GSU Transformer Supply, Oahe Dam, SD & Ft Peck Dam, MT
Solicitation number
W9128F25RA053
Issued by

About this file

This document is a Measurement and Payment section (Section 01 22 00) for a GSU Transformer Supply contract for Fort Peck Dam in Montana and Oahe Dam in South Dakota. The contract involves designing, manufacturing, testing, delivering, and installing multiple power transformers at two different dam sites. Specifically, the contract includes:

For Oahe Dam: One 103,000 kVA three-phase GSU power transformer (115 kV high-voltage, 13.8 kV low-voltage) and nine 68,667 kVA single-phase GSU power transformers (230/132.79 kV high-voltage, 13.8 kV low-voltage). For Fort Peck Dam: Two 42,000/56,000 kVA three-phase GSU power transformers (230 kV high-voltage, 13.8 kV low-voltage). The payment structure is detailed and broken down into multiple line items covering design approvals, tank production, winding construction, core construction, assembly, testing, delivery, offloading, site installation, and spare parts. Each major stage of transformer production and delivery has a specific percentage of the total line item value allocated to it, with the final testing and delivery receiving the remaining balance.

View the file

Other files

File Type Posted
Attachment 2 Sheet G-103 Am-0006.pdf PDF
Solicitation Amendment W9128F25RA0530006 SF 30.pdf PDF
Attachment 3 Transformer Oil Tests Table Am-0006.pdf PDF
Attachment 1 Specifications Am-0006.pdf PDF
Solicitation Amendment W9128F25BA0080002 SF 30.pdf PDF
Solicitation Amendment W9128F25RA0530005 SF 30.pdf PDF
Attachment 6 Sheet G_204.pdf PDF
Attachment 4 Specifications AM 0005.pdf PDF
Attachment 5 Sheet G_203 .pdf PDF
Attachment 1 Price Schedule Am-0005.pdf PDF
Attachment 2 Addendum to 52.212-2 Am-0005.pdf PDF
Solicitation Amendment - W9128F25RA0530005.pdf PDF
Solicitation Amendment W9128F25RA0530004 SF 30.pdf PDF
Attachment-1 Price Schedule - Updated.pdf PDF
Solicitation Amendment W9128F25RA0530003 SF 30.pdf PDF
Site Visit Attendees Fort Peck_MT.pdf PDF
Site Visit Attendees Attendees Oahe Dam_SD.pdf PDF
Solicitation Amendment - W9128F25RA0530002 SF 30.pdf PDF
Solicitation Amendment W9128F25RA0530001 SF 30.pdf PDF
Attachment-4 OA_FP GSU Transformer Contract Drawings 2 of 3 (1).pdf PDF
Attachment-4 OA_FP GSU Transformer Contract Drawings 2 of 3.pdf PDF
Attachment-5 OA_FP GSU Transformer Supply specs.pdf PDF
Attachment-3 Oahe GSU Transformer Reference Drawings.pdf PDF
Attachment-4 OA_FP GSU Transformer Contract Drawings 1 of 3.pdf PDF
Addendum to 52.212-2.pdf PDF
Attachment-1 Price Schedule.pdf PDF
Solicitation - W9128F25RA053.pdf PDF
Attachment-4 OA_FP GSU Transformer Contract Drawings 3 of 3.pdf PDF
Attachment-4 OA_FP GSU Transformer Contract Drawings 2 of 3.pdf PDF
Attachment-2 Fort Peck GSU Transformer Reference Drawings.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GSU Transformer Supply - Fort Peck, MT and Oahe Dam, SD OA00106

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 MEASUREMENT

1.3 PAYMENT

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 22 00 Page 1

Am-0005

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

*Am-5 COLE'S EDIT **Am-5 In each instance the contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another bid item. In the event any work is required by the specification sections or by the drawings and not specifically mentioned in the measurement and payment paragraphs, separate or direct payment will not be made and all costs thereof are incidental to and included in the contract prices and payments for all items listed in the bid schedule.

1.2 MEASUREMENT

Items measured as a Lump Sum (LS) will be measured for payment as a completed job, in place, in the locations indicated. This measurement includes all incidental work and materials that are necessary to make a complete job. Unless the payment paragraph makes a specific exception of an item, incidental items will not be measured under another item, even though there is another listing for the work or material.

1.3 PAYMENT

Payment for all work specified, shown, or incidental to complete the work will be made as follows. Items with an (OA) designation refers to Oahe Dam, and items with an (FP) designation refers to Fort Peck Dam.

a. Line Item No. 0001; (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , three-phase GSU power transformer . Payment will be full compensation for the operations, materials, and equipment required to manufacture and test the transformer and accessories at the manufacturing facility.

a1. Line Item No. 0001A; (OA) 60% Design approval of the 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , three-phase GSU power transformer.

Payment will be a maximum of five percent of the total value of Line Item No. 0001 for the submission and subsequent government approval of the Outline and Assembly Drawings and Transformer Design Data Review Report in SECTION 48 19 23.05 26.

a2. Line Item No. 0001B; (OA) Final Design approval of the 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , three-phase GSU power transformer.

Payment will be a maximum of 10 (ten) percent of the total value of Line Item No. 0001 for the submission and subsequent government approval of the Detail Drawings, Descriptive Data, and Spare Parts List in SECTION 48 19 23.05 26.

SECTION 01 22 00 Page 2 a3. Line Item No. 0001C; (OA) Tank Production for the 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , three-phase GSU power transformer. Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0001 for the completion of building and painting the main transformer tank as approved in the Detail Drawings in

SECTION 48 19 23.05 26.

a4. Line Item No. 0001D; (OA) Winding Construction for the 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , three-phase GSU power transformer.

Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0001 for the completion of winding, drying, and pressing the transformer windings.

a5. Line Item No. 0001E; (OA) Core Construction for the 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , three-phase GSU power transformer.

Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0001 for the completion of slitting, stacking, banding, and clamping of the lower core assembly into a complete unit ready for installation of transformer windings.

a6. Line Item No. 0001F; (OA) Assembly of the 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , three-phase GSU power transformer in the factory.

Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0001 for the complete factory assembly and oil-filling of the transformer and installation of all external components.

a7. Line Item No. 0001G; (OA) Testing of the 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , three-phase GSU power transformer in the factory.

Payment will be the remaining balance of the total value of Line Item No. 0001 for the completion of factory transformer testing.

b. Line Item No. 0002; (OA) Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , single-phase GSU power transformers .

Payment will be full compensation for the operations, materials, and equipment required to manufacture and test the nine (9) transformers and accessories at the manufacturing facility.

b1. Line Item No. 0002A; (OA) 60% Design approval of the 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , single-phase GSU power transformers.

Payment will be a maximum of five percent of the total value of Line Item No. 0002 for the submission and subsequent government approval of the Outline and Assembly Drawings and Transformer Design Data Review Report in SECTION 48 19 23.05 26 b2. Line Item No. 0002B; (OA) Final Design approval of the 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , single-phase GSU power transformers.

Payment will be a maximum of 10 (ten) percent of the total value of Line Item No. 0002 for the submission and subsequent government approval of the Detail Drawings, Descriptive Data, and Spare Parts

SECTION 01 22 00 Page 3

List in SECTION 48 19 23.05 26.

b3. Line Item No. 0002C; (OA) Tank Production for the 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , single-phase GSU power transformers. Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0002 for the completion of building and painting the main transformer tanks as approved in the Detail Drawings in

SECTION 48 19 23.05 26.

b4. Line Item No. 0002D; (OA) Winding Construction for the 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , single-phase GSU power transformers.

Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0002 for the completion of winding, drying, and pressing the transformer windings.

b5. Line Item No. 0002E; (OA) Core Construction for the 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , single-phase GSU power transformers.

Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0002 for the completion of slitting, stacking, banding, and clamping of the lower core assembly into a complete unit ready for installation of transformer windings.

b6. Line Item No. 0002F; (OA) Assembly of the 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , single-phase GSU power transformers in the factory. Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0002 for the complete factory assembly and oil-filling of the transformer and installation of all external components.

b7. Line Item No. 0002G; (OA) Testing of the 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF *Am-5 or ODAF **Am-5 , single-phase GSU power transformers in the factory. Payment will be the remaining balance of the total value of Line Item No. 0002 for the completion of factory transformer testing.

c. Line Item No. 0003; (OA) Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant . Payment will be full compensation for the operations, materials, and equipment required to transport the transformer and accessories from the manufacturing facility to the Oahe Dam power plant.

d. Line Item No. 0004; (OA) Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformers and accessories from the manufacturing facility complete to the Oahe Dam power plant . Payment will be full compensation for the operations, materials, and equipment required to transport the nine (9) transformers and accessories from the manufacturing facility to the Oahe Dam power plant.

e. Line Item No. 0005; (OA) Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting

SECTION 01 22 00 Page 4

Engineer . Payment will be full compensation for the labor, materials and equipment required to offload the transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish transformer oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. Payment for provision of services of an Erecting Engineer will include the following:

Payment will cover the total number of working days during the period of time that the Erecting Engineer is in the service to the Government and is at the project site and working. Payment will include the time required to travel by the most direct commercial airline from the Erecting Engineer's home station or duty station to the job site. Return travel time will only be allowed from time of first available transportation after release by the Government for return to home station or duty station.

Payment will cover the daily cost of a rental car to transport the Erection Engineer from the local motel to the Oahe Dam power plant work site, and per-diem costs for meals and lodging.

f. Line Item No. 0006; (OA) Offload the 68,667 kVA, 230/132.79 kV single-phase power transformers and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer . Payment will be full compensation for the labor, materials and equipment required to offload the nine (9) transformers and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish transformer oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. Payment for provision of services of an Erecting Engineer will include the following:

Payment will cover the total number of working days during the period of time that the Erecting Engineer is in the service to the Government and is at the project site and working. Payment will include the time required to travel by the most direct commercial airline from the Erecting Engineer's home station or duty station to the job site. Return travel time will only be allowed from time of first available transportation after release by the Government for return to home station or duty station.

Payment will cover the daily cost of a rental car to transport the Erection Engineer from the local motel to the Oahe Dam power plant work site, and per-diem costs for meals and lodging.

g. Line Item No. 0007; (OA) Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent . Payment will be full compensation for the labor, materials and equipment required to move the fully assembled transformer from temporary storage location at Oahe Dam to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide

SECTION 01 22 00 Page 5 the of services of an Erecting Engineer and Commissioning Agent.

Payment for provision of services of an Erecting Engineer and Commissioning Agent will include the following:

Payment will cover the total number of working days during the period of time that the Erecting Engineer or Commissioning Agent is in the service to the Government and is at the project site and working. Payment will include the time required to travel by the most direct commercial airline from the Erecting Engineer's or Commissioning Agent's home station or duty station to the job site. Return travel time will only be allowed from time of first available transportation after release by the Government for return to home station or duty station.

Payment will cover the daily cost of a rental car to transport the Erection Engineer or Commissioning Agent from the local motel to the Oahe Dam power plant work site, and per-diem costs for meals and lodging.

h. Line Item No. 0008; (OA) Move the 68,667 kVA, 230/132.79 kV single-phase power transformers from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent .

Payment will be full compensation for the labor, materials and equipment required to move the nine (9) fully assembled transformers from temporary storage location at Oahe Dam to the permanent operating locations, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. Payment for provision of services of an Erecting Engineer and Commissioning Agent will include the following:

Payment will cover the total number of working days during the period of time that the Erecting Engineer or Commissioning Agent is in the service to the Government and is at the project site and working. Payment will include the time required to travel by the most direct commercial airline from the Erecting Engineer's or Commissioning Agent's home station or duty station to the job site. Return travel time will only be allowed from time of first available transportation after release by the Government for return to home station or duty station.

Payment will cover the daily cost of a rental car to transport the Erection Engineer or Commissioning Agent from the local motel to the Oahe Dam power plant work site, and per-diem costs for meals and lodging.

i. Line Item No. 0009; (OA) Furnish Spare Parts (See Section 48 19

23.05 26) . Furnishing spare parts for the Oahe Dam transformers will be measured for payment as a complete pay item (Lot). Payment will be made at the contract lump sum price, which price and payment will be full compensation for furnishing the spare parts for the transformers, complete, as specified in Section 48 19 23.05 26, and as approved.

j. Line Item No. 0010; (FP) Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformers . Payment will be full compensation for the operations, SECTION 01 22 00 Page 6 materials, and equipment required to manufacture and test the two (2) transformers and accessories at the manufacturing facility.

j1. Line Item No. 0010A; (FP) 60% Design approval of the 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformers. Payment will be a maximum of five percent of the total value of Line Item No. 0010 for the submission and subsequent government approval of the Outline and Assembly Drawings and Transformer Design Data Review Report in SECTION 48 19 23.05 26 j2. Line Item No. 0010B; (FP) Final Design approval of the 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformers. Payment will be a maximum of 10 (ten) percent of the total value of Line Item No. 0002 for the submission and subsequent government approval of the Detail Drawings, Descriptive Data, and Spare Parts List in SECTION 48 19 23.05 26.

j3. Line Item No. 0010C; (FP) Tank Production for the 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformers. Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0002 for the completion of building and painting the two (2) main transformer tanks as approved in the Detail Drawings in SECTION 48 19 23.05 26.

j4. Line Item No. 0010D; (FP) Winding Construction for the 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformers. Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0002 for the completion of winding, drying, and pressing the transformer windings.

j5. Line Item No. 0010E; (FP) Core Construction for the 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformers. Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0002 for the completion of slitting, stacking, banding, and clamping of the lower core assembly into a complete unit ready for installation of transformer windings.

j6. Line Item No. 0010F; (FP) Assembly of the 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformers in the factory. Payment will be a maximum of 20 (twenty) percent of the total value of Line Item No. 0002 for the complete factory assembly and oil-filling of the transformer and installation of all external components.

j7. Line Item No. 0010G; (FP) Testing of the 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformers in the factory. Payment will be the remaining balance of the total value of Line Item No. 0002 for the completion of factory transformer testing.

k. Line Item No. 0011; (FP) Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformers and accessories from the manufacturing facility complete to the Fort Peck Dam power plant . Payment will be full compensation for the operations, materials, and equipment

SECTION 01 22 00 Page 7 required to transport the transformers and accessories from the manufacturing facility to the Fort Peck Dam power plant.

l. Line Item No. 0012; (FP) Offload the 42,000/56,000 kVA, 230 kV three-phase power transformers and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer . Payment will be full compensation for the labor, materials and equipment required to offload the transformers and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish transformer oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. Payment for provision of services of an Erecting Engineer will include the following:

Payment will cover the total number of working days during the period of time that the Erecting Engineer is in the service to the Government and is at the project site and working. Payment will include the time required to travel by the most direct commercial airline from the Erecting Engineer's home station or duty station to the job site. Return travel time will only be allowed from time of first available transportation after release by the Government for return to home station or duty station.

Payment will cover the daily cost of a rental car to transport the Erection Engineer from the local motel to the Fort Peck Dam power plant work site, and per-diem costs for meals and lodging.

m. Line Item No. 0013; (FP) Move the 42,000/56,000 kVA, 230 kV three-phase power transformers from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent .

Payment will be full compensation for the labor, materials and equipment required to move the fully assembled transformers from temporary storage location at Fort Peck Dam to the permanent operating locations, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. Payment for provision of services of an Erecting Engineer and Commissioning Agent will include the following:

Payment will cover the total number of working days during the period of time that the Erecting Engineer or Commissioning Agent is in the service to the Government and is at the project site and working. Payment will include the time required to travel by the most direct commercial airline from the Erecting Engineer's or Commissioning Agent's home station or duty station to the job site. Return travel time will only be allowed from time of first available transportation after release by the Government for return to home station or duty station.

Payment will cover the daily cost of a rental car to transport the Erection Engineer or Commissioning Agent from the local motel to the Fort Peck Dam power plant work site, and per-diem costs for meals and lodging.

SECTION 01 22 00 Page 8

n. Line Item No. 0014; (FP) Furnish Spare Parts (See Section 48 19

23.04 26) . Furnishing spare parts for the Fort Peck Dam transformers will be measured for payment as a complete pay item (Lot). Payment will be made at the contract lump sum price, which price and payment will be full compensation for furnishing the spare parts for the transformers, complete, as specified in Section 48 19 23.04 26, and as approved.

PART 2 PRODUCTS

(NOT USED)

PART 3 EXECUTION

(NOT USED)

-- End of Section --