This document appears to be a Monthly Status Report template for a federal contract opportunity related to the Fuel Program Recurring Maintenance and Minor Repair (RMMR) program. The RMMR program provides maintenance and repair services for federal petroleum facilities and systems to sustain a robust fueling capability in support of the Department of Defense and Defense Logistics Agency.
The template covers key details such as service order overview, recurring maintenance overview, current available funds, quality and safety information, photographs, schedule, maintenance repair items, minor repairs, and points of contact. It also includes appendices for safety reports, photographs, and the schedule. This appears to be a standard reporting template for the contractor to provide monthly status updates on the execution of this contract.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX B – ATTACHMENT 2
Monthly Report Template
DLA Recurring Maintenance and Minor Repairs Program US Army Corps of Engineers, Engineering and Support Center, Huntsville
Monthly Status Report
Contract No. W912DY-13-G-XXXX Task Order No. XXXX
Task order title
Submission Date:
Submitted By:
Company Name
TABLE OF CONTENTS
1.0 SERVICE ORDER OVERVIEW
2.0 RECURRING MAINTENANCE OVERVIEW
3.0 CURRENT AVAILABLE FUNDS
4.0 QUALITY
5.0 SAFETY
6.0 PHOTOGRAPHS
7.0 SCHEDULE
8.0 TOP 10 MAINTENANCE REPAIR ITEMS
9.0 MINOR REPAIRS INCIDENTAL TO MAINTENANCE ACTIVITIES
10.0 MISCELLANEOUS MINOR REPAIRS
11.0 POINTS OF CONTACT
12.0 APPENDICES
Appendix A – Safety Report Appendix B – Photographs Appendix C – Schedule
1.0 SERVICE ORDER OVERVIEW
Service Order Overview- As of today current option
SO Category Number of SOs Total Cost Submitted to HNC Approved by HNC Executed Disapproved / Cancelled by HNC Awaiting HNC Approval In-Progress (have not been to HNC)
Service Order Overview- During this Period
SO Category Number of SOs Total Cost Submitted to HNC Approved by HNC Executed Disapproved / Cancelled by HNC
SO # General Description
NTP
Date
Completed Date days after
NTP
date
# days to complete
# days less than
# days over 30 (from
NTP)
Remarks
Every SO submitted during this period shall be included in this table.
2.0 RECURRING MAINTENANCE OVERVIEW
Table 1 Required & Completed Maintenance Visits Completed as of today current option
Site Name Code Phase Quarterly Semi-Annual Annual Required Completed Required Completed Required Completed
Table 2 Number & Total Costs of Maintenance Visits- During this period
Effort Number of Maintenance Visits this Month Total Cost Quarterly Maintenance Semi-Annual Maintenance Annual Maintenance
Table 1 Required & Completed Maintenance Visits Completed during this period
Site Name Code Phase Quarterly Semi-Annual Annual Required Completed Required Completed Required Completed
3.0 CURRENT AVAILABLE FUNDS
CLIN Amount Balance (Approved SOs)
Balance (Submitted SOs) Comments
4.0 QUALITY
Customer Feedback Surveys
Sixty-three (63) customer quality feedback surveys were sent for recurring maintenance and repair actions during the reporting period. As of the close of this reporting period, 20 surveys were received.
These surveys reflected neutral to positive comments on the JVs performance to date.
Question
Total Quantity of Responses
Yes No
Was work performed in a quality manner?
Was work performed safely?
Was work performed in a timely manner?
Did the prime contractor successfully manage the subcontractor?
Did contractor communicate with you prior to and upon completion of work?
Was the work area kept clean during and upon completion of work?
Did contractor have all necessary certifications?
Were there any issues with the work performed?
Did contractor arrive with all parts, materials, and tools needed to complete the repair?
The following comments were received on the surveys:
5.0 SAFETY
A. Reportable Incidents this period:
B. Safety training/briefings this period and (attendees):
Safety reports are included in Appendix A.
6.0 PHOTOGRAPHS
Representative photographs of maintenance repair work are included in Appendix B.
7.0 SCHEDULE
The updated schedule for anticipated RM and MR/ER work is included in Appendix C.
8.0 TOP 10 MAINTENANCE REPAIR ITEMS
Rank Maintenance/Repair Number
9.0 MINOR REPAIRS INCIDENTAL TO MAINTENANCE ACTIVITIES
Provide tracking of all repairs completed under this CLIN for each option year. Refer to Appendix H for list of items that should be tracked in this section.
10.0 MISCELLANEOUS MINOR REPAIRS
Provide quantity of repairs completed under this CLIN for each option year.
11.0 POINTS OF CONTACT
Contract Administrators Program Manager Project Manager Project Engineer Site Manager
12.0 APPENDICES
Appendix A – Safety Report Appendix B – Photographs Appendix C – Schedule
| 1.0 SERVICE ORDER OVERVIEW |
| 2.0 RECURRING MAINTENANCE OVERVIEW |
| 3.0 CURRENT AVAILABLE FUNDS |
| 4.0 QUALITY |
| 5.0 SAFETY |
| 6.0 PHOTOGRAPHS |
| 7.0 SCHEDULE |
| 8.0 TOP 10 MAINTENANCE REPAIR ITEMS |
| 9.0 MINOR REPAIRS INCIDENTAL TO MAINTENANCE ACTIVITIES |
| 10.0 MISCELLANEOUS MINOR REPAIRS |
| 11.0 POINTS OF CONTACT |
| 12.0 APPENDICES |
| Appendix A – Safety Report |
| Appendix B – Photographs |
| Appendix C – Schedule |