This document is an amendment to a solicitation for the construction of an Advanced Individual Training Complex at Fort Gordon. The amendment extends the response due date from April 14, 2021 to April 21, 2021. It also provides revised technical specifications and drawings. The construction project will include a battalion headquarters, barracks to house 600 soldiers, supporting facilities, and energy and security systems. The estimated value of the construction is between $25 million and $100 million. The Department of the Army Corps of Engineers Savannah District will evaluate bids following FAR Part 14 sealed bidding procedures. A price evaluation preference will be provided to HUBZone small businesses. The period of performance is 720 calendar days.

View the file

Other files

File Type Posted
C.04. W912HN21B3003 AIT Abstract-s1_Page_2.jpg JPG image
C.04. W912HN21B3003 AIT Abstract-s1_Page_1.jpg JPG image
AIT Bid Opening Roster.jpg JPG image
B.08. W912HN21B30030004 Amendment.pdf PDF
B.08. 21B3003_Amd04_Specs_Vol5_BNHQ.PDF PDF
B.08. 21B3003_Amd04_Specs_Vol4_BCOF.PDF PDF
B.08. 21B3003_Amd04_Specs_Vol1_BCOF.PDF PDF
B.08. W912HN-21-B-3003_DRAWINGS_VOL2_AMD4.pdf PDF
B.08. 21B3003_Amd04_Specs_Vol2_BCOF.PDF PDF
B.08. 21B3003-Amd04_Specs_Vol6_BNHQ.PDF PDF
B.08. W912HN21B30030004 Conformed Copy.pdf PDF
21B3003_Amd03_Specs_Vol5_BNHQ Rev3.PDF PDF
21B3003_Amd03_Specs_Vol6_BNHQ Rev3.PDF PDF
W912HN-21-B-3003_DRAWINGS_VOL2_AMD3.pdf PDF
W912HN-21-B-3003_DRAWINGS_VOL3_AMD3.PDF PDF
W912HN-21-B-3003_DRAWINGS_VOL4_AMD3.PDF PDF
W912HN-21-B-3003_DRAWINGS_VOL1_AMD3.pdf PDF
B.08. 21B3003_Amd03_Specs_Vol2_BCOF Rev3.PDF PDF
B.08. 21B3003_Amd03_Specs_Vol3_BCOF Rev2.PDF PDF
B.08. 21B3003_Amd03_Specs_Vol1_BCOF Rev3.PDF PDF
B.08. W912HN21B3003 0003 Conformed Copy.pdf PDF
B.08. 21B3003_Amd03_Specs_Vol4_BCOF Rev3.PDF PDF
W912HN-21-B-3003_DRAWINGS_VOL4_AMD2.PDF PDF
21B3003_Specs_Vol6_BNHQ Rev2.PDF PDF
21B3003_Specs_Vol5_BNHQ Rev2.PDF PDF
21B3003_Specs_Vol3_BCOF Rev1.PDF PDF
W912HN-21-B-3003_DRAWINGS_VOL3_AMD2.PDF PDF
W912HN21B3003 0002 Conformed copy.pdf PDF
21B3003_Specs_Vol2_BCOF Rev2.PDF PDF
W912HN-21-B-3003_DRAWINGS_VOL2_AMD2.pdf PDF
21B3003_Specs_Vol4_BCOF Rev2.PDF PDF
W912HN21B3003 0002 Amendment.pdf PDF
21B3003_Specs_Vol1_BCOF Rev2.PDF PDF
W912HN-21-B-3003_DRAWINGS_VOL3_AMD1.PDF PDF
21B3003_Specs_Vol2_BCOF_Rev1.PDF PDF
B.08. W912HN21B30030001 Site Visit IMG_0858.JPG JPG image
W912HN21B30030001 Amendment.pdf PDF
W912HN-21-B-3003_DRAWINGS_VOL1_AMD1.pdf PDF
21B3003_Specs_Vol5_BNHQ_Rev1.PDF PDF
W912HN21B3003 0001 Conformed Copy.pdf PDF
21B3003_Specs_Vol6_BNHQ_Rev1.PDF PDF
20B3003_Specs_Vol1_BCOF_Rev1.PDF PDF
21B3003_Specs_Vol4_BCOF_Rev1.PDF PDF
AIT Phase III Site Visit Sign-In Sheet_02Mar2021.pdf PDF
AIT Phase III Site Plans.pdf PDF
W912HN-21-B-3003_DRAWINGS_VOL2_AMD1.pdf PDF
20B3003_Specs_Vol1_BCOF.PDF PDF
21B3003_Specs_Vol7_Apps.PDF PDF
21B3003_Specs_Vol5_BNHQ.PDF PDF
21B3003_Specs_Vol4_BCOF.PDF PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

55516

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is:

A. Extend bid due date from 14 April 2021 to 21 April 2021. ProjNet w ill close for questions on 07 April 2021.

B. Updated specifications and draw ings.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 02-Apr-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HN21B3003

X 9B. DATED (SEE ITEM 11)

12-Feb-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

02-Apr-2021

CODE

USACE - SAVANNAH DISTRICT

100 W. OGLETHORPE AVE

SAVANNAH GA 31401

W912HN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HN21B3003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0003

A. CONTRACT CHANGES: Bid extension from 14 April 2021 to 21 April 2021.

B. TECHNICAL SPECIFICATION CHANGES: The revised Sections listed below (revised by Amendment No. 0003) are hereby added to and made a part of the solicitation. Revised or added information is underlined and deleted information is struck out. Revisions can be found in the appropriate volume of specifications by searching for an asterisk and amendment number (i.e., *1). The replaced Sections listed below (replaced and added by Amendment No. 0003) are hereby added to and made a part of the solicitation; such Sections are replaced and added in their entirety and changes are neither underlined nor struck out. Deleted Sections are also indicated below.

Barracks/COF:

Revised Sections Revised Sections (cont.) Replaced Sections Deleted Section 01 45 00 10 14 00.10 10 22 39 32 12 36.13 05 52 00 10 21 13 12 48 13 06 61 16 12 36 00 07 22 00 21 12 00 07 27 10 21 13 13 07 41 13 23 05 15 08 31 00 23 64 26 09 06 00 23 81 47 09 29 00 27 10 00 09 62 38 32 05 33 33 40 00

BN HQ:

Revised Sections Revised Sections (cont.)

05 50 13 10 14 00.10 05 52 00 12 36 00 07 27 10.0010 23 05 15 07 41 13 23 64 26 09 06 00 23 81 47 09 62 38 27 10 00

Note: Section 09 90 00 was revised by Amendment 0002, but was inadvertently omitted from the narrative.

C. CONTRACT DRAWINGS – File No. 721-21-04:

Volume 1:

Sheets GI001, GC003, CS101, CS102, CS105, CS201, CS501, CS502, CG105, CG202, MS101, ES101, ES102, ES103, ES104, ES105, ES106, ES601, and ES602, with Revision 1 dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Sheets CS503 and CE507, with Revision 2 dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Sheet ES105A, dated 31 March 2021, is hereby added to and made a part of the Contract Drawings.

Volume 2:

Sheets SB501, SB503, SB601, SF162, SF172, SF401, SF511, SF513, SF602, A-002, A-101, A-103, A-104, A-108, A-121, A-145, A-152, A-200, A-202, A-205, A-302, A-312, A-313, A- 314, A-315, A-316, A-401, A-404, A-408, A-409, A-423, A-503, A-505, A-605, A-629, A-630, A-703, A-801, A-802, A-803, A-804, A-805, A-901, I-104, I-603, I-608, I-612, I-617, I-621, FA001, FA115, FX001, FX101, FX102, FX103, FX104, FX105, FX106, FX107, FX108, FX109, FX110, FX111, FX112, FX113, FX114, FX115, FX116, FX117, FX118, FX119, FX501, FX502, and FX902, with Revision 1 dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Sheets GI001, GI002, SB102, SF122, A-110A, A-113A, A-116A, A-119, A-119A, A-301, A-411, A-426, A-521, A-600, I-505, I-601, I-602, I-604, I-605, I-606, I-607, I-609, I-610, I-611, I-613, I-614, I-615, I-616, I-618, I-619, I-620, I-622, I-623, and I-624, with Revision 2 dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Sheets A-601 and A-604, with Revision 3 dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Sheets SF132A, SF132B, SF402, SF403, SF516, SF517, SF518, and FA117, dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Sheet SF132 is hereby removed and is no longer a part of the Contract Drawings.

Volume 3:

Sheets GI001, PL101, PL105, PL118, PL122, PL134, PL407, PL601, PL901, PL902, PL910, PL911, MH101, MH102, MH111, MH112, MH121, MH122, MH131, MH132, MH141, MH142, MH143, MH505, MH602, MH603, MH604, MH605, MH606, MH607, MH608, MH702, MI807, MI811, MI812, MI815, MP142, EL115, EL118, EP102, EP104, EP116, EP118, EP601, EP602, EP607, EP611, EP612, EP613, EP614, EP615, EP616, EP621, EP622, EP623, EP624, EP631, EP632, EP633, EP634, EP641, EP642, EP643, EP644, EP651, EP652, EP653, EP654, EG101, T-102, MH601X, and MI801X, with Revision 1 dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Sheets MH103, MH104, MH113, MH123, MH133, MH601, and T-001, with Revision 2 dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Sheets MH151, MP151, and T-118, dated 31 March 2021, are hereby added to and made a part of the Contract Drawings.

Volume 4:

Sheets SB501 and T-001, with Revision 1 dated 19 March 2021, are hereby added to and made a part of the Contract Drawings.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 14-Apr-2021 01:00 PM to 21-Apr-2021 01:00 PM.

(End of Summary of Changes)