A2-8 HAZMAT Phase I Site Investigation Report

View the file

Other files for this federal contract opportunity

Other files attached to Replace/Upgrade Pier 2, newest first.
File Type Posted
C01.13_Award_Announcement_(synopsis).pdf PDF
A13.2_Bidder_Inquiries_11-6-2017_(FIO).pdf PDF
W9123817R0065_Amend_0005.pdf PDF
Attachment_16_Final_NMFS_Letter_signed_4Oct2016_v10042016_(clean).pdf PDF
Amendment_0005_Specifications.pdf PDF
W9123817R0065_Amend_0005_Conform_Copy.pdf PDF
W9123817R0065_Amend_0004_Conform.pdf PDF
W9123817R0065_Amend_0004.pdf PDF
Bidder_Inquiry_Reopened.pdf PDF
17-R-0065_Amend_003_Conform.docx DOCX document
Amendment_0003_Drawings_(marked_delta_2).pdf PDF
17-R-0065_Amend_003.docx DOCX document
Wage_Determination_-_CA_29.pdf PDF
SAV_Mitigation_Plan_081814.pdf PDF
NAVFAC_USACE_PPQ_Form_Sep_2011.doc DOC document
W9123817R0065_Amend_0002_Conform_Copy.pdf PDF
W9123817R0065_Amend_0002.pdf PDF
Amendment_0002_Specification_2026.pdf PDF
SCA_Wage_Determination_WD_15-5623_(Rev.-4).pdf PDF
30005CM_-_March_1988_repair.pdf PDF
30009CM_-_1958_rehabilitation.pdf PDF
Pier_MEC_Clearance_Completion_Report,_Rev_0.pdf PDF
30006CM_-_May_1967_extension_2_of_2.pdf PDF
30008CM_-_May_1967_deck_repair.pdf PDF
Pier_2_&_Barge_Pier_Naval_Weapons_Sta_Concord_CA_1994.pdf PDF
30007CM_-_Marginal_pile_records_dated_13_Oct_1944.pdf PDF
A2-9_HAZMAT_Phase_II_Report.pdf PDF
Batymetry_Layer_71057V-HP01.dwg DWG drawing
Cultural_Resources_Treatment_and_Discoveries_Plan_MOTCO_Pier_2.pdf PDF
MEC_-_Pier_2_MEC_RA_DD_Form_2977-signed.pdf PDF
Pier_2,_WFI-MCO-11-00128_Final_Reduced.pdf PDF
2002_Repair_Drawings_&_Fenders.pdf PDF
A7.3_MOTCO_Industry_Day_Photos_Nov_2016.pdf PDF
Pier_2_Site_Visit_Photos.pdf PDF
Subcontracting_Goals_(FIO).pdf PDF
DDESB_Approval,_Explosives_Safety_Submission,_Removal_ActionConstruction.PDF PDF
Attachment_4_-_MOTCO_Pier_2_Final_Supplemental_Environmental_Assessment.pdf PDF
W9123817R0065_Amend_0001.pdf PDF
Attachment_6_-_NMFS_Biological_Opinion_11_19_2014_MOTCO_Piers_2.pdf PDF
Attachment_5_-_MOTCO_Pier_2_Supplemental_Environmental_Assessment_Final_FNSI_signed.pdf PDF
Attachment_7_-_PD_Final_Environmental_Impact_Statement_MOTCO_Piers_2_2015-02-10.pdf PDF
W9123817R0065_Amend_0001_Conform_RFP.pdf PDF
Attachment_8_-_USFWS_2014-F-0002-5_MOTCO_Pier_2_Final_Biological_Opinion.PDF PDF
A7.3_Industry_Day_Maps.pdf PDF
A2.1_W9123817R0065_09-08-2017.pdf PDF
Attachment_2_-_Drawings_-_Updated_RTA_Design_Drawings_(2017-05-08).pdf PDF
Attachment_1-MOTCO_PIER_2_SPECIFICATIONS_07SEP2017.pdf PDF
MOTCO_190-3__JUN_2016-1_Final.xlsx XLSX spreadsheet
NCIC_CONSENT_FORM_-_DEC_2016_Fillable.pdf PDF
Industry_Day-Site_Vists_MOTCO_Pier_2_Replace_and_Update_Information.docx DOCX document
Show all 50

Replace/Upgrade Pier 2 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITEK ENVIRONMENTAL GUAM

PHASE 1 ENVIRONMENTAL SITE

ASSESSMENT

Pier Two Military Ocean Terminal Concord (MOTCO)

Concord, CA

Prepared for PBI/CYS Civil & Structural Consultants

2495 Natomas Park Drive, Suite 650 Sacramento, CA 95833

December 18 2014

Table of Contents Section Page

SECTION 1 EXECUTIVE SUMMARY

1.1 Current Project and Site Description

1.2 Site History

Site Reconnaissance, Records Review, and Interviews

1.3 Findings, Opinions and Conclusions

SECTION 2 INTRODUCTION

2.1 Scope of the Assessment: Purpose; Special Terms, and Conditions

2.1.1 Scope of the Assessment: Purpose

2.1.2 Scope of the Assessment: Special Terms and Conditions

2.1.3 Limitations and Exceptions of Assessment

2.1.4 Limiting Conditions and Methodology Used

2.1.5 Reliance on Information Provided by Others

2.1.6 Deviations

SECTION 3 SITE DESCRIPTION AND HISTORY

3.1 Location and Legal Description

3.2 Site and Vicinity Characteristics

3.3 Current Uses of the Property

3.4 Current Uses of Adjacent Properties

3.5 Site History and Past Uses of the Property

SECTION 4 USER PROVIDED INFORMATION

4.1 Land Ownership Records

4.2 Environmental Liens or Activity and Use Limitations

4.3 Specialized Knowledge

4.4 Commonly Known or Reasonably Ascertainable Information

4.5 Valuation Reduction for Environmental Issues

4.6 Owner, Property Manager, and Occupant Information

4.7 Reason for Performing Phase I

SECTION 5 ENVIRONMENTAL RECORDS REVIEW

5.1 Standard Environmental Record Sources

5.2 Additional Environmental Record Sources

5.3 Physical Setting Source(s)

5.4 Historical Use Information on the Property and Adjacent Properties

SECTION 6 SITE RECONNAISSANCE

6.1 Methodology and Limiting Conditions

6.2 General Site Settings

6.3 Exterior Observations

6.4 Asbestos-Containing Building Materials

6.5 PCB Electrical Equipment and Contamination

6.6 Indications of Lead Contamination

6.7 Indications of Solid Waste Disposal

6.8 Hazardous Materials Used

Phase 1 Environmental Site Assessment -i- MOTCO Pier 2 Concord Ca

6.9 Hazardous Material Wastes and Unidentified Containers

6.10 Storage Tanks

6.10.1 Observations Underground tanks

6.10.2 Observations Aboveground tanks

6.11 Potential Surface/Subsurface Contamination

6.12 Indications of Vapor Intrusion

SECTION 7 INTERVIEWS

SECTION 8 EVALUATION

8.1 Environmental Professionals Statement

8.2 References

8.3 Signature of Environmental Professional

Appendix A Site Reconnaissance Photos Appendix B Qualification of Environmental Professional

ATTACHMENTS:

1. MOTCO Explosive Safety Submission

2. MOTCO Pier 2 ESA - Radius Map Report

3. MOTCO Pier 2 ESA - Sanborn Map

4. MOTCO Pier 2 ESA - Historical Map Report

5. MOTCO Pier 2 ESA - Vapor Encroachment Screening Report

6. MOTCO Pier 2 ESA - Site Historical Maps

Phase 1 Environmental Site Assessment -ii- MOTCO Pier 2 Concord Ca

SECTION 1 EXECUTIVE SUMMARY

1.1 Current Project and Site Description

Unitek Environmental-Guam, Inc. (Unitek) was retained by PBI/CYS Civil & Structural Consultants to conduct a standard ASTM E 1527-13 Phase 1 Environmental Site Assessment (ESA) for Pier 2 of the Military Ocean Terminal Concord (MOTCO) located in Concord, California. The subject site covered by this survey is approximately 159,000 square ft., or approximately 4 acres.in size and is currently in the process of being repaired and upgraded by the US Army Corps of Engineers. The subject site currently supports a munitions handling pier, rail and truck access and operating buildings/offices located on and adjacent to the pier. The pier and associated structures were built in 1944 with modifications and repairs from that period to the present. Most of the existing structure is planned for demolition as part of repairs and upgrades to the facility. The site is located within a remote area of MOTCO due to its use as an ordnance ship loading/unloading facility.

1.2 Site History

During World War II, Pier 2 was part of an extensive ordnance loading and transportation facility supporting ammunition shipments to the Pacific area of operations as part of a facility then known as Port Chicago. In July 1944, a major explosive incident occurred at Pier 1, located immediately to the west of Pier 2, which destroyed Pier 1, two ammunition loaded ships and killed several hundred workers. The scattered munitions and debris significantly contaminated the Pier 2 water and land areas with Munitions and Explosives of Concern (MEC), which still exists in the area. An Explosive Safety Submission (ESS) was conducted in August of 2013 which documented the MEC hazard and imposed explosive safety precautions for construction activities within the area which includes planned Pier 2 demolition and construction.

The following information is quoted from the Explosive Safety Submission (Attachment 1):

The Munition Response Sites (MRSs) addressed in this ESS (Port Chicago Terrestrial Explosion Area MRS, and the Port Chicago Water Explosion Area MRS) of MOTCO are located within the affected area of the Port of Chicago Explosion of July 1944. From the 1940s through the 1990s, CNWS was a major naval munitions trans-shipment port on the West Coast. In 1944, there was an explosion in what was then known as Port Chicago, which is located in the Suisun Bay. The explosion involved more than 5,000 tons of ammunition, including MK79 fire bombs, MK47 depth bombs, MK49 650-lb depth bombs, M66 2,000-lb bombs, M65 1,000-lb bombs, MK33 1,000-lb bombs, M64 500-lb bombs, M58 500-lb bombs, MK54 350-lb bombs, MK10 projectors, 12-inch projectiles, 7.2-inch rockets, 5-inch rockets, 4.5-inch rockets, 3.5-inch rockets, 3- and 5-inch projectiles, M-5 fragmentation bombs, 20-lb fragmentation bombs, 220-lb fragmentation bombs, MK66

Phase 1 Environmental Site Assessment -3- MOTCO Pier 2 Concord Ca rocket motors, 83-mm rockets, pyrotechnics (MK1, MK 2, MK4, MK13), and 20- and 40-mm projectiles (Army-Navy Explosives Safety Board, 1945). As a result of the blast, munitions that underwent incomplete detonation or did not explode were scattered throughout the MRSs addressed in this ESS as well as the 135 acre Tidal Explosive Ordnance Disposal (EOD) Area. Based on the quantity of munitions on the ships and railcars, the Preliminary Assessment (PA) estimated an impact radius of 12,000 feet extending from the former Pier 1.

Site Reconnaissance, Records Review, and Interviews

The site reconnaissance was performed by John Scott of Unitek Environmental Guam (Unitek) during the period 3-8 November 2014. Visual site inspections, site photographs and data collection, as well as interviews with MOTCO explosive safety and MEC contractor personnel were performed on these dates. Unitek physically inspected all accessible areas of the property and collected photographic evidence of potential hazardous waste. Follow up telephone interviews and emails were also conducted during this assessment.

1.3 Findings, Opinions and Conclusions

Primary Hazardous Waste: The results of this Phase 1 Environmental Site Assessment indicated there is documented evidence of MEC within the planned construction area.

Previous project records indicate a history of MEC exists on the site in the form of military ordnance associated with the July 1944 explosive incident.

Possible Hazardous Waste: There is also a possibility that small quantities of asbestos materials and/or lead based paint may be present at the site associated with the original construction from the 1940’s according to government documents research. This would represent limited environmental liability during the planned demolition phase. A building inspection should be performed to positively identify and quantify these materials prior to demolition. The Phase 1 did not indicate any other evidence of significant environmental items of concern for the site.

The information obtained for this Environmental Site Assessment indicates that Pier 2 contains environmental conditions which could pose significant liability in the form of

MEC.

Although asbestos and lead based paint may exist in the older portions of the original facility, the quantities are likely to be very small and would likely represent a small investment to abate. Overall, Pier 2 is not considered to have significant environmental impairment for asbestos and/or lead paint which would cause the owner to be liable for significant environmental damage at this time.

Phase 1 Environmental Site Assessment -4- MOTCO Pier 2 Concord Ca

SECTION 2 INTRODUCTION

2.1 Scope of the Assessment: Purpose; Special Terms, and

Conditions

2.1.1 Scope of the Assessment: Purpose

The purpose of the physical site reconnaissance was to identify immediately recognizable potential and existing environmental hazards including MEC, ACM (asbestos-containing building materials), toxic substances, PCB (polychlorinated biphenyl) containing electrical equipment, hazardous chemical materials, hazardous chemical wastes, underground storage tank systems, potential surface/subsurface contamination.

2.1.2 Scope of the Assessment: Special Terms and Conditions

Unitek Environmental-Guam, Inc. (Unitek) was retained by PBI/CYS Civil & Structural Consultants to conduct a standard ASTM E 1527-13 Phase 1 Environmental Site Assessment for Pier 2 located at Military Ocean Terminal Concord, Concord California.

The subject site is approximately 159,000 square ft, or approximately 4 acres.in size and is currently owned by, and is currently in the process of being repaired and upgraded by the US Army Corps of Engineers. This Phase 1 was performed pursuant to acquiring all pertinent information related to recognizable or potential environmental impairments and/or liability associated with the subject site at this time.

2.1.3 Limitations and Exceptions of Assessment

Phase I Environmental Site Assessments are not intended to address all environmental issues including, but not limited to: fire or explosion hazards (which could be addressed by an insurance loss control survey or inspection by the fire marshal), biological concerns (such as disease or infectious waste), public health/safety issues, community/worker right-to-know regulations, radiation hazards, and many other environmental regulatory compliance requirements.

2.1.4 Limiting Conditions and Methodology Used

This site survey consisted of a review of readily accessible documentation, interviews with people having knowledge of the site, and a visual inspection of the site as it existed at the time of the site visits. A visual survey for MEC, ACM,PCB-containing electrical equipment, hazardous chemicals, toxic materials and wastes, underground storage tank systems, surface/subsurface contamination and the potential for vapor intrusion was conducted. A review of public and accessible records, and follow-up telephone interviews were also conducted. Although this assessment provides an initial screening for potential environmental liability, it should not be construed as a comprehensive evaluation of all possible environmental impairment associated with this site.

Phase 1 Environmental Site Assessment -5- MOTCO Pier 2 Concord Ca

2.1.5 Reliance on Information Provided by Others

As a matter of necessity, Unitek relies largely on readily available sources of information, such as the client, public records, and interviews, for recognizing potential environmental liabilities at a subject site/facility. Requests for information resources are made to collect relevant data on current and past practices conducted at the subject site/facility. Unitek may not receive all information requested or be able to confirm all information provided during the course of this site survey. Therefore, Unitek shall not be held responsible for errors, omissions or misrepresentations resulting from documentation or from inaccurate information provided by such sources.

2.1.6 Deviations

There were no deviations from ASTM E 1527-13 in the preparation of this report. This Phase I Environmental Site Assessment did include “all appropriate inquiry into the previous ownership and uses of the property consistent with good commercial or customary practice” as defined in CERCLA, 42 U.S.C 960(35)(B). Requested information from regulatory agencies and personnel affiliated with the site that was not received as of the date of this report will be forwarded to client upon receipt if information provided affects the contents of this report.

Phase 1 Environmental Site Assessment -6- MOTCO Pier 2 Concord Ca

SECTION 3 SITE DESCRIPTION AND HISTORY

3.1 Location and Legal Description

Pier 2 is located within the Military Ocean Terminal Concord DoD facility within Suisan Bay. The location, project boundaries and vicinity of this Phase 1 are shown in Figures 1 and 2.

Figure 1. Overview Map (Source: 2014 EDR Inc., 2010 Tele Atlas Rel 07/2009)

Phase 1 Environmental Site Assessment -7- MOTCO Pier 2 Concord Ca

Figure 2. General Plan of Site Survey Area and Site Vicinity. (photo date: Nov. 5, 2014, Department of the Army Corps of Engineers Sacramento, California , Moffatt & Nichol)

The subject site covered by this survey is a site approximately 159,000 square ft, or approximately 4 acres.in size and is currently in the process of being repaired and upgraded by the US Army.

3.2 Site and Vicinity Characteristics

Pier 2 was originally built as a timber structure in 1944 with wood decking and wooden piling supports. Since that date, several additions to the pier have included a concrete apron and approach trestle and addition of some small operating buildings. The wooden structure has deteriorated over the years, reducing its support capacity to the point access is no longer authorized due to weight restrictions. A new concrete pier is planned after demolition of the pier structure as indicated in Figure 2.

The area around the pier has limited structures including a road and parking areas with rail approaches and revetments. Most of the surrounding area has no infrastructure due to explosive safety Exclusion Zones due to the pier’s use as a ship loading/offloading facility for explosives and munitions.

Phase 1 Environmental Site Assessment -8- MOTCO Pier 2 Concord Ca

3.3 Current Uses of the Property

The site is used for ship loading/offloading operations. General housekeeping around the facility is good with minimal additional materials or trash located at the site.

3.4 Current Uses of Adjacent Properties

No industry, housing or occupied work structures are within the vicinity of the pier structure other than those directly involved in pier operations.

3.5 Site History and Past Uses of the Property

During World War II, Pier 2 was part of an extensive ordnance loading and transportation facility supporting ammunition shipments to the Pacific area of operations as part of a facility then known as Port Chicago. In July 1944, a major explosive incident occurred at Pier 1, located immediately to the west of Pier 2, which destroyed Pier 1, two ammunition loaded ships and killed several hundred workers. The scattered munitions and debris significantly contaminated the Pier 2 water and land areas with MEC which still exists in the area. An Explosive Safety Submission was conducted in August of 2013 which documented the MEC hazard and imposed explosive safety precautions for construction activities within the area which includes planned Pier 2 demolition and construction.

Phase 1 Environmental Site Assessment -9- MOTCO Pier 2 Concord Ca

Figure 5. Port Chicago Historical Map 1947 Source: EDR Radius Report

Phase 1 Environmental Site Assessment -10- MOTCO Pier 2 Concord Ca

SECTION 4 USER PROVIDED INFORMATION

4.1 Land Ownership Records

Environmental Data Resources (EDR) Radius Reports indicate the site is owned by the US Government.

4.2 Environmental Liens or Activity and Use Limitations

No environmental liens against the subject site were discovered during the site reconnaissance and research efforts.

4.3 Specialized Knowledge

The site is known to have been contaminated by MEC due to an ordnance explosive incident in World War II. This information is documented in detail in the US Army Corps of Engineers Explosive Safety Submission dated 6 August 2013 (Attachment 1).

4.4 Commonly Known or Reasonably Ascertainable Information

Older buildings, especially those constructed in the 1940’s, are more likely than newer buildings to have issues related to asbestos and lead based paint as well as other environmental issues.

4.5 Valuation Reduction for Environmental Issues

No environmental issues were identified which would be considered cause for a significant reduction in value of the site.

4.6 Owner, Property Manager, and Occupant Information

The subject site is currently owned by the US Government and is currently managed by the Commanding Officer, Military Ocean Terminal Concord. No transfer of property is planned.

4.7 Reason for Performing Phase I

This ESA Phase 1 was performed to evaluate readily available information and immediately recognizable environmental conditions pursuant to "due diligence" standards (ASTM E 1527-13) for determining the likelihood of environmental contamination of the subject property. This ESA Phase I is being conducted in support of planned demolition of Pier 2 in preparation for upgrades and repairs to the facility.

Phase 1 Environmental Site Assessment -11- MOTCO Pier 2 Concord Ca

SECTION 5 ENVIRONMENTAL RECORDS REVIEW

The ASTM Standard E 1527-13 indicates appropriate search distances from the nearest site boundaries for various types of land uses in the vicinity of a particular site. Figure 6 shows the approximate 0.5 mile and 1 mile search distances from the subject site.

Figure 6. Site with approximate 0.5 and 1.0 mile search radiuses (Source: 2014 EDR Inc. , 2010 Tele Atlas Rel. 07/2009)

Phase 1 Environmental Site Assessment -12- MOTCO Pier 2 Concord Ca

5.1 Standard Environmental Record Sources

The Federal databases reviewed for this Phase 1 are listed below and findings are summarized in Table 5-1.

Table 5-1 Standard Environmental Records Sources- Federal

Record Type of Information Sought

Status of Property

National Priority List (Federal) (US EPA, 2012)

If site is under

CERCLA

consideration.

Not on list; none within 1.0 mile

CERCLIS (Federal)

(US EPA, 2012)

If site is a CERCLA site or are CERCLA sites nearby.

Not on list; none within 0.5 miles

RCRA (Federal lists)(US EPA,2012)

If site is a hazardous waste generator or if there are generators on neighboring properties.

Not on list; none within 1.0 mile

RCRA -TSD (Federal) (US EPA, September, 2009)

If site is a treatment, storage or disposal facility for hazardous waste

Not on list; none within 0.5 miles

Formerly Used Defense Site (FUDS)

If site is a FUDS or if there are FUDS within

0.5 miles.

Not on list; none within 1.0 mile

Leaking Underground Storage Tanks

If site has notified the local authority of any leaking underground storage tanks (USTs) for the site or within

0.5 miles.

None on site, none within 0.5 miles reported by EPA.

USEPA

Registered Underground Storage Tanks

If site or neighboring properties have registered USTs

None permitted on site or neighboring properties.

(National Response Center, Compiled from 1990 to 2010 records)

If spills have occurred at or near the site

No Spills reported at or adjacent to site.

Phase 1 Environmental Site Assessment -13- MOTCO Pier 2 Concord Ca

5.2 Additional Environmental Record Sources

Local government records and other additional records reviewed for this Phase 1 are listed below and findings are summarized in Table 5-2.

Table 5-2 Standard Environmental Records Sources- Local, State and Tribal

Records Source and Minimum Search Distance

Sites Present within Minimum Search Distance

State and Tribal Equivalent CERCLIS (1.0 mile)

MILITARY OCEAN TERMINAL CONCORD

& NAD CONCORD.

State and Tribal Equivalent NPL (1.0 miles)

Not on list; none within 1.0 mile

State and Tribal Landfill or Solid Waste Disposal Sites (0.5 miles)

Not on list; none within 0.5 miles

State and Tribal Leaking Underground Storage Tanks (LUSTs) (0.5 miles)

US ARMY MOTCO (FORMERLY

CONCORD)

State and Tribal Registered Underground Storage Tank Lists (UST, AST, Indian UST, FEMA UST) (0.250 miles)

Not on list; none within 0.250 miles

State and Tribal Voluntary Cleanup Sites (0.5 miles)

Not on list; none within 0.5 miles

Local Lists of Landfill / Solid Waste Disposal Sites (0.5 miles)

Not on list; none within 0.5 miles

Local Lists of Hazardous Waste / Contaminated Sites (1.0 mile)

Not on list; none within 1.0 mile

Local Lists of Registered Storage Tanks (0.250 miles)

Not on list; none within 0.250 miles

Records of Emergency Release Reports (Target Property)

Not on list; none on target property

5.3 Physical Setting Source(s)

The physical setting sources used for this Phase 1 include the USGS 7.5 minute series topographic maps produced in 2000 and 1975.

Phase 1 Environmental Site Assessment -14- MOTCO Pier 2 Concord Ca

5.4 Historical Use Information on the Property and Adjacent

Properties

Historical use of the site and surrounding properties was evaluated mainly through sited publications written on the history of Port Chicago, historical aerial photographs and maps, and interview information with persons having knowledge of the property history.

The US Army Corps of Engineers provided additional information specific to the project site.

Phase 1 Environmental Site Assessment -15- MOTCO Pier 2 Concord Ca

SECTION 6 SITE RECONNAISSANCE

The site reconnaissance was performed by John Scott, UNITEK Environmental Professional on November 3 – 8, 2014. Visual site inspections, site photographs and data collection, as well as interviews with occupants of the site were performed on these dates. Unitek inspected the subject site, surrounding lots and accessible site improvements. Follow up telephone interviews were also conducted during this assessment. Site photographs from the site reconnaissance are included (Appendix A).

6.1 Methodology and Limiting Conditions

This Environmental Site Assessment consisted of interviews with people having knowledge of the site and visual inspections of accessible portions of the site as it existed at the time of the site visit. A visual survey for asbestos, hazardous chemicals, toxic materials and wastes, underground storage tank systems, surface/subsurface contamination was performed. Although this assessment provides an initial screening for potential environmental liability, it should not be construed as a comprehensive evaluation of all possible environmental impairment associated with this site.

6.2 General Site Settings

Pier 2 is located on the shore of Suisan Bay east of San Francisco Bay. The site is sparsely populated with minimal infrastructure. Short grass and open, treeless terrain surround the site. Infrastucture consists of an access roadway, rail lines, ship channel and nearby revetments for the storage of munitions rail cars and trucks. .

6.3 Exterior Observations

• The site is maintained with de-minimis landscaping features.

• No evidence of stressed vegetation or staining of soil was observed on the site. Oil spotting in the parking areas was observed which is typical.

• Very little construction debris and other solid waste piles were observed in the immediate vicinity of the pier. Most or all of the material observed was quite inert with no likelihood for property contamination as a result of its presence.

• No hazardous materials were observed being stored or spilled on the site.

The exterior site appeared in general good environmental condition.

6.4 Asbestos-Containing Building Materials

Buildings built prior to 1980 are more likely to contain asbestos building materials. As the pier operating building was built in 1944, it is recommended this building be inspected and suspect materials including vinyl flooring and mastic which were observed should be sampled prior to disturbance during demolition to identify whether any asbestos may be present.

6.5 PCB Electrical Equipment and Contamination

No pole or pad mounted transformers were observed at the site. Fluorescent lighting was observed within the office building. It is possible lighting ballasts inside may have been built earlier than 1979 and should be inspected prior to demolition.

6.6 Indications of Lead Contamination

Since the original construction was completed in 1944 when lead based paints were heavily used, it is recommended the operating building coatings be tested to determine if lead based coatings may exist within this building prior to demolition. This would be necessary so that workers can be protected from lead dust during demolition activities.

6.7 Indications of Solid Waste Disposal

There was no evidence that any solid waste material was being buried on site or permanently disposed.

6.8 Hazardous Materials Used

No materials were observed on site, which may require notification, under 40 CFR 355.30, of the Local Emergency Planning Committee (LEPC) due to their extremely hazardous nature. The complete list of extremely hazardous materials may be found in 40 CFR 355 Appendix A.

6.9 Hazardous Material Wastes and Unidentified Containers

No indications of hazardous waste disposal at the site or unidentified chemical containers were observed on the site.

6.10 Storage Tanks

No underground tanks are registered for the site or adjoining properties with EPA.

6.10.1 Observations Underground tanks

No indications of underground petroleum tanks such as tank access ports or vent pipes observed at the site.

6.10.2 Observations Aboveground tanks

No above ground storage tanks were observed on the site.

6.11 Potential Surface/Subsurface Contamination

No soil staining or stressed vegetation was observed at the site which indicated potential surface or subsurface contamination.

6.12 Indications of Vapor Intrusion

No indications of vapor intrusion were detected on site.

SECTION 7 INTERVIEWS

Mr. Travis Wexler – MOTCO Safety Officer Mr. Amir Zand – Earth Mechanics, Inc.

Mr. David Titzel – Parsons Transportation Group Mr. Trent Milligan – AOR Diving

SECTION 8 EVALUATION

8.1 Environmental Professionals Statement

Unitek Environmental Guam (Unitek) has conducted this Phase I Environmental Site Assessment on behalf of PBI/CYS Civil & Structural Consultants. A thorough review all appropriate records made available and a visual site inspection of the selected facilities was performed during this assessment. The information contained within the survey report is based on records made available and, to the best of Unitek’s knowledge, is correct and current as of December 14, 2014.

8.2 References

EDR Radius map and reporting services/. General Planning Map Series.

ASTM. Standard 1527 Revision 2013. Standard Practice for Environmental Site Assessments: Phase 1 Site Assessment Process.

(U.S. EPA) United States Environmental Protection Agency. Code of Federal Regulations, Title 40, Parts 261-8.

(U.S. EPA) United States Environmental Protection Agency. Code of Federal Regulations, Title 40, Part 300 Appendix B.

(U.S. EPA) United States Environmental Protection Agency. Code of Federal Regulations, Title 40, Part 280.

(U.S. EPA) United States Environmental Protection Agency. Code of Federal Regulations, Title 40, Parts 761-763.

(U.S. EPA) United States Environmental Protection Agency. Code of Federal Regulations, Title 40, Part 112.

8.3 Signature of Environmental Professional

John Scott Environmental Professional Unitek Environmental Guam

Appendix A Site Reconnaissance Photos

ESA PHASE I Photograph Locations

Location 1. Pipe under pier with possible Asbestos Containing Material pipe wrap.

Close-up of Pipe Wrap

Location 2: Potential Asbestos Containing Material in Floor Tile

Location 3: Potential Asbestos Containing Material in Floor Mastic

Location 4: Potential Lead Based Paint

Location 5: Pipe Wrap – Unknown covering Recommend Testing for ACM

Location 6: Pipe Wrap with Suspected ACM

Close-up of Suspected ACM Pipe Wrap

Appendix B Qualification of Environmental Professional

John Scott Unitek Environmental Guam 31 Years Relevant Experience ASTM E1527-05/E1528-06 Training

Cover Sheet
Table of Contents
Table of Appendices
Table of Supplements
Preface
Report Body
Appendices
A1.0_Final Design Schedule and Org Chart 100p
A1.1_MOTCO Pier 2, 100p Schedule (2015-09-01)
A1.2_Org Chart 100p Design
A2.0_Engineering Data Collection Reports 100p
A2.1_Memo-Sea Level Change Analysis (2016-01-12)
A2.2_MOTCO Pier 2 Mooring Analysis R1 (2016-03-10)
A2.3_Crane_Final Wheel Load Report_(2014-12-30)
Background
Criteria
Analysis
Stowed Wind Load
Stability Requirements
Crane Loads
Seismic Loads
Extreme Overloads
Appendix A
Appendix B
Appendix C
A2.4_MOTCO - Geotechnical Data Report (2015-01-15)
A2.5_MOTCO Pier 2 Geotechnical Design Report EMI (2016-03-01)
A2.6_MOTCO Pier 2 Site-Specific Ground Motion Report Rev1EMI (2016-01-13)
A2.7_00 MEC Hazard Reduction Plan - MOTCO Pier 2 (2014-12-31)
A2.8_00 MOTCO Pier 2 ESA Phase 1 Report (2014-12-18)
Table of Contents
SECTION 1 EXECUTIVE SUMMARY
1.1 Current Project and Site Description
1.2 Site History
Site Reconnaissance, Records Review, and Interviews
1.3 Findings, Opinions and Conclusions
SECTION 2 INTRODUCTION
2.1 Scope of the Assessment: Purpose; Special Terms, and Conditions
2.1.1 Scope of the Assessment: Purpose
2.1.2 Scope of the Assessment: Special Terms and Conditions
2.1.3 Limitations and Exceptions of Assessment
2.1.4 Limiting Conditions and Methodology Used
2.1.5 Reliance on Information Provided by Others
2.1.6 Deviations
SECTION 3 SITE DESCRIPTION AND HISTORY
3.1 Location and Legal Description
3.2 Site and Vicinity Characteristics
3.3 Current Uses of the Property
3.4 Current Uses of Adjacent Properties
3.5 Site History and Past Uses of the Property
SECTION 4 USER PROVIDED INFORMATION
4.1 Land Ownership Records
4.2 Environmental Liens or Activity and Use Limitations
4.3 Specialized Knowledge
4.4 Commonly Known or Reasonably Ascertainable Information
4.5 Valuation Reduction for Environmental Issues
4.6 Owner, Property Manager, and Occupant Information
4.7 Reason for Performing Phase I
SECTION 5 ENVIRONMENTAL RECORDS REVIEW
5.1 Standard Environmental Record Sources
5.2 Additional Environmental Record Sources
5.3 Physical Setting Source(s)
5.4 Historical Use Information on the Property and Adjacent Properties
SECTION 6 SITE RECONNAISSANCE
6.1 Methodology and Limiting Conditions
6.2 General Site Settings
6.3 Exterior Observations
6.4 Asbestos-Containing Building Materials
6.5 PCB Electrical Equipment and Contamination
6.6 Indications of Lead Contamination
6.7 Indications of Solid Waste Disposal
6.8 Hazardous Materials Used
6.9 Hazardous Material Wastes and Unidentified Containers
6.10 Storage Tanks
6.10.1 Observations Underground tanks
6.10.2 Observations Aboveground tanks
6.11 Potential Surface/Subsurface Contamination
6.12 Indications of Vapor Intrusion
SECTION 7 INTERVIEWS
SECTION 8 EVALUATION
8.1 Environmental Professionals Statement
8.2 References
8.3 Signature of Environmental Professional
Appendix A Site Reconnaissance Photos
Appendix B Qualification of Environmental Professional
A2.9_Rs-100%-MOTCO-Pier 2 (Haz-Mat Report for MOTCO-PIER2-BLDG 21)(2015-07-27)
A2.10_Flow Test KSN Appendix-FH_Flow_Test (2014-12-03)
A3.0_Main Platform Structural Appendix 100p
A3.0_MOTCO Main Platform Structural Appendix 100p Calcs (2016-03-16)
8655 FINAL COMPILATION 100% SUBMITTAL
Table of Contents
Cover Gravity and Environmental
Cover Seismic Demand
Cover Seismic Capacity
Cover Kinematic
Cover Pile Design
Cover Fender System
Cover Details
Cover Misc Calcs
Cover Bollard Anchorage
Cover Crane Power Vault Beam
Cover Crane Stop
Cover Crane Stowage Pin
Cover Expansion Joint Plate
Cover Guard Rail Anchorage
Cover Light Pole Support
Cover Pipe System Support
Cover Sewer Vault
Cover Trench Design
A4.0_West Trestle Appendix 100p
A4.1_MOTCO - West Trestle 100p Calcs (2016-03-14)
Seismic Evaluation of West Trestle (2016 March)

A4.2_West Trestle and Personnel Trestle Seismic Analysis_rev2 (2014-12-31)

A5.0_PersonnelForklift Trestle Appendix (Moved to Supplements) 100p
A6.0_East Trestle Appendix 100p
A6.1_East Trestle Calculations (2016-03-18)
A6.2_East Trestle Seismic Vulnerability Assessment (FINAL)(2014-12-31)
A7.0_Mechanical Systems App 100p
A7.0_Mechanical Systems Appendix comb (2015-12-28)
141205-FH_Flow_Test
Input_Analysis
Fathom_Output_Results
A8.0_Electrical and Communications Systems App 100p
A8.0_Electrical and Communications Systems Appendix (2016-03-14)
A9.0_Operations Building App 100p
A9.0_Operations Building Appendix comb (2016-03-18)
A9.1.7 Water Reduction Calc
A9.2_Ops Bldg Structural_100p Submittal Calcs
A9.3.2.1 Heating and Cooling Load Calcs
A9.3.2.2 HVAC Equipment Cut Sheets
A9.4.2.2 Plumbing Cut Sheets
A9.4.2.3 WaterCalc
A9.4.2.3.a Waste dFU to gpm
A9.4.2.3.b Sewage_Ejector_Pump_Calcs
A9.4.2.3.c Wet Well # of Starts Calculation
A9.5.2.2 Electrical Load Calcs (2016-03-16)
A9.5.2.3 LED Lighting Fixtures
AL Direct_Indirect Suspended LED
BL Direct_Indirect Suspended LED
CL Direct_Indirect Wall LED
DL-DLE Wraparound LED
FL Bath Vanity LED
GL-GLE Bath Downlight LED
JL-JLE Comm Wraparound LED
KL Direct recessed downlight LED
WLE Wall Pack LED
XLE LED Emergency exit combo light
A9.6.1.2 - fire prot Material Data Sheets (R1)
A9.6.1.3 fire protection hydraulic calculation (R7)
A10.0_Civil Roadway App 100p
A10.0_Civil Roadway Appendix comb (2015-12-23)
A10.1_Flexible Pavement Calcs_151118
A10.2_Riprap Calcs_151203
A10.3_Exh_Truck Turns_151211
A11.0_Civil Utilities App 100p
A11.0_Civil Utilities Appendix comb (2015-12-23)
A11.1_Cathodic_Protection_TechMemo_151124
A11.2_Restrained Pipe Calcs_151215
A11.3_FH_Flow_Test
A11.4_Pier Stormwater Deck Drainage and Filter
A12.0_Value Engineering Reports 100p
A12.1_MOTCO Pier 2 Value Eng Report Eval (2015-05-28)
A12.2_EIS Modification Report (2015-05-28)
EIS modification report
Holman&Associates_EIS_Memo_May2015

A12.3_MOTCO VE Imp Charrette Mtg Minutes (2015-07-30) FINAL

Supplements
S3.0_Main Platform Structural Appendix (65p Sub)
S3-MainPlatformStructuralApp_20150722
Supplement S1: Main Platform Structural Appendix Revs
Gravity Loads
Seismic Demand
Seismic Capacity
Kinematic + Inertial
Fender System
Miscellaneous Calculations
Crane Power Vault
Crane Stop
Guard Rail Anchorage
Light Pole
Pipe Support System
Seismic Joint Plate
Sewer Pump Support Beam
Vault Covers
Water Filter Vault Beam