RFI log for posting 9.23.26.xlsx

XLSX spreadsheet 52 KB Posted

Attached to
Construction of the Power Generation with Microgrid at Joint Base McGuire-Dix-Lakehurst (JBMDL), New Hanover, NJ
Solicitation number
W912DS26BA032
Issued by

About this file

This is an RFI (Request for Information) log documenting 111 inquiries submitted by potential bidders regarding a design-bid-build solicitation for construction of a Power Generation with Microgrid system at Joint Base McGuire-Dix-Lakehurst (JBMDL) in Ocean County, New Jersey. The solicitation is issued by the U.S. Army Corps of Engineers (USACE) under Solicitation Number W912DS26BA032.

The project encompasses design and construction of a distributed energy resource (DER) microgrid system including three 500 kW/500 kWh battery energy storage systems (BESS), two natural gas-fired generators (Cummins C500N6B basis of design), a solar photovoltaic array (414.72 kW DC with Mission Solar modules and CPS inverter as basis of design), pad-mounted transformers, electrical switchgear, controls integration, and associated civil infrastructure. The microgrid control system is based on Schneider Electric's C&I Microgrid Flex ECC platform. The contract duration is 720 calendar days from Notice to Proceed, with a bid deadline initially set for September 28, 2026, extended to September 30, 2026 at 2:00 PM EDT. Liquidated damages are specified at $3,246 per calendar day of delay. Key technical clarifications addressed in the RFI log include BESS sizing confirmation (500 kW/500 kWh per unit; 1.5 MW/1.5 MWh total), correction of Davis-Bacon wage determination from Burlington County to Ocean County, New Jersey, cybersecurity requirements per UFC 4-010-06 and UFGS 25 05 11 standards, equipment specifications for meters (Siemens 9410 or Schneider 8650 preferred; SEL-735 rejected), temporary and permanent load bank requirements, utility coordination responsibilities, and site-specific conditions including geotechnical reports and environmental permitting requirements. The Government will provide prevailing utility rates (electric at $0.247610/kWh, water at $8.574110 per thousand gallons, sewage at $6.011510 per thousand gallons, natural gas at $2.779790 per CCF) but contractors are responsible for all utility connection installations at their cost. Responses confirm contractor responsibility for NJDEP Air Quality Permit modifications, field testing and inspections, Davis-Bacon compliance, and submittals required prior to mobilization, with coordination required through the Contracting Officer's Representative and JBMDL Civil Engineer Center.

View the file

Other files

File Type Posted
Bid Abstract Form Power Generation Microgrid Revised Final.pdf PDF
AF Meter Data Management Plan 20250610.pdf PDF
RFI-50 - ES103 - ENLARGED - ELECTRICAL SITE PLAN.pdf PDF
RFI-08 - SPEC 09 90 00.pdf PDF
RFI-22 - CS502 - SITE DETAILS - 2.pdf PDF
RFI-90 - SPEC 26 31 00.pdf PDF
RFI-16 - SPEC 32 31 13.pdf PDF
RFI-47 - ES503 - ELECTRICAL SITE DETAILS.pdf PDF
RFI-74 - EP701 - PARTIAL ONE-LINE DIAGRAM A - NEW WORK.pdf PDF
RFI-32 - M-702 - MECHANICAL CONTROLS ARCHITECTURE.pdf PDF
RFI-11 - M-501 - MECHANICAL DETAILS.pdf PDF
RFI-21 - SPEC 26 08 00.pdf PDF
RFI-17 - CS112 - SITE PLAN - AREA 2.pdf PDF
RFI-62 - SPEC 31 00 00.pdf PDF
01 45 35 - Attachment - Schedule_of_Special_Inspections.pdf PDF
Solicitation Amendment W912DS26BA0320001 SF 30.pdf.pdf PDF
RFI-75 - SPEC 26 12 19.pdf PDF
RFI-49 - ES102 - ENLARGED - ELECTRICAL SITE PLAN.pdf PDF
RFI-02 - SPEC 26 37 13.pdf PDF
RFI-63 - SPEC 32 11 26.pdf PDF
2026.09.03_Site Visit_Sign in for Power Gen_Lakehurst.pdf PDF
2026.09.03_Site Visit_Sign in for Power Gen_Lakehurst.pdf PDF
Power Gen w. microgrid bidder walkthrough packet.pdf PDF
A.03.09 Drawings - 100%.pdf PDF
Power Generation with Microgrid - Specifications - RTA_rev1.pdf PDF
Solicitation - W912DS26BA032.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Power Generation with Microgrid Lakehurst, Joint Base McGuire-Dix-Lakehurst, NJAE: Burns & McDonnell
UPDATED 23 SEPTEMBER 2026
99 / 107
RFI #FROMTASKEDDATE RECEIVEDQUESTIONRESPONSENOTESStatus
1Schweitzer Engineering Laboratories, Inc.JBMDL1-SepThe specifications identify approved electric meter models for AMRS integration. Would the Government accept the SEL-735 Power Quality and Revenue Meter as a U.S. manufactured equivalent, subject to the Contractor demonstrating compliance with all applicable metering, communications, cybersecurity, and AMRS compatibility requirements through the specified submittal and approval process?Only the meters that are explicitly listed in the Meter Data Management Plan will be authorized on the network by the Air Force Civil Engineer Center who oversees the entire AMRS network. So unfortunately no, that meter cannot be used.

JBMDL preference is for the Siemens 9410 meter. An alternative option is the Schneider 8650. However, we were recently informed that this meter will no longer be manufactured.

2 Willdan AE 2-Sep Battery Energy Storage System Capacity Discrepancy The solicitation appears to contain conflicting BESS sizing information.

The drawings identify three Battery Energy Storage Systems rated at approximately 500 kW / 500 kWh each (total nominal capacity approximately 1.5 MWh).

However, Specification Section 26 37 appears to identify each BESS as approximately 500 kW / 1.5 MWh (total nominal capacity approximately 4.5 MWh).

Question:

Please confirm the required BESS power rating and energy-storage capacity for:

•each individual BESS unit,
•total system power capacity,
•total system energy capacity.

Reason for clarification:

The discrepancy materially affects equipment selection, footprint, fire protection requirements, controls integration, commissioning requirements, and project pricing. Each individual BESS: 500KW/KWH Total System Power Capacity: 1.5MW Total System Energy Capacity: 1.5MWH

Spec section to be updated for clarityUpdated spec/dwg included
3WilldanCT2-SepApplicable Davis-Bacon Wage Determination

The solicitation references a wage determination associated with Burlington County, New Jersey.

The project site appears to be located at Joint Base McGuire-Dix-Lakehurst in Ocean County, New Jersey.

Question:

Please confirm the applicable Davis-Bacon wage determination for this project and whether the current wage determination reference is correct. The Government acknowledges the inquiry regarding the geographic location of the project site at Joint Base McGuire-Dix-Lakehurst.

To ensure compliance with the Davis-Bacon Act and physical project requirements, the Government is issuing a revised Wage Determination. General Decision Number NJ20260039, dated 05/18/2026, for Ocean County, New Jersey, is hereby incorporated into this solicitation under Amendment 0004. Offerors must utilize these revised rates when preparing and submitting their final proposals.

4 Willdan CT/PM 2-Sep Site Walk Date Clarification The solicitation references a site visit as occurring on "Friday, 03 September 2026."

However, 03 September 2026 falls on a Thursday.

Question:

Please confirm the official date and time of the site walkthrough.Walk thru was held 9/3/26.
5WilldanAE/JBMDL2-SepExisting SCADA Integration Requirements

The specifications reference integration between the new microgrid control system and existing installation systems.

Question:

Please identify:

· Existing SCADA platform manufacturer

· Existing SCADA software version

· Existing communication protocols

· Existing cybersecurity boundary requirements

Will interface control documentation be made available to the successful contractor after award?Concerning existing cybersecurity boundary requirements; Any connections to the existing base EMCS must be coordinated with and approved by the JBMDL CECS ISSM (Christopher Loosa). JBMDL:currently, we do not have the information for the Scada system. Its still in engineering and being installedNo spec/drawing update required.
6WilldanAE/JBMDL2-SepCybersecurity / RMF Requirements

The specifications include multiple references to cybersecurity support and RMF activities.

Question:

Please clarify:

· Required contractor cybersecurity deliverables

· Expected contractor participation in RMF activities

· Authority-to-Operate support requirements

· Government-furnished versus contractor-developed documentation responsibilities Cybersecurity / RMF Requirements The specifications include multiple references to cybersecurity support and RMF activities.

Question:

Please clarify:

· Required contractor cybersecurity deliverables

· Expected contractor participation in RMF activities

· Authority-to-Operate support requirements

· Government-furnished versus contractor-developed documentation responsibilitiesThe contractor/vendor will not be responsible for the ATO. The contractor’s/vendor’s responsibility is to deliver a hardened system in accordance with the UFC 4-010-06 and UFGS 25 05 11’s to support the System Owners ATO efforts. UFGS 25 05 11.01, 25 05 11.05 and 25 05 11.06 provide the cybersecurity requirements for the contractor. The documentation requirements for cybersecurity shall be IAW the UFGS 25 05 11.01, 25 05 11.05 and 25 05 11.06 and its requirted submittals.No spec/drawing update required.
7WilldanCT2-SepCPARS and Past Performance Questionnaires (PPQs)

The Supplementary Instructions to Bidders references Contractor Representatives are responsible for reviewing and commenting on evaluations submitted on the Contractor Performance Assessment Reporting System Question:

If a contractor does not have prime contractor CPARS ratings in the CPARS system, is an alternative available to submit PPQs from completed work not in CPARS. If so, please provide direction.This solicitation is an Invitation for Bid (IFB), and the award will be made to the responsible bidder with the lowest responsive bid. As per Federal Acquisition Regulation (FAR) Part 9, the Government will assess contractor responsibility, which includes a satisfactory performance record. While the Government primarily uses the Contractor Performance Assessment Reporting System (CPARS) to review past performance, contractors without CPARS ratings may be asked to provide information from which their past performance can be evaluated. If requested by the Contracting Officer, you may be required to furnish information on past performance, which could include Past Performance Questionnaires (PPQs) for recent and relevant projects.
8DAVID BOLAND, INCAE4-SepSpec: 09 06 00 – Schedules for Finishes, 09 90 00 – Paints and Coatings

Question: Paragraph 1.6.3 of Section 09 90 00 of the specifications requires the use of an SSPC QP 1 certified painter. Paragraph 2.3 of Section 09 60 00 of the specifications requires the use of an MPI 163 approved product for this project. MPI 163 is a Water-Based Emulsion, Semi-Gloss (MPI Gloss Level 5) Paint, suitable for both industrial and architectural exterior wood & metal surfaces.

SSPC QP 1 certified painters are certified to perform field coating applications on complex industrial and marine structures such as bridges, offshore drilling platforms, wastewater treatment facilities, and storage tanks. They are typically large metal structures requiring abrasive blast cleaning and spray painting. Additionally, the UFGS 09 90 00 – Paints and Coatings provides guidance for the designer, stating, “Use bracket option below concerning SSPC QR 1 only when industrial coatings are required”.

The painting work on this project does not seem to fall within the category of structures typically reserved for the requirements of SSPC QP 1. Additionally, This requirement will prohibit local experienced, small business painting subcontractors from being able to perform the work and will result in a substantial increase in the cost of this work, which will be reflected in the prime contractors’ bids submitted to the Government.

Based on the explanations provided above, will the Government please remove the requirement for the use of SSPC QP 1 certified painting contractors from the specifications for this project?Concur, will strike the requirement for SSPC QP 1.Updated spec/dwg included
9DAVID BOLAND, INCAE4-SepSpec: 01 45 35 Special Inspections
Question: Subpart 1.2 of Section 01 45 35 of the specifications states that the “Schedule of Special Inspections” is included as an attachment to the specification section; however, it is not attached. Instead, there are duplicate copies of the “Statement of Special Inspections” (as Attachments A and B). Please provide bidders with the “Schedule of Special Inspections.”Concur, this attachment has been sent to USACE for inclusion in the documents.Correct attachment sent to USACE for inclusion in the set.
10DAVID BOLAND, INCAE4-Sep1.Discipline: Structural

Sheet: S-501 Detail: K15 Spec:

Question: On Sheet S-501 Detail K15 calls out a typical exterior pad detail. Note 2 of this detail reads, “Dimension in any horizontal direction shall not exceed 11’-0””. Detail A1 on Sheet S-501 gives the equipment pad detail for the BESS and Generators.

The 16’ x 20’ Electrical Equipment Pad on Sheet CS111 and the 5’ x 15’ Electrical Switchgear Pad on Sheet CS112 are both too large to use the Typical Exterior Pad Detail. They are also neither the BESS or Generator.

Will the Government please clarify which Detail should be used for the Electrical Equipment Pad and Switchgear Pad?Detail K15 on sheet S-501 is to be used for Electrical Equipment Pad and Switchgear PadNo spec/drawing update required.
11DAVID BOLAND, INCAE4-Sep1.Discipline: Civil / Mechanical

Sheet: CS112 & M-501 Detail:

Spec:

Question: Sheet CS112 shows a 2” Natural Gas Line. Sheet M-501 Detail J14 calls out a 4” Natural Gas Line. Sheet CS112 also calls out an underground electric line as “Gas Line”

Will the Government please clarify if the Natural Gas Line is to be 2” or 4” and correct the “Gas Line” call-out?Confirmed 2". Gas line callout on CS112 is indicated correctly.Updated spec/dwg included
12DAVID BOLAND, INCUSACE DB4-Sep1.Discipline: Contracting

Sheet:

Detail:

Spec: 01 58 00 – Project Identification

Question: With regard to the Project Identification Sign on this project, Paragraph 1.4 of Section 01 58 00 of the specifications states, “Construct the sign in accordance with project sign detail, which can be downloaded at: http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/forms-graphics-tables.”

This link is broken and does not load. However, when navigating to the Whole Building Design Guide (WBDG) and navigating to the UFGS Forms, Graphics, and Tables page the project sign details that are available show many different sizes and styles of signs depending on the type of MILCON project and do not address a project safety sign at all.

Paragraph 1.4.1 also mentions both Navy and Air Force and refers to the signs being, “created in the design indicated,”

Paragraph 1.4.3 of Section 01 58 00 of this same specification refers us to EP 310-1-6a for the “construction project sign package.”

Will the Government please confirm our assumption that we are to utilize Publication EP-310-a-6a for the typical construction project sign package. Additionally, if we are to utilize the WBDG sign details please provide the exact sign type, size, and style required including the correct decal identification required. Follow the link provided in https://www.wbdg.org/dod/ufgs/ufgs-01-58-00 for Project sign details, attachment A. Refer to EP-310-a-6a, section 16-1, 16-2 and 16-3, 16-4 for Project safe sign and related requirements.

Para 1.4.1 is referring to the logo. Please download the zip folder in the link provided to correctly locate the Air Force Logo.

13 DAVID BOLAND, INC CT 4-Sep 1. Discipline: Contacting Sheet:

Detail:

Spec:

Question: General Decision Number: NJ20260027 /7/28/2026 provided in the Solicitation is for the County of Burlington, NJ. Since this location of the Joint Base is located in Ocean County New Jersey, will the Government please provide the General Decision Number for Ocean County.

The Government acknowledges the inquiry regarding the geographic location of the project site at Joint Base McGuire-Dix-Lakehurst.

To ensure compliance with the Davis-Bacon Act and physical project requirements, the Government is issuing a revised Wage Determination. General Decision Number NJ20260039, dated 05/18/2026, for Ocean County, New Jersey, is hereby incorporated into this solicitation under Amendment 0004. Offerors must utilize these revised rates when preparing and submitting their final proposals.

14 DAVID BOLAND, INC PM 4-Sep 1. Discipline: Contracting Sheet:

Detail:

Spec: Standard Form 1442

Question: The solicitation provides 720 calendar days from the Notice to Proceed (“NTP”) to complete the project.

As the Government is aware, there is a substantial amount of specialized equipment and material that will be required to be provided by the Contractor, much of which will require a substantial amount of time to prepare/review/approve submittals and then fabricate and deliver before the physical work, integration, start-up, check-out, testing, and commissioning can be performed. Much of this specialized equipment and material will require months (and in some cases, over a year) to procure after approval of the submittals.

It is understood that the Contractor will be required to diligently begin the preparation/review/submission of the submittals upon the Government’s issuance of the NTP so that the fabrication of the equipment and materials required for the project will begin as soon as possible.

Will the Government allow the Contractor to schedule its physical mobilization to the project site and be able to schedule the commencement of the physical work commensurate with (and coordinated with) the delivery of the long lead-time equipment and materials, as well as the duration required to perform and complete the physical work and commissioning activities by no later than the contract completion date?The contractor is required to submit all required documents, plans, initial schedule submissions and more (follow the specifications) for approval and in coordination with the contracting officers representative many of which are requried prior to mobilization. Follow the specifications as its written.
15DAVID BOLAND, INCCT4-Sep1.Discipline: Contracting

Sheet:

Detail:

Spec: Standard Form 1442

Question: Will the Government please clarify the DPAS (Defense Priorities and Allocations System) rating for this contract?The solicitation does not currently assign a Defense Priorities and Allocations System (DPAS) rating to this contract. If a DPAS rating becomes necessary during the performance of the contract, it will be incorporated by the Contracting Officer via a contract modification.
16DAVID BOLAND, INCAE4-Sep1.Discipline: Civil

Sheet:

Detail:

Spec: Section 32 31 13 – Chain Link Fences and Gates

Question: Subpart 2.2.1 – Fabric of Section 32 31 13 of the specifications states, “Provide fabric consisting of wires woven into a 1 inch diamond mesh.”

It is unusual for the Government to specify “1-inch” mesh for this particular application of chain-link fences and gates; “2-inch” mesh is more commonly specified.

Will the Government please confirm that “1-inch diameter mesh” is in fact required for the permanent chain-link fences and gates for this project?2-inch diameter mesh is acceptable for use on this project. Specification to be updated accordingly.Updated spec/dwg included
17DAVID BOLAND, INCAE4-Sep1.Discipline: Civil

Sheet: CS112 Detail:

Spec:

Question: There are existing pavement markings located where the existing asphalt pavement is required to be cut and patched for the electrical duct bank routed between the existing electrical manhole (“A7”) and the new pad-mounted medium voltage switch (“SW-1”).

Is the Contractor required to patch these existing pavement markings and, if so, are the pavement markings required to be paint or thermoplastic?Note added to CS112: "Replace pavement markings in kind with marking materials that meet NJDOT specifications."Updated spec/dwg included
18DAVID BOLAND, INCAE4-Sep1.Discipline: Civil

Sheet: CD111 Detail:

Spec:

Question: General Sheet Note 4 on Sheet ID CD111 of the contract drawings states, “Prior to installation of PV array, remove all vegetation from paved surfaces, apply weed repellent and seal all cracks in existing pavement.”

Will the Government please provide the bidders with the assumed quantity (i.e., linear feet) of cracks that will require sealing for which the bidders are to base their bids?Assume 6,000 LF of crack sealing in existing pavement area.No spec/drawing update required.
19DAVID BOLAND, INCAE4-Sep1.Discipline: Civil

Sheet:

Detail:

Spec: Section 32 11 26 – Hot-Mix Bituminous Base Course for Roads and Streets

Question: Subpart 2.5 – Recycled Asphalt Pavement of Section 32 11 26 of the specifications states, “RAP is not permitted.”

Will the Government please confirm that recycled asphalt pavement is in fact not permitted for the base course asphalt for this project?Confirmed, RAP is not permitted for use on this project.No spec/drawing update required.
20DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet:

Detail:

Spec: Section 26 08 00 – Apparatus Inspection and Testing

Question: Subpart 1.4.1 – Qualifications of Section 26 08 00 of the specifications states, “Organization must be independent of the supplier, manufacturer, and installer of the equipment. The organization must be a first-tier subcontractor. No work required by this section of the specification may be performed by a second-tier subcontractor.”

Will the Government please confirm that the qualified testing organization for this project will in fact be required to be “independent of the supplier, manufacturer, and installer of the equipment,” “a first-tier subcontractor,” and not “a second-tier subcontractor?”Confirmed , the qualified testing organization must be independent of the supplier, manufacturer, and installer of the equipment.No spec/drawing update required.
21DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet:

Detail:

Spec: Section 26 08 00 – Apparatus Inspection and Testing

Question: Subpart 1.2 – Related Requirements of Section 26 12 19 – Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers of the specifications states, “Section 26 08 00 APPARATUS INSPECTION AND TESTING applies to this section, with the additions and modifications specified herein.” However, Section 26 12 19 – Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers of the specifications is missing from the list of specification sections included within Subpart 3.1 of Section 26 08 00 of the specifications.

Will the Government please clarify if Section 26 12 19 – Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers of the specifications should be added to the list of specification sections included within Subpart 3.1 of Section 26 08 00 of the specifications?

Concur, updated.Updated spec/dwg included
22DAVID BOLAND, INCAE4-Sep1.Discipline: General

Sheet: CS502 Detail:

Spec: Section 01 50 00 – Temporary Construction Facilities and Controls

Question: Subparts 2.3.2, 2.3.3, and 3.6.2 of Section 01 50 00 of the specifications specify the that temporary chain-link fencing is to be “6 feet high.” However, details H1, H8, and H15 on Sheet ID CS502 of the contract drawings indicate that the temporary chain-link fencing is to be 7’-0” high.

Will the Government please confirm our understanding that the temporary chain-link fencing is only required to be 6’-0” (not 7’-0”) high for this project?6' high temporary fencing is correct. CS502 detail to be updated.Updated spec/dwg included
23DAVID BOLAND, INCAE4-Sep1.Discipline: General

Sheet: CS502 Detail:

Spec: Section 01 50 00 – Temporary Construction Facilities and Controls

Question: When constructing the long runs of new duct banks not located within the two larger Limit of Construction Areas—for example, duct bank A1/ES502 that runs between the PV area and the Generator/BESS area, and duct bank H11/ES501 that runs between the Generator/BESS area and existing Building 678—will the Government please confirm our understanding that the Contractor will be able to utilize temporary orange safety fencing for these areas (in lieu of temporary chain-link fencing that will be provided around the PV area, Generator/BESS area, and temporary trailer area)?

This would seem logical, as the long runs of new duct banks type work is more linear/utility in nature.

If our understanding is not correct, and the Government will require the Contractor to utilize temporary chain-link fencing in these duct bank areas as well, please clarify.Long utility runs may be indicated with orange safety fence in lieu of temporary chain link fence.No spec/drawing update required.
24DAVID BOLAND, INCAE4-Sep1.Discipline: Structural

Sheet: CS111, S-501 Detail:

Spec:

Question: Will the Government please clarify which detail is applicable to the 16’ x 20’ Electrical Equipment Pad indicated on Sheet ID CS111 of the contract drawings—detail A1 or detail K15 on Sheet ID S-501 of the contract drawings?Detail K15 on sheet S-501 is to be used for Electrical Equipment Pad and Switchgear PadNo spec/drawing update required.
25DAVID BOLAND, INCAE4-Sep1.Discipline: Mechanical

Sheet: M-501 Detail:

Spec:

Question: Note(s) 2 and 3 with the Natural Gas Pressure Regulator With Meter detail J14 on Sheet ID M-501 of the contract drawings contemplates “confirm[ing]” the natural gas regulator assembly layout and pad size with the “Utility Provider.” However, the contract drawings and specifications do not include any information associated with any “Utility Provider[s].”

If the Contractor is required to coordinate with and/or have any work performed by any “Utility Provider” (for any type of utility on this project), will the Government please update the contract documents to clarify the following:

•Point of contact and contact information for the Utility Provider(s) representative(s).
•What specific work is to be performed by the Utility Provider(s)?
•What specific work is to be coordinated with the Utility Provider(s)?
•Who (the Government or the Contractor) is required to contract with the Utility Provider(s)? If the Contractor is required to contract with the Utility Provider(s), please clarify the amount of costs/fees that the Contractor is required to include in their bid amount for any payments (if there are any payments) required to be paid to the Utility Provider(s).The natural gas service is by NJNG. NJNG installs the gas service and meterset. All piping after the meterset is the responsibility of the contractor. JBMDL to confirm NJNG POC to be used and contract delineation.No spec/drawing update required.
26DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: ED401, ES401 Detail:

Spec:

Question: Sheet Keynote 3 on Sheet ID ED401 of the contract drawings states, “Disconnect and remove existing service transformer. Maintain existing secondary feeders for re-use. Refer to ES100 series for additional information.”

Sheet Keynote 4 on Sheet ID ES401 of the contract drawings states, “Splice existing secondary transformer feeders to new MC-1 feeders in above grade pullbox.”

Will the Government please confirm our understanding that the existing concrete pad (for the existing service transformer that is to be removed) may be reused for the new electrical pullbox?

If a new concrete pad is required, please clarify such.The design intent is to utilize the existing concrete pad to house the new electrical pull box. The new installation must be made weatherproof and secure. The contractor may utilize the existing pad if the necessary conditions can be met, or provide new if needed.No spec/drawing update required.
27DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: ED401 Detail:

Spec:

Question: Sheet Keynote 2 on Sheet ID ED401 of the contract drawings states, “Disconnect and remove existing metal enclosed medium voltage load interrupter switch, SW-A11.”

Will the Government please confirm our understanding that the existing concrete pad (for the existing interrupter switch that is to be removed) may remain in place (and not require removal)?Confirmed, existing concrete pad for the existing interrupter switch may remain.No spec/drawing update required.
28DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: ED401 Detail:

Spec:

Question: Sheet Keynote 10 on Sheet ID ED401 of the contract drawings states, “Disconnect and remove existing primary ductbank from transformer T3-A11 and medium voltage load interrupter switch back to existing to remain manhole A7.”

Will the Government please confirm our understanding that the existing ductbank (whether it be concrete encased or non-concrete encased) may remain and be abandoned in place? (It is understood that the existing electrical cables would still need to be removed.)

This would be logical, as it appears the existing ductbank is routed below other existing equipment and utilities and would be inaccessible for removal.This must be approved by JBMDL. Suggest keeping the design intent the same and during construction, it can be a deduct option of JBMDL approves.No spec/drawing update required.
29DAVID BOLAND, INCAE4-Sep1.Discipline: Architectural

Sheet:

Detail:

Spec: Section 09 06 00 – Schedules for Finishes // Section 09 90 00 – Paints and Coatings

Question: Subpart(s) 2.1.1.1 – Paint and 2.3 – Placement Schedule of Section 09 06 00 of the specifications describe “Exposed galvanized steel (conduit),” “above ground conduits,” and “new at grade elec. service equip. and cabinets” (at “B678 exterior wall of main elec. room”) as requiring painting. Additionally, Subpart 1.1.3a.(1) – Mechanical and Electrical Painting of Section 09 90 00 of the specifications describes “Exposed conduit and at grade electric service equipment” as requiring painting.

It is unclear as to exactly which items the Government will require field-painting.

Is our understanding correct, that the only field-painting (of “[e]xposed conduit and at grade electric service equipment”) required will be of the conduit/box/fittings exposed on the exterior wall of Building 678 (as indicated by detail A13 / ES507)?

If field-painting of any other new electrical equipment (such as the two (2) generators, three (3) BESS, switchgear enclosure [and adjacent electrical panel enclosures], above-grade pullbox, pad-mounted switch, pad-mounted transformer, and electrical equipment enclosures located to the plan east of the PV Array area) is required, will the Government please clarify such?

Generally, the specifications for the new electrical equipment described above only require factory-finishing of the enclosures. Further, if custom-color factory-finishing is required, please clarify such.Concur, only field painting required is at the B678 facility.No spec/drawing update required.
30DAVID BOLAND, INCAE4-Sep1.Discipline: Quality Control

Sheet:

Detail:

Spec: Section 01 45 35 – Special Inspections

Question: The “Schedule of Special Inspections” mentioned in Subpart 1.2 of Section 01 45 35 of the specifications is missing from the attachments to that section. (It appears the “Statement of Special Inspections” was inadvertently attached twice.)

Will the Government please provide the “Schedule of Special Inspections?”Concur, this attachment has been sent to USACE for inclusion in the documents.Correct attachment sent to USACE for inclusion in the set.
31DAVID BOLAND, INCAE4-Sep1.Discipline: Mechanical

Sheet: M-701 through M-705 Detail:

Spec:

Question: Is there a specific DDC control contractor that the Contractor will be required to utilize to perform the DDC controls (UMCS) related work for this project?JBMDL to confirm if preferred controls contractor is required and provide contact information if applicable.No spec/drawing update required.
32DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: M-702 Detail:

Spec:

Question: Note 3 on Sheet ID M-702 of the contract drawings states, “120-volt single phase power connection junction boxes have been provided for use to power DDC system components. These junction boxes are shown on the electrical power plan drawings. The DDC controls contractor is responsible for all power wiring and components downstream of these junction boxes and verifying the quantity and location of the junction boxes is adequate. Additional power connections are the responsibility of the DDC controls contractor.”

We are unable to locate where these “120-volt single phase power connection junction boxes” are shown on the electrical power plan drawings.

Will the Government please clarify where these items are shown?Mechanical drawings M-702 has been updated. The intent is to utilize the existing 120 volt single phase power connection junction box located in the main electrical room of B678.Updated spec/dwg included
33DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: E-002 Detail:

Spec:

Question: General Note 2 on Sheet ID E-002 of the contract drawings makes mention of “utility interconnection requirements.”

Since this project is a design-bid-build type project, will the Government please confirm our understanding that by constructing the new work per the requirements contained throughout the contract drawings and specifications, that all “utility interconnection requirements” will be satisfied?

If anything, additional is required (above and beyond what is indicated within the contract documents), please clarify.Correct, coordinate with JBMDL and the COR for these connections, but all must be completed by the Contractor.No spec/drawing update required.
34DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: EP701 Detail:

Spec:

Question: The Partial One-Line Diagram A – New Work detail A1 on Sheet ID EP701 of the contract drawings shows two (2) “100% Rated Load Bank[s]”—one load bank at each new generator.

It is unclear who provides these load banks.

Will the Government please clarify if the load banks are:

1)Temporary or permanent?
2)Provided by the Government or by the Contractor?
3)To be provided in accordance with some specification?These are temporary load banks to be provided by the contractor, in accordance with 26 32 15 and generator manufacturer requirements.No spec/drawing update required.
35DAVID BOLAND, INCAE4-Sep1.Discipline: Architectural

Sheet:

Detail:

Spec: Section 09 90 00 – Paints and Coatings

Question: Subpart 1.6.2 – Coating Contractor’s Qualification of Section 09 90 00 of the specifications includes requirements regarding the experience of the coating contractor. However, it appears that the Government may have inadvertently included Subpart 1.6.3 – SSPC QP 1 Certification of Section 09 90 00 of the specifications in the specifications as well.

Subpart 1.6.3 states, "Contractors that perform surface preparation or coating application on steel substrates must be certified by the Society for Protective Coatings (formerly Steel Structures Painting Council) (SSPC) to the requirements of SSPC QP 1 prior to Contract award, and must remain certified while accomplishing any surface preparation or coating application."

Per the SSPC website (now AMPP), QP 1 certification is primarily meant to attest to the ability to apply coatings on complex structures, such as bridges, industrial tanks, marine vessels, water/wastewater facilities, and power plants.

Additionally, the UFGS 09 90 00 – Paints and Coatings provides guidance for the designer, stating, "Use bracket option below concerning SSPC QP 1 only when industrial coatings are required. Painting qualifications for projects such as BEQ's, training facilities and general administration buildings do not require QP 1 certification."

The painting for this project does not appear to fall within the categories of structures typically reserved for the requirements of SSPC QP 1.

This requirement will prohibit local experienced, small business painting subcontractors from being able to perform the work and will result in a substantial increase in the cost of this work, which will be reflected in the prime contractors' bids submitted to the Government.

SSPC QP 1 certified painting contractors typically do not perform painting work for the types of surfaces that are required to be painted for this project.

Based on the guidance provided in UFGS 09 90 00 and the explanations provided above, will the Government please remove the requirement for the use of SSPC QP 1 certified painting contractors from the specifications for this project?Concur, will strike the requirement for SSPC QP 1. Similar to RFI-08 response.Updated spec/dwg included/ Redundant with RFI-08
36DAVID BOLAND, INCAE4-Sep1.Discipline: Structural

Sheet:

Detail:

Spec: Section 03 30 00 – Cast-In-Place Concrete

Question: Subpart 1.6.9c – Laboratory Accreditation – Contractor Quality Control of Section 03 30 00 of the specifications states, "All sampling and testing must be performed by an approved, onsite, independent, accredited laboratory."

Will the Government please confirm our understanding that the intent of the referenced specification is that the validated testing laboratory representative(s) be on-site to collect and prepare specimen and conduct testing that is required on-site; however, the actual testing laboratory facility is not required to be physically on-site during the performance of the contract?Confirmed, the testing laboratory facility is not required to be physically on-site.No spec/drawing update required.
37DAVID BOLAND, INCAE4-Sep1.Discipline: Structural

Sheet: S-001 Detail:

Spec:

Question: Geotechnical, Source Note 1 on Sheet ID S-001 of the contract drawings states, “Geotechnical Report: JB MDL EV Charging Infrastructure Lakehurst Naval Engineering Station, GEI Consultants, Inc. December 2024.”

Will the Government please provide the bidders with the referenced geotechnical report?BMcD has no problem with the Contractor reviewing the Geotech Report. If USACE agrees, please provide to the Contractor. It is presently in an attachment of the Design Analysis.No spec/drawing update required.
38DAVID BOLAND, INCPM4-Sep1.Discipline: Contracting

Sheet:

Detail:

Spec: Section 01 11 00 – Summary of Work

Question: Will the Contractors and subcontractors be required to make payment for access badges in order to timely access Joint Base MDL (Lakehurst) on a daily basis?No, payments are not required.
39DAVID BOLAND, INCAE4-Sep1.Discipline: General

Sheet:

Detail:

Spec: Section 01 45 00 – Quality Control

Question: Subpart 1.6.2.2 – Quality Control (QC) Manager, Qualifications of Section 01 45 00 of the specifications requires the Quality Control (“QC”) Manager to “possess at least a Bachelor's degree in engineering, architecture, or construction management, with a current professional engineer registration in a US State or Territory or a current licensed architect in a US State or Territory . . .”

The requirements for the QC Manager to be a Professional Engineer (“PE”) or Licensed Architect appear to be excessive for the level of complexity of the project. This requirement is more commonly found on design-build projects; however, this project is a design-bid-build project.

Will the Government please consider removing the requirement for the QC Manager to have a “current professional engineer registration in a US State or Territory or a current licensed architect in a US State or Territory” from the requirements for this project?

This would be more in line with the type and complexity of the project, and would avoid eliminating a large pool of capable and experienced potential QC Managers.BMcD will need USACE approval to remove this requirement. While we agree that this is not a large project, it is somewhat complex given the equipment and phasing involved. Our recommendation is to bid as designed.No spec/drawing update required.
40DAVID BOLAND, INCPM4-Sep1.Discipline: Contracting

Sheet:

Detail:

Spec: Section 01 35 26 – Governmental Safety Requirements

Question: Will the Government please confirm our understanding that, for this project, the Site Safety and Health Officer (“SSHO”) is to be assigned no other duties other than SSHO?

s.Yes, SSHO is to be assigned, no other duties.
41DAVID BOLAND, INCPM4-Sep1.Discipline: Contracting

Sheet:

Detail:

Spec: Section 01 45 00 – Quality Control

Question: Subpart 1.6.2.1 – Quality Control (QC) Manager, Duties of Section 01 45 00 of the specifications states, “In addition to implementing and managing the QC program, the QC Manager may perform the duties of Project Superintendent.”

Will the Government please confirm our understanding that the QC Manager will in fact be able to also perform the duties for Project Superintendent for this project?

The quality control manager (QC) is to follow the responsiblities as outlined in section 01 45 00 supart 1.6.2.1.
42DAVID BOLAND, INCCT4-Sep1.Discipline: Contracting

Sheet:

Detail:

Spec: Standard Form 1442

Question: The solicitation indicates that the bids are due to 2:00 p.m. on Monday, 28 September 2026.

We respectfully request that the Government consider shifting the bid due date to another business day.

A Monday morning bid due date significantly limits the contractor’s ability to finalize bids after the close of business on the preceding day, as during the weekend, subcontractors, suppliers, and other key personnel are generally unavailable to respond to last-minute questions, provide clarifications, resolve discrepancies, and submit revised pricing.

In addition, many subcontractors and suppliers routinely submit their final quotes on the last business day before the bid due date. A Monday morning bid due date essentially eliminates the opportunity for meaningful review, coordination, and confirmation of those quotes before submitting the bids.

Providing a bid due date on another business day would allow the contractors to complete appropriate and thorough review, improve the accuracy and completeness of the bids, and encourage greater competition, ultimately benefiting the Government through more competitive pricing. The Government has evaluated the request to shift the bid due date. Due to strict fiscal year-end funding availability constraints, the deadline cannot be extended beyond the end of the fiscal year.

To maximize competition and accommodate contractor coordination needs as much as possible, the Government is granting a partial extension. The bid due date is hereby shifted from Monday, 28 September 2026, to Wednesday, 30 September 2026 at 2:00 PM EDT.

This change is officially incorporated into the solicitation under Amendment 0004. Offerors must acknowledge this amendment in their proposals.

43 DAVID BOLAND, INC PM 4-Sep 1. Discipline: Contracting Sheet:

Detail:

Spec: Section 01 30 00 – Administrative Requirements

Question: Subparts 1.14 through 1.14.1g of Section 01 30 00 of the specifications require formal partnering be conducted for this project.

Subpart 1.14f states, “Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less. Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer.”

Will the Government please clarify the following:

1)Will the follow-on partnering sessions be held in-person or virtually?
2)Will the facilitator be required to attend the follow-on partnering sessions in-person or virtually?For both questions the contractor is to coordianted with the contracting officer.
44DAVID BOLAND, INCPM4-Sep1.Discipline: General

Sheet:

Detail:

Spec: Section 01 32 01.00 10 – Project Schedule

Question: Subpart 3.6.1 – Periodic Schedule Update Meetings of Section 01 32 01.00 06 of the specifications states, " The Contractor scheduler must attend in person unless virtual attendance is approved by Contracting Officer.”

With the user-friendliness of current technology, it has become customary for the Scheduler to participate in update meetings virtually.

Will the Government please consider allowing the Scheduler to attend and perform their duties virtually during the Periodic Schedule Update Meetings?

Allowing the Scheduler to participate virtually will increase efficiency due to having more direct access to the required technology, without sacrificing the effectiveness of the meetings.The scheduler may attend virtually if approved by the contract officer further the contract is awarded as stated in the specifications.
45DAVID BOLAND, INCCT4-Sep1.Discipline: Contracting

Sheet:

Detail:

Spec: Section 00 72 00 – General Conditions

Question: Will the Government please clarify if a sales tax exemption is applicable for this project?FAR Clause 52.229-3, "Federal, State, and Local Taxes," included in this solicitation (page 37 of the solicitation document), states that the contract price includes all applicable Federal, State, and local taxes and duties. The clause also outlines the process for price adjustments if tax exemptions are granted. Per FAR Subpart 29.3, the U.S. Government is generally exempt from direct state and local taxes. However, the applicability of a sales tax exemption on purchases made by the contractor for this project depends on the laws of the state of New Jersey. The contractor is responsible for determining the applicability of any tax exemptions and for obtaining any necessary exemption certificates.
46DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: EG101 through EG502 Detail:

Spec: Section 26 41 00 – Lightning Protection System

Question: Section 26 41 00 – Lightning Protection System is included in the specifications, and includes generic lightning protection system requirements. However, neither the specifications nor the contract drawings indicate specifically where the lightning protection system is to be provided. Sheet IDs EG101 through EG502 of the contract drawings indicates certain grounding and bonding requirements; however, do not clarify where lightning protection system(s) are specifically required.

Will the Government please clarify where the lightning protection system(s) is (are) required to be provided?Lightning protection must be provided for all new exterior equipment associated with the microgrid. This include lighting protection for the PV Array, all exterior site lighting (Shown on ES503 detail A12), Natural Gas Generators, and Battery Energy Storage System (BESS).No spec/drawing update required.
47DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: ES401 Detail:

Spec:

Question: HH-12 is indicated on Sheet ID ES401 of the contract drawings; however, HH-12 is not included in the Handhole Schedule on the Electrical Handhole detail A7 on Sheet ID ES503 of the contract drawings.

Will the Government please add HH-12 and the relevant information to the refenced Handhole Schedule?Provide handhole size of 36"Lx24"Wx18"DUpdated spec/dwg included
48DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: EP701 Detail:

Spec:

Question: General Sheet Note 4 on Sheet ID EP701 of the contract drawings states, “As soon as practical after award, Contractor must connect a power meter to the main service at SWGR-1 and record the power for at least 30 days. This data must be submitted to the 87 CES and COR for review at least six weeks prior to any equipment submittals.”

Will the Government please clarify if this power meter is required to be permanent (and remain in place)?

Additionally, will the Government please clarify if this power meter is the power meter (“DM”) indicated on Sheet ID EP707 of the contract drawings?General Note 4 on EP701 requires only a temporary power meter to accurately record and measure the existing electrical load to the facility. The multi-function digital meter "MFM" is a fixed permanent meter that should be installed in accordance with the contract drawings.No spec/drawing update required.
49DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: ES102, EP701 Detail:

Spec:

Question: The size/characteristics of the new pad-mounted medium-voltage switch indicated by Sheet Keynote 2 on Sheet ID ES102 of the contract drawings does not match the size/characteristics of the new pad-mounted medium-voltage switch indicated by the Partial One-Line Diagram A – New Work detail A1 on Sheet ID EP701 of the contract drawings.

Will the Government please clarify this discrepancy?The ratings on EP701 is correct. ES102 will be updated to reflect those ratingsUpdated spec/dwg included
50DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet: ES103, EP701 Detail:

Spec:

Question: The size/characteristics of the new pad-mounted utility transformer indicated by Sheet Keynote 6 on Sheet ID ES103 of the contract drawings does not match the size/characteristics of the new pad-mounted utility transformer indicated by the Partial One-Line Diagram A – New Work detail A1 on Sheet ID EP701 of the contract drawings.

Will the Government please clarify this discrepancy?The ratings on EP701 are correct. ES103 is updated to reflect those ratingsUpdated spec/dwg included
51DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet:

Detail:

Spec: Section 48 18 00 – Battery Energy Storage System

Question: Will the Government please provide the basis-of-design manufacturer for the BESS(s) that was used in development of the specifications and contract drawings?We can provide the Basis of Design for USACE to distribute to the contractors. We do not have a J&A and have not sole-sourced the design. Please let BMcD know if the separate Basis of Design documents are needed (they are presently in the Design Analysis).No spec/drawing update required.
52DAVID BOLAND, INCJBMDL4-Sep1.Discipline: General

Sheet:

Detail:

Spec: Section 01 50 00 – Temporary Construction Facilities and Controls

Question: Will the Government please confirm our understanding that the Contractor will not be charged for the natural gas usage that will be required to start up, test, inspection, and commission the microgrid system and components between the time of equipment start-up through substantial completion of the project?Generally, the contractor is responsible for all utility usasge until after final inspection, testing, and acceptance by the government.
53DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet:

Detail:

Spec: Section 26 37 13 – Microgrid Control System

Question: Will the Government please provide the basis-of-design manufacturer for the microgrid control system that was used in development of the specifications and contract drawings?Schneider Electric: C&I Microgrid Flex ECCNo spec/drawing update required.
54DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet:

Detail:

Spec: Section 26 32 15 – Engine-Generator Set Stationary, 15-2500 KW, With Auxiliaries

Question: Will the Government please provide the basis-of-design manufacturer for the generator sets that was used in development of the specifications and contract drawings?Cummins C500N6BNo spec/drawing update required.
55DAVID BOLAND, INCAE4-Sep1.Discipline: Electrical

Sheet:

Detail:

Spec: Section 26 31 00 – Facility-Scale Solar Photovoltaic (PV) Systems

Question: Will the Government please provide the basis-of-design manufacturer for the facility-scale solar photovoltaic (PV) system that was used in development of the specifications and contract drawings?PV Modules: Mission Solar Energy P-PERC Bifacial 144HC 550W. Inverter: CPS SCH100/125KTL-DO/US-600. Combiner: SMA String-Combiner.No spec/drawing update required.
56DAVID BOLAND, INCAE4-Sep1.Discipline: Civil

Sheet: C-002 Detail:

Spec:

Question: Existing Condition Note 6 on Sheet ID C-002 of the contract drawings states, “Special handling and consideration is required for excavated soils thought to contain contaminated substances.”

Since the contract drawings (and specifications) do not indicate (specify) any "excavated soils thought to contain contaminated substances," the bidders cannot determine prior to bidding the project the extent to which any existing soils may or may not be contaminated.

Therefore, will the Government please confirm our understanding that, if contaminated soils are actually encountered during construction, the Government will consider the additional work a change and will issue an equitable adjustment for the costs and impacts from this changed work?

If not, will the Government please clarify to the bidders the quantity of contaminated soils removal the bidders are to include in their bid amounts?This would be handled as and unforeseen circumstance.No spec/drawing update required.
57DAVID BOLAND, INCAE4-Sep1.Discipline: General

Sheet:

Detail:

Spec: Section 01 78 00 – Closeout Submittals

Question: Requirements related to “Advanced Modeling” are included within Section 01 78 00 of the specifications.

Will the Government please clarify if “Advanced Modeling” will in fact be required for this project?This would include Civil 3D and any associated BIM Modeling software, rather than simple 2D CAD for the construction records.No spec/drawing update required.
58DAVID BOLAND, INCAE/JBMDL4-Sep1.Discipline: General

Sheet:

Detail:

Spec: Section 01 57 19 – Temporary Environmental Controls

Question: Subpart 1.5 – Special Environmental Requirements of Section 01 57 19 of the specifications states, “Comply with the special environmental requirements listed here and attached at the end of this section.

This is the start of the file's text. The full file is on GovTribe.