PN 88410 Construct Aircraft Maintenance Hangar, Hunter Army Airfield, Savannah, GA
Solicitation number
W912HN20R3009
Issued by

About this file

This solicitation package includes specifications and drawings for the construction of an aircraft maintenance hangar at Hunter Army Airfield in Savannah, Georgia. The project involves demolishing an existing building and constructing a new hangar, along with associated site work. Proposals are due by December 15, 2020 at 1:00pm ET. The specifications cover requirements for demolition, hazardous materials abatement, concrete, masonry, metals, wood, thermal and moisture protection, openings, finishes, specialties, equipment, utilities, fire suppression, plumbing, HVAC, electrical, communications, security, and earthwork. Relevant agencies include the Department of the Army Corps of Engineers Savannah District.

View the file

Other files

File Type Posted
B.08 - W912HN20R3009 - AMD-0008.pdf PDF
B.08 - W912HN20R3009 - AMD0008CC.pdf PDF
B.08 - W912HN20R3009 - AMD0007.pdf PDF
B.08 - W912HN20R3009 - AMD0007CC.pdf PDF
20R3009vol1amd06.pdf PDF
B.08 - W912HN20R3009 - AMD0006.pdf PDF
B.08 - W912HN20R3009 - AMD0006 CC.pdf PDF
W912HN-20-R-3009_VOL3_AMD6.pdf PDF
20R3009vol1_AMD5.pdf PDF
20R3009vol3_AMD5.pdf PDF
B.08. W912HN20R30090005.pdf PDF
W912HN-20-R-3009_VOL2_AMD5.pdf PDF
20R3009vol2_AMD5.pdf PDF
W912HN-20-R-3009_VOL3_AMD5.pdf PDF
W912HN-20-R-3009_VOL1_AMD4.pdf PDF
W912HN-20-R-3009_VOL3_AMD4.pdf PDF
W912HN-20-R-3009_VOL2_AMD4.pdf PDF
20R3009vol3 .pdf PDF
20R3009vol5 .pdf PDF
20R3009vol1 .pdf PDF
20R3009vol4 .pdf PDF
B.08 - W912HN20R3009 - AMD0004 Conform Copy.pdf PDF
B.08 - W912HN20R3009 - AMD0004.pdf PDF
W912HN-20-R-3009_VOL1 Revision 1.pdf PDF
20R3009vol5 Revision 1.pdf PDF
B.08 - W912HN20R3009 - AMD0003.pdf PDF
W912HN-20-R-3009_VOL2 Revision 1.pdf PDF
20R3009vol3 Revision 1.pdf PDF
20R3009vol1 Revision 3.pdf PDF
20R3009vol1 ver 2.pdf PDF
B.08. W912HN20R30090002.pdf PDF
20R3009vol2 ver 2.pdf PDF
20R3009vol1.pdf PDF
B.08 W912HN20R30090001.pdf PDF
20R3009vol4.pdf PDF
20R3009vol2.pdf PDF
W912HN-20-R-3009_VOL2.pdf PDF
W912HN-20-R-3009_VOL1.pdf PDF
W912HN-20-R-3009_VOL3.pdf PDF
20R3009vol3.pdf PDF
20R3009vol1.pdf PDF
20R3009vol4.pdf PDF
20R3009vol5.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hunter AAF, Georgia

Solicitation Number

W912HN20R3009

Aircraft Maintenance Hanger Volume 2 of 5: Specification Divisions 02 - 07

PN 88410

October 2020

U.S. ARMY ENGINEER DISTRICT, SAVANNAH

CORPS OF ENGINEERS

100 WEST OGLETHORPE AVENUE

SAVANNAH, GEORGIA 31401-3640

US Army Corps of Engineers Savannah District

Construct Aircraft Maintenance Hangar 20R3009 Hunter AAF, GA

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 TOTAL BUILDING COMMISSIONING

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 DEMOLITION

02 82 00 ASBESTOS REMEDIATION

DI VI SI ON 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

03 42 13 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

CONSTRUCTION

DI VI SI ON 04 - MASONRY

04 20 00 UNIT MASONRY

DI VI SI ON 05 - METALS

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 41 16 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

07 14 00 FLUID-APPLIED WATERPROOFING

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 22 00 ROOF AND DECK INSULATION

PROJECT TABLE OF CONTENTS Page 1

07 27 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 41 13 METAL ROOF PANELS

07 42 13 METAL WALL PANELS

07 60 00 FLASHING AND SHEET METAL

07 61 14 STEEL STANDING SEAM ROOFING

07 81 00 * 2 DELETEDSPRAY-APPLIED FIREPROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DI VI SI ON 08 - OPENI NGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 33 13 COILING COUNTER DOORS

08 33 23 OVERHEAD COILING DOORS

08 34 16.10 STEEL SLIDING HANGAR DOORS

08 34 59 VAULT DOORS AND DAY GATES

08 34 73 SOUND CONTROL DOOR ASSEMBLIES

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DI VI SI ON 09 - FI NI SHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 62 38 STATIC-CONTROL FLOORING

09 65 00 RESILIENT FLOORING

09 67 23.13 STANDARD RESINOUS FLOORING

09 67 23.15 FUEL RESISTIVE RESINOUS FLOORING, 3-COAT SYSTEM

09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DI VI SI ON 10 - SPECI ALTI ES

10 11 00 *4 VISUAL DISPLAY UNITS

10 14 00.20 INTERIOR SIGNAGE

10 14 53 TRAFFIC SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 22 13 WIRE MESH PARTITIONS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 43 FIRE EXTINGUISHER ACCESSORIES

10 51 13 METAL LOCKERS

DI VI SI ON 11 - EQUI PMENT

11 11 33.51 AIRCRAFT WASH RACK

DI VI SI ON 12 - FURNI SHI NGS

PROJECT TABLE OF CONTENTS Page 2

12 24 13 ROLLER WINDOW SHADES

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

12 93 00 SITE FURNISHINGS

DI VI SI ON 13 - SPECI AL CONSTRUCTI ON

13 12 80 RELOCATABLE HAZARDOUS MATERIAL AND HAZARDOUS WASTE

STORAGE BUILDINGS

13 34 19 METAL BUILDING SYSTEMS

13 48 00 SEISMIC BRACING FOR MISCELLANEOUS EQUIPMENT

DI VI SI ON 14 - CONVEYI NG EQUI PMENT

14 24 23 HYDRAULIC PASSENGER ELEVATORS

DI VI SI ON 21 - FI RE SUPPRESSI ON

21 13 13 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

21 13 25 HIGH-EXPANSION FOAM SYSTEM, FIRE PROTECTION

21 30 05.16 FIRE PUMPS AND ENCLOSURES

DI VI SI ON 22 - PLUMBI NG

22 00 00 PLUMBING, GENERAL PURPOSE

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 15 COMMON PIPING FOR HVAC

23 05 48.19 SEISMIC BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 23 00 REFRIGERANT PIPING

23 52 00 HEATING BOILERS

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS

23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT

23 82 00 TERMINAL HEATING UNITS

DI VI SI ON 25 - I NTEGRATED AUTOMATI ON

25 05 11.21 CYBERSECURITY FOR FOAM APPLICATION SYSTEMS

25 05 11.23 CYBERSECURITY FOR HVAC SYSTEMS

25 05 11.26 CYBERSECURITY FOR LIGHTING SYSTEMS

25 05 11.28 CYBERSECURITY FOR FIRE ALARM/MASS NOTIFICATION SYSTEMS

25 05 11.30 CYBERSECURITY FOR ELEVATOR CONTROL SYSTEM

DI VI SI ON 26 - ELECTRI CAL

26 05 48 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 13 SWITCHBOARDS

PROJECT TABLE OF CONTENTS Page 3

26 28 01 COORDINATED POWER SYSTEM PROTECTION

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER

26 36 01 NON-AUTOMATIC TRANSFER SWITCH (NATS)

26 37 00 SANITARY SEWER PUMP STATION EMERGENCY STAND-BY POWER

SYSTEM

26 41 00 LIGHTNING PROTECTION SYSTEM

26 42 14 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)

26 42 15 CATHODIC PROTECTION SYSTEM (STEEL WATER TANKS)

26 51 00 LIGHTING

DI VI SI ON 27 - COMMUNI CATI ONS

27 05 14 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 05 29 PROTECTIVE DISTRIBUTION SYSTEM (PDS) FOR SIPRNET

COMMUNICATION SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 51 16 PUBLIC ADDRESS SYSTEM

27 51 23.10 INTERCOMMUNICATION SYSTEM

DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEMS

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 GEOTEXTILE

31 05 22 GEOTEXTILES USED AS FILTERS

31 11 00 CLEARING AND GRUBBING

31 31 16.13 CHEMICAL TERMITE CONTROL

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 11.51 PAINT REMOVAL FROM AIRFIELD PAVEMENTS

32 01 16.71 COLD MILLING ASPHALT PAVING

32 01 19.61 RESEALING OF JOINTS IN RIGID PAVEMENT

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 23 AGGREGATE BASE COURSES

32 11 23.23 BASE COURSE DRAINAGE LAYERS

32 12 13 BITUMINOUS TACK AND PRIME COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY

PAVEMENTS

32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 31 13 CHAIN LINK FENCES AND GATES

32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

32 92 19 SEEDING

32 92 23 SODDING

32 93 00 EXTERIOR PLANTS

DI VI SI ON 33 - UTI LI TI ES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

PROJECT TABLE OF CONTENTS Page 4

33 16 15 WATER STORAGE STEEL TANKS

33 16 23 GROUND-LEVEL STEEL WATER STORAGE TANKS

33 30 00 SANITARY SEWERAGE

33 31 23 SANITARY SEWER FORCE MAIN PIPING

33 32 13.13 PACKAGED SEWAGE LIFT STATIONS, WET WELL TYPE

33 40 00 STORM DRAINAGE UTILITIES

33 46 16 SUBDRAINAGE PIPING

33 51 15 NATURAL-GAS DISTRIBUTION PIPELINES

33 61 13.13 PREFABRICATED UNDERGROUND HYDRONIC ENERGY DISTRIBUTION

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DI VI SI ON 41 - MATERI AL PROCESSI NG AND HANDLI NG EQUI PMENT

41 22 13.13 BRIDGE CRANES

DI VI SI ON 46 - WATER AND WASTEWATER EQUI PMENT

46 25 14 OIL-WATER SEPARATORS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

SECTION TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 02 41 00

DEMOLITION

05/10

PART 1 GENERAL

1.1 REFERENCES

1.2 PROJECT DESCRIPTION

1.2.1 Definitions

1.2.1.1 Demolition

1.2.1.2 Demolition Plan

1.2.2 Demolition Plan

1.2.3 General Requirements

1.3 ITEMS TO REMAIN IN PLACE

1.3.1 Existing Construction Limits and Protection

1.3.2 Trees

1.3.3 Utility Service

1.4 BURNING

1.5 SUBMITTALS

1.6 QUALITY ASSURANCE

1.6.1 Dust and Debris Control

1.7 PROTECTION

1.7.1 Traffic Control Signs

1.7.2 Protection of Personnel

1.8 FOREIGN OBJECT DAMAGE (FOD)

1.9 RELOCATIONS

1.10 EXISTING CONDITIONS

PART 2 PRODUCTS

2.1 FILL MATERIAL

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

3.1.1 Structures

3.1.2 Utilities and Related Equipment

3.1.2.1 General Requirements

3.1.2.2 Disconnecting Existing Utilities

3.1.3 Chain Link Fencing

3.1.4 Paving and Slabs

3.1.5 Roofing

3.1.6 Masonry

3.1.7 Concrete

3.1.8 Airfield Lighting

3.1.9 Air Conditioning Equipment

3.1.10 Cylinders and Canisters

3.1.11 Mechanical Equipment and Fixtures

3.1.11.1 Preparation for Storage

3.1.11.2 Piping

SECTION 02 41 00 Page 1

3.1.11.3 Ducts

3.1.11.4 Fixtures, Motors and Machines

3.1.12 Electrical Equipment and Fixtures

3.1.12.1 Fixtures

3.1.12.2 Electrical Devices

3.1.12.3 Wiring Ducts or Troughs

3.1.12.4 Conduit and Miscellaneous Items

3.1.13 Elevators and Hoists

3.2 CONCURRENT EARTH-MOVING OPERATIONS

3.3 DISPOSITION OF MATERIAL

3.3.1 Title to Materials

3.3.2 Reuse of Materials and Equipment

3.3.3 Salvaged Materials and Equipment

3.3.4 Disposal of Ozone Depleting Substance (ODS)

3.3.4.1 Special Instructions

3.3.4.2 Fire Suppression Containers

3.3.5 Transportation Guidance

3.3.6 Unsalvageable and Non-Recyclable Material

3.4 CLEANUP

3.5 DISPOSAL OF REMOVED MATERIALS

3.5.1 Regulation of Removed Materials

3.5.2 Burning on Government Property

3.5.3 Removal to Spoil Areas on Government Property

3.5.4 Removal from Government Property

-- End of Section Table of Contents --

SECTION 02 41 00 Page 2

SECTION 02 41 00

DEMOLITION

05/10

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)

AHRI Guideline K (2009) Guideline for Containers for Recovered Non-Flammable Fluorocarbon Refrigerants

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO M 145 (1991; R 2012) Standard Specification for Classification of Soils and Soil-Aggregate Mixtures for Highway Construction Purposes

AASHTO T 180 (2017) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. DEFENSE LOGISTICS AGENCY (DLA)

DLA 4145.25 (Jun 2000; Reaffirmed Oct 2010) Storage and Handling of Liquefied and Gaseous Compressed Gases and Their Full and Empty Cylinders http://www.aviation.dla.mil/UserWeb/aviationengineering/HazInfo/

U.S. DEPARTMENT OF DEFENSE (DOD)

DOD 4000.25-1-M (2006) MILSTRIP - Military Standard Requisitioning and Issue Procedures

MIL-STD-129 (2014; Rev R) Military Marking for Shipment and Storage

SECTION 02 41 00 Page 3

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 70/7460-1 (2015; Rev L) Obstruction Marking and Lighting

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 61 National Emission Standards for Hazardous Air Pollutants

40 CFR 82 Protection of Stratospheric Ozone

49 CFR 173.301 Shipment of Compressed Gases in Cylinders and Spherical Pressure Vessels

1.2 PROJECT DESCRIPTION

1.2.1 Definitions

1.2.1.1 Demolition

Demolition is the process of wrecking or taking out any load-supporting structural member of a facility and removal of utilities and pavements,together with any related handling and disposal operations.

1.2.1.2 Demolition Plan

A Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.

1.2.2 Demolition Plan

Prepare a Demolition Plan and submit proposed demolition, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, and airfield lighting, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan shall be approved by Contracting Officer prior to work beginning.

1.2.3 General Requirements

Do not begin demolition until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site; do not allow accumulations on airfield pavements. The work includes demolition,, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.

1.3 ITEMS TO REMAIN IN PLACE

Take necessary precautions to avoid damage to existing items to remain in

SECTION 02 41 00 Page 4 place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.

Coordinate the work of this section with all other work indicated.

Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. Do not overload pavements to remain. Provide new supports and reinforcement for existing construction weakened by demolition, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

1.3.1 Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components as needed to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.

1.3.2 Trees

Protect trees within the project site which might be damaged during demolition, and which are indicated to be left in place, by a 4 foot high orange construction fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer.

1.3.3 Utility Service

Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, utilities serving each area of alteration or removal will be shut off by the Government and disconnected and sealed by the Contractor.

1.4 BURNING

The use of burning at the project site for the disposal of refuse and debris will not be permitted.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Demolition Plan ; G, RO

Existing Conditions

SD-07 Certificates

SECTION 02 41 00 Page 5

Notification ; G, RO

SD-11 Closeout Submittals

Receipts

1.6 QUALITY ASSURANCE

Submit timely notification of demolition projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61 , Subpart M.

Notify the Regional Office of the United States Environmental Protection Agency (USEPA), State's environmental protection agency, local air pollution control district/agency, and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6 .

Comply with the Environmental Protection Agency requirements specified.

Use of explosives will not be permitted.

1.6.1 Dust and Debris Control

Prevent the spread of dust and debris on airfield pavements and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep pavements as often as necessary to control the spread of debris that may result in foreign object damage potential to aircraft.

1.7 PROTECTION

1.7.1 Traffic Control Signs

a. Where pedestrian, driver and aircraft safety is endangered in the area of removal work, use traffic barricades with flashing lights.

Anchor barricades in a manner to prevent displacement by wind, jet or prop blast. Notify the Contracting Officer prior to beginning such work.

Provide a minimum of 2 FAA type L-810 steady burning red obstruction lights on temporary structures (including cranes) over 100 feet , but less than 200 ft, above ground level. The use of LED based obstruction lights are not permitted. For temporary structures (including cranes) over 200 ft above ground level provide obstruction lighting in accordance with FAA AC 70/7460-1 . Light construction and installation shall comply with FAA AC 70/7460-1 . Lights shall be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer. Maintain the temporary services during the period of construction and remove only after permanent services have been installed and tested and are in operation.

1.7.2 Protection of Personnel

Before, during and after the demolition work, continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without

SECTION 02 41 00 Page 6 sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.

1.8 FOREIGN OBJECT DAMAGE (FOD)

Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such materials that may appear on operational aircraft pavements due to the Contractor's operations. If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to control the spread of FOD potential debris. The barricade shall include a fence covered with a fabric designed to stop the spread of debris. Anchor the fence and fabric to prevent displacement by winds or jet/prop blasts.

Remove barricade when no longer required.

1.9 RELOCATIONS

Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.

1.10 EXISTING CONDITIONS

Before beginning any demolition work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.

PART 2 PRODUCTS

2.1 FILL MATERIAL

a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures.

b. Fill material shall conform to the definition of satisfactory soil material as defined in AASHTO M 145, Soil Classification Groups A-1, A-2-4, A-2-5 and A-3. In addition, fill material shall be free from roots and other organic matter, trash, debris, frozen materials, and stones larger than 2 inches in any dimension.

c. Proposed fill material must be sampled and tested by an approved soil testing laboratory, as follows:

SECTION 02 41 00 Page 7

Soil classification AASHTO M 145

Moisture-density relations AASHTO T 180 , Method B or D

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled.

Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified.

Materials shall be designated for reuse onsite whenever possible.

3.1.1 Structures

a. Remove existing structures indicated to be removed to grade. Interior walls, other than retaining walls and partitions, shall be removed to grade or to top of concrete slab on ground. Remove sidewalks, curbs, gutters and street light bases as indicated.

b. Demolish structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed.

Demolish concrete and masonry walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer.

c. Locate demolition equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing.

d. Building, or the remaining portions thereof, not exceeding 40 feet in height may be demolished by the mechanical method of demolition.

3.1.2 Utilities and Related Equipment

3.1.2.1 General Requirements

Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition work until all utility disconnections have been made. Shut off and cap utilities for future use, as indicated.

3.1.2.2 Disconnecting Existing Utilities

Remove existing utilities , as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to completeing any further work in that area. Remove meters and related equipment and deliver to a location on the station in accordance with instructions of the Contracting Officer.

SECTION 02 41 00 Page 8

3.1.3 Chain Link Fencing

Remove chain link fencing, gates and other related salvaged items scheduled for removal and transport to designated areas. Remove gates as whole units. Cut chain link fabric to 25 foot lengths and store in rolls off the ground.

3.1.4 Paving and Slabs

Sawcut and remove concrete and asphaltic concrete paving and slabs including aggregate base as indicated to a depth of 6 inches below existing adjacent grade. Provide neat sawcuts at limits of pavement removal as indicated. Pavement and slabs not to be used in this project shall be removed from the Installation at Contractor's expense.

3.1.5 Roofing

Remove existing roof system and associated components in their entirety down to existing roof deck. Remove roofing to effect the connections with new flashing or roofing.Remove roofing system and insulation without damaging the roof deck. Sequence work to minimize building exposure between demolition or deconstruction and new roof materials installation.

Note that roofing materials have not been tested for asbestos -containing materials.

3.1.6 Masonry

Sawcut and remove masonry so as to prevent damage to surfaces to remain and to facilitate the installation of new work. Where new masonry adjoins existing, the new work shall abut or tie into the existing construction as specified for the new work. Provide square, straight edges and corners where existing masonry adjoins new work and other locations.

3.1.7 Concrete

Saw concrete along straight lines to a depth of a minimum 2 inch . Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete.

3.1.8 Airfield Lighting

Remove existing airfield lighting as indicated and terminate in a manner satisfactory to the Contracting Officer. Remove edge lights, associated transformers and other electrical components as shown on the demolition plans and dispose of off station.

3.1.9 Air Conditioning Equipment

Remove air conditioning, refrigeration, and other equipment containing refrigerants without releasing chlorofluorocarbon refrigerants to the atmosphere in accordance with the Clean Air Act Amendment of 1990. Recover all refrigerants prior to removing air conditioning, refrigeration, and other equipment containing refrigerants and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)." Turn in salvaged Class I ODS refrigerants as specified in paragraph, "Salvaged Materials and Equipment."

SECTION 02 41 00 Page 9

3.1.10 Cylinders and Canisters

Remove all fire suppression system cylinders and canisters and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."

3.1.11 Mechanical Equipment and Fixtures

Disconnect mechanical hardware at the nearest connection to existing services to remain, unless otherwise noted. Disconnect mechanical equipment and fixtures at fittings. Remove service valves attached to the unit. Salvage each item of equipment and fixtures as a whole unit;

listed, indexed, tagged, and stored. Salvage each unit with its normal operating auxiliary equipment. Transport salvaged equipment and fixtures, including motors and machines, to a designated storage area as directed by the Contracting Officer. Do not remove equipment until approved. Do not offer low-efficiency equipment for reuse; provide to recycling service for disassembly and recycling of parts.

3.1.11.1 Preparation for Storage

Remove water, dirt, dust, and foreign matter from units; tanks, piping and fixtures shall be drained; interiors, if previously used to store flammable, explosive, or other dangerous liquids, shall be steam cleaned.

Seal openings with caps, plates, or plugs. Secure motors attached by flexible connections to the unit. Change lubricating systems with the proper oil or grease.

3.1.11.2 Piping

Disconnect piping at unions, flanges, valves, and fittings as required to reduce the pipe into straight lengths for practical storage. Store salvaged piping according to size and type. If the piping that remains can become pressurized due to upstream valve failure, end caps, blind flanges, or other types of plugs or fittings with a pressure gage and bleed valve shall be attached to the open end of the pipe to ensure positive leak control. Carefully dismantle piping that previously contained gas, gasoline, oil, or other dangerous fluids, with precautions taken to prevent injury to persons and property. Store piping outdoors until all fumes and residues are removed. Box prefabricated supports, hangers, plates, valves, and specialty items according to size and type.

Wrap sprinkler heads individually in plastic bags before boxing. Classify piping not designated for salvage, or not reusable, as scrap metal.

3.1.11.3 Ducts

Classify removed duct work as scrap metal.

3.1.11.4 Fixtures, Motors and Machines

Remove and salvage fixtures, motors and machines associated with plumbing, heating, air conditioning, refrigeration, and other mechanical system installations. Salvage, box and store auxiliary units and accessories with the main motor and machines. Tag salvaged items for identification, storage, and protection from damage. Classify non-porcelain broken, damaged, or otherwise unserviceable units and not caused to be broken, damaged, or otherwise unserviceable as debris to be disposed of by the Contractor. Salvage and crush porcelain plumbing fixtures unsuitable for

SECTION 02 41 00 Page 10 reuse.

3.1.12 Electrical Equipment and Fixtures

Salvage motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Salvage wiring systems and components. Box loose items and tag for identification. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.

3.1.12.1 Fixtures

Remove and salvage electrical fixtures. Salvage unprotected glassware from the fixture and salvage separately. Salvage incandescent, mercury-vapor, and fluorescent lamps and fluorescent ballasts manufactured prior to 1978, boxed and tagged for identification, and protected from breakage.

3.1.12.2 Electrical Devices

Remove and salvage switches, switchgear, transformers, conductors including wire and nonmetallic sheathed and flexible armored cable, regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items. Box and tag these items for identification according to type and size.

3.1.12.3 Wiring Ducts or Troughs

Remove and salvage wiring ducts or troughs. Dismantle plug-in ducts and wiring troughs into unit lengths. Remove plug-in or disconnecting devices from the busway and store separately.

3.1.12.4 Conduit and Miscellaneous Items

Salvage conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.

3.1.13 Elevators and Hoists

Remove elevators, hoists, and similar conveying equipment and salvage as whole units, to the most practical extent. Remove and prepare items for salvage without damage to any of the various parts. Salvage and store rails for structural steel with the equipment as an integral part of the unit.

3.2 CONCURRENT EARTH-MOVING OPERATIONS

Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition work in areas occupied by structures to be demolished until all demolition in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.

SECTION 02 41 00 Page 11

3.3 DISPOSITION OF MATERIAL

3.3.1 Title to Materials

Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.

3.3.2 Reuse of Materials and Equipment

Remove and store materials and equipment listed in the Demolition Plan to be reused or relocated to prevent damage, and reinstall as the work progresses. Capture re-use of materials in the diversion calculations for the project.

3.3.3 Salvaged Materials and Equipment

Remove materials and equipment that are listed in the Demolition Plan to be removed by the Contractor and that are to remain the property of the Government, and deliver to a storage site , as directed within 20 miles of the work site.

a. Salvage items and material to the maximum extent possible.

b. Store all materials salvaged for the Contractor as approved by the Contracting Officer and remove from Government property before completion of the contract. Capture salvaged materials in the diversion calculations for the project.

c. Remove salvaged items to remain the property of the Government in a manner to prevent damage, and packed or crated to protect the items from damage while in storage or during shipment. Items damaged during removal or storage must be repaired or replaced to match existing items. Properly identify the contents of containers. Deliver the following items reserved as property of the Government to the areas designated: .

d. Remove the following items reserved as property of the using service prior to commencement of work under this contract.

e. Remove historical items in a manner to prevent damage. Deliver the following historical items to the Government for disposition: Corner stones, contents of corner stones, and document boxes wherever located on the site.

f. Remove and capture all Class I ODS refrigerants in accordance with the Clean Air Act Amendment of 1990.

To view the web site for ODS, link to:

https://www.osd.mil/denix/Public/News/DLA/ODS/sect1.html

SECTION 02 41 00 Page 12

3.3.4 Disposal of Ozone Depleting Substance (ODS)

Class I and Class II ODS are defined in Section, 602(a) and (b), of The Clean Air Act. Prevent discharge of Class I and Class II ODS to the atmosphere. Place recovered ODS in cylinders meeting AHRI Guideline K suitable for the type ODS (filled to no more than 80 percent capacity) and provide appropriate labeling. Recovered ODS shall be removed from Government property and disposed of in accordance with 40 CFR 82 .

Products, equipment and appliances containing ODS in a sealed, self-contained system (e.g. residential refrigerators and window air conditioners) shall be disposed of in accordance with 40 CFR 82 . Submit Receipts or bills of lading, as specified. Submit a shipping receipt or bill of lading for all containers of ozone depleting substance (ODS) shipped to the Defense Depot, Richmond, Virginia.

3.3.4.1 Special Instructions

No more than one type of ODS is permitted in each container. A warning/hazardous label shall be applied to the containers in accordance with Department of Transportation regulations. All cylinders including but not limited to fire extinguishers, spheres, or canisters containing an ODS shall have a tag with the following information:

a. Activity name and unit identification code

b. Activity point of contact and phone number

c. Type of ODS and pounds of ODS contained

d. Date of shipment

e. National stock number (for information, call (804) 279-4525).

3.3.4.2 Fire Suppression Containers

Deactivate fire suppression system cylinders and canisters with electrical charges or initiators prior to shipment. Also, safety caps must be used to cover exposed actuation mechanisms and discharge ports on these special cylinders.

3.3.5 Transportation Guidance

Ship all ODS containers in accordance with MIL-STD-129 , DLA 4145.25 (also referenced one of the following: Army Regulation 700-68, Naval Supply Instruction 4440.128C, Marine Corps Order 10330.2C, and Air Force Regulation 67-12), 49 CFR 173.301 , and DOD 4000.25-1-M .

3.3.6 Unsalvageable and Non-Recyclable Material

Dispose of unsalvageable and non-recyclable noncombustible material in the disposal area located off the installation.

3.4 CLEANUP

Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

SECTION 02 41 00 Page 13

3.5 DISPOSAL OF REMOVED MATERIALS

3.5.1 Regulation of Removed Materials

Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified off the site . Storage of removed materials on the project site is prohibited.

3.5.2 Burning on Government Property

Burning of materials removed from demolished structures will not be permitted on Government property. Comply with Federal, State and local laws regulating the building and maintaining of brush and trash fires.

3.5.3 Removal to Spoil Areas on Government Property

Transport noncombustible materials removed from demolition of structures to designated spoil areas on Government property as directed by the COR.

Note that painted materials cannot be used as environmental stabilization materials.

3.5.4 Removal from Government Property

Transport waste materials removed from demolished structures, except waste soil, from Government property for legal disposal. Dispose of waste soil as directed.

-- End of Section --

SECTION 02 41 00 Page 14

SECTION TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 02 82 00

ASBESTOS REMEDIATION

11/18

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 ACM

1.2.2 Amended Water

1.2.3 Area Sampling

1.2.4 Asbestos

1.2.5 Asbestos Control Area

1.2.6 Asbestos Fibers

1.2.7 Asbestos Permissible Exposure Limit

1.2.8 Authorized Person

1.2.9 Background

1.2.10 Competent Person (CP)

1.2.11 Contractor

1.2.12 Disposal Bag

1.2.13 Disturbance

1.2.14 Encapsulation

1.2.15 Encapsulants

1.2.16 Friable Asbestos Material

1.2.17 Glovebag Technique

1.2.18 Government Consultant (GC)

1.2.19 HEPA Filter Equipment

1.2.20 Model Accreditation Plan (MAP)

1.2.21 Negative Pressure Enclosure (NPE)

1.2.22 NESHAP

1.2.23 Nonfriable Asbestos Material

1.2.24 Permissible Exposure Limits (PELs)

1.2.24.1 PEL-Time Weighted Average(TWA)

1.2.24.2 PEL-Excursion Limit

1.2.25 Personal Sampling

1.2.26 Private Qualified Person (PQP)

1.2.27 Qualified Person (QP)

1.2.28 TEM

1.2.29 Time Weighted Average (TWA)

1.2.30 Transite

1.2.31 Wetting Agent

1.2.32 Worker

1.3 REQUIREMENTS

1.3.1 Description of Work

1.3.2 Unexpected Discovery of Asbestos

1.3.3 Medical Requirements

1.3.3.1 Medical Examinations

1.3.3.2 Medical Records

1.3.4 Employee Training

1.3.5 Permits, Licenses, and Notifications

SECTION 02 82 00 Page 1

1.3.6 Environment, Safety and Health Compliance

1.3.7 Respiratory Protection Program

1.3.7.1 Respirator Program Records

1.3.7.2 Respirator Fit Testing

1.3.7.3 Respirator Selection and Use Requirements

1.3.8 Asbestos Hazard Control Supervisor

1.3.9 Hazard Communication

1.3.10 Asbestos Hazard Abatement Plan

1.3.11 Testing Laboratory

1.3.12 Landfill Approval

1.3.13 Transporter Certification

1.3.14 Medical Certification

1.4 SUBMITTALS

1.5 QUALITY ASSURANCE

1.5.1 Private Qualified Person Documentation

1.5.2 Competent Person Documentation

1.5.3 Worker's License

1.5.4 Contractor's License

1.5.5 Air Sampling Results

1.5.6 Protective Clothing Decontamination Facility Notification

1.5.7 Federal, State or Local Citations on Previous Projects

1.5.8 Preconstruction Conference

1.6 SECURITY

1.7 EQUIPMENT

1.7.1 Rental Equipment

PART 2 PRODUCTS

2.1 DUCT TAPE

2.2 DISPOSAL CONTAINERS

2.3 SHEET PLASTIC

2.3.1 Flame Resistant

2.3.2 Reinforced

2.4 MASTIC REMOVING SOLVENT

2.5 LEAK-TIGHT WRAPPING

2.6 VIEWING INSPECTION WINDOW

PART 3 EXECUTION

3.1 EQUIPMENT

3.1.1 Air Monitoring Equipment

3.1.2 Respirators

3.1.2.1 Respirators for Handling Asbestos

3.1.3 Exterior Whole Body Protection

3.1.3.1 Outer Protective Clothing

3.1.3.2 Work Clothing

3.1.3.3 Personal Decontamination Unit

3.1.3.4 Eye Protection

3.1.4 Regulated Areas

3.1.5 Load-out Unit

3.1.6 Warning Signs and Labels

3.1.6.1 Warning Sign

3.1.6.2 Warning Labels

3.1.7 Tools

3.1.8 Rental Equipment

3.1.9 Glovebags

3.1.10 Single Stage Decontamination Area

3.1.11 Decontamination Area Exit Procedures

3.2 WORK PROCEDURE

SECTION 02 82 00 Page 2

3.2.1 Building Ventilation System and Critical Barriers

3.2.2 Protection of Existing Work to Remain

3.2.3 Furnishings

3.2.4 Precleaning

3.2.5 Asbestos Control Area Requirements

3.2.5.1 Glovebag

3.2.5.2 Regulated Area for Class II Removal

3.2.6 Removal Procedures

3.2.6.1 Sealing Contaminated Items Designated for Disposal

3.2.6.2 Exposed Pipe Insulation Edges

3.2.7 Methods of Compliance

3.2.7.1 Mandated Practices

3.2.7.2 Control Methods

3.2.7.3 Unacceptable Practices

3.2.8 Class II Work Procedures

3.2.9 Specific Control Methods for Class II Work

3.2.9.1 Vinyl Flooring Materials and Mastic

3.2.9.2 Sealants and Mastic

3.2.10 Air Sampling

3.2.10.1 Sampling Prior to Asbestos Work

3.2.10.2 Sampling During Asbestos Work

3.2.10.3 Final Clearance Requirements, NIOSH PCM Method

3.2.10.4 Final Clearance Requirements, EPA TEM Method

3.2.10.5 Sampling After Final Clean-Up (Clearance Sampling)

3.2.10.6 Air Clearance Failure

3.2.11 Lock-Down

3.2.12 Site Inspection

3.3 CLEAN-UP AND DISPOSAL

3.3.1 Housekeeping

3.3.2 Title to Materials

3.3.3 Disposal of Asbestos

3.3.3.1 Procedure for Disposal

3.3.3.2 Asbestos Disposal Quantity Report

-- End of Section Table of Contents --

SECTION 02 82 00 Page 3

SECTION 02 82 00

ASBESTOS REMEDIATION

11/18

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP Z9.2 (2018) Fundamentals Governing the Design and Operation of Local Exhaust Ventilation Systems

ASTM INTERNATIONAL (ASTM)

ASTM D4397 (2016) Standard Specification for Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications

ASTM E1368 (2014) Visual Inspection of Asbestos Abatement Projects

COMPRESSED GAS ASSOCIATION (CGA)

CGA G-7 (2014) Compressed Air for Human Respiration; 6th Edition

INTERNATIONAL SAFETY EQUIPMENT ASSOCIATION (ISEA)

ANSI/ISEA Z87.1 (2015) Occupational and Educational Personal Eye and Face Protection Devices

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 701 (2019) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films

NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH)

NIOSH NMAM (2016; 5th Ed) NIOSH Manual of Analytical Methods

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA 340/1-90/018 (1990) Asbestos/NESHAP Regulated Asbestos Containing Materials Guidance

SECTION 02 82 00 Page 4

EPA 560/5-85-024 (1985) Guidance for Controlling Asbestos-Containing Materials in Buildings (Purple Book)

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.147 The Control of Hazardous Energy (Lock Out/Tag Out)

29 CFR 1926.51 Sanitation

29 CFR 1926.59 Hazard Communication

29 CFR 1926.103 Respiratory Protection

29 CFR 1926.200 Accident Prevention Signs and Tags

29 CFR 1926.1101 Asbestos

40 CFR 61-SUBPART A General Provisions

40 CFR 61-SUBPART M National Emission Standard for Asbestos

40 CFR 763 Asbestos

42 CFR 84 Approval of Respiratory Protective Devices

49 CFR 107 Hazardous Materials Program Procedures

49 CFR 171 General Information, Regulations, and Definitions

49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements

49 CFR 173 Shippers - General Requirements for Shipments and Packagings

UNDERWRITERS LABORATORIES (UL)

UL 586 (2009; Reprint Dec 2017) UL Standard for Safety High-Efficiency Particulate, Air Filter Units

1.2 DEFINITIONS

1.2.1 ACM

Asbestos Containing Materials.

1.2.2 Amended Water

Water containing a wetting agent or surfactant with a maximum surface tension of 0.00042 psi .

SECTION 02 82 00 Page 5

1.2.3 Area Sampling

Sampling of asbestos fiber concentrations which approximates the concentrations of asbestos in the theoretical breathing zone but is not actually collected in the breathing zone of an employee.

1.2.4 Asbestos

The term asbestos includes chrysotile, amosite, crocidolite, tremolite asbestos, anthophyllite asbestos, and actinolite asbestos and any of these minerals that has been chemically treated or altered. Materials are considered to contain asbestos if the asbestos content of the material is determined to be at least one percent.

1.2.5 Asbestos Control Area

That area where asbestos removal operations are performed which is isolated by physical boundaries which assist in the prevention of the uncontrolled release of asbestos dust, fibers, or debris.

1.2.6 Asbestos Fibers

Those fibers having an aspect ratio of at least 3:1 and longer than 5 micrometers as determined by National Institute for Occupational Safety and Health (NIOSH) Method 7400.

1.2.7 Asbestos Permissible Exposure Limit

0.1 fibers per cubic centimeter of air as an 8-hour time weighted average measured in the breathing zone as defined by 29 CFR 1926.1101 or other Federal legislation having legal jurisdiction for the protection of workers health.

1.2.8 Authorized Person

Any person authorized by the Contractor and required by work duties to be present in the regulated areas.

1.2.9 Background

The ambient airborne asbestos concentration in an uncontaminated area as measured prior to any asbestos hazard abatement efforts. Background concentrations for other (contaminated) areas are measured in similar but asbestos free locations.

1.2.10 Competent Person (CP)

A person meeting the requirements for competent person as specified in 29 CFR 1926.1101 including a person capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the authority to take prompt corrective measures to eliminate them, and is specifically trained in a training course which meet the criteria of EPA's Model Accreditation Plan ( 40 CFR 763 ) for project designer or supervisor, or its equivalent. The competent person must have a current State of Georgia asbestos contractors or supervisors license.

SECTION 02 82 00 Page 6

1.2.11 Contractor

The Contractor is that individual, or entity under contract to perform the herein listed work.

1.2.12 Disposal Bag

A 6 mil thick, leak-tight plastic bag, pre-labeled in accordance with 29 CFR 1926.1101 , used for transporting asbestos waste from containment to disposal site.

1.2.13 Disturbance

Activities that disrupt the matrix of ACM, crumble or pulverize ACM, or generate visible debris from ACM. Disturbance includes cutting away small amounts of ACM, no greater than the amount which can be contained in one standard sized glovebag or waste bag, not larger than 60 inches in length and width in order to access a building component.

1.2.14 Encapsulation

The abatement of an asbestos hazard through the appropriate use of chemical encapsulants.

1.2.15 Encapsulants

Specific materials in various forms used to chemically or physically entrap asbestos fibers in various configurations to prevent these fibers from becoming airborne. There are four types of encapsulants as follows which must comply with performance requirements as specified herein.

a. Removal Encapsulant (can be used as a wetting agent)

b. Bridging Encapsulant (used to provide a tough, durable surface coating to asbestos containing material)

c. Penetrating Encapsulant (used to penetrate the asbestos containing material encapsulating all asbestos fibers and preventing fiber release due to routine mechanical damage)

d. Lock-Down Encapsulant (used to seal off or "lock-down" minute asbestos fibers left on surfaces from which asbestos containing material has been removed).

1.2.16 Friable Asbestos Material

A term defined in 40 CFR 61-SUBPART M and EPA 340/1-90/018 meaning any material which contains more than 1 percent asbestos, as determined using the method specified in 40 CFR 763 , Polarized Light Microscopy (PLM), that when dry, can be crumbled, pulverized, or reduced to powder by hand pressure.

1.2.17 Glovebag Technique

Those asbestos removal and control techniques put forth in 29 CFR 1926.1101 .

1.2.18 Government Consultant (GC)

That qualified person employed directly by the Government to monitor, SECTION 02 82 00 Page 7 sample, inspect the work or in some other way advise the Contracting Officer. The GC is normally a private consultant, but can be an employee of the Government.

1.2.19 HEPA Filter Equipment

High efficiency particulate air (HEPA) filtered vacuum and exhaust ventilation equipment with a filter system capable of collecting and retaining asbestos fibers. Filters must retain 99.97 percent of particles

0.3 microns or larger as indicated in UL 586 .

1.2.20 Model Accreditation Plan (MAP)

USEPA training accreditation requirements for persons who work with asbestos as specified in 40 CFR 763 .

1.2.21 Negative Pressure Enclosure (NPE)

That engineering control technique described as a negative pressure enclosure in 29 CFR 1926.1101 .

1.2.22 NESHAP

National Emission Standards for Hazardous Air Pollutants. The USEPA NESHAP regulation for asbestos is at 40 CFR 61-SUBPART M .

1.2.23 Nonfriable Asbestos Material

Material that contains asbestos in which…