Attach 16, Final NMFS Letter signed 4Oct2016.
View the file
Other files for this federal contract opportunity
Show all 50
Replace/Upgrade Pier 2 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 6, 2016
SUBJECT: Follow-on Section 7 Consultation Regarding Revised Design for the
Project to Replace/Upgrade Pier 2 at Military Ocean Terminal Concord, Concord, CA
Gary Stern National Marine Fisheries Service Santa Rosa Area Office West Coast Region 777 Sonoma Ave., Room 325 Santa Rosa, CA 95404
Dear Mr. Stern:
The Department of the Army (Army) submitted a letter to the National Marine
Fisheries Service (NMFS) dated January 29, 2016 regarding the proposed design changes for the project to replace/upgrade Pier 2 at Military Ocean Terminal Concord (MOTCO), California and potential need for re-initiation of formal consultation under Section 7 of the Endangered Species Act. At the request of U.S. Fish and Wildlife Service (USFWS) and as coordinated with NMFS, the Army prepared a letter dated June 3, 2016 wherein the Army evaluated the potential changes in the effects as compared to the NMFS Biological Opinion (BO) and Essential Fish Habitat (EFH) Response dated November 19, 2014 (SWR-2013-9819). This letter concluded that, overall, the effects of the revised design are expected to have lesser impact on the species addressed in the BO and EFH Consultation.
A conference call was held on August 10, 2016 with NMFS and USFWS to further exchange information regarding the revised design and analysis. This letter is in response to additional information and clarification requested during this conference call, including reconsideration of some design elements to further ensure that the potential effects of the redesign would have lesser effect to the species as addressed in the BO.
Specifically, the Army has 1) reverted to a conceptual redesign construction timeline that conforms with the notional schedule provided in prior consultations and
2) revised the placement of the electrical feeder line for the electrical substation.
Additionally, the Habitat Restoration Plan and associated Shoreline Protection Plan are under preparation and we expect to submit these for your review and approval in late October. As stated in the February 2015 Final Environmental Impact Statement for the Modernization and Repair of Piers 2 and 3 at MOTCO, these plans were developed as part of the design process and the Army committed to providing NMFS with an opportunity for review of these plans. A brief summary of the content of these plans is provided below. All other elements of the revised design are the same as those described in the June 3, 2016 letter. With these changes, the Army is confident that all effects of the redesign are within the scope of the impacts of the Pier 2 project as
DEPARTMENT OF THE ARMY
Military Surface Deployment and Distribution Command
834Th Transportation Battalion 410 Norman Avenue
Concord, California 94520-1142
REPLY TO
ATTENTION OF
previously addressed in the BO.
Construction and Demolition Timeframes. The requested additional detail on the planned schedule for implementation of the project is provided in Enclosure 1. The Army has ensured that this schedule conforms to the timeline of the BO, specifically: 27 months to complete the project start to finish; including 24 months for construction and 7 months for demolition.
Substation Electrical Feeder Line Corridor Realignment. The Army has evaluated an alternate pathway, shown in Enclosure 2, and the proposed utility corridor has been rerouted to occur within the footprint of existing roadways. The proposed rerouting of the utility line corridor avoids the potential impacts for USFWS administered species noted in the June 3, 2016 letter.
Habitat Restoration Plan and Shoreline Protection Plan. The Habitat Restoration Plan addresses the restoration of habitat within the areas currently occupied by structures to be removed. The Habitat Restoration Plan also includes the removal of stands of perennial pepperweed (Lepidium latifolium), grading to establish elevations less favorable for pepperweed, and restoration in place for wetlands disturbed during construction to provide a more continuous intertidal to upland marsh habitat dominated by native species. The associated Shoreline Protection Plan details the plan for prevention of erosion of the shoreline west of Pier 2 and repair of the shoreline rock revetment along White Road and includes an estimated approximately 0.25-acre area of unavoidable impact to intertidal wetlands. The Habitat Restoration Plan provides for no net loss of wetlands and a 2:1 wetlands mitigation ratio (approximately 0.57 acres).
These plans also will be submitted to the U.S. Army Corps of Engineers and the San Francisco Bay Regional Water Quality Board as part of the Clean Water Act Section 404 and 401 permitting for the Pier 2 project.
The following additional details are provided to supplement the June 3, 2016 letter with additional information as requested by NMFS and USFWS during the August 10, 2016 conference call.
Use of Cushion Blocks. The Army remains committed to the use of cushion blocks made of wood or a composite material, such as Micarta™, to reduce impact pile driving noise. The June 3, 2016 letter updated the noise analysis to reflect newer guidance against applying a specific sound level reduction credit for the use of a cushion block.
No Simultaneous Pile Driving. Pile driving will occur at the same rate as analyzed in the BO (4-5 piles per day, on average). The June 3, 2016 letter included analysis that assumed that two pile driving rigs may be used for an approximately 15-day period. The BO did not specify number of rigs and the Army’s noise analysis in the BA was based on one rig being operational at any given time. The June 3, 2016 letter analyzed a worst-case scenario assumption involving simultaneous strikes of two pile drivers. However, the Army is committed to implementing management practices to ensure piles will not be driven simultaneously by these rigs. Specifically, the contractor will be required to ensure that there is communication between the two operations that will allow one rig to commence pile driving activities while the second is positioning and staging the next pile installation during the approximately 15-day period. Thus, contemporaneous rig operations will not result in additive sound pressure levels experienced by species in the vicinity of the work area.
As indicated in the updated conceptual schedule for the project, Enclosure 1, much of the pile driving work would occur during the approved salmonid work window of June 1st through November 30th. This updated work schedule is similar to the notional schedule that the Army provided in the August 2014 Addendum to the Army’s Biological Assessment for the Pier 2 project. The approximately 15-day contemporaneous pile driving at the West Trestle and Main Platform is scheduled for August 2018.
Summary Differences Between the Pier 2 Redesign as Compared to the Project as Defined in the EFH and BO.
• Reduced total Pier 2 footprint (the new pier will be reduced by
30,942 square feet under the existing Pier 2 footprint, which is approximately 15,963 square feet smaller than the footprint of the previous design).
• New West Trestle. Under the redesign, the west trestle would be combined with the forklift trestle, thus eliminating the second trestle approach footprint (see Enclosure 2). The habitat impacts of the new west trestle footprint would be offset by the removal of structures associated with the existing west trestle, forklift trestle, and pedestrian trestle and associated habitat restoration. Therefore, the overall trestle footprint would be over a similar sized area and within the project footprint as addressed in the BO.
• Fewer piles (the redesign includes installation of 793 24-inch octagonal concrete piles, whereas the BO included 876 of these piles).
• No dredging.
• Less extensive repairs to White Road (the redesign would repair 1,350 linear feet; the BO included approximately 8,500 linear feet of this road).
• Please see the June 3, 2016 letter for additional detail.
Conclusion. The Army believes the determinations of potential impacts to species analyzed in the BO and EFH Consultation remain unchanged with the Pier 2 redesign.
These conclusions are restated as likely to adversely affect but not likely to jeopardize the continued existence of Central Valley steelhead, Central California Coast steelhead, Sacramento River Winter-run Chinook, Central Valley Spring-run Chinook, or North American green sturgeon. The Pier 2 project is likely to adversely affect but not likely to jeopardize the continued existence of these species or destroy or adversely modify Sacramento winter-run Chinook or green sturgeon designated critical habitat. With respect to EFH, these conclusions were that the Pier 2 project would have an adverse effect to Pacific Groundfish, Pacific Coast Salmon, and Coastal pelagic EFH:
The Army remains committed to continued adherence to the reasonable and prudent measures, terms and conditions, and conservation recommendations of the BO pursuant to Section 7 of the Endangered Species Act and the EFH Conservation Recommendations pursuant to the Magnuson-Stevens Fishery Conservation and Management Act. The Army hereby requests written concurrence from NMFS on the Army’s conclusions that revised design for the project to replace/upgrade Pier 2 does not change the determinations of the BO and EFH Consultation and that re-initiation of l2ct9dec Sticky Note How to mitigate...
ID Task Name Duration Start Finish Predecessors Resource Names
Successors
1 REPLACE/UPGRADE PIER 2 PROJECT 575.9 days 7/17/17 10/25/19
2 PRECONSTRUCTION MEETING 0 days 7/17/17 7/17/17
3 PRE-CONSTRUCTION SUBMITTALS 70 days 7/17/17 10/24/17
4 Notice to Proceed 0 days 7/17/17 7/17/17 5,14,16SS+10 days
5 General Submittals & Schedule 50 days 7/17/17 9/26/17 4 6SS+20 days
6 Construction Materials & Procedures Submittals 50 days 8/14/17 10/24/17 5SS+20 days 12,11,8,18
7 MATERIAL PROCUREMENT 320 days 7/17/17 10/22/18
8 Furnish PC/PS Concrete Indicator Piles 10 days 10/24/17 11/7/17 6,16 37SS+30 days
9 Production Pile Indicator Program Analysis 45 days 12/19/17 2/26/18 37 10
10 Furnish PC/PS Concrete Production Piles 66 days 2/26/18 5/30/18 9 45SS+30 days,38SS+22 days,11
11 Furnish PC/PS Concrete Deck Slabs 80 days 5/30/18 9/21/18 6,10 55
12 Furnish Electrical Substation 250 days 10/24/17 10/22/18 6 80
13 General Mobilization & Prepatory Work 53 days 7/17/17 9/29/17
14 General Mobilization and Setup 43 days 7/17/17 9/15/17 4 15SS+10 days,18,64
15 Strengthen West Trestle for Construction Access 43 days 7/31/17 9/29/17 14SS+10 days 18
16 Construct Yard and Storage Areas 20 days 7/31/17 8/28/17 4SS+10 days 8
17 DEMOLITION 151 days 10/24/17 6/1/18
18 Mobilization - Demolition 5 days 10/24/17 10/31/17 6,14,15 21,63SS,22,19
19 Hazmat Removal & Treatment 10 days 10/31/17 11/14/17 18 20,23,25
20 Demolish Building A21 5 days 11/14/17 11/21/17 19
21 Salvage Railroad Tracks 16 days 10/31/17 11/22/17 18
22 Salvage Fender System (excl. concrete piles) 8 days 10/31/17 11/10/17 18 DF #2
23 DEMOLISH WEST TRESTLE (1st 1/2) 22 days 11/14/17 12/18/17 19 24
24 DEMOLISH WEST TRESTLE (2ND 1/2) 22 days 12/18/17 1/22/18 23 27
25 DEMOLISH PEDESTRIAN TRESTLE 10 days 11/14/17 11/30/17 19 26
26 DEMOLISH MIDDLE TRESTLE 22 days 11/30/17 1/3/18 25 38
27 Demolish Main Platform - Concrete Superstructure 19 days 1/22/18 2/16/18 24 DF #1 28
28 Demolish Main Platform - Extract/Breakoff Concrete Piles 10 days 2/16/18 3/5/18 27 DF #1 29,30SS+10 days
29 Demolish Main Platform - Extract Concrete Piles 22 days 3/5/18 4/4/18 28 DF #1,DF #2
30 Demolish Main Platform - Timber Superstructure 40 days 3/5/18 4/30/18 28SS+10 days DF #2 32SS+15 days,31SS+10 days
31 Demolish Main Platform - Extract Timber Piles, Breakoff 30 days 3/19/18 4/30/18 30SS+10 days DF #1
32 Demolish Main Platform - Extract Timber Piles 40 days 3/26/18 5/21/18 30SS+15 days DF #1,DF #2 36,45SS+20 days,33
33 Demolish East Trestle - Concrete Superstructure 5 days 5/21/18 5/29/18 32 DF #1 54,34
34 Misc. Demolition 3 days 5/29/18 6/1/18 33 DF #2 85
35 PIER CONSTRUCTION 464.9 days 12/7/17 10/10/19
36 Mobilization - Pier Construction 30 days 5/21/18 7/3/18 32 38
37 Drive Concrete Indicator Piling - Main Platform 8 days 12/7/17 12/19/17 8SS+30 days MC #1 9
38 Drive Concrete Piling - West Trestle 24 days 7/3/18 8/7/18 10SS+22 days,36,26 MC #2 39,45
39 Concrete Abutment & Approach - West Trestle 20 days 8/7/18 9/5/18 38 MC #2 40
40 CIP Concrete Pile Caps - West Trestle 40 days 9/5/18 10/31/18 39 MC #2 41
41 PC/PS Concrete Deck Panels - West Trestle 43 days 10/31/18 1/4/19 40 MC #2 42,43,44
42 CIP Concrete Deck Topping Slab - West Trestle 15 days 1/4/19 1/28/19 41 MC #2
43 Metal Guardrails - West Trestle 5 days 1/4/19 1/11/19 41
44 M&E Utilities - West Trestle 40 days 1/4/19 3/5/19 41 61
45 Drive Concrete Piling - Main Platform 170 days 8/7/18 4/11/19 10SS+30 days,32SS+20 days,38MC #1 46SS+25 days,49
46 CIP Concrete Caps/Beams/Deck - Main Platform 210 days 9/12/18 7/15/19 45SS+25 days MC #3 48,53FF+21 days,60SS+100 days,47,49FF
47 Crane Rail/Stops - Main Platform 30 days 8/26/19 10/7/19 46 MC #1 61
48 Expansion Joints - Main Platform 15 days 7/15/19 8/5/19 46 MC #3 51
49 Drive Concrete Fender Piling - Main Platform 26 days 6/6/19 7/15/19 45,46FF MC #1 50
50 Fender System - Main Platform 12 days 8/27/19 9/13/19 49 MC #1 61
575.9 days
PRECONSTRUCTION MEETING
70 days PRE-CONSTRUCTION SUBMITTALS
General Submittals & Schedule
Construction Materials & Procedures Submittals
320 days MATERIAL PROCUREMENT
Furnish PC/PS Concrete Indicator Piles
Production Pile Indicator Program Analysis
Furnish PC/PS Concrete Production Piles
Furnish PC/PS Concrete Deck Slabs
Furnish Electrical Substation
53 days
General Mobilization and Setup
Strengthen West Trestle for Construction Access
Construct Yard and Storage Areas
151 days DEMOLITION
Mobilization - Demolition
Hazmat Removal & Treatment
Demolish Building A21
Salvage Railroad Tracks
Salvage Fender System (excl. concrete piles)
DEMOLISH WEST TRESTLE (1st 1/2)
DEMOLISH WEST TRESTLE (2ND 1/2)
DEMOLISH PEDESTRIAN TRESTLE
DEMOLISH MIDDLE TRESTLE
Demolish Main Platform - Concrete Superstructure
Demolish Main Platform - Extract/Breakoff Concrete Piles
Demolish Main Platform - Extract Concrete Piles
Demolish Main Platform - Timber Superstructure
Demolish Main Platform - Extract Timber Piles, Breakoff
Demolish Main Platform - Extract Timber Piles
Demolish East Trestle - Concrete Superstructure
Misc. Demolition
464.9 days PIER CONSTRUCTION
Mobilization - Pier Construction
Drive Concrete Indicator Piling - Main Platform
Drive Concrete Piling - West Trestle
Concrete Abutment & Approach - West Trestle
CIP Concrete Pile Caps - West Trestle
PC/PS Concrete Deck Panels - West Trestle
CIP Concrete Deck Topping Slab - West Trestle
Metal Guardrails - West Trestle
M&E Utilities - West Trestle
Drive Concrete Piling - Main Platform
CIP Concrete Caps/Beams/Deck - Main Platform
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May 2017 2018
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
MILITARY OCEAN TERMINAL CONCORD (MOTCO)
REPLACE/UPGRADE PIER 2
MOTCO REPLACE/UPGRADE PIER 2
Project: 8655-02 MOTCO PIER 2 100%
Salmonid Work Window Overlapping Salmonid and Delta Smelt Work Window carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle
ID Task Name Duration Start Finish Predecessors Resource Names
Successors
51 Mooring Bollards/Life Rings - Main Platform 5 days 8/5/19 8/12/19 48 MC #3 52
52 Guardrail - Main Platform 5 days 8/12/19 8/19/19 51 MC #3 61
53 M&E Utilities - Main Platform 68 days 5/7/19 8/13/19 46FF+21 days 82
54 CIP Concrete Caps - East Trestle 20 days 5/29/18 6/26/18 33 MC #4 55
55 PC/PS Concrete Deck Panels - East Trestle 10 days 9/21/18 10/5/18 11,54 MC #4 56
56 CIP Concrete Infill Beams - East Trestle 60 days 10/5/18 1/3/19 55 MC #4 57
57 FRP Beam Reinforcement - East Trestle 80 days 1/3/19 4/29/19 56 MC #4 58
58 Repair Deck Concrete/Paving - East Trestle 30 days 4/29/19 6/11/19 57 MC #4 59,84SS
59 Electrical Utilities - East Trestle 20 days 6/11/19 7/10/19 58 61
60 Pier Operations Building 80 days 2/6/19 5/31/19 46SS+100 days 61
61 Pier Construction Demobilization 3 days 10/8/19 10/10/19 59,60,47,44,50,52 87,88
62 LANDSIDE CONSTRUCTION 512 days 9/15/17 9/27/19
63 MEC/UXO Clearance 20 days 10/24/17 11/21/17 18SS
64 Place Initial Surcharge Fill - West Trestle Approach 2 days 9/15/17 9/19/17 14 65
65 Install Wick Drains - West Trestle Approach/White Rd. 30 days 9/19/17 10/31/17 64 66
66 Place Surcharge Fill - West Trestle Approach/White Rd. 3 days 10/31/17 11/3/17 65 67
67 Two Week Waiting Period 10 days 11/3/17 11/17/17 66 68
68 Place Surcharge Fill - West Trestle Approach/White Rd. 3 days 11/17/17 11/22/17 67 69
69 Two Week Waiting Period 10 days 11/22/17 12/8/17 68 70
70 Place Surcharge Fill - West Trestle Approach/White Rd. 3 days 12/8/17 12/13/17 69 71
71 Surcharge Period incl. Boring/CPT's 110 days 12/13/17 5/22/18 70 72
72 Remove Surcharge 10 days 5/22/18 6/6/18 71 73
73 Whites Road Improvements 90 days 6/6/18 10/12/18 72 74,79FF,76
74 West Trestle Approach Improvements 20 days 10/12/18 11/9/18 73 75
75 East Trestle Approach Improvements 10 days 11/9/18 11/27/18 74 84
76 Electrical Substation Concrete Pad 12 days 10/12/18 10/30/18 73 77,80
77 Striping & Signage 3 days 10/30/18 11/2/18 76 78,82
78 Misc. Sitework Items 5 days 11/2/18 11/9/18 77 85
79 Mechanical Utilities - White Road Improvements 30 days 8/30/18 10/12/18 73FF 82
80 Electrical Substation incl. Entrance Connection 90 days 10/30/18 3/13/19 76,12 81
81 Connections to Pier Electrical Systems 5 days 3/13/19 3/20/19 80 85
82 Connections to Pier Water & Sewer Systems 3 days 8/13/19 8/16/19 53,77,79 85
83 GENERAL CLOSEOUT 106 days 4/29/19 9/27/19
84 Punchlist and Cleanup 53 days 4/29/19 7/15/19 58SS,75 85FF+10 days
85 Demobilization 29 days 8/16/19 9/27/19 84FF+10 days,82,81,78,34 90
86 POST-CONSTRUCTION SUBMITTALS 11 days 10/11/19 10/25/19
87 Project Record Documents 10 days 10/11/19 10/24/19 61 90
88 Closeout Procedures 10 days 10/11/19 10/24/19 61 89
89 Project Complete 1 day 10/25/19 10/25/19 88
90 Project Complete 1 day 10/25/19 10/25/19 85,87
CIP Concrete Caps - East Trestle
PC/PS Concrete Deck Panels - East Trestle
CIP Concrete Infill Beams - East Trestle
FRP Beam Reinforcement - East Trestle
Repair Deck Concrete/Paving - East Trestle
Pier Operations Building
512 days LANDSIDE CONSTRUCTION
MEC/UXO Clearance
Place Initial Surcharge Fill - West Trestle Approach
Install Wick Drains - West Trestle Approach/White Rd.
Place Surcharge Fill - West Trestle Approach/White Rd.
Two Week Waiting Period
Place Surcharge Fill - West Trestle Approach/White Rd.
Two Week Waiting Period
Place Surcharge Fill - West Trestle Approach/White Rd.
Surcharge Period incl. Boring/CPT's
Remove Surcharge
Whites Road Improvements
West Trestle Approach Improvements
East Trestle Approach Improvements
Electrical Substation Concrete Pad
Striping & Signage
Misc. Sitework Items
Mechanical Utilities - White Road Improvements
Electrical Substation incl. Entrance Connection
Connections to Pier Electrical Systems
106 days
Punchlist and Cleanup
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May 2017 2018
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
MILITARY OCEAN TERMINAL CONCORD (MOTCO)
REPLACE/UPGRADE PIER 2
MOTCO REPLACE/UPGRADE PIER 2
Project: 8655-02 MOTCO PIER 2 100%
Salmonid Work Window Overlapping Salmonid and Delta Smelt Work Window carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle
ID Task Name Duration Start
1 REPLACE/UPGRADE PIER 2 PROJECT 575.9 days 7/17/17
2 PRECONSTRUCTION MEETING 0 days 7/17/17
3 PRE-CONSTRUCTION SUBMITTALS 70 days 7/17/17
4 Notice to Proceed 0 days 7/17/17
5 General Submittals & Schedule 50 days 7/17/17
6 Construction Materials & Procedures Submittals 50 days 8/14/17
7 MATERIAL PROCUREMENT 320 days 7/17/17
8 Furnish PC/PS Concrete Indicator Piles 10 days 10/24/17
9 Production Pile Indicator Program Analysis 45 days 12/19/17
10 Furnish PC/PS Concrete Production Piles 66 days 2/26/18
11 Furnish PC/PS Concrete Deck Slabs 80 days 5/30/18
12 Furnish Electrical Substation 250 days 10/24/17
13 General Mobilization & Prepatory Work 53 days 7/17/17
14 General Mobilization and Setup 43 days 7/17/17
15 Strengthen West Trestle for Construction Access 43 days 7/31/17
16 Construct Yard and Storage Areas 20 days 7/31/17
17 DEMOLITION 151 days 10/24/17
18 Mobilization - Demolition 5 days 10/24/17
19 Hazmat Removal & Treatment 10 days 10/31/17
20 Demolish Building A21 5 days 11/14/17
21 Salvage Railroad Tracks 16 days 10/31/17
22 Salvage Fender System (excl. concrete piles) 8 days 10/31/17
23 DEMOLISH WEST TRESTLE (1st 1/2) 22 days 11/14/17
24 DEMOLISH WEST TRESTLE (2ND 1/2) 22 days 12/18/17
25 DEMOLISH PEDESTRIAN TRESTLE 10 days 11/14/17
26 DEMOLISH MIDDLE TRESTLE 22 days 11/30/17
27 Demolish Main Platform - Concrete Superstructure 19 days 1/22/18
28 Demolish Main Platform - Extract/Breakoff Concrete Piles 10 days 2/16/18
29 Demolish Main Platform - Extract Concrete Piles 22 days 3/5/18
30 Demolish Main Platform - Timber Superstructure 40 days 3/5/18
31 Demolish Main Platform - Extract Timber Piles, Breakoff 30 days 3/19/18
32 Demolish Main Platform - Extract Timber Piles 40 days 3/26/18
33 Demolish East Trestle - Concrete Superstructure 5 days 5/21/18
34 Misc. Demolition 3 days 5/29/18
35 PIER CONSTRUCTION 464.9 days 12/7/17
36 Mobilization - Pier Construction 30 days 5/21/18
37 Drive Concrete Indicator Piling - Main Platform 8 days 12/7/17
38 Drive Concrete Piling - West Trestle 24 days 7/3/18
39 Concrete Abutment & Approach - West Trestle 20 days 8/7/18
40 CIP Concrete Pile Caps - West Trestle 40 days 9/5/18
41 PC/PS Concrete Deck Panels - West Trestle 43 days 10/31/18
42 CIP Concrete Deck Topping Slab - West Trestle 15 days 1/4/19
43 Metal Guardrails - West Trestle 5 days 1/4/19
44 M&E Utilities - West Trestle 40 days 1/4/19
45 Drive Concrete Piling - Main Platform 170 days 8/7/18
46 CIP Concrete Caps/Beams/Deck - Main Platform 210 days 9/12/18
47 Crane Rail/Stops - Main Platform 30 days 8/26/19
48 Expansion Joints - Main Platform 15 days 7/15/19
49 Drive Concrete Fender Piling - Main Platform 26 days 6/6/19
50 Fender System - Main Platform 12 days 8/27/19
575.9 days
PRECONSTRUCTION MEETING
70 days PRE-CONSTRUCTION SUBMITTALS
General Submittals & Schedule
Construction Materials & Procedures Submittals
320 days MATERIAL PROCUREMENT
Furnish PC/PS Concrete Indicator Piles
Production Pile Indicator Program Analysis
Furnish PC/PS Concrete Production Piles
Furnish PC/PS Concrete Deck Slabs
Furnish Electrical Substation
53 days
General Mobilization and Setup
Strengthen West Trestle for Construction Access
Construct Yard and Storage Areas
151 days DEMOLITION
Mobilization - Demolition
Hazmat Removal & Treatment
Demolish Building A21
Salvage Railroad Tracks
Salvage Fender System (excl. concrete piles)
DEMOLISH WEST TRESTLE (1st 1/2)
DEMOLISH WEST TRESTLE (2ND 1/2)
DEMOLISH PEDESTRIAN TRESTLE
DEMOLISH MIDDLE TRESTLE
Demolish Main Platform - Concrete Superstructure
Demolish Main Platform - Extract/Breakoff Concrete Piles
Demolish Main Platform - Extract Concrete Piles
Demolish Main Platform - Timber Superstructure
Demolish Main Platform - Extract Timber Piles, Breakoff
Demolish Main Platform - Extract Timber Piles
Demolish East Trestle - Concrete Superstructure
Misc. Demolition
464.9 days PIER CONSTRUCTION
Mobilization - Pier Construction
Drive Concrete Indicator Piling - Main Platform
Drive Concrete Piling - West Trestle
Concrete Abutment & Approach - West Trestle
CIP Concrete Pile Caps - West Trestle
PC/PS Concrete Deck Panels - West Trestle
CIP Concrete Deck Topping Slab - West Trestle
Metal Guardrails - West Trestle
M&E Utilities - West Trestle
Drive Concrete Piling - Main Platform
CIP Concrete Caps/Beams/Deck - Main Platform
Crane Rail/Stops - Main Platform
Expansion Joints - Main Platform
Drive Concrete Fender Piling - Main Platform
Fender System - Main Platform
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 2018 2019 2020
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
MILITARY OCEAN TERMINAL CONCORD (MOTCO)
REPLACE/UPGRADE PIER 2
MOTCO REPLACE/UPGRADE PIER 2
Project: 8655-02 MOTCO PIER 2 100%
Salmonid Work Window Overlapping Salmonid and Delta Smelt Work Window carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle
ID Task Name Duration Start
51 Mooring Bollards/Life Rings - Main Platform 5 days 8/5/19
52 Guardrail - Main Platform 5 days 8/12/19
53 M&E Utilities - Main Platform 68 days 5/7/19
54 CIP Concrete Caps - East Trestle 20 days 5/29/18
55 PC/PS Concrete Deck Panels - East Trestle 10 days 9/21/18
56 CIP Concrete Infill Beams - East Trestle 60 days 10/5/18
57 FRP Beam Reinforcement - East Trestle 80 days 1/3/19
58 Repair Deck Concrete/Paving - East Trestle 30 days 4/29/19
59 Electrical Utilities - East Trestle 20 days 6/11/19
60 Pier Operations Building 80 days 2/6/19
61 Pier Construction Demobilization 3 days 10/8/19
62 LANDSIDE CONSTRUCTION 512 days 9/15/17
63 MEC/UXO Clearance 20 days 10/24/17
64 Place Initial Surcharge Fill - West Trestle Approach 2 days 9/15/17
65 Install Wick Drains - West Trestle Approach/White Rd. 30 days 9/19/17
66 Place Surcharge Fill - West Trestle Approach/White Rd. 3 days 10/31/17
67 Two Week Waiting Period 10 days 11/3/17
68 Place Surcharge Fill - West Trestle Approach/White Rd. 3 days 11/17/17
69 Two Week Waiting Period 10 days 11/22/17
70 Place Surcharge Fill - West Trestle Approach/White Rd. 3 days 12/8/17
71 Surcharge Period incl. Boring/CPT's 110 days 12/13/17
72 Remove Surcharge 10 days 5/22/18
73 Whites Road Improvements 90 days 6/6/18
74 West Trestle Approach Improvements 20 days 10/12/18
75 East Trestle Approach Improvements 10 days 11/9/18
76 Electrical Substation Concrete Pad 12 days 10/12/18
77 Striping & Signage 3 days 10/30/18
78 Misc. Sitework Items 5 days 11/2/18
79 Mechanical Utilities - White Road Improvements 30 days 8/30/18
80 Electrical Substation incl. Entrance Connection 90 days 10/30/18
81 Connections to Pier Electrical Systems 5 days 3/13/19
82 Connections to Pier Water & Sewer Systems 3 days 8/13/19
83 GENERAL CLOSEOUT 106 days 4/29/19
84 Punchlist and Cleanup 53 days 4/29/19
85 Demobilization 29 days 8/16/19
86 POST-CONSTRUCTION SUBMITTALS 11 days 10/11/19
87 Project Record Documents 10 days 10/11/19
88 Closeout Procedures 10 days 10/11/19
89 Project Complete 1 day 10/25/19
90 Project Complete 1 day 10/25/19
Mooring Bollards/Life Rings - Main Platform
Guardrail - Main Platform
M&E Utilities - Main Platform
CIP Concrete Caps - East Trestle
PC/PS Concrete Deck Panels - East Trestle
CIP Concrete Infill Beams - East Trestle
FRP Beam Reinforcement - East Trestle
Repair Deck Concrete/Paving - East Trestle
Electrical Utilities - East Trestle
Pier Operations Building
Pier Construction Demobilization
512 days LANDSIDE CONSTRUCTION
MEC/UXO Clearance
Place Initial Surcharge Fill - West Trestle Approach
Install Wick Drains - West Trestle Approach/White Rd.
Place Surcharge Fill - West Trestle Approach/White Rd.
Two Week Waiting Period
Place Surcharge Fill - West Trestle Approach/White Rd.
Two Week Waiting Period
Place Surcharge Fill - West Trestle Approach/White Rd.
Surcharge Period incl. Boring/CPT's
Remove Surcharge
Whites Road Improvements
West Trestle Approach Improvements
East Trestle Approach Improvements
Electrical Substation Concrete Pad
Striping & Signage
Misc. Sitework Items
Mechanical Utilities - White Road Improvements
Electrical Substation incl. Entrance Connection
Connections to Pier Electrical Systems
Connections to Pier Water & Sewer Systems
106 days
Punchlist and Cleanup
Demobilization
11 days POST-CONSTRUCTION SUBMITTALS
Project Record Documents
Closeout Procedures
1 day
Project Complete
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 2018 2019 2020
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
MILITARY OCEAN TERMINAL CONCORD (MOTCO)
REPLACE/UPGRADE PIER 2
MOTCO REPLACE/UPGRADE PIER 2
Project: 8655-02 MOTCO PIER 2 100%
Salmonid Work Window Overlapping Salmonid and Delta Smelt Work Window carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle carol.wirth Rectangle
Suisun Bay
White Rd.
WEST TRESTLE
MAIN PLATFORM
LOT 2
Mo rd oh R d.
WEST TRESTLE
SECURITY LIGHTFORKLIFT TRESTLE
EAST TRESTLE
RECONSTRUCTION
WEST TRESTLE
APPROACH PLAN
RELOCATED
ELECTRICAL SUBSTATION
WHITE ROAD
CONSTRUCTION
PLAN
EAST TRESTLE
BUILDING 160
DEMOLITION FOOTPRINT
SECURITY LIGHT
Pier 2 Footprint
Pier 2 Redesign Footprint
Mean High Tide Line
Electrical Feeder Lines
New West Trestle Approach Grading
Relocated West Trestle Approach Grading1
Relocated Electrical Substation1
White Road Grading Plan1
White Road and East Trestle Construction Plan1
East Trestle Structural Rehabilitation Footprint2
Existing Pier 2 Proposed for Demolition
Landside Demolition Area Outside of Proposed New Features
0 250125 Feet
± 0 5025 Meters Notes:
1. These areas of shoreside construction were described but not mapped in the BA for the Modernization and Repair of Piers 2 and 3. Additionally, the segments of White Road included in the Pier 2 project have been refined (and reduced) from that presented in the BA.
2. The retrofit and strengthening of the East Trestle was described but not mapped in the BA for the Modernization and Repair of Piers 2 and 3.
Enclosure 2: Pier 2 Redesign Footprints (Updated)