Solicitation Amendment W912DS26RA0320001 SF 30.pdf

PDF 645 KB Posted

Attached to
Two Phase Design and Construction of the Port Monmouth Phase II, Contract 1 Mitigation Project
Solicitation number
W912DS26RA032
Issued by

About this file

This is Standard Form 30 (Amendment 0001) issued by the U.S. Army Corps of Engineers (USACE), New York District, for solicitation W912DS26RA032, dated 17 September 2026, effective 2 October 2026. The amendment responds to contractor inquiries regarding a two-phase design-build selection procedure.

Key changes include: (1) revision of the proposal due date and time to 19 October 2026, 2:00 p.m. Eastern Daylight Time (EDT) to resolve conflicting time-zone designations; (2) correction of footer markings throughout the Phase One and Phase Two design-build selection procedure documents; (3) incorporation of a revised Form A2 (Relative Specialized Experience); and (4) removal of hard-copy submission requirements with proposals to be submitted electronically. Additionally, the amendment clarifies that CUI markings inadvertently included in the Phase One and Phase Two procedure documents have been removed and documents have been revised accordingly. The amendment includes 11 questions and answers addressing proposal submission requirements, including clarification that the Proposal Cover Sheet, Table of Contents, and Form A1 do not count toward the 30-page Volume I, Tab A limit; confirmation that Form A1 satisfies the Pro Forma Data Sheet requirement; clarification that fifteen years is the correct project-experience recency period for Tab A, Factor 1; and confirmation that retired client representatives may complete Form A3 (Past Performance Questionnaire). Offerors must acknowledge receipt of the amendment by the specified proposal due date.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

J 1 5

0001 02 OCT 2026 N/A

W912DS

W2SD ENDIST NEW YORK

KO CONTRACTING DIVISION, 26 FEDERAL PLAZA ROOM 16 300

NEW YORK, NY 10278-0004

UNITED STATES

ADRIAN STAFFORD-BROWNE, EMAIL: ADRIAN.J.STAFFORD-BROWNE@USACE.

ARMY.MIL TELEPHONE: 917-790-8087

SCD: PAS:

W912DS26RA032

17 SEP 2026

SEE SECTION G - CONTRACT ADMINISTRATION DATA

The purpose of this amendment is to respond to contractor inquiries.

NOTE: Offerors must acknowledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the following methods: in the space provided on SF1442, by separate letter, or by signing block 15 below. FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208)

FRANCIS CASHMAN

02 OCT 2026

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

Miscellaneous text in this section has been added to:

The solicitation Documents are revised as follows:

Delete "Phase One of a Two-Phase Design-Build Selection Procedure" in its entirety and replace it with the attached revised "Phase One of a Two-Phase Design-Build Selection Procedure-- Amendment 0001." The revised document corrects the footer markings throughout, incorporates the revised Form A2, and revises the proposal-format instructions to remove hard-copy submission requirements.

Delete "Phase Two of a Two-Phase Design-Build Selection Procedure" in its entirety and replace it with the attached revised "Phase Two of a Two-Phase Design-Build Selection Procedure-- Amendment 0001." The revised document corrects the footer markings throughout and revises the proposal format instructions to remove hard-copy submission requirements.

Regarding the Bid Opening:

To resolve conflicting time-zone designations, the proposal due date and time is hereby revised to 19 October 2026, 2:00 p.m. Eastern Daylight Time (EDT).

RFI Disclaimer

Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors for information only and do not revise the solicitation, plans, or specifications.

Question 1: The RFP documents are marked CUI. Please confirm if this was accurately referenced for this solicitation?

Government Response 1: See Government Response 7.

Question 2: Does the Proposal Cover Sheet, Table of Contents and Form A1 Proposal Data Sheet count towards the Volume 1 Tab A page limit ?.

Government Response 2: The Proposal Cover Sheet, Table of Contents, and Form A1, Proposal Data Sheet, do not count toward the Volume I, Tab A, 30-page limit. The Proposal Cover Sheet may be submitted as the first page of Volume I, before Tabs A and B, but shall be considered part of Tab C for administrative purposes.

Question 3: Please confirm the instructions to submit 'original and copies' noted in the Section IV, PHASE ONE OF A TWO-PHASE DESIGN-BUILD SELECTION PROCEDURE, 5. Proposal Submission Requirements and Instructions B.5. General Instructions, Format Requirements is to be followed for this RFP or if it should be disregarded since we are instructed to transmit this RFP via e-mail. Please clarify.

Government Response 3: The Phase One of a Two-Phase Design-Build Selection Procedure has been revised to delete the hard-copy submission instructions. Offerors shall submit proposals electronically in accordance with the solicitation's electronic proposal-submission instructions.

Question 4: Please confirm if the Pro Forma Data Sheet referred to in the Section IV, PHASE ONE OF A TWO-PHASE DESIGN-BUILD SELECTION PROCEDURE, B.3. General Instructions refers to the Form A1 Proposal Data Sheet or is there is otherwise a specific form we are expected to use?

Government Response 4: The Pro Forma Data Sheet referenced in Section IV, Paragraph B.3, General Instructions, of the Phase One of a Two-Phase Design-Build Selection Procedure is Form

A1, Proposal Data Sheet, in Attachment F. Offerors shall use Form A1 to satisfy the Pro Forma Data Sheet requirement.

Question 5: Which Tab is Form A4 - Letter of Commitment to be included in?

Government Response 5: Form A4 shall be submitted in Tab C.

Question 6: Please confirm if the Form A2 - Relative Specialized Experience to be of Projects within the last 10 years (noted on Form A2) or within the last 15 years (noted in the Section IV, PHASE ONE OF A TWO-PHASE DESIGN-BUILD SELECTION PROCEDURE, D.Tab A - Submission Requirements. Please also note Tab B - Factor 2 requests performance recognition documents received within the last 10 years. Please clarify as there are differing periods noted in this RFP.

Government Response 6: The fifteen (15)-year requirement in Tab A, Factor 1, is correct. The conflicting ten (10)-year project-experience language has been removed from Form A2. Offerors shall use the fifteen (15)-year requirement for relevant specialized experience submitted under Tab A, Factor 1. The ten (10)-year requirement for performance-recognition documents under Tab B, Factor 2, remains unchanged.

Question 7: The file attachment "Phase one of a two phase design-build selection procedure.pdf" contains CUI markings. Please confirm whether the Government considers the information contained in this attachment to be CUI and whether receipt, storage, transmission, or use of this document by offerors requires compliance with any specific DFARS, NIST SP 800-171, CMMC, or other cybersecurity requirements.

Government Response 7: The Phase One and Phase Two of a Two-Phase Design-Build Selection Procedure documents were inadvertently marked as CUI. The documents have been revised to remove the inadvertent markings. See the revised attachments to this amendment.

Offerors are responsible for complying with all applicable solicitation provisions and clauses, and other DFARS provisions listed in the solicitation. The solicitation does not include DFARS 252.204- 7021 and does not establish a Cybersecurity Maturity Model Certification (CMMC) requirement or specify a CMMC level.

Question 8: Section 01 10 10 1.1.3.a states "Minimum qualifications for certain project personnel and staff below are outlined in the 30% Design Technical Specifications. As necessary, the DBC may submit qualifications for additional disciplines and subject matter experts (SMEs) as needed.

These must be approved by the COR." We cannot find any reference to minimum qualifications for a Project Manager or Project Superintendent in any of the reference documents provided. Please advise if there are minimum qualifications and what they are for these Key Project Personnel.

Government Response 8: The RFP does not require offerors to identify or submit qualifications for key personnel as part of either the Phase One or Phase Two proposal submissions. The Technical Specifications establish qualification requirements for certain contract-performance positions, including the Superintendent per Technical Specifications, Section 01 30 00, Paragraph 1.7.1, Superintendent Qualifications. The Phase One instructions state that technical specifications and drawings are not evaluated factors during solicitation; however, offerors are not relieved from meeting all technical or other requirements of the RFP.

Question 9: Form A3 requires the "Client" to fill out a portion of the form. In cases where all employees of that agency (client) with knowledge of a contractor's past performance are retired or no longer employed by the agency, who should be completing the form?

Government Response 9: A client representative with direct knowledge of the offeror's performance, including a retired former client representative, may complete Form A3, Past Performance Questionnaire (PPQ).

Question 10: Due to the limited time to send and receive completed "Form A3", we ask for a time extension.

Government Response 10: The Government is not extending the proposal due date at this time.

Offerors shall submit proposals by the date and time specified in the solicitation.

Question 11: Section IV, Tab A permits construction experience completed within the past fifteen

(15) years, while Form A2 requests projects constructed within the past ten (10) years. Please confirm the applicable project-experience recency period and revise Form A2 as appropriate.

Government Response 11: See Government Response 6.

File details come from the government source that posted it. Updated .