FY23 B1 PWS - Fort Stewart CM Appendix E Resident Management System 20230105.docx

DOCX document 23 KB Posted

Attached to
Fort Stewart – Hunter Army Airfield – GA
Solicitation number
W912DY-23-R-0006
Issued by

About this file

This document outlines requirements for a Resident Management System to be used under a construction contract at Fort Stewart, Hunter Army Airfield in Georgia. The selected contractor must install and utilize the latest version of the Resident Management System software within 7 days of the notice to proceed in order to facilitate electronic information exchange and overall contract management between the contractor and the Army Corps of Engineers. Key responsibilities for the contractor include entering administrative data, correspondence, equipment lists, payment requests, quality control information, safety reporting, submittals, schedules, and closeout documents into the system and keeping this information updated on at least a weekly basis throughout the contract period. Failure to properly utilize and maintain the system may result in corrective action from the contracting officer.

View the file

Other files

File Type Posted
Attachment 8_ QandA.xlsx XLSX spreadsheet
B.08_AMEND 04 .pdf PDF
TE2 PWS FY24 B1 Fort Stewart M and S TE2 Bay Door List 20231107.xlsx XLSX spreadsheet
Collective Bargaining Agreement Chatham.pdf PDF
TE 1PWS FY24 B1 Fort Stewart M and S TE1.1 FS Facility List 202307028.xlsx XLSX spreadsheet
TE5 PWS FY24 B1 Fort Stewart M and S TE5 Engineer Form 3394 20230801.pdf PDF
Collective Bargaining Agreement Liberty.pdf PDF
TE1 PWS FY24 B1 Fort Stewart M and S TE 1.2 HAAF Facility List 20230728.xlsx XLSX spreadsheet
TE4 PWS FY24 B1 Fort Stewart M and S TE4 Service Order Forms 20231107.pdf PDF
TE3 PWS FY24 B1 Fort Stewart M and S TE3 Monthly Progress Report Format 20231107.pdf PDF
B.08 AMEND 03.pdf PDF
Attachment 03 Fort Stewart M and S Pricing Workbook.xlsx XLSX spreadsheet
Attachment 01PWS FY24 B1 Fort Stewart M and S 20231107 with Appendices.pdf PDF
Collective Bargaining Agreement Bryan.pdf PDF
FY23 B1 PWS - Fort Stewart CM Appendix A Technical Exhibits 20230130.docx DOCX document
FY23 B1 PWS - Fort Stewart CM Appendix G Government Points of Contact 20230105.docx DOCX document
FY23 B1 PWS - Fort Stewart CM Appendix H Service Order Process 20230821 Rev1.docx DOCX document
FY23 B1 PWS - Fort Stewart CM Appendix B Safety Variance 20230105.pdf PDF
FY23 B1 PWS - Fort Stewart CM Appendix D Required Submittals 20230130.docx DOCX document
Projnet Q_A Amendment 2.pdf PDF
FY23 B1 PWS - Fort Stewart CM Appendix C PRS 20230309.docx DOCX document
FY23 B1 PWS - Fort Stewart CM 20230821 Rev1.docx DOCX document
Amended RFP W912DY23R0006.pdf PDF
FY23 B1 PWS - Fort Stewart CM Appendix F Applicable Codes Standards and Regulations.docx DOCX document
FY23 B1 PWS - Fort Stewart CM TE-3 Acronyms and Definitions 20230821 Rev1.docx DOCX document
Davis Bacon Act Effingham.pdf PDF
Davis Bacon Act Tattnall.pdf PDF
Davis Bacon Act Liberty.pdf PDF
Collective Bargaining Agreement Bryan.pdf PDF
Projnet Answer Amendment 1.pdf PDF
Collective Bargaining Agreement Chatham.pdf PDF
RFP W912DY23R0006 Amendment 1.pdf PDF
Collective Bargaining Agreement Liberty.pdf PDF
PPQ.pdf PDF
FY23 B1 PWS - Fort Stewart CM TE-6 Eng_Form_3394_Aug 2021.pdf PDF
SCA Chatham.pdf PDF
FY23 B1 PWS - Fort Stewart CM TE-1.2 HAAF Facility List 20230728.xlsx XLSX spreadsheet
SCA_Evans County 08012023.pdf PDF
RFP_W912DY-23-R-0006 Ft Stewart.pdf PDF
FY23 B1 PWS - Fort Stewart CM TE-4 Monthly Progress Report Format 20230130.pdf PDF
FY23 B1 PWS - Fort Stewart CM TE-1.1 FS Facility List 202307028.xlsx XLSX spreadsheet
FY23 B1 PWS w Appendices- Ft Stewart CM 20230728.pdf PDF
WageDetermination-SCA-20230628-025340.zip ZIP file
FSG CM only FY23 Price workbook 20230703.xlsx XLSX spreadsheet
FY23 B1 PWS - Fort Stewart CM TE-5 Service Order Forms 20230728.pdf PDF
FY23 B1 PWS - Fort Stewart CM TE-3 Acronyms and Definitions 20230130.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PWSAppendix EFort Stewart CM
Resident Management System
E.1Resident Management System (RMS).

The Government will use the Resident Management System (RMS) to assist in its monitoring and administration of this contract. The Government accesses the system using the Government Mode of RMS (RMS GM) and the Contractor accesses the system using the Contractor Mode (RMS CM). The term RMS will be used in the remainder of this section for both RMS GM and RMS CM. The joint Government-Contractor use of RMS facilitates electronic exchange of information and overall management of the contract. The Contractor shall use RMS for all submittals and supporting documentation, to include contract deliverables, requests for information (RFI), and pay requests for invoicing. The work of this section is not measured for payment. The Contractor is responsible for the work of this section, without any direct compensation other than the payment received for contract items.

E.1.1 RMS Software.

RMS is a web based application. Download, install, and be able to utilize the latest version of RMS within 7 calendar days of receipt of the Notice to Proceed. RMS software, user manuals, access and installation instructions, program updates and training information are available from the RMS website (https://rms.usace.army.mil). The Government and the Contractor will have different access authorities to the same contract database through RMS. The common database is updated automatically each time a user finalizes an entry or change.

E.1.2 Contract Database – Government.

The Government will enter the basic contract award data in RMS prior to granting the Contractor access. The Government entries into RMS will generally be related to submittal reviews, correspondence status, and Quality Assurance (QA) comments, as well as other miscellaneous administrative information.

E.1.3 Contract Database – Contractor.

Contractor entries into RMS establish, maintain, and update data throughout the duration of the contract. Contractor entries generally include prime and subcontractor information, reports, submittals, RFI's, schedule updates and payment requests. RMS includes the ability to import attachments and export reports in many of the modules, including submittals. The Contractor responsibilities for entries in RMS typically include the following items:

· Administration.

· Contractor Information. Enter all current Contractor administrative data and information into RMS within 7 calendar days of receiving access to the contract in RMS. This includes, but is not limited to, Contractor's name, address, telephone numbers, management staff, and other required items.

· Subcontractor Information. Enter all missing subcontractor administrative data and information into RMS CM within 7 calendar days of receiving access to the contract in RMS or within 7 calendar days of the signing of the subcontractor agreement for agreements signed at a later date. This includes name, trade, address, phone numbers, and other required information for all subcontractors. A subcontractor is listed separately for each trade to be performed.

· Correspondence. Identify all Contractor correspondence to the Government with a serial number. Prefix correspondence initiated by the Contractor's site office with "S". Prefix letters initiated by the Contractor's home (main) office with "H". Letters are numbered starting from 0001 (e.g., H-0001 or S-0001). The Government's letters to the Contractor will be prefixed with "C" or "RFP".

· Equipment. Enter and maintain a current list of equipment planned for use or being used on the jobsite, including the most recent and planned equipment inspection dates.

· Reports. Track the status of the project utilizing the reports available in RMS. The value of these reports is reflective of the quality of the data input. These reports include the Progress Payment Request worksheet, QC comments, Submittal Register Status, and QC worksheets.

· Request for Information (RFI). Create and track requests for information (RFI) in the RMS Administration Module for Government review and response.

· Finances.

· Pay Activity Data. Develop and enter a list of pay activities in conjunction with the project schedule. The sum of pay activities equals the total contract amount, including modifications. Each pay activity must be assigned to a Contract Line Item Number (CLIN). The sum of the activities assigned to a CLIN equals the amount of each CLIN.

· Payment Requests. Prepare all progress payment requests using RMS. Update the work completed under the contract at least monthly, measured as percent or as specific quantities. After the update, generate a payment request and prompt payment certification using RMS. Submit the signed prompt payment certification and payment request as well as supporting data either electronically or by hard copy. Unless waived by the Contracting Officer, a signed paper copy of the approved payment certification and request is also required and will govern in the event of discrepancy with the electronic version.

· Quality Control. Enter and track implementation of the QC System, QC testing, and warranties in RMS. Prepare weekly reports, identify and track deficiencies, document progress of work, and support other Contractor QC requirements in RMS. Maintain all data weekly. Insure that RMS reflects all quality control methods, tests, and actions contained within the Contractor Quality Control (CQC) Plan and Government review comments of same within 7 calendar days of Government acceptance of the CQC Plan.

· Quality Control Reports. The Contractor's Quality Control (QC) Weekly Report in RMS is the official report. The Contractor can use other supplemental formats to record QC data, but information from any supplemental formats are to be consolidated and entered into the RMS QC Weekly Report. Any supplemental information may be entered into RMS as an attachment to the report. QC Weekly Reports must be finalized and signed in RMS within 24 hours after the date covered by the report. Provide the Government a printed signed copy of the QC Weekly Report, unless waived by the Contracting Officer.

· Deficiency Tracking. Use the QC Daily Report Module to enter and track deficiencies. Deficiencies identified and entered into RMS by the Contractor or the Government will be sequentially numbered with a QC or QA prefix for tracking purposes. Enter each deficiency into RMS the same day that the deficiency is identified. Monitor, track, and resolve all QC and QA entered deficiencies. A deficiency is not considered to be corrected until the Government indicates concurrence in RMS.

· Quality Control Meetings. Maintain scheduled and actual dates and times of QC meetings in RMS. Worksheets for the QC meetings are generated within RMS.

· Labor and Equipment Hours. Enter labor and equipment exposure hours on a daily basis. Roll up the labor and equipment exposure data into a monthly exposure report.

· Accident/Safety Reporting. Both the Contractor and the Government enter safety related comments in RMS as a deficiency. The Contractor must monitor, track, and show resolution for safety issues in the QC Daily Report area of RMS. In addition, follow all reporting requirements for accidents and incidents as required in EM 385-1-1 and as required by any other applicable Federal, State or local agencies.

· Definable Features of Work. Enter each feature of work, as defined in the approved CQC Plan, into the RMS QC Module. A feature of work may be associated with a single or multiple pay activities, however a pay activity is only to be linked to a single feature of work.

· Activity Hazard Analysis. Import activity hazard analysis electronic document files into the RMS QC Module utilizing the document package manager.

· Submittal Management. Enter all current submittal register data and information into RMS within 7 calendar days of receiving access to the contract in RMS. Group electronic submittal documents into transmittal packages to send to the Government, except very large electronic files, samples, spare parts, mock ups, color boards, or where hard copies are specifically required. Track transmittals and update the submittal register in RMS on a daily basis throughout the duration of the contract. Submit hard copies of all submittals unless waived by the Contracting Officer.

· Schedule. Enter and update the contract project schedule in RMS by either manually entering all schedule data or by importing the Standard Data Exchange Format (SDEF) file.

· Closeout. Closeout documents, processes, and forms are managed and tracked in RMS by both the Contractor and the Government. Ensure that all closeout documents are entered, completed, and documented within RMS.

E.2 Implementation. Use of RMS as described in the preceding paragraphs is mandatory. Ensure that sufficient resources are available to maintain contract data within the RMS system. RMS is an integral part of the Contractor's required management of quality control.

E.3 Notification of Noncompliance. Take corrective action within 7 calendar days after receipt of notice of RMS non-compliance by the Contracting Officer.

Page 1 of 6 05 January 2023