This is a technical specification section (Section 26 08 00) for Apparatus Inspection and Testing as part of a Power Generation with Microgrid project at Joint Base McGuire-Dix-Lakehurst, New Jersey (Contract 164947).

The specification establishes requirements for independent third-party acceptance testing and inspection of electrical distribution and generation equipment. A qualified testing organization must be engaged as a first-tier subcontractor to perform inspection, testing, calibration, and adjustment services in accordance with NETA ATS (2025) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems. The testing organization must have a minimum of five years' experience in testing electrical materials and devices, maintain a calibration program, and have calibrated test instruments per NETA standards. The lead engineering technician must be NETA Level III or NICET certified with a minimum of five years' experience in electrical distribution and generation equipment inspection and testing. Test procedure reports must be submitted at least 45 days prior to the planned testing date for government approval (classification G, RO), and certified test reports documenting results must be submitted within 10 days of completion. The Contracting Officer must be notified at least 14 days in advance of testing. Testing is required for engine-generator sets (15-2500 KW), pad-mounted transformers, grounding systems, solar photovoltaic systems, microgrid control systems, battery energy storage systems, and switchboards. A representative of the approved testing organization must be present when tested equipment is initially energized and placed in service. Final system acceptance is contingent upon satisfactory completion of all acceptance tests and inspections.

View the file

Other files

File Type Posted
Bid Abstract Form Power Generation Microgrid Revised Final.pdf PDF
RFI log for posting 9.23.26.xlsx XLSX spreadsheet
AF Meter Data Management Plan 20250610.pdf PDF
RFI-50 - ES103 - ENLARGED - ELECTRICAL SITE PLAN.pdf PDF
RFI-08 - SPEC 09 90 00.pdf PDF
RFI-22 - CS502 - SITE DETAILS - 2.pdf PDF
RFI-90 - SPEC 26 31 00.pdf PDF
RFI-16 - SPEC 32 31 13.pdf PDF
RFI-47 - ES503 - ELECTRICAL SITE DETAILS.pdf PDF
RFI-74 - EP701 - PARTIAL ONE-LINE DIAGRAM A - NEW WORK.pdf PDF
RFI-32 - M-702 - MECHANICAL CONTROLS ARCHITECTURE.pdf PDF
RFI-11 - M-501 - MECHANICAL DETAILS.pdf PDF
RFI-49 - ES102 - ENLARGED - ELECTRICAL SITE PLAN.pdf PDF
RFI-02 - SPEC 26 37 13.pdf PDF
RFI-63 - SPEC 32 11 26.pdf PDF
RFI-17 - CS112 - SITE PLAN - AREA 2.pdf PDF
RFI-62 - SPEC 31 00 00.pdf PDF
01 45 35 - Attachment - Schedule_of_Special_Inspections.pdf PDF
Solicitation Amendment W912DS26BA0320001 SF 30.pdf.pdf PDF
RFI-75 - SPEC 26 12 19.pdf PDF
2026.09.03_Site Visit_Sign in for Power Gen_Lakehurst.pdf PDF
2026.09.03_Site Visit_Sign in for Power Gen_Lakehurst.pdf PDF
Power Gen w. microgrid bidder walkthrough packet.pdf PDF
A.03.09 Drawings - 100%.pdf PDF
Solicitation - W912DS26BA032.pdf PDF
Power Generation with Microgrid - Specifications - RTA_rev1.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Power Generation with Microgrid 164947 Joint Base McGuire-Dix-Lakehurst, New Jersey

SECTION 26 08 00

APPARATUS INSPECTION AND TESTING

11/22

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)

NETA ATS (2025) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems

1.2 RELATED REQUIREMENTS

Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM applies to this section with additions and modifications specified herein.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-06 Test Reports

Acceptance Tests and Inspections ; G, RO

SD-07 Certificates

Qualifications of Organization, and Lead Engineering Technician;

G, RO

Acceptance Test and Inspections Procedure ; G, RO

1.4 QUALITY ASSURANCE

1.4.1 Qualifications

Engage the services of a qualified testing organization to provide inspection, testing, calibration, and adjustment of the electrical distribution system and generation equipment listed in paragraph ACCEPTANCE TESTS AND INSPECTIONS herein. Organization must be independent of the supplier, manufacturer, and installer of the equipment. The organization must be a first tier subcontractor. No work required by this section of the specification may be performed by a second tier subcontractor.

SECTION 26 08 00 Page 1

a. Submit name and qualifications of organization. Organization must have been regularly engaged in the testing of electrical materials, devices, installations, and systems for a minimum of 5 years. The organization must have a calibration program, and test instruments used must be calibrated in accordance with NETA ATS.

b. Submit name and qualifications of the lead engineering technician performing the required testing services. Include a list of three comparable jobs performed by the technician with specific names and telephone numbers for reference. Testing, inspection, calibration, and adjustments must be performed by an engineering technician, certified by NETA (Level III) or the National Institute for Certification in Engineering Technologies (NICET) with a minimum of 5 years' experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.

1.4.2 Acceptance Tests and Inspections Reports

Submit certified copies of inspection reports and test reports. Include certification of compliance with specified requirements, identify deficiencies, and recommend corrective action when appropriate. Type and neatly bind test reports to form a part of the final record. Submit test reports documenting the results of each test not more than 10 days after test is completed.

1.4.3 Acceptance Test and Inspections Procedure

Submit test procedure reports for each item of equipment to be field tested at least 45 days prior to planned testing date. Do not perform testing until after test procedure has been approved.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 ACCEPTANCE TESTS AND INSPECTIONS

Testing organization will perform acceptance tests and inspections. Test methods, procedures, and test values must be performed and evaluated in accordance with NETA ATS, the manufacturer's recommendations, and paragraph FIELD QUALITY CONTROL of each applicable specification section.

Tests identified as optional in NETA ATS are not required unless otherwise specified. Place equipment in service only after completion of required tests and evaluation of the test results have been completed. Supply to the testing organization complete sets of shop drawings, settings of adjustable devices, and other information necessary for an accurate test and inspection of the system prior to the performance of any final testing. Notify Contracting Officer at least 14 days in advance of when tests will be conducted by the testing organization. Perform acceptance tests and inspections on applicable equipment and systems specified in the following sections:

a. Section 26 32 15 ENGINE-GENERATOR SET STATIONARY 15-2500 KW, WITH AUXILIARIES. Functional engine shutdown tests, vibration base-line test, and load bank test will not be performed by the testing organization, but by the start-up engineer.

SECTION 26 08 00 Page 2

b. Section 26 12 19 PAD-MOUNTED, LIQUID-FILLED, MEDIUM-VOLTAGE

TRANSFORMERS.

c. Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION. Grounding systems only.

d. Section 26 31 00 FACILITY-SCALE SOLAR PHOTOVOLTAIC (PV) SYSTEMS.

e. Section 26 37 13 MICROGRID CONTROL SYSTEM.

f. Section 48 18 00 BATTERY ENERGY STORAGE SYSTEMS.

g. Section 26 24 13 SWITCHBOARDS.

3.2 SYSTEM ACCEPTANCE

Final acceptance of the system is contingent upon satisfactory completion of acceptance tests and inspections.

3.3 PLACING EQUIPMENT IN SERVICE

A representative of the approved testing organization must be present when equipment tested by the organization is initially energized and placed in service.

-- End of Section --

SECTION 26 08 00 Page 3

26 08 00 - APPARATUS INSPECTION AND TESTING
PART 1 GENERAL
1.1 REFERENCES
1.2 RELATED REQUIREMENTS
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.4.1 Qualifications
1.4.2 Acceptance Tests and Inspections Reports
1.4.3 Acceptance Test and Inspections Procedure
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 ACCEPTANCE TESTS AND INSPECTIONS
3.2 SYSTEM ACCEPTANCE
3.3 PLACING EQUIPMENT IN SERVICE