W9123817R0065_Amend_0004.pdf

PDF 71 KB Posted

Attached to
Replace/Upgrade Pier 2 Federal contract opportunity
Solicitation number
W9123817R0065
Issued by
Department of the Army Corps of Engineers Engineering District Sacramento

About this file

W9123817R0065 Amendment 0004

View the file

Other files for this federal contract opportunity

Other files attached to Replace/Upgrade Pier 2, newest first.
File Type Posted
C01.13_Award_Announcement_(synopsis).pdf PDF
A13.2_Bidder_Inquiries_11-6-2017_(FIO).pdf PDF
Amendment_0005_Specifications.pdf PDF
W9123817R0065_Amend_0005_Conform_Copy.pdf PDF
W9123817R0065_Amend_0005.pdf PDF
Attachment_16_Final_NMFS_Letter_signed_4Oct2016_v10042016_(clean).pdf PDF
W9123817R0065_Amend_0004_Conform.pdf PDF
Bidder_Inquiry_Reopened.pdf PDF
Wage_Determination_-_CA_29.pdf PDF
SAV_Mitigation_Plan_081814.pdf PDF
17-R-0065_Amend_003_Conform.docx DOCX document
Amendment_0003_Drawings_(marked_delta_2).pdf PDF
17-R-0065_Amend_003.docx DOCX document
NAVFAC_USACE_PPQ_Form_Sep_2011.doc DOC document
Amendment_0002_Specification_2026.pdf PDF
SCA_Wage_Determination_WD_15-5623_(Rev.-4).pdf PDF
W9123817R0065_Amend_0002_Conform_Copy.pdf PDF
W9123817R0065_Amend_0002.pdf PDF
30008CM_-_May_1967_deck_repair.pdf PDF
Pier_2_&_Barge_Pier_Naval_Weapons_Sta_Concord_CA_1994.pdf PDF
30007CM_-_Marginal_pile_records_dated_13_Oct_1944.pdf PDF
30005CM_-_March_1988_repair.pdf PDF
30009CM_-_1958_rehabilitation.pdf PDF
Pier_MEC_Clearance_Completion_Report,_Rev_0.pdf PDF
30006CM_-_May_1967_extension_2_of_2.pdf PDF
Cultural_Resources_Treatment_and_Discoveries_Plan_MOTCO_Pier_2.pdf PDF
MEC_-_Pier_2_MEC_RA_DD_Form_2977-signed.pdf PDF
Pier_2,_WFI-MCO-11-00128_Final_Reduced.pdf PDF
2002_Repair_Drawings_&_Fenders.pdf PDF
A2-9_HAZMAT_Phase_II_Report.pdf PDF
Batymetry_Layer_71057V-HP01.dwg DWG drawing
A7.3_MOTCO_Industry_Day_Photos_Nov_2016.pdf PDF
Pier_2_Site_Visit_Photos.pdf PDF
Subcontracting_Goals_(FIO).pdf PDF
DDESB_Approval,_Explosives_Safety_Submission,_Removal_ActionConstruction.PDF PDF
Attachment_5_-_MOTCO_Pier_2_Supplemental_Environmental_Assessment_Final_FNSI_signed.pdf PDF
Attachment_7_-_PD_Final_Environmental_Impact_Statement_MOTCO_Piers_2_2015-02-10.pdf PDF
W9123817R0065_Amend_0001_Conform_RFP.pdf PDF
Attachment_8_-_USFWS_2014-F-0002-5_MOTCO_Pier_2_Final_Biological_Opinion.PDF PDF
Attachment_4_-_MOTCO_Pier_2_Final_Supplemental_Environmental_Assessment.pdf PDF
W9123817R0065_Amend_0001.pdf PDF
Attachment_6_-_NMFS_Biological_Opinion_11_19_2014_MOTCO_Piers_2.pdf PDF
A7.3_Industry_Day_Maps.pdf PDF
Attachment_2_-_Drawings_-_Updated_RTA_Design_Drawings_(2017-05-08).pdf PDF
Attachment_1-MOTCO_PIER_2_SPECIFICATIONS_07SEP2017.pdf PDF
A2.1_W9123817R0065_09-08-2017.pdf PDF
NCIC_CONSENT_FORM_-_DEC_2016_Fillable.pdf PDF
Industry_Day-Site_Vists_MOTCO_Pier_2_Replace_and_Update_Information.docx DOCX document
MOTCO_190-3__JUN_2016-1_Final.xlsx XLSX spreadsheet
Forms_instructions_2.0_USACE.docx DOCX document
Show all 50

Replace/Upgrade Pier 2 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

A. The purpose of this amendment is to make minor changes and clarif ications to the solicitations.

B. Except as noted in the ofllow ing pages, all other terms and conditions remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 19

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Oct-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123817R0065

X 9B. DATED (SEE ITEM 11)

08-Sep-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Oct-2017

CODE

USACE SACRAMENTO DISTRICT

ATTN: CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123817R0065

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

The following have been added by full text:

CONT. OF SF-30 AMEND 0004

Specification Section 01 57 20, Paragraph 1.5 is revised to the following:

SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Environmental Protection Plan; G

Biological and Cultural Resource Monitor Qualifications; G

Submit the Preconstruction Submittals no less than 30 calendar days prior to the start of on-site construction activities. Work at the site will not be allowed to commence until all required Preconstruction submittals have been reviewed and approved by the Government. Note: the Contractor must submit that the Hydroacoustic Monitoring Plan component of the Environmental Protection Plan to the National Marine Fisheries Service and the US Fish and Wildlife Service must be approved at least 90 days prior to the initiation of pile driving at Pier 2. The Army will provide the final Environmental Protection and any other construction-related plans consisting of environmental BMPs to U.S. Fish and Wildlife Service (USFWS) at least 30 days prior to the start of construction actions.

The following have been modified:

FUNDING

Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available. Please note: award is currently expected July August 2018.

As noted elsewhere in Amendment 0004, the solicitation acceptance period is being extended to 270 days due to the expected date of receipt of the balance of funds for this project.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 07-Nov-2017 12:00 PM to 14-Nov-2017 02:00 PM.

The offeror acceptance period has increased by 110 from 160 to 270.

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

INSTRUCTIONS TO PROPOSERS

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

INQUIRIES:

Prospective offerors should submit inquiries related to this solicitation in accordance with the following (collect calls will not be accepted):

a. For information related to amendments, and the dates set for receipt of proposals, please check http://www.fedbizopps.gov

b. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

1. To submit and review bid inquiry items, offerors will need to be a current registered user or self-register into the system. To self-register go to the aforementioned web page and click on the QUICK ADD link. Select agency as USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e-mail address, and then click continue. Fill in all required information and click Add User.

2. From this page you may view all bidder inquiries or add an inquiry.

3. Bidders will receive an acknowledgement of their question via e-mail, followed by an answer to their question after it has been processed.

4. The Solicitation Number is : W9123817R0065

The Bidder Inquiry Key is: 6HMFK6-35999A

c. The Bidder Inquiry System will be available for new inquiries shortly after the issuance of the Phase-I solicitation up until 10:00 am on 30 10 Oct 2017 in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

d. Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

g. The point of contact for this solicitation is:

Contract Specialist: Daniel Czech Telephone: (916) 557-7012

E-MAIL: Daniel.E.Czech@usace.army.mil

DIRECTIONS FOR SUBMITTING OFFERS:

Envelopes/packages containing offers must be sealed, marked and addressed as follows:

MARK ENVELOPES/PACKAGES:

Solicitation No. W9123817R0065

ADDRESS ENVELOPES/PACKAGES TO:

Department of the Army U.S. Army Engineer District, Sacramento ATTN: Contracting Division, Daniel Czech 1325 J Street Sacramento CA 95814-2922

SPECIAL INSTRUCTION PERTAINING TO HAND-CARRIED OFFERS:

Hand-carried offers must be delivered to: The Building Lobby at 1325 J Street, Sacramento, CA.

Due to security precautions, offerors may no longer hand-carry their offers directly to Contracting Division. Offers may NOT be turned-in at the Security Desk or left unattended elsewhere in the Lobby. Additionally, you are advised that there is no public parking in the Building.

The contract specialist will be in the Building Lobby 20 minutes prior to the closing time to accept hand-carried offers.

Offerors who desire to hand-deliver their offers at an earlier time must coordinate with the contract specialist in advance in order to arrange to be met in the Building Lobby by Contracting Division personnel.

Please ensure that all courier and delivery personnel are aware of these procedures.

CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY:

In order to determine a contractor's responsibility for purposes of contract award in accordance with FAR Part 9, the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work (see Section 00 22 00, Preaward Survey). All offerors will complete and return the Preaward Survey as part of the Price/Cost proposal. Failure to submit the Preaward Survey in conjunction with the price proposal will not of itself render the offer unacceptable.

Determination of Contractor Responsibility will be completed in accordance with FAR 9.104-1:

If the contractor or subcontractor does not already have sufficient resources demonstrated in the completed Preaward Survey, acceptable evidence of "the ability to obtain" the required, adequate resources (all of the resources discussed in FAR 9.104-

1) normally consists of a commitment or explicit arrangement that will be in existence at the time of contract award to rent, purchase or otherwise acquire the needed facilities, equipment, other resources, or personnel.

The Preaward Survey as a tool used by the Government in determining responsibility of the offeror is submitted as part of the Price/Cost proposal and is separate from the technical proposal's response to the technical evaluation criteria found later in this section. Some of the information required from the offeror for completion of the Preaward Survey and the technical proposal may be duplicative but it is necessary that the information be provided in full in both places and that the Price/Cost proposal and the Technical proposal be separate documents. DO NOT state, for example, in the technical proposal, "See Price/Cost proposal for past performance information".

AVAILABILITY OF CORPS OF ENGINEERS PUBLICATIONS DESCRIPTIONS:

a. The internet URL for Corps of Engineers publications is:

http://www.publications.usace.army.mil/

b. Construction Criteria Base (CCB). The Construction Criteria Base (CCB) system available through the National Institute of Building Sciences includes copies of Corps of Engineers methods and specifications. Information about the CCB can be obtained from:

http://www.wbdg.org/ccb/ccb.php

PREPARATION OF SUBCONTRACTING PLAN:

(a) See FAR 52.219-9 (DEVIATION 2016-O0009), Section 00 70 00, of this solicitation. Subcontracting Plans will be developed considering only the subcontracts actually to be awarded. Subcontracting Plans are required from other than small businesses if the contract price is over $1,500,000; they are not required from small business firms regardless of the contract price.

(b) For information on the evaluation of subcontracting plans, see Army Federal

Acquisition Regulation Supplement, Appendix DD.

(c) Contact Michelle Stratton (916)557-7641, Deputy for Small Business, with questions on the Subcontracting Plan requirements and further instructions on submission of Electronic Subcontracting Reporting System (eSRS) as required by FAR 52.219-9.

(d) Offerors are to propose their own small business goals (see the Small Business Participation Factor in Section 00 22 00, pargraph 5.3.5:

The goals are calculated as a percentage of the THE TOTAL CONTRACT AMOUNT.

FACSIMILE BIDS/OFFERS:

Facsimile bids/offers, modifications thereto, or cancellations of bids/offers will not be accepted.

PERFORMANCE AND PAYMENT BONDS:

The bidder/offeror whose bid/offer is accepted will, within the time established in the contract, furnish performance and payment bonds in accordance with FAR 52.228-15.

INDIVIDUAL SURETIES IN SUPPORT OF BID BONDS:

Bidders/offerors utilizing individual sureties in support of a bid bond shall include a Standard Form (SF) 28 (Affidavit of Individual Surety), accompanied by a pledge of acceptable assets from each person acting as an individual surety, and include these with the SF 24 (Bid Bond), and the bid itself (see clause titled "Pledges of Assets," FAR 52.228-11).

Pledges of acceptable assets shall be in the form of (1) evidence of an escrow account and/or (2) a recorded lien on real estate.

ACCEPTANCE OF OFFERS:

A written award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.

System for Award Management (SAM) Registration:

It is a requirement that any and all contractors that intend to do business with the government must be registered in the System for Award Management (SAM) database.

No contract may be awarded by the government to any contractor who is not registered in SAM. If your company is not registered in SAM, you must register in order to be eligible for any government award.

The following link provides access to the SAM website:

https://www.sam.gov/portal/public/SAM/

If you have difficulties with or questions regarding the SAM registration, the following link has been set up by the Defense Logistics Agency (DLA) to assist contractors registering for CAGE codes for enrollment and navigation within SAM:

https://www.logisticsinformationservice.dla.mil/CAGETier3/

—End Section—

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

SUPPLEMENTARY CONDITIONS

UAI 5152.211-9001 VARIATIONS IN ESTIMATED QUANTITIES — SUBDIVIDED

ITEMS (MAR 1995)

This variation in estimated quantities clause is applicable only to item Nos. 0013, 0014, 0015, 0016, 0021, 0022, 0023, 0024, 0025, and 0027.

(a) Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.

(b) Where the actual quantity of work performed for the aforementioned item is less than 85% of the quantity of the first sub-item listed under such item, the contractor will be paid at the contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause Federal Acquisition Regulation (FAR) 52.211-18, Variation in Estimated Quantities.

(c) If the actual quantity of work performed under the aforementioned item exceeds 115% or is less than 85% of the total estimated quantity of the sub-item under that item and/or if the quantity of the work performed under the second sub-item or any subsequent sub-item under the aforementioned items exceeds 115% or is less than 85% of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.

(End of clause)

UAI 5152.236-9001 PERSONNEL, SUBCONTRACTORS, AND OUTSIDE

ASSOCIATES OR

CONSULTANTS (MAY 2006)

In connection with this contract, any in-house personnel, subcontractors, and outside associates or consultants will be limited to individuals or firms that were specifically identified in the Contractor's accepted proposal. The Contractor shall obtain the Contracting Officer's written consent before making any substitution for these designated in-house personnel, subcontractors, associates, or consultants. If the Contractor proposes a substitution, it shall submit the same type of information that was submitted in the accepted proposal to the Contracting Officer for evaluation and approval. The level of qualifications and experience submitted in the accepted proposal or that required by the Solicitation, whichever is greater, is the minimum standard for any substitution.

(End of clause)

UAI 5152.249-9000 BASIS FOR SETTLEMENT OF PROPOSALS (MAR 2009)

Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under Federal Acquisition Regulation (FAR) 49.206-2(b). In evaluating a termination settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:

(a) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.

(b) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.

(c) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.

(d) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of Federal Acquisition Regulation

(FAR) 31.205-11).

(e) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.

(End of clause)

EMPLOYEE IDENTIFICATION AND FINGERPRINTS:

If employee identification is required for security or other reasons, the Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. All prescribed identification shall immediately be delivered to the Contracting Officer, for cancellation upon the release of any employee. When required by the Contracting Officer, the Contractor shall obtain and submit fingerprints of all persons employed or to be employed on the project. The Contractor is responsible for compliance with the REAL ID Act.

ADDITIONAL AT-OPSEC REQUIREMENTS

All contractor and subcontractor personnel must be US Citizens to access the work site.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites:

https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.

The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award."

*When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative.

This Form will be provided to the Contracting Officer and shall become part of the official contract file.

MINIMUM INSURANCE

In accordance with FAR 52.228-5, Insurance-Work on a Government Installation, the Contractor shall procure and thereafter maintain during the entire period of his performance under this contract the following minimum insurance.

Type and Amount

Worker's compensation and employer's liability: At least $100,000

General liability: Bodily injury liability of at least $500,000 per occurrence

Automobile liability: Coverage of at least $200,000 per person; $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage.

SAFETY AND HEALTH REQUIREMENTS MANUAL

a. The contractor shall comply with all provisions of the U.S. Army Engineers Safety and Health Requirements Manual, EM 385-1-1.

b. The Internet URL for EM 385-1-1, entitled “Safety and Health Requirements Manual” is:

http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirement sManual.aspx

c. Whenever the Contracting Officer becomes aware of any noncompliance with these safety and health requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor's representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to an equitable adjustment of the contract price or extension of the performance schedule based on any stop work order issued under this authority.

WORK DAYS AND HOURS:

a. Federal law (5 U.S.C. 6103) establishes the following public holidays for Federal employees. When a holiday falls on a Saturday, the holiday is generally observed on the preceding Friday. When a holiday falls on a Sunday, the holiday is generally observed on the following Monday. Further information pertaining to Federal holidays is available at http://www.opm.gov/fedhol.

b. The normal work days and hours for this project will be Monday through Friday, excluding the observation of federal holidays, from 7:00 a.m, to 5:00 p.m. and in accordance with Specification 01 14 00 Work Restrictions, Paragraph 1.2.2 (within the afreomentioned timeframe). Access to the work site may be restricted to these hours and days. Work during other than normal hours and days must be coordinated in advance with the Administrative Contracting Officer.

ALTERNATE STRUCTURED APPROACH TO WEIGHTED GUIDELINE METHOD

FOR CONSTRUCTION CONTRACTS:

The following alternate structured approach shall be used for all fixed-price construction contract actions.

Factor Rate Weight Value

Degree of risk 20 Relative difficulty of work 15 Size of job 15 Period of performance 15 Contractor's investment 5 Assistance by Government 5 Subcontracting 25

Total 100%

Based on the circumstances of the procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. “Value” shall be obtained by multiplying the rate by the weight. The Value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.

The profit percentage should be multiplied by the total contract costs, including general and administrative costs.

(1) Degree of risk. Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Lump sum items shall generally have a higher weight than unit price items; other things to consider include the nature of the work and where it is to be performed. Consider the portion of the work to be done by subcontractors, amount and type of labor included in costs, whether the negotiation is before or after performance of the work, etc. Modifications settled before the fact have much greater risk than those settled after the fact. A weight of .03 is appropriate for after the fact equitable adjustments and/or settlements.

(2) Relative Difficulty of Work: If the work is difficult and complex, the weight should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some other things to consider are the nature of the work, by whom it is to be done (i.e., subcontractors, consultants), what is the time schedule.

(3) Size of Job. Work of $100,000 or less shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.

Work from $5,000,000 to $10,000,000 shall be weighted at .04. Work in excess of $10,000,000 shall be weighted at .03. It should be noted that control of fixed expenses generally improves with increased job magnitude.

(4) Period of Performance. Work not to exceed one month is to be proportionately weighted at .03. Durations between one month and 24 months are to be proportionately weighted between .03 and .12. Work in excess of 24 months is to be weighted at .12.

(5) Contractor's Investment. To be weighted from .03 to .12 on the basis of below average, average and above average. Things to consider include amount of subcontracting, Government-furnished property or data such as surveys, soil tests, method of making progress payments, and any mobilization payment items.

(6) Assistance by Government. To be weighted from .12 to .03 on the basis of average to above average. Consider use of Government-owned property, equipment and facilities, and expediting assistance.

(7) Subcontracting. To be weighted inversely proportional to the amount of subcontracting. Where 80% or more of the work is to be subcontracted use .03. The weighting should be increased proportionately to .12 where all the work is performed by the contractor's own forces.

CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR

PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS

The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8, PAYROLLS AND BASIC RECORDS and FAR 52.222-13, COMPLIANCE WITH DAVIS-BACON AND

RELATED ACT REGULATIONS.

If the contractor elects to use an electronic Davis-Bacon payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon and related Act regulations.

When the contractor uses an electronic Davis-Bacon payroll system, the electronic payroll services shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic Davis-Bacon payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the Davis-Bacon and related Act regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.

The contractor’s provision and use of an electronic payroll processing system shall meet the following basic functional criteria: commercially available; compliant with appropriate Davis Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;

capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at http://www.rmssupport.com/guides.aspx) for export in an Excel spreadsheet to be imported into the contractor’s Quality Control system (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government’s Resident Management system (RMS); demonstrated security of data and data entry rights; ability to produce contractor-certified electronic versions of weekly payroll data; ability to identify erroneous entries and track the data/time of all versions of the certified Davis Bacon payrolls submitted to the government over the life of the contract capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic Davis-Bacon payroll processing system shall be provided to the Government during contract closeout.

All contractor-incurred costs related to the contractor’s provision and use of an electronic payroll processing service shall be included in the contractor’s price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid/proposed or reimbursed item under this contract.

HAZARDOUS MATERIALS DELIVERED UNDER THIS CONTRACT:

(a) If any hazardous materials will be delivered under this contract (see Section 00 45 00, FAR 52.223-3, and DFARS 252.223-7001), the Material Safety Data Sheets (MSDS) for locally purchased, nonstandard stock hazardous material will be submitted to the Corps of Engineers Contracting Officer or Contracting Officer's Representative. For all other materials, the MSDS will also be submitted to U.S.

Army Environmental Hygiene Agency, ATTN: HSE-OI, Aberdeen Proving Grounds MD 21010.

(b) Hazardous material is defined in Federal Standard No. 313, sold by the General Services Administration Specifications Unit (3FBP-W), 7th & D Streets, SW, Washington DC 20407.

EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

(a) This statement shall become operative only for negotiated contracts where cost or pricing data is requested, and for modifications to sealed bid or negotiated contracts where cost or pricing data is requested. This clause does not apply to terminations.

See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.

(b) Allowable cost for CONSTRUCTION and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, CONSTRUCTION Equipment Ownership and Operating Expense Schedule, Region VII.

Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.

(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.

(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the small purchase threshold, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.

NOTE 1: EP 1110-1-8 is available on the Internet at the following location:

http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx?u dt_43545_param_orderby=Pub_x0020_Date_UDT_Value&udt_43545_param_direction =descending

NOTE 2: Standard Form 1411 is no longer a current form. The Contracting Officer may require submission of cost or pricing data in the format indicated in Table 15-2 of FAR 15.408, specify an alternative format, or permit submission in the contractor’s format.

Information other than cost or pricing data may be submitted in the contractor’s own format unless the use of a specific format is prescribed elsewhere in this contract.

INVOICES:

The Government shall pay the Contractor upon submission of proper invoices for supplies delivered and accepted or services rendered and accepted for the portion of work actually performed under this contract. Refer to Section 00 72 00 Clause 252.232-7003 “Electronic Submission of Payment Requests and Receiving Reports” for registration and procedures. An additional copy of invoices will be submitted to the address in Block 26, SF-1442, which will be completed at time of award. Invoices shall be submitted on ENG Form 93 which will be provided to the Contractor by the Government.

AS-BUILT DRAWINGS (PROGRESS PAYMENT):

One-half of one percent of construction award money shall be withheld until the final as-built drawings and CADD files are accepted by the Government.

AVAILABLE UTILITIES:

As required by FAR clause 52.236-14 the available utilities are:

One fire hydrant; however, please note: the water pressure is very low near the pier. Any contractor use of the fire hydrant must be intermittent. Contractor must allow hyrdant access to emergency personnel as needed.

Electrical outlets.

SALVAGE AND SCRAP GOVERNMENT PROPERTY:

(a) "Government property" means all property owned by or leased to the Government or acquired by the Government under the terms of the contract. It includes both Government-furnished property and contractor-acquired property.

(b) "Salvage" means Government property in possession of a contractor, including subcontractors, that, because of its worn, damaged, deteriorated, or incomplete condition or specialized nature, has no reasonable prospect of sale or use as serviceable property without major repairs, but has some value in excess of its scrap value.

(c) "Scrap" means Government personal property that has no value except for its basic material content.

(d) The Contractor shall maintain records of all scrap and salvage generated from this contract. The Contractor's records shall contain the following information:

(1) Contract Number

(2) Description of salvageable items or classification (material content) of scrap

(3) Quantity on hand

(e) The Contractor shall provide final accounting and disposition recommendations of all Government property not consumed in performing this contract or delivered to the Government including salvage and scrap. The Government will review the Contractor's records and shall cause correction if the Government disagrees with the classification of items as salvage or scrap. The Contractor shall dispose of the items as directed by the Contracting Officer. Items designated as scrap (agreed to by the Contracting Officer) shall be retained by the Contractor; its disposition shall be the responsibility of the Contractor. See Specification Section 01 00 00, paragraph entitled "Scrap Material".

Items designated as salvageable items (agreed to by the Contracting Officer) shall be turned over to the Government.

SUSTAINABILITY REQUIREMENTS

1. EPA Designated Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials, and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit http://www.epa.gov/epawaste/conserve/tools/cpg/products for a complete list of designated products and the associated recommended content levels. Offerors must be able to demonstrate that each offered product meets minimum content levels upon request.

2. Safer Choice The contractor shall provide Safer Choice labeled products under this contract, as applicable. The contractor is encouraged to visit http://www2.epa.gov/saferchoice/products for updated lists of qualifying products.

3. Bio-based

The United States Department of Agriculture (USDA) designates certain biobased products for federal procurement and specifies minimum biobased content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred’s minimum biobased content level. Visit the BioPreferred web site for the complete list of designated products and the associated minimum biobased content level requirements.

4. Energy Star As required in clause 52.223-15 Energy Efficiency in Energy-Consuming Products, the contractor shall only provide products that earn the ENERGY STAR label and meet ENERGY STAR specifications for energy efficiency. The contractor is encouraged to visit http://www.energystar.gov for complete product specifications and updated lists of qualifying products.

5. EPEAT

The contractor shall exclusively provide EPEAT-registered products under this contract, as applicable. The Contractor is responsible for ensuring products meet the latest EPEAT requirements at the time of delivery. Visit www.epeat.net for complete product specifications, registration requirements, and updated lists of qualifying products.

Sustainable Product Reporting

The contractor shall submit a [quarterly/semi-annual/annual] report to the Contracting Officer’s Representative quantifying the number of EPEAT-registered products delivered under this contract (by product type and EPEAT rating). The report shall include data for the current quarter, current fiscal year, and total contract period. A sample matrix for this data is shown below.

Product Type Non-EPEAT

Registered

EPEAT

Bronze

EPEAT Silver EPEAT Gold

Computers & Displays

Imaging Equipment

Televisions

6. Asset Take-Back The Contractor shall assess the remaining value of purchased equipment at the end of its useful life based on its current value. The Government may return the equipment to the Contractor and use the assessed value to offset the purchase price of a new device.

As part of the proposal, the Contractor shall clearly identify its approach to device end-of-life management. Unless approved by the Government as a management option, electronic assets shall not be disposed of in a landfill or by incineration.

For any equipment removed by the Contractor and scheduled to be refurbished or recycled, the Contractor is required to demonstrate as part of its management plan that those actions will be handled by a refurbisher or recycler that is third-party certified to one of the known electronics recycling certification programs that is used in the United States, the Responsible Recycling Standard (R2) or the E-Stewards Standard.

7. FEMP

As required in clause 52.223-15 Energy Efficiency in Energy-Consuming Products, the contractor shall only provide products that meet Federal Energy Management Program (FEMP) purchasing specifications for energy efficiency under this contract, as applicable. Covered product categories and the applicable energy efficiency requirements can be found at http://energy.gov/eere/femp/covered-product-categories.

8. WaterSense The contractor shall provide WaterSense labeled products under this contract, as applicable. The contractor is encouraged to visit http://www.epa.gov/watersense for complete product specifications and updated lists of qualifying products.

Contractor Tasks Throughout the Solicitation and Contract

The Contractor shall be responsible for all tasks contained in the Contract and Attachments (See table of contents) which are not specifically identified as a responsibility of a party that is not the contractor. For example, if a task read "[task] shall be completed," The contractor would be responsible for that task.

However, because the biological opinions are written to the Government, for the Attached NMFS Biological Opinion 11_19_2014 MOTCO Pier and USFWS 2014-F- 0002-5 MOTCO Pier 2 Final Biological Opinion, the Contractor shall perform all tasks where the Government is identified as the responsible party. However, please note: the mitigation bank credits described in these biological opinions are excluded from contractor responsibilities and remain a Government responsibility.

Time Extensions for Unusually Severe Weather.

Refer to FAR 52.249-10, Default (Fixed-Priced Construction). All weather delays will need to be submitted and approved by the Contracting Officer Representative.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

(06) (05) (05) (04) (01) (00) (00) (00) (01) (02) (05) (06)

(End of Summary of Changes)