20R3009vol5 .pdf

PDF 3 MB Posted

Attached to
PN 88410 Construct Aircraft Maintenance Hangar, Hunter Army Airfield, Savannah, GA
Solicitation number
W912HN20R3009
Issued by

About this file

This document package describes a federal solicitation for the construction of an aircraft maintenance hangar at Hunter Army Airfield in Savannah, Georgia. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Savannah on October 29, 2020, with a proposal due date of December 15, 2020 at 1:00pm ET. The solicitation includes three drawings files and five specifications files covering the project scope of work. Offerors are required to construct a new aircraft maintenance hangar to the specifications provided. The solicitation provides all necessary details for offerors to submit a responsive proposal for award of the firm-fixed price construction contract.

View the file

Other files

File Type Posted
B.08 - W912HN20R3009 - AMD-0008.pdf PDF
B.08 - W912HN20R3009 - AMD0008CC.pdf PDF
B.08 - W912HN20R3009 - AMD0007.pdf PDF
B.08 - W912HN20R3009 - AMD0007CC.pdf PDF
20R3009vol1amd06.pdf PDF
B.08 - W912HN20R3009 - AMD0006.pdf PDF
B.08 - W912HN20R3009 - AMD0006 CC.pdf PDF
W912HN-20-R-3009_VOL3_AMD6.pdf PDF
20R3009vol1_AMD5.pdf PDF
20R3009vol3_AMD5.pdf PDF
B.08. W912HN20R30090005.pdf PDF
W912HN-20-R-3009_VOL2_AMD5.pdf PDF
20R3009vol2_AMD5.pdf PDF
W912HN-20-R-3009_VOL3_AMD5.pdf PDF
W912HN-20-R-3009_VOL1_AMD4.pdf PDF
W912HN-20-R-3009_VOL3_AMD4.pdf PDF
W912HN-20-R-3009_VOL2_AMD4.pdf PDF
20R3009vol3 .pdf PDF
20R3009vol1 .pdf PDF
20R3009vol4 .pdf PDF
B.08 - W912HN20R3009 - AMD0004 Conform Copy.pdf PDF
B.08 - W912HN20R3009 - AMD0004.pdf PDF
20R3009vol2 .pdf PDF
W912HN-20-R-3009_VOL1 Revision 1.pdf PDF
20R3009vol5 Revision 1.pdf PDF
B.08 - W912HN20R3009 - AMD0003.pdf PDF
W912HN-20-R-3009_VOL2 Revision 1.pdf PDF
20R3009vol3 Revision 1.pdf PDF
20R3009vol1 Revision 3.pdf PDF
20R3009vol1 ver 2.pdf PDF
B.08. W912HN20R30090002.pdf PDF
20R3009vol2 ver 2.pdf PDF
20R3009vol1.pdf PDF
B.08 W912HN20R30090001.pdf PDF
20R3009vol4.pdf PDF
20R3009vol2.pdf PDF
W912HN-20-R-3009_VOL2.pdf PDF
W912HN-20-R-3009_VOL1.pdf PDF
W912HN-20-R-3009_VOL3.pdf PDF
20R3009vol3.pdf PDF
20R3009vol1.pdf PDF
20R3009vol4.pdf PDF
20R3009vol5.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hunter AAF, Georgia

Solicitation Number

W912HN20R3009

Aircraft Maintenance Hanger Volume 5 of 5: Specification Divisions 27 - 41

PN 88410

October 2020

U.S. ARMY ENGINEER DISTRICT, SAVANNAH

CORPS OF ENGINEERS

100 WEST OGLETHORPE AVENUE

SAVANNAH, GEORGIA 31401-3640

US Army Corps of Engineers Savannah District

Construct Aircraft Maintenance Hangar 20R3009 Hunter AAF, GA

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 TOTAL BUILDING COMMISSIONING

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 DEMOLITION

02 82 00 ASBESTOS REMEDIATION

DI VI SI ON 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

03 42 13 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

CONSTRUCTION

DI VI SI ON 04 - MASONRY

04 20 00 UNIT MASONRY

DI VI SI ON 05 - METALS

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 41 16 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 14 00 FLUID-APPLIED WATERPROOFING

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 22 00 ROOF AND DECK INSULATION

PROJECT TABLE OF CONTENTS Page 1

07 27 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 41 13 METAL ROOF PANELS

07 42 13 METAL WALL PANELS

07 60 00 FLASHING AND SHEET METAL

07 61 14 STEEL STANDING SEAM ROOFING

07 81 00 * 2 DELETEDSPRAY-APPLIED FIREPROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DI VI SI ON 08 - OPENI NGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 33 13 COILING COUNTER DOORS

08 33 23 OVERHEAD COILING DOORS

08 34 16.10 STEEL SLIDING HANGAR DOORS

08 34 59 VAULT DOORS AND DAY GATES

08 34 73 SOUND CONTROL DOOR ASSEMBLIES

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DI VI SI ON 09 - FI NI SHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 62 38 STATIC-CONTROL FLOORING

09 65 00 RESILIENT FLOORING

09 67 23.13 STANDARD RESINOUS FLOORING

09 67 23.15 FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM

09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DI VI SI ON 10 - SPECI ALTI ES

10 11 00 *4 VISUAL DISPLAY UNITS

10 14 00.20 INTERIOR SIGNAGE

10 14 53 TRAFFIC SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 22 13 WIRE MESH PARTITIONS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 43 FIRE EXTINGUISHER ACCESSORIES

10 51 13 METAL LOCKERS

DI VI SI ON 11 - EQUI PMENT

11 11 33.51 AIRCRAFT WASH RACK

DI VI SI ON 12 - FURNI SHI NGS

PROJECT TABLE OF CONTENTS Page 2

12 24 13 ROLLER WINDOW SHADES

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

12 93 00 SITE FURNISHINGS

DI VI SI ON 13 - SPECI AL CONSTRUCTI ON

13 12 80 RELOCATABLE HAZARDOUS MATERIAL AND HAZARDOUS WASTE

STORAGE BUILDINGS

13 34 19 METAL BUILDING SYSTEMS

13 48 00 SEISMIC BRACING FOR MISCELLANEOUS EQUIPMENT

DI VI SI ON 14 - CONVEYI NG EQUI PMENT

14 24 23 HYDRAULIC PASSENGER ELEVATORS

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 13 25 HIGH-EXPANSION FOAM SYSTEM, FIRE PROTECTION

21 30 05.16 FIRE PUMPS AND ENCLOSURES

DI VI SI ON 22 - PLUMBI NG

22 00 00 PLUMBING, GENERAL PURPOSE

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 15 COMMON PIPING FOR HVAC

23 05 48.19 SEISMIC BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 23 00 REFRIGERANT PIPING

23 52 00 HEATING BOILERS

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS

23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 82 00 TERMINAL HEATING UNITS

DI VI SI ON 25 - I NTEGRATED AUTOMATI ON

25 05 11.21 CYBERSECURITY FOR FOAM APPLICATION SYSTEMS

25 05 11.23 CYBERSECURITY FOR HVAC SYSTEMS

25 05 11.26 CYBERSECURITY FOR LIGHTING SYSTEMS

25 05 11.28 CYBERSECURITY FOR FIRE ALARM/MASS NOTIFICATION SYSTEMS

25 05 11.30 CYBERSECURITY FOR ELEVATOR CONTROL SYSTEM

DI VI SI ON 26 - ELECTRI CAL

26 05 48 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

PROJECT TABLE OF CONTENTS Page 3

26 28 01 COORDINATED POWER SYSTEM PROTECTION

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER

26 36 01 NON-AUTOMATIC TRANSFER SWITCH (NATS)

26 37 00 SANITARY SEWER PUMP STATION EMERGENCY STAND-BY POWER

SYSTEM

26 41 00 LIGHTNING PROTECTION SYSTEM

26 42 14 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

26 42 15 CATHODIC PROTECTION SYSTEM (STEEL WATER TANKS)

26 51 00 LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 05 14 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 05 29 PROTECTIVE DISTRIBUTION SYSTEM (PDS) FOR SIPRNET

COMMUNICATION SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 51 16 PUBLIC ADDRESS SYSTEM

27 51 23.10 INTERCOMMUNICATION SYSTEM

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEMS

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

31 05 22 GEOTEXTILES USED AS FILTERS

31 11 00 CLEARING AND GRUBBING

31 31 16.13 CHEMICAL TERMITE CONTROL

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 11.51 PAINT REMOVAL FROM AIRFIELD PAVEMENTS

32 01 16.71 COLD MILLING ASPHALT PAVING

32 01 19.61 RESEALING OF JOINTS IN RIGID PAVEMENT

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 23 AGGREGATE BASE COURSES

32 11 23.23 BASE COURSE DRAINAGE LAYERS

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY

PAVEMENTS

32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 31 13 CHAIN LINK FENCES AND GATES

32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

32 92 19 SEEDING

32 92 23 SODDING

32 93 00 EXTERIOR PLANTS

DI VI SI ON 33 - UTI LI TI ES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

PROJECT TABLE OF CONTENTS Page 4

33 16 15 WATER STORAGE STEEL TANKS

33 16 23 GROUND-LEVEL STEEL WATER STORAGE TANKS

33 30 00 SANITARY SEWERAGE

33 31 23 SANITARY SEWER FORCE MAIN PIPING

33 32 13.13 PACKAGED SEWAGE LIFT STATIONS, WET WELL TYPE

33 40 00 STORM DRAINAGE UTILITIES

33 46 16 SUBDRAINAGE PIPING

33 51 15 NATURAL-GAS DISTRIBUTION PIPELINES

33 61 13.13 PREFABRICATED UNDERGROUND HYDRONIC ENERGY DISTRIBUTION

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DI VI SI ON 41 - MATERI AL PROCESSI NG AND HANDLI NG EQUI PMENT

41 22 13.13 BRIDGE CRANES

DI VI SI ON 46 - WATER AND WASTEWATER EQUI PMENT

46 25 14 OIL-WATER SEPARATORS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

SECTION TABLE OF CONTENTS

DIVISION 27 - COMMUNICATIONS

SECTION 27 05 14

CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

04/06

PART 1 GENERAL

1.1 REFERENCES

1.2 SUMMARY

1.3 SUBMITTALS

1.4 QUALIFICATIONS

1.4.1 Minimum Contractor Qualifications

1.4.2 Minimum Manufacturer Qualifications

1.5 DELIVERY, STORAGE, AND HANDLING

1.6 ENVIRONMENTAL REQUIREMENTS

1.7 EXTRA MATERIALS

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

2.1.1 Coaxial Cable

2.1.2 CATV Outlets

2.1.3 Outlet Boxes

2.1.4 Backboards

2.1.5 CATV Grounding Busbar

PART 3 EXECUTION

3.1 INSTALLATION

3.1.1 Horizontal Cable Installation

3.1.2 Riser Cable Installation

3.1.3 Cables

3.1.4 Pull Cords

3.2 TERMINATIONS

3.3 GROUNDING

3.4 TESTING

3.5 OPERATION AND MAINTENANCE MANUALS

-- End of Section Table of Contents --

SECTION 27 05 14 Page 1

SECTION 27 05 14

CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

04/06

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2020; TIA 20-1; TIA 20-2; TIA 20-3; TIA

20-4; TIA 20-5; TIA 20-5; TIA 20-6; TIA

20-9; ERTA 1; ERTA 2; ERTA 3) National Electrical Code

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-607 (2015c; Addendum 1 2017) Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises

1.2 SUMMARY

Provide a cable TV premises distribution system consisting of coaxial cables and connecting hardware to transport television signals throughout the building to user locations as indicated. Submit As-Built Drawings for the installed cable system showing the locations of cable terminations, including outlets, and location and routing of cables. The identifier for each termination and cable shall appear on the drawings. Include vertical riser diagrams, elevation drawings of CATV backboards, outlet face plate details for each outlet configuration, and descriptions and types of cables and conduits. Include a complete list of equipment and materials.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

As-Built Drawings ; G, RO

SD-03 Product Data

Coaxial Cable ; G, RO CATV Outlets ; G, RO Grounding Busbar ; G, RO Backboards ; G, RO Spare Parts Test Plan ; G, RO

SECTION 27 05 14 Page 2

Qualifications ; G, RO

SD-06 Test Reports

Testing ; G, RO

SD-07 Certificates

Materials and Equipment

SD-08 Manufacturer's Instructions

Manufacturer's Recommendations

SD-10 Operation and Maintenance Data

Operation and Maintenance Manuals

1.4 QUALIFICATIONS

Submit proof of the qualifications of the Contractor, Installers, and Manufacturers that will perform the work, and provide the specified products.

1.4.1 Minimum Contractor Qualifications

Work under this section shall be performed, and equipment shall be furnished and installed, by a qualified Contractor as defined herein. The Contractor shall have a minimum of two years of experience in the installation and testing of coaxial cable-based TV distribution systems and equipment. Installers assigned to the installation of this system or its components shall have a minimum of two years of experience in the installation of the specified coaxial cable and components.

1.4.2 Minimum Manufacturer Qualifications

The equipment and hardware provided under this contract shall be products of manufacturers that have a minimum of two years of experience in producing the types of systems and equipment specified.

1.5 DELIVERY, STORAGE, AND HANDLING

Protect equipment delivered and placed in storage from the weather, humidity and temperature variation, dirt and dust or other contaminants.

1.6 ENVIRONMENTAL REQUIREMENTS

Connecting hardware shall be rated for operation under ambient conditions of 32 to 140 degrees F and in the range of 0 to 95 percent relative humidity, non-condensing.

1.7 EXTRA MATERIALS

Submit spare parts data for each different item of material and equipment specified, after approval of detail drawings, not later than 2 months prior to the date of beneficial occupancy. The data shall include a complete list of parts, tools, test equipment and supplies, with current unit prices and source of supply, and a list of spare parts recommended for stocking. Provide the following additional materials required for

SECTION 27 05 14 Page 3 facility startup:

a. 10 of each type of connector used.

b. 10 of each type of cover plate, with connector.

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

Provide materials and equipment which are the standard products of a manufacturer regularly engaged in the manufacture of the products and that are the manufacturer's latest standard design that has been in satisfactory use for at least one year prior to installation. Where materials or equipment are specified to conform, be constructed or tested to meet specific requirements, submit certification that the items provided conform to such requirements. Certification by a nationally recognized testing laboratory that a representative sample has been tested to meet the requirements, or a published catalog specification statement to the effect that the item meets the referenced standard, is acceptable as evidence that the item conforms. Compliance with these requirements does not relieve the Contractor from compliance with other requirements of the specifications. Materials and equipment shall conform to the respective publications and other requirements specified below and to the applicable requirements of NFPA 70 . Cables shall be labeled on both ends with circuit number, room number, or other appropriate marking allowing for correct identification of the cable and its destination. Each faceplate shall be labeled with its function and a unique number to identify the cable run.

2.1.1 Coaxial Cable

Coaxial cable shall be RG-6/U, quad shield. Cable shall be label-verified. Cable jacket shall be factory marked at regular intervals identifying cable type. Cable shall be rated CMP, CMR, or CMG in accordance with NFPA 70 . Interconnecting cables shall be cable assemblies consisting of RG-6/U coaxial cable with male connectors at each end, provided in lengths determined by equipment locations as shown.

2.1.2 CATV Outlets

Provide flush mounted, 75-ohm, F-type connector outlet rated from 5 to 1000 MHz in standard electrical outlet boxes with mounting frame.

2.1.3 CATV Faceplates

Provide modular faceplates for mounting of CATV Outlets. Faceplate:

include designation labels and label covers for circuit identification.

Faceplate color: match outlet and switch coverplates.

2.1.3 Outlet Boxes

Electrical boxes for cable television outlets shall be 4-11/16 inch square by 2-1/8 inches deep with minimum 3/8 inch deep single or two gang plaster ring as shown. Conduits shall be minimum 1 inch .

2.1.4 Backboards

Provide void-free, fire-retardant, interior grade A-C plywood 3/4 inch thick with no added urea formaldehyde. Fire stamp shall be clearly

SECTION 27 05 14 Page 4 visible.

2.1.5 CATV Grounding Busbar

Provide corrosion-resistant grounding busbar suitable for indoor installation in accordance with TIA-607 . Busbars: plated for reduced contact resistance. If not plated, clean the busbar prior to fastening the conductors to the busbar and apply an anti-oxidant to the contact area to control corrosion and reduce contact resistance. Provide a secondary bonding busbar (SBB) at each location of CATV equipment. Provide grounding busbars with the following:

a. Predrilled copper busbar provided with holes for use with standard sized lugs.

b. Minimum dimensions of 0.25 in thick by 4 in wide x 20 in long.

c. Listed by a nationally recognized testing laboratory.

PART 3 EXECUTION

3.1 INSTALLATION

Install system components and appurtenances in accordance with NFPA 70 , manufacturer's instructions and as shown. Provide necessary interconnections, services, and adjustments required for a complete cable television distribution system, ready to connect to external television signal sources. Penetrations in fire-rated construction shall be firestopped in accordance with Section 07 84 00 FIRESTOPPING. Install conduits, outlets, and wiring in accordance with Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM. Cables and outlets shall be individually labeled and marked. Cables shall be installed in conduits. Cables shall not be installed in the same cable tray, utility pole compartment, or floor trench compartment with ac power cables or other communications cables.

3.1.1 Horizontal Cable Installation

The rated cable pulling tension shall not be exceeded. Cable shall not be stressed such that twisting, stretching or kinking occurs. Cable shall not be spliced. Cable shall not be run through structural members or in contact with pipes, ducts, or other potentially damaging items. Placement of cable parallel to power conductors shall be avoided, if possible; a minimum separation of 12 inches shall be maintained when such placement cannot be avoided. Cables shall be terminated unless shown otherwise.

Minimum bending radius shall not be exceeded during installation or once installed. Cable ties shall not be excessively tightened such that the transmission characteristics of the cable are altered.

3.1.2 Riser Cable Installation

The rated cable pulling tension shall not be exceeded. Riser cable support intervals shall be in accordance with manufacturer's recommendations . Where installation procedures, or any part thereof, are required to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations shall be provided prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received and approved. Cable bend radius shall not be less than ten times the outside diameter of the cable during installation and once installed. Maximum

SECTION 27 05 14 Page 5 tensile strength rating of the cable shall not be exceeded. Cable shall not be spliced.

3.1.3 Cables

Cables shall have a minimum of 6 inches of slack cable loosely coiled into the cable television outlet boxes. Minimum manufacturer's bend radius shall not be exceeded.

3.1.4 Pull Cords

Pull cords shall be installed in conduits serving the cable television premises distribution system which do not initially have cable installed.

3.2 TERMINATIONS

Cables and conductors shall sweep into termination areas; cables and conductors shall not bend at right angles. Manufacturer's minimum bending radius shall not be exceeded. Coaxial cables shall be terminated with appropriate connectors as required. Cable shield conductor shall be grounded to communications ground at only one point and shall not make electrical contact with ground anywhere else.

3.3 GROUNDING

The cable television distribution system ground shall be installed in the cable television entrance facility and in any auxiliary closet identified in Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM or otherwise indicated.

Equipment racks shall be connected to the electrical safety ground.

3.4 TESTING

Submit test reports in booklet form with witness signatures verifying execution of tests. The cable system testing documentation shall include the physical routing and a test report for each cable (end-to-end) from the installed outlet to the main termination point. Test reports shall be submitted within 7 days after completion of testing.Materials and documentation to be furnished under this specification are subject to inspections and tests.

a. Submit a Test Plan defining the tests required to ensure that the system meets technical, operational and performance specifications, 60 days prior to the proposed test date. The plan shall be approved before testing begins. The test plan shall identify the capabilities and functions to be tested, and include detailed instructions for the setup and execution of each test and procedures for evaluation and documentation of the results.

b. Components shall be terminated prior to testing.

c. Equipment and systems will not be accepted until the required inspections and tests have been made, demonstrating that the cable television premises distribution system conforms to the specified requirements, and that the required equipment, systems, and documentation have been provided.

d. After installation of the cable and before connecting system components, each cable section shall be end-to-end tested using a time domain reflectometer (TDR) to determine shorts, opens, kinks, and

SECTION 27 05 14 Page 6 other impedance discontinuities and their locations. Cable sections showing adverse impedance discontinuities (greater than 6 dB loss) shall be replaced at the Contractor's expense.

e. There shall be no cable splices between system components unless approved by the Government.

3.5 OPERATION AND MAINTENANCE MANUALS

Submit commercial, off-the-shelf manuals for operation, installation, configuration, and maintenance of products provided as a part of the cable television premises distribution system.

-- End of Section --

SECTION 27 05 14 Page 7

SECTION TABLE OF CONTENTS

DIVISION 27 - COMMUNICATIONS

SECTION 27 05 28.36

CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

05/17

PART 1 GENERAL

1.1 REFERENCES

1.2 PRE-INSTALLATION MEETINGS

1.3 SUBMITTALS

1.4 QUALITY CONTROL

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

2.2 FABRICATION

2.3 SUPPORTS

2.4 MATERIALS

PART 3 EXECUTION

3.1 INSTALLATION

3.1.1 Manufacturer's Instructions

3.1.2 Installation Drawings

3.1.3 Grounding

SECTION 27 05 28.36 Page 1

SECTION 27 05 28.36

CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

05/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products

ASTM A1008/A1008M (2016) Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA VE 1 (2017) Metal Cable Tray Systems

NEMA VE 2 (2013; ERTA 2016) Cable Tray Installation Guidelines

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2020; TIA 20-1; TIA 20-2; TIA 20-3; TIA

20-4; TIA 20-5; TIA 20-5; TIA 20-6; TIA

20-9; ERTA 1; ERTA 2; ERTA 3) National Electrical Code

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-569 (2015d) Commercial Building Standard for Telecommunications Pathways and Spaces

1.2 PRE-INSTALLATION MEETINGS

The Contracting Officer will schedule a pre-installation meeting within 30 days of contract award. Submit fabrication drawings for review and approval.

Submit manufacturer's product data for the following items:

a. Cable Trays

b. Supports

SECTION 27 05 28.36 Page 2

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Fabrication Drawings ; G, RO

Installation Drawings ; G, RO

SD-03 Product Data

Cable Trays ; G, RO

Supports ; G, RO

SD-08 Manufacturer's Instructions

Manufacturer's Instructions

1.4 QUALITY CONTROL

Comply with NEMA VE 1.

Comply with NEC, requirements that apply to the construction and installation of cable tray and cable channel systems (Article 392 NEC).

Provide products that are UL-classified and labeled with the UL classification mark.

PART 2 PRODUCTS

2.1 SYSTEM DESCRIPTION

Provide basket cable trays consisting of straight sections of continuous wire mesh, field formed horizontal and vertical bends, tees, drop outs, supports, and accessories.

Provide cable runway consisting of side stringers and welded cross members, bends, tees, drop outs, supports, and accessories.

2.2 FABRICATION

Submit fabrication drawings for cable trays. Ensure the drawings contain details showing the fabrication and assembly details performed in the factory.

Before assembly, use an antioxidant compound to coat the contact surfaces of trays. Ensure that the finishes of edges, fittings, and hardware are free from burrs and sharp edges. Include splice and end plates, dropouts, and miscellaneous hardware.

2.3 SUPPORTS

Permit both vertical and horizontal adjustment, where possible on supports

SECTION 27 05 28.36 Page 3 and hangers. Provide an adequate bearing surface for the tray on the horizontal and vertical tray supports, and ensure that the surface can accommodate holddown clamps or fasteners. Provide a means, other than friction, for securely fastening cable trays to supports.

Provide support for cable trays at intervals of no more than 6-foot .

Place supports for horizontal-elbow tray fittings within 2-feet of each fitting extremity and as recommended by the cable tray manufacturer.

Ensure that the cable trays can carry at least 150 pounds per linear foot when supported at 6-foot intervals. Ensure that the tray fittings have a load-carrying capacity that is equal to or greater than that of straight tray sections. Ensure that the radius of tray fittings is based on the minimum bending radius of the cables, as specified by the cable manufacturer.

2.4 MATERIALS

Provide cable trays constructed of steel in accordance with ASTM A1008/A1008M and that has a zinc coating which was applied after fabrication.

Provide hot-dipped galvanized steel trays with a finish in accordance with

ASTM A123/A123M .

PART 3 EXECUTION

Comply with NEMA VE 2 for cable tray installation.

3.1 INSTALLATION

Install cable trays in accordance with TIA-569 . Install cable trays parallel with or at right angles to ceilings, walls, and structural members. Support in accordance with manufacturer recommendations but at not more than 6 foot intervals. Ensure edges, fittings, and hardware are finished free from burrs and sharp edges. Terminate cable trays 10 inches from both sides of smoke and fire partitions. Install conductors run through smoke and fire partitions in 4 inch rigid steel conduits with grounding bushings, extending 12 inches beyond each side of partitions.

Seal conduit on both ends to maintain smoke and fire ratings of partitions. Firestop penetrations in accordance with Section 07 84 00 , FIRESTOPPING. Provide supports to resist forces of 0.5 times the equipment weight in any direction and 1.5 times the equipment weight in the downward direction.

3.1.1 Manufacturer's Instructions

Submit the manufacturer's instructions for cable trays, including special provisions required to install equipment components and system packages.

Ensure that the instructions specify impedances, hazards and safety precautions.

3.1.2 Installation Drawings

No later than 30 calendar days before shipment, submit installation drawings to the Contracting Officer for approval. Coordinate drawings with those being used for all other work in the immediate area to ensure that this other work does not conflict with the installation. Include the layout of the cable tray work and details on both horizontal and vertical

SECTION 27 05 28.36 Page 4 supports as specified in the paragraph SUPPORTS.

3.1.3 Grounding

Provide properly grounded cable trays by means that has a low-resistance conductor of sufficient capacity, and that is no smaller than No. 1/0 AWG copper. Bond the grounding conductor to cable tray sections and fittings by compatible bolted connections. Consider cable tray sections in tandem assembly as having electrical continuity when these sections are bonded with appropriate high-strength bolts. Provide permanent and continuous effective grounding with an impedance that is low enough to limit the potential above ground and to facilitate operation of overcurrent devices in the circuit. Provide grounding and bonding for cable trays in accordance with NFPA 70 .

SECTION 27 05 28.36 Page 5

SECTION TABLE OF CONTENTS

DIVISION 27 - COMMUNICATIONS

SECTION 27 05 29

PROTECTIVE DISTRIBUTION SYSTEM (PDS) FOR SIPRNET COMMUNICATION SYSTEMS

08/11

PART 1 GENERAL

1.1 REFERENCES

1.2 ADMINISTRATIVE REQUIREMENTS

1.2.1 Conditions

1.2.2 Construction Methods

1.2.3 PDS Design

1.2.4 PDS Design Technical Review

1.2.5 PDS Design Approval Request

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Manufacturer's Qualifications

1.4.2 Installer's Qualifications

1.4.3 Equipment

1.5 DELIVERY, STORAGE, AND HANDLING

PART 2 PRODUCTS

2.1 PDS CARRIER CONFIGURATION

2.1.1 Fittings and Components

2.1.2 Mounting Accessories

2.1.3 Through Wall Penetrating

2.1.4 Pull Boxes

2.2 User Drop Boxes

2.3 ENCLOSURES

PART 3 EXECUTION

3.1 EXAMINATION

3.2 PDS CARRIER ROUTING

3.2.1 General

3.2.2 Mounting Location Considerations

3.2.3 Adjacent Infrastructure Considerations

3.3 INSTALLATION

3.3.1 Mounting PDS Carrier

3.3.2 Enclosures

3.3.2.1 User Drop Box (UDB)

3.3.2.2 Other Enclosures

3.3.3 Mechanical Security

3.3.4 Carrier Support

3.4 FIELD QUALITY ASSURANCE

3.4.1 Physical Inspection

3.4.2 Magnetic Test

3.5 CLEANING AND PROTECTION

SECTION 27 05 29 Page 1

SECTION 27 05 29 Page 2

SECTION 27 05 29

PROTECTIVE DISTRIBUTION SYSTEM (PDS) FOR SIPRNET COMMUNICATION SYSTEMS

08/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

COMMITTEE ON NATIONAL SECURITY SYSTEMS (CNSS)

CNSSAM TEMPEST/1-13 (2014) RED/BLACK Installation Guidance

CNSSI-7003 (2015) Protective Distribution Systems

(PDS)

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-569-D (2015d; Add 2 2018; Add 1 2016) Telecommunications Pathways and Spaces

1.2 ADMINISTRATIVE REQUIREMENTS

1.2.1 Conditions

Notify the Contracting Officer if it is impossible to install SIPRNET PDS that complies with this section and references.

1.2.2 Construction Methods

Methods of construction that are not specifically described or indicated in the Contract will be subject to the control and approval of the Contracting Officer.

1.2.3 PDS Design

Include separate plans, elevations, sections, details, and attachments to other work. Indicate PDS carrier route, PDS carrier mounting height above finished floor, user drop box mounting height, and user drop box locations. Submit the PDS design to the cognizant Central TEMPEST Technical Authority (CTTA) and 7th Signal, for a technical review prior to the acquisition of material, through the installation Network Enterprise Center (NEC).

1.2.4 PDS Design Technical Review

Coordinate with the installation NEC and submit PDS design for technical review to CTTA and 7th Signal. Provide PDS carrier shop drawings, List of Material (LOM), and any other documentation required 90-days prior to PDS carrier installation.

1.2.5 PDS Design Approval Request

PDS design approving authority is the installation NEC/DOIM Designated

SECTION 27 05 29 Page 3

Approving Authority (DAA). Submit PDS design and CTTA technical review to the installation NEC to obtained PDS design approval from the DAA prior to installation.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

PDS Design ; G, DO PDS Design Technical Review ; G, DO PDS Design Approval ; G, DO

SD-03 Product Data

PDS Hardened Carrier ; G, DO

SD-04 Samples

PDS Carrier Surface Mounted Pull Boxes Fittings User Drop Boxes

SD-11 Closeout Submittals

User Drop Box Other Enclosures

1.4 QUALITY ASSURANCE

1.4.1 Manufacturer's Qualifications

Use firms regularly engaged in manufacture of secure raceway systems, boxes, and fittings of the types and sizes required, whose products have been in satisfactory use in similar service for not less than 3 years.

1.4.2 Installer's Qualifications

Installer is required to obtain certification from the manufacturer of secure raceway system and install secure raceway system in accordance with manufacturer's instructions.

1.4.3 Equipment

PDS Hardened Carrier shall meet or exceed guidelines as defined by CNSSI-7003 and shall be approved for use by U.S. Army. Submit manufacturer's descriptive data.

1.5 DELIVERY, STORAGE, AND HANDLING

Deliver secure raceways, conduit, fittings and components in factory labeled packages. Store and handle in strict compliance with manufacturer's written instructions and recommendations. Protect from

SECTION 27 05 29 Page 4 damage due to weather, excessive temperature, and construction operations.

PART 2 PRODUCTS

2.1 PDS CARRIER CONFIGURATION

Use secure raceway hardened carrier system. All components of the PDS shall be from a single manufacturer.

Provide secure raceway, fittings and components manufactured from ferrous material. Submit three 6-inch lengths of exposed type PDS carrier surface mounted conduit material, including component and fitting samples from the manufacturer, along with a LOM to the NEC/DOIM. Show finishes available (if applicable). PDS carrier that is comprised of Secure Raceway systems shall be:

a. Square or rectangular design with removable top covers or solid construction

b. 2 by 2 inch raceway and/or 2 by 6 inch raceway as required for cable fill capacity for horizontal backbone and vertical riser runs

c. 1 by 1 inch raceway for vertical user drops from horizontal backbone

d. Utilize elbows, couplings, fittings and connectors constructed from the same type of ferrous material as the secure raceway

e. Do not exceed 70 percent cable fill capacity of secure raceway with removable top cover in horizontal runs. TIA-569-D cable fill standards do not apply.

f. Do not exceed 60 percent fill capacity of secure raceway of solid construction. TIA-569-D cable fill standards do not apply.

2.1.1 Fittings and Components

Fittings and components include flat internal and external elbows, tees, couplings for joining raceway sections, nipples, wire clips, blank end fittings, and device mounting brackets and plates as applicable. Provide full capacity corner elbows and fittings to maintain a controlled 2-inch cable bend radius that meet the TIA-569-D specification for Fiber Optic and UTP cabling and exceeding the requirements for communications pathways.

2.1.2 Mounting Accessories

Mount secure raceways to the wall partition using 1-inch stand-off mounting brackets or spacers. Do not mount the secure raceways flush with the wall partition.

2.1.3 Through Wall Penetrating

a. Use trim plates threaded rigid pipe and locking rings on both the inside and outside of the raceway to secure the thru-wall penetration.

b. Provide dielectric breaks when penetrating secure room wall partitions.

c. Seal space between wall partition and through wall penetration using fire-stop material.

SECTION 27 05 29 Page 5

d. Fire-stop vertical risers and through wall penetrations of fire rated wall partitions after pulling cabling. Annotate firewall penetrations on PDS design.

2.1.4 Pull Boxes

a. Provide a pull point for secure raceway with removable top cover every 270 degree change in direction. Provide additional pull points in accordance with the manufacturer's instructions.

b. Provide a pull point for secure raceway of solid construction every 180 degree change in direction. Provide additional pull points in accordance with the manufacturer's instructions.

2.2 User Drop Boxes

Provide User Drop Boxes (UDB) (aka Secure User Workstation Enclosures, Drop Boxes, or Lockboxes) that are at least 7-inch high by 6-inch wide by 4-inch deep, tamper-resistant design constructed from 16 gauge steel with welded internal hinges, without pre-punched knockouts; and have a single door that has a built-in steel hasp that accepts a GSA approved changeable combination padlock. UDB shall accommodate a complete line of open connectivity outlets; modular inserts for Category 6 UTP or STP cable; fiber optic cabling with matching faceplates. STP cabling shall use shielded connectors, jacks, and patch panels. UDB with exterior hinges, pre-punched knockouts, and built-in locks are not acceptable.

2.3 ENCLOSURES

Provide equipment and pull-box enclosures constructed from 16 gauge steel;

have a single door with a built-in steel hasp or multi-point security hasp that accepts a GSA approved changeable combination padlock; without pre-punched knockouts; and a tamper-resistant design with welded internal hinges.

PART 3 EXECUTION

3.1 EXAMINATION

Examine the route and mounting locations of the raceways, boxes, distribution systems, supporting structure and accessories, to determine if conditions exist that will inhibit or prevent proper PDS installation.

Notify the Contracting Officer in writing of conditions detrimental to proper completion of the work (i.e. that would render the distribution system non-compliant with governing security regulations). Do not proceed with work until unsatisfactory conditions are corrected.

3.2 PDS CARRIER ROUTING

3.2.1 General

Route the PDS carrier in a tree type fashion.

a. Start the PDS horizontal backbone at the TR (SIPRNET TR or at IPS container location) with a single raceway or conduit sized accordingly (70 percent cable fill for secure raceway with removable top cover to contain CAT6 UTP cable runs.

SECTION 27 05 29 Page 6

b. Extend the PDS carrier from the PDS horizontal backbone throughout the facility to areas where SIPRNET access is required. Branch off the PDS horizontal backbone with a horizontal run to an area where the UDB is located.

c. Use vertical carrier runs from the horizontal run to the UDB.

TIA-569-D change in direction standard does not apply.

d. Maintain RED/BLACK cable separation in accordance with

CNSSAM TEMPEST/1-13.

e. Remove all burrs from carrier segments prior to installation.

f. Mark all simple distribution PDS (non hardened carriers) with (2) 1" red tape strips every 8 feet for inspection.

3.2.2 Mounting Location Considerations

a. Route the PDS carrier so that it does not cross windows or doorway openings; does not cross ceiling or wall mounted lighting fixtures;

does not obscure EXIT signs or fire alarms; and maintains a minimum 3-foot separation from fire sprinkler heads.

b. Bend (saddle or offset) conduit to follow wall contours and avoid wall obstacles (columns, pipes, etc.).

c. Use offset raceway to route secure raceway systems around columns and other wall partition obstacles.

d. Route PDS carrier so that it is surface mounted on interior walls wherever possible. Obtain exceptions from NEC prior to installation to mount PDS carrier on exterior wall partitions.

e. Route PDS carrier to maximized cable fills in horizontal runs and reduce the number of horizontal runs within the same space.

f. Use all-thread rod to mount the PDS carrier to true ceiling structure when routing across open areas (e.g. large hallways, open office areas, large rooms) that exceed 8 feet . Mounting the PDS carrier directly from suspended ceiling framework is not acceptable.

3.2.3 Adjacent Infrastructure Considerations

Keep conduit a minimum of 6 inches from parallel runs of flues and steam or hot water pipes. A minimum separation of 6-inches is required between the PDS carrier and water pipes, electrical wires, electrical pipes, plumbing, air conditioning, etc.

3.3 INSTALLATION

Strictly comply with manufacturer's installation instructions and recommendations and approved shop drawings. Coordinate installation with adjacent work to ensure proper clearances and compliance with project site manager and NEC.

3.3.1 Mounting PDS Carrier

Mount PDS carrier to a wall partition every 5 feet and/or within 18 inches of a section or component connection. Do not mount the PDS Carrier

SECTION 27 05 29 Page 7 directly to the wall surface.

a. Where wall mounting is unavailable, use appropriately sized all thread rods to mount PDS carrier to ceiling structure.

b. Do not mount PDS carrier to acoustical tile ceiling (ATC) framework.

c. Fasten PDS carrier and component items to building wall partitions using appropriate anchor and fastener for wall partition type.

d. Mount PDS carrier so that is is level and plumb along its route. The top edge of the carrier is horizontally level. Whenever possible maintain a minimum of 2-inches below the suspended ceiling line or the true ceiling line, whichever is lower.

e. Struts are not allowed to be used to mount secure raceway to wall partitions.

f. No more than 1/4 inch play is allowed on TOP CAP (top cover) and span cut per segment span.

g. Install the PDS carrier to permit visual inspections of its entire run.

h. Do not block doorways or access to emergency exits and do not inhibit the operation of windows.

i. Do not paint or cover the PDS carrier with wallpaper or other covering unless the paint is applied by the carrier manufacturer.

j. Bond PDS carrier to TGB or TMGB at point of origin.

3.3.2 Enclosures

Use of enclosures with pre-punched knockouts or external hinges is not acceptable. Fasten UDB, pull boxes, and enclosures to the wall partition using fasteners appropriate for the wall partition type.

3.3.2.1 User Drop Box (UDB)

a. Indicate UDB locations in the PDS Plan and on as-built drawings.

b. Size the UDB to terminate up to 6 cables.

c. Coordinate drop box location with furniture, fixtures and equipment that will be used in the vicinity (provided by others). Surface mount drop boxes on the wall partition approximately 4 to 5 feet above final floor line depending on room furniture height and layout or as specified on drawings.

3.3.2.2 Other Enclosures

Indicate enclosure type (user drop box, equipment, or pull-box) on shop and as-built drawings.

3.3.3 Mechanical Security

Apply a continuous bead of epoxy at all seams and joints of the carrier system. Seal pull box covers to the pull boxes around the mating surfaces after installation if they cannot be secured with GSA approved changeable

SECTION 27 05 29 Page 8 combination padlock.

3.3.4 Carrier Support

Support carrier with mounting brackets at intervals not to exceed 5 feet .

3.4 FIELD QUALITY ASSURANCE

3.4.1 Physical Inspection

Physically inspect all interfaces to ensure that they are tight and cannot turn. Also, physically inspect lock covers to ensure that the lock cap is properly sealed inside the locking mechanism.

3.4.2 Magnetic Test

Perform magnet test on all components (e.g. carrier raceway, pull boxes, enclosures, cover plates, etc) and fittings used to construct the carrier. Place a magnet on the carrier component or fitting to verify that construction is from ferrous material. Some alloys will fail the magnet test (e.g. 309 stainless steel) but meet the ferrous material requirements. Provide alloy material property list for components that fail magnet test to the Contracting Officer for approval. Use of components and fittings that fail the magnet test and are not made from ferrous material is not acceptable.

3.5 CLEANING AND PROTECTION

Clean exposed surfaces using non-abrasive materials and methods recommended by manufacturer. Protect raceways and boxes until acceptance.

SECTION 27 05 29 Page 9

SECTION TABLE OF CONTENTS

DIVISION 27 - COMMUNICATIONS

SECTION 27 10 00

BUILDING TELECOMMUNICATIONS CABLING SYSTEM

08/11

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 Campus Distributor (CD)

1.2.2 Building Distributor (BD)

1.2.3 Floor Distributor (FD)

1.2.4 Telecommunications Room (TR)

1.2.5 Entrance Facility (EF) (Telecommunications)

1.2.6 Equipment Room (ER) (Telecommunications)

1.2.7 Open Cable

1.2.8 Open Office

1.2.9 Pathway

1.3 SYSTEM DESCRIPTION

1.4 SUBMITTALS

1.5 QUALITY ASSURANCE

1.5.1 Shop Drawings

1.5.1.1 Telecommunications Drawings

1.5.1.2 Telecommunications Space Drawings

1.5.2 Telecommunications Qualifications

1.5.2.1 Telecommunications Contractor

1.5.2.2 Key Personnel

1.5.2.3 Minimum Manufacturer Qualifications

1.5.3 Test Plan

1.5.4 Regulatory Requirements

1.5.5 Standard Products

1.5.5.1 Alternative Qualifications

1.5.5.2 Material and Equipment Manufacturing Date

1.6 DELIVERY AND STORAGE

1.7 ENVIRONMENTAL REQUIREMENTS

1.8 WARRANTY

1.9 MAINTENANCE

1.9.1 Operation and Maintenance Manuals

1.9.2 Record Documentation

PART 2 PRODUCTS

2.1 COMPONENTS

2.2 OUTLET BOXES AND FLOOR OUTLET BOXES

2.3 TELECOMMUNICATIONS PATHWAY

2.4 TELECOMMUNICATIONS CABLING

2.4.1 Backbone Cabling

2.4.1.1 Backbone Copper

2.4.1.2 Backbone Optical Fiber

2.4.2 Horizontal Cabling

2.5 WIRELESS ACCESS POINT MOUNTING KIT

SECTION 27 10 00 Page 1

2.6 ANTENNA KIT

2.7 TELECOMMUNICATIONS SPACES

2.7.1 Backboards

2.7.2 Equipment Support Frame

2.7.3 Connector Blocks

2.7.4 Cable Guides

2.7.5 Patch Panels

2.7.5.1 Modular to 110 Block Patch Panel

2.7.5.2 Fiber Optic Patch Panel

2.8 TELECOMMUNICATIONS OUTLET/CONNECTOR ASSEMBLIES

2.8.1 Outlet/Connector Copper

2.8.2 Optical Fiber Adapters(Couplers)

2.8.3 Optical Fiber Connectors

2.8.4 Cover Plates

2.9 TELECOMMUNICATIONS GROUNDING BUSBAR

2.10 FIRESTOPPING MATERIAL

2.11 MANUFACTURER'S NAMEPLATE

2.12 FIELD FABRICATED NAMEPLATES

2.13 FACTORY REEL TESTS

PART 3 EXECUTION

3.1 INSTALLATION

3.1.1 Cabling

3.1.1.1 Backbone Cable

3.1.1.2 Horizontal Cabling

3.1.2 Telecommunications and Signal System Pathway

3.1.3 Service Entrance Conduit, Underground

3.1.4 Work Area Outlets

3.1.4.1 Terminations

3.1.4.2 Cover Plates

3.1.4.3 Cables

3.1.4.4 Pull Cords

3.1.5 Telecommunications Space Termination

3.1.5.1 Connector Blocks

3.1.5.2 Patch Panels

3.1.5.3 Equipment Support Frames

3.1.6 Electrical Penetrations

3.1.7 Grounding and Bonding

3.2 LABELING

3.2.1 Labels

3.2.2 Cable

3.2.3 Termination Hardware

3.3 FIELD APPLIED PAINTING

3.4 FIELD FABRICATED NAMEPLATE MOUNTING

3.5 TELECOMMUNICATIONS CABLING TESTING

3.5.1 Inspection

3.5.2 Verification Tests

3.5.3 Performance Tests

SECTION 27 10 00 Page 2

SECTION 27 10 00

BUILDING TELECOMMUNICATIONS CABLING SYSTEM

08/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D709 (2017) Standard Specification for Laminated Thermosetting Materials

ELECTRONIC COMPONENTS INDUSTRY ASSOCIATION (ECIA)

ECIA EIA/ECA 310-E (2005) Cabinets, Racks, Panels, and Associated Equipment

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 100 (2000; Archived) The Authoritative Dictionary of IEEE Standards Terms

INSULATED CABLE ENGINEERS ASSOCIATION (ICEA)

ICEA S-83-596 (2016) Indoor Optical Fiber Cables

ICEA S-90-661 (2012) Category 3, 5, & 5e Individually Unshielded Twisted Pair Indoor Cables for Use in General Purpose and LAN Communications Wiring Systems Technical Requirements

NATIONAL ELECTRICAL CONTRACTORS ASSOCIATION (NECA)

NECA/BICSI 568 (2006) Standard for Installing Building Telecommunications Cabling

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

ANSI/NEMA WC 66 (2013) Performance Standard for Category 6 and Category 7 100 Ohm Shielded and Unshielded Twisted Pairs

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2020; TIA 20-1; TIA 20-2; TIA 20-3; TIA

20-4; TIA 20-5; TIA 20-5; TIA 20-6; TIA

20-9; ERTA 1; ERTA 2; ERTA 3) National Electrical Code

SECTION 27 10 00 Page 3

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-455-21 (1988a; R 2012) FOTP-21 - Mating Durability of Fiber Optic Interconnecting Devices

TIA-526-7 (2015a) OFSTP-7 Measurement of Optical Power Loss of Installed Single-Mode Fiber Cable Plant

TIA-568.0 (2015d) Generic Telecommunications Cabling for Customer Premises

TIA-568.1 (2015d) Commercial Building Telecommunications Infrastructure Standard

TIA-568.2 (2018d) Balanced Twisted-Pair Telecommunications Cabling And Components Standard

TIA-568.3 (2016d) Optical Fiber Cabling And Components Standard

TIA-569 (2015d) Commercial Building Standard for Telecommunications Pathways and Spaces

TIA-570 (2012c) Residential Telecommunications Infrastructure Standard

TIA-606 (2017c) Administration Standard for the Telecommunications Infrastructure

TIA-607 (2015c; Addendum 1 2017) Generic Telecommunications Bonding and Grounding (Earthing) for Customer Premises

TIA-1152 (2009) Requirements for Field Test Instruments and Measurements for Balanced Twisted-Pair Cabling

TIA/EIA-598 (2014D; Add 2 2018) Optical Fiber Cable Color Coding

TIA/EIA-604-2 (2004b; R 2014) FOCIS 2 Fiber Optic Connector Intermateability Standard

U.S. FEDERAL COMMUNICATIONS COMMISSION (FCC)

FCC Part 68 Connection of Terminal Equipment to the Telephone Network (47 CFR 68)

UNDERWRITERS LABORATORIES (UL)

UL 50 (2015) UL Standard for Safety Enclosures for Electrical Equipment, Non-Environmental Considerations

UL 444 (2008; Reprint Apr 2015) Communications Cables

SECTION 27 10 00 Page 4

UL 467 (2013; Reprint Jun 2017) UL Standard for Safety Grounding and Bonding Equipment

UL 514C (2014; Reprint Nov 2018) UL Standard for Safety Nonmetallic Outlet Boxes, Flush-Device Boxes, and Covers

UL 969 (2017; Reprint Mar 2018) UL Standard for Safety Marking and Labeling Systems

UL 1666 (2007; Reprint Jun 2012) Test for Flame Propagation Height of Electrical and Optical-Fiber Cables Installed Vertically in Shafts

UL 1863 (2004; Reprint Sep 2016) UL Standard for Safety Communication Circuit Accessories

1.2 DEFINITIONS

Unless otherwise specified or indicated, electrical and electronics terms used in this specification shall be as defined in TIA-568.1 , TIA-568.2 , TIA-568.3 , TIA-569 , TIA-606 and IEEE 100 and herein.

1.2.1 Campus Distributor (CD)

A distributor from which the campus backbone cabling emanates.

(International expression for main cross-connect (MC).)

1.2.2 Building Distributor (BD)

A distributor in which the building backbone cables terminate and at which connections to the campus backbone cables may be made. (International expression for intermediate cross-connect (IC).)

1.2.3 Floor Distributor (FD)

A distributor used to connect horizontal cable and cabling subsystems or equipment. (International expression for horizontal cross-connect (HC).)

1.2.4 Telecommunications Room (TR)

An enclosed space for housing telecommunications…

This is the start of the file's text. The full file is on GovTribe.