This document contains a site visit report and related federal contract opportunity. The site visit report details surveys of two ponds, Greta's Pond and Nest Pond, located at Swallows Nest Country Club in Sacramento, California. It includes maps with pond dimensions and depth readings, as well as photographs of structural features like wells, inlets, and a concrete weir.

The related federal contract opportunity is a solicitation for the Natomas Reach A Levee Repairs project. Bids are due on August 16, 2021 at 1:00PM PST. The solicitation includes 18 technical attachments, with two oversized attachments containing plans and a geotechnical report that must be requested separately. The purpose of the project is to repair levees in the Natomas Reach A area of Sacramento. The soliciting agency is the U.S. Army Corps of Engineers Sacramento District.

View the file

Other files

File Type Posted
C04 - Bid Abstract for W9123821B0012.pdf PDF
B08 Amendment 0005.pdf PDF
B08 Amendment 0005 - updated section 31 56 14.pdf PDF
B08 - Drawing 701 and 702.pdf PDF
B08 Amendment 0004.pdf PDF
B08 - Pricing Schedule.Final.pdf PDF
B08 - Drawing 701 and 702.pdf PDF
B08 W91238-B-21-0012_AM04 Summary of Changes.pdf PDF
B08 SIP (AM-04) PP1A Outfall Grouting - Plan View.pdf PDF
B08 SIP (AM-04) Mix-In-Place Cutoff Wall - Butt Joint and Overlap Schematic.pdf PDF
B08 - Drawing C-228.pdf PDF
B08 SIP (AM-04) Kaufman_Borrow_Staging_Reach-A_20210728.pdf PDF
B08 W91238-B-21-0012_AM04_2172_20210804 Specifications Updates.pdf PDF
B08 Amendment 3_Updated Plans and Specifications.pdf PDF
B08 Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Amendment 2 - Specification Changes.pdf PDF
B07 Site Visit Attendance List.pdf PDF
Amendment 0001 - Site Visit Date Change.pdf PDF
B08 Reach A IFB W9123821B0012.pdf PDF
B08 IFB Atch 9 - SIP_Plant 1A and 1B Duperon Self-Cleaning Trash Rake Manual.pdf PDF
B08 IFB Atch 10 - SIP_Plant 1B datum conversion.pdf PDF
B08 IFB Atch 15 - SIP_Pumping Plant No 1 Rockwell Automation order info.pdf PDF
B08 IFB Atch 12 - SIP_Pumping Plant 1B Drawings - As-built Markups (2003).pdf PDF
B08 IFB Atch 14 - SIP_Pumping Plant No 1 Rockwell Automation existing pump starters.pdf PDF
B08 IFB Atch 17 - SIP_USACE ARCF Executed PA 20150910.pdf PDF
B08 IFB Atch 18 - SIP_USACE ARCF GRR HPMP Final_071317.pdf PDF
B08 IFB Atch 8 - SIP_Natomas Reach A - R1 Cutoff Wall As-Builts (Complete Drawing Set).pdf PDF
B08 IFB Atch 16 - SIP_Reach I Contract 1 Stockpile Information Report.pdf PDF
B08 IFB Atch 20 - Pre-Award Survey.pdf PDF
B08 IFB Atch 11 - SIP_PP1B Cascade 20003 Pump Shop Drawing.pdf PDF
B08 IFB Atch 6 - SIP_Natomas Reach A - Borrow Site GDR - 20190321.pdf PDF
B08 IFB Atch 5 - SIP_Kaufman_Borrow_Site_Reach-A_34x22_20210607.pdf PDF
B08 IFB Atch 13 - SIP_Pumping Plant 1B Operating Elevations.docx DOCX document
B08 IFB Atch 19 - Davis Bacon Wage Determination 6.25.2021.pdf PDF
B08 IFB Atch 2 - Reach A Specifications_2172_20210616.pdf PDF
B08 IFB Atch 4 - SIP_City Sump 160 - Design Drawings (1990s).pdf PDF
B08 IFB Atch 3 - Reach A_Final Design Pricing Schedule.xlsx XLSX spreadsheet
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Natomas Reach A Sacramento, CA

Introduction

This Report consist of a site visit to Swallows Nest Country Club and I-80 Bridge at Garden Highway, Sacramento California. The United States Army Corps of Engineers (USACE), Sacramento District conducted a site visit to survey two ponds located at Swallows Nest Country Club, Greta’s pond and Nest pond and the I-80 Bridge at Garden Highway, see Appendix for maps, dimensions and pictures. Brian Sauer and Richard Harvey conducted the site visit from USACE 1 February 2018.

Swallows Nest Country Club

During the site to Swallows Nest Country Club Rick Webb, the chair for Swallows Nest Homeowners

Association Design Review Committee, escorted us around to the two ponds, Greta’s pond and Nest pond, to complete the survey. Rick Webb provided us with a small aluminum boat and paddles to aid in surveying the bottom depth of the ponds.

Greta’s Pond

Greta’s pond dimensions were measured using a surveyors measuring wheel and are 220’ length by 60’ width. The depth of the pond was measured using a fiberglass surveying grade/ level rod, see Appendix for map with depth and location readings. There are several structural features around the pond that can be seen on the map in Appendix. South East of the pond located on the other side of a fence is a well that supplies water to

Greta’s pond, it is approximately 115’ south of the pond. The well inlet to the pond is approximately 45’ west of the east side of the pond on the south shore. The well water to the pond runs on a float system that fills the pond when the water gets low and using a concrete weir located on the North West shore of the pond keeps the pond at a consistent level. Rick informed us that Greta’s pond is about a foot below the normal water level due to the float system being a little off center that will be fixed soon. The slope of the side of the pond was measured at on the south side of the pond and had a 5’ Run and 2’ Rise, with the water elevation being 2’ below the ground surface elevation. This pond is only for ascetics.

Nest Pond

Nest pond dimensions were measured using a surveyors measuring wheel and are located on the map in

Appendix. The depth of the pond was measured using a fiberglass surveying grade/ level rod, see Appendix for map with depth and location readings. There are several structural features around the pond that can be seen on the map in Appendix. The well that supplies Greta’s pond also supplies Nest pond. The well inlet to the pond is located on the East shore of the pond. The well water to the pond runs on a float system that fills the pond when the water gets low and using a concrete weir located on the North West shore of the pond keeps the pond at a consistent level. The slope of the side of the pond was measured at on the south side of the pond and had a 10’

Run and 3’ Rise, with the water elevation being 3’ below the ground surface elevation. This pond is used as

Storm water Management Basin to catch runoff from the community to the west.

Swallows Nest Country Club contact information

Rick Webb, Chair

Swallows Nest Homeowners Association Design Review Committee

Email: rfwebb@sbcglobal.net mailto:rfwebb@sbcglobal.net

L2EDGKAK

Rectangle

Greta’s Pond Map with Dimensions

Pictures

Greta’s Pond

Greta’s Pond Overview Picture

Concrete Culvert Structure

Well South of Greta’s Pond

Well Inlet to Greta’s Pond 1

Well Inlet to Greta’s Pond 2

Well Pump to Pond Float System

Concrete Weir

File details come from the government source that posted it. Updated .