (1) Technical, (2) Past/Present Performance and (3) Price. To arrive at a Best Value decision, the Source Selection Authority will integrate the evaluation of Past/Present Performance, Technical and Price as set out in the solicitation. In terms of the relative importance of the factors, the Technical factor is somewhat more important than Present/ Past Performance and when combined however, the non-cost factors are approximately equal to the Price Factor.

2.1.1. The overarching evaluation approach for all factors and subfactors is as follows:

a. Adequacy of Response. The proposal will be evaluated to determine whether the offeror’s methods and approach have adequately and completely considered, defined, and satisfied the requirements specified in the RFP. The proposal will be evaluated to determine the extent to which each requirement has been addressed in the proposal in accordance with the proposal submission section of the RFP.

b. Feasibility of Approach. The proposal will be evaluated to determine the extent to which proposed approach is workable and the end results achievable. The proposal will be evaluated to determine the extent to which successful performance is contingent upon proven devices and techniques. The proposal will be evaluated to determine the extent to which the offeror is expected to be able to successfully complete the proposed task and technical requirements within the required schedule.

2.2. TECHNICAL PROPOSAL: TECHNICAL EVALUATION FACTOR RATINGS:

1. 2.2.1. Technical Rating: Technical Capability will be evaluated on an Acceptable/Unacceptable basis. An offeror shall obtain an “Acceptable” rating to continue further in the competition. Offerors who are deemed to merit an “Unacceptable” rating in the Technical Capability Factor will be removed from further consideration for award. Once the minimum requirements are established, the team shall evaluate the offeror's proposal against these requirements to determine whether the proposal is acceptable or unacceptable, using the ratings and descriptions outlined in Table below. Proposals are evaluated for acceptability, but not ranked using the non-price factors/subfactors. In order to be considered awardable, there must be an "acceptable" rating in every non-price factor/subfactor.

Adjectival Rating Description Acceptable Proposal meets the requirements of the solicitation.

Unacceptable Proposal does not meet the requirements of the solicitation.

2.2.3. Subfactor 1 Experience and Capability Proposal: The Experience and Capability Proposal is limited to 10 single pages, exclusive of table of contents, tabs, and dividers. Pages in excess of the limit will not be evaluated.

The elements in subfactor 1 are of equal importance.

2.2.3.1. Using the information in Technical Proposal, and the projects/contracts discussed and listed in the Exhibit A’s, the Government will evaluate the extent of related experience. To be deemed “Acceptable” the proposal must demonstrate experience and capability to perform a project of this magnitude and complexity.

2.2.3.2. The Government will evaluate the offeror’s understanding of the contract requirements, and determine to what degree their technical and administrative capabilities, proposed organization and management plan are adequate to meet contract requirements. To be considered adequate the Experience and Capability proposal will address the full spectrum of activities involved in the management of a resulting contract in a manner that gives the Government confidence that the offeror understands all of the requirements. An adequate proposal will include the information necessary to give the Government confidence of the offeror’s ability to successfully perform complete project management of the scope requirements.

2.2.3.3. Proposal demonstrates adequate quality control processes to give the government confidence of the offeror’s ability to successfully manage the material submittal process, and ensure subcontractor compliance with contract documents.

2.2.3.4. Proposal demonstrates, as a minimum, that the following key personnel: Project Manager, Site Superintendent(s), Quality Control Manager (on site), and Safety Representative have experience in managing projects/contracts of the same/similar dollar magnitude, size, complexity and scope, in the capacity in which they are proposed for this project.

2.2.4. Subfactor 2 Construction Schedule. The Schedule itself is not subject to page limits. The offeror shall provide information on the schedule using a critical path scheduling approach considering a Notice to Proceed date of October 14, 2016 that demonstrated an offerors understanding of the requirements. The Construction Schedule is an integrated and networked multi-layered schedule of program/project tasks. It identifies project events, accomplishment, and criteria and the expected dates of each. These dates are based on the calendar dates provided as the starting point and the logical flow of dates provided by calculating the addition of duration of all tasks using typical schedule networking tools. Each major task will be directly traceable to the requirements of the project. The NTP date for the schedule is for the purpose of evaluation only.

2.2.5. Subfactor 3: Experience with building to United States Green Building Council (USGBC) LEED® standards. Experience with building to United States Green Building Council (USGBC) LEED® standards. The Government will evaluate the number and magnitude of previous projects that achieved USGBC LEED® certification, or any level of recognition. Additionally, indicate the key construction personnel and demonstrate they have experience and required qualifications in assigned roles with building to USGBC LEED® standards. If no experience is indicated, the Government will evaluate the offeror’s proposed approach for overcoming the lack of experience. For any intended personnel who are not part of the contractor’s organization at the time of proposal submission, the Government will verify submission and proper completion of Exhibit B, “Subcontractor Information and Consent Form”.

2.3. PAST/PRESENT PERFORMANCE EVALUATION

2.3.1. The Government will evaluate the offeror’s record of past and current performance to ascertain the probability of successfully performing the required efforts of the Plans and Specifications. The past performance evaluation is an assessment of the offeror' s probability of meeting the minimum past performance solicitation requirements. This assessment is based on the offeror' s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements.