About this file

This document contains a pre-award survey template for prospective construction contractors and details regarding the Natomas Reach A Levee Repairs solicitation. The survey template collects information from prospective contractors including organization type, personnel details, equipment owned, financial data, descriptions and values of past construction projects, and type of work specialized in. The federal contract opportunity seeks bids for levee repairs along Natomas Reach A, with bids due on August 16, 2021. Qualified bidders must attend a July 8 site visit, and requests for two oversized attachments containing plans and geotechnical data should be directed to the specified Contract Administrator and Contracting Officer via email. The opportunity is issued by the Department of the Army Corps of Engineers Sacramento District for levee repairs.

View the file

Other files for this federal contract opportunity

Other files attached to Natomas Reach A Levee Repairs, newest first.
File Type Posted
C04 - Bid Abstract for W9123821B0012.pdf PDF
B08 Amendment 0005.pdf PDF
B08 Amendment 0005 - updated section 31 56 14.pdf PDF
B08 - Drawing 701 and 702.pdf PDF
B08 - Drawing 701 and 702.pdf PDF
B08 Amendment 0004.pdf PDF
B08 SIP (AM-04) PP1A Outfall Grouting - Plan View.pdf PDF
B08 SIP (AM-04) Gretas Pond Supplemental Info_and_Photos - Feb_2018.pdf PDF
B08 - Drawing C-228.pdf PDF
B08 W91238-B-21-0012_AM04_2172_20210804 Specifications Updates.pdf PDF
B08 - Pricing Schedule.Final.pdf PDF
B08 W91238-B-21-0012_AM04 Summary of Changes.pdf PDF
B08 SIP (AM-04) Mix-In-Place Cutoff Wall - Butt Joint and Overlap Schematic.pdf PDF
B08 SIP (AM-04) Kaufman_Borrow_Staging_Reach-A_20210728.pdf PDF
B08 Amendment 3_Updated Plans and Specifications.pdf PDF
B08 Amendment 0003.pdf PDF
Amendment 2 - Specification Changes.pdf PDF
Amendment 0002.pdf PDF
B07 Site Visit Attendance List.pdf PDF
Amendment 0001 - Site Visit Date Change.pdf PDF
B08 IFB Atch 16 - SIP_Reach I Contract 1 Stockpile Information Report.pdf PDF
B08 IFB Atch 9 - SIP_Plant 1A and 1B Duperon Self-Cleaning Trash Rake Manual.pdf PDF
B08 IFB Atch 8 - SIP_Natomas Reach A - R1 Cutoff Wall As-Builts (Complete Drawing Set).pdf PDF
B08 IFB Atch 17 - SIP_USACE ARCF Executed PA 20150910.pdf PDF
B08 IFB Atch 5 - SIP_Kaufman_Borrow_Site_Reach-A_34x22_20210607.pdf PDF
B08 Reach A IFB W9123821B0012.pdf PDF
B08 IFB Atch 19 - Davis Bacon Wage Determination 6.25.2021.pdf PDF
B08 IFB Atch 4 - SIP_City Sump 160 - Design Drawings (1990s).pdf PDF
B08 IFB Atch 3 - Reach A_Final Design Pricing Schedule.xlsx XLSX spreadsheet
B08 IFB Atch 2 - Reach A Specifications_2172_20210616.pdf PDF
B08 IFB Atch 10 - SIP_Plant 1B datum conversion.pdf PDF
B08 IFB Atch 18 - SIP_USACE ARCF GRR HPMP Final_071317.pdf PDF
B08 IFB Atch 15 - SIP_Pumping Plant No 1 Rockwell Automation order info.pdf PDF
B08 IFB Atch 14 - SIP_Pumping Plant No 1 Rockwell Automation existing pump starters.pdf PDF
B08 IFB Atch 13 - SIP_Pumping Plant 1B Operating Elevations.docx DOCX document
B08 IFB Atch 12 - SIP_Pumping Plant 1B Drawings - As-built Markups (2003).pdf PDF
B08 IFB Atch 11 - SIP_PP1B Cascade 20003 Pump Shop Drawing.pdf PDF
B08 IFB Atch 6 - SIP_Natomas Reach A - Borrow Site GDR - 20190321.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Award Survey of Prospective Contractors

CONSTRUCTION CONTRACTOR DATA DATE:

Firm Name and Telephone Number Main Office Address (Street, City, and State)

Branch Offices Services Rendered

Construction

Design

Consultant

Organization

Individual Joint Venture

Partnership Corporation

Date Organized Date Incorporated:

State:

Names of Officers and Other Key Personnel

I – PRESENT PAYROLL PERSONNEL (List Number of Each Category Below)

Partners:

Officers:

Other Key:

Remainder: Subtotal Permanent:

Maximum Personnel at Any Time:

Date:

Total:

II—EQUIPMENT OWNED III—FINANCIAL DATA AS OF

(DATE): Present Value ($)

Current Assets:

Acquisition Cost ($) Current Liabilities:

Net Worth:

IV—TOTAL VALUE OF CONSTRUCTION AND DEMOLITION

WORK IN PAST 6 YRS EXCLUSIVE OF JOINT VENTURE

(LIST MOST RECENT FIRST)

V—LARGEST JOB EVER

CONTRACTED

(If Other Than in Past Six Years)

$ LARGEST JOB IN PAST 6 YRS Contract Amount:

Date:

Description:

Owner:

$ Contract Amount:

Date:

Description:

Owner:

Avg. Annual Income

VI—TYPE OF WORK IN WHICH FIRM SPECIALIZES

NAME AND POSITION/TITLE OF PERSON SIGNING SIGNATURE

See attachment for explanations or detailed description of item(s) reported above.

CONSTRUCTION CONTRACTOR DATA – SCHEDULE A – EXISTING COMMITMENTS

List below the construction projects your firm currently has under way, including recent awards. Also list construction projects for which your firm is the apparent successful offeror/bidder, but for which a contract has not yet been awarded.

CONTRACT

NUMBER

AMOUNT

DESCRIPTION/

LOCATION

ORGANIZATION/

CONTACT PERSON/

PHONE NUMBER

PERCENT

COMPLETE

CONSTRUCTION CONTRACTOR DATA – SCHEDULE B – COMPLETED PROJECTS

List below the principal construction projects your firm has completed within the past six years, including all DoD contracts.

NUMBER

AMOUNT

DESCRIPTION/

LOCATION

ORGANIZATION/

CONTACT PERSON/

PHONE NUMBER

PERCENT

SUBLET

CONSTRUCTION CONTRACTOR DATA – SCHEDULE C –

CONSTRUCTION AND/OR TECHNICAL EQUIPMENT

List total equipment and facilities owned for performing the prospective contract and present status as to whether or not it is currently committed to existing contracts.

QUANTITY

DESCRIPTION

CONDITION

YEARS OF

SERVICE

PRESENT

STATUS