This document contains an invitation for bid for construction services. The U.S. Army Corps of Engineers, New York District is seeking bids for Segment C2 and H Contract 2 of the Green Brook Flood Risk Management Project located in Middlesex Borough, New Jersey. The scope of work includes construction of two pump stations, 1,700 feet of earthen levee, 100 feet of floodwall, one road closure gate, and 3,600 feet of earthen levee tying into a railroad embankment along with 576 feet of floodwall and another road closure gate. The estimated value of the contract is between $25-100 million. The period of performance is 730 calendar days from notice to proceed. Questions must be submitted in writing to the contract specialist by the response due date. Bids must be submitted electronically through the System for Award Management by the specified deadline. The North American Industry Classification System code for this opportunity is 237990.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Green Brook Flood Risk Management Project Segments C2&H Contract 2 limited to frames, discs, seals, hinge links, pins, bushes, anchorage, and all other appurtenances, in place and complete as intended by the product manufacturer for its use. The basis of design is Alfa Laval Inc. - Coplastix.
1.2.1 Standard Products
Material and equipment shall be the standard products of a manufacturer regularly engaged in the manufacture of the products and shall essentially duplicate items that have been in satisfactory use for at least 5 years prior to bid opening. Equipment shall be supported by a service organization that is, in the opinion of the Contracting Officer, reasonably convenient to the site. All Slide-Gates installed on this project shall be the products of a single manufacturer; all Flap-Gates installed on this project shall be the products of a single manufacturer.
1.2.2 Nameplates
Each major item of equipment shall have the manufacturer's name, address, type or style, model, serial number, and catalog number on a plate secured to the item of equipment. Nameplate for each electric motor shall show the horsepower, speed in revolutions per minute, full load current, voltage, frequency, phase, time rating, maximum ambient temperature, insulation class code letter, and service factor.
1.2.3 Verification of Dimensions
The Contractor shall become familiar with all details of the work, verify all dimensions in the field and shall advise the Contraction Officer of any discrepancy before performing the work.
1.2.4 Warranty and Guarantee
The Manufacturer shall guarantee the Slide Gates and Flap Gates, when installed and operated as recommended by the Manufacturer, for trouble-free operation for a period of ten (10) years. If the Contracting Officer determines that the products do not operate as intended, the Manufacturer shall remedy the problems at no additional cost to the Government. The Manufacturer shall guarantee the following:
a. Leakage for both Slide Gates and Flap Gatea shall be no more than allowed by ANSI/AWWA C563 during the guarantee period. Under normal operating conditions both Slide-Gates and Flap-Gates shall be near watertight.
b. Slide Gate doors (discs) shall move when operated manually or with the electric operator without sticking or binding. The flaps on the Flap Gate shall shall move freely without sticking or binding. Slide Gate operators shall have the greater of the manufacturer's standard warranty period or 1 year. The warranty period shall not commence until the successful completion of the field acceptance tests.
1.2.5 Other Requirements for Slide Gates
a. All gates shall be fully assembled in their frames except for operators, guides, stem-extension, stem covers and operator pedestals. Where shipping constraints prevent it, frame may be partially assembled such that the top may be easily mounted to the bottom containing the disc.
SECTION 35 22 25 Page 2
Stauder, Gerry Highlight