Spec Section 02 41 00

View the file

Other files

File Type Posted
KE1-09-0509 Electrical REPOSTED —
KEI-09-0507-CD102-CD112_AMENDMENTS_(11_Sheets).pdf PDF
KEI-09-0517-C-120_AMENDMENT_(1_Sheet).pdf PDF
KEI-09-0508 Instrumentation REPOSTED —
1966_AMENDMENT_0006__SUMMARY.pdf PDF
A0.1.10_Attachment_17_Utility_Poles_(17-R-0006)_ADDED-Attachment.pdf PDF
KE1-09-0510 Electrical REPOSTED —
KEI-09-0510 Instrumentation REPOSTED —
KEI-09-0525-SR502_AMENDMENT_(1_Sheet).pdf PDF
A01.10_Attachment_03_Geotechnical_Data_Report_(17-R-0006)_REVISED_PAGES_1-4_ONLY.pdf PDF
Price_Schedule_-_Isabella_Ph_II_1_May_2017.pdf PDF
KE1-09-0510-ST100_AMENDMENT_(1_Sheet).pdf PDF
KEI-09-0509-CD101-CD104_AMENDMENTS_(4_Sheets).pdf PDF
A01.10_Attachment_09_Suppelmental_Info_GIR_(17-R-0006)_REVISED-PAGES_1-5_ONLY.pdf PDF
Revised_Specifications.pdf PDF
KE1-09-0509-SD201_AMENDMENT_(1_Sheet).pdf PDF
KE1-09-0507-ES005_AMENDMENT_(1_Sheet).pdf PDF
KEI-09-0509 Instrumentation —
KEI-09-0524-A-111_to_A-113_AMENDMENT_(3_Sheets).pdf PDF
W91238-17-R-0006-0006.pdf PDF
Attachment_06_Wage_Determination_(CA_31)_-_Isabella_Ph_II_UPDATED.pdf PDF
Price_Schedule_-_Isabella_Ph_II_UPDATED_for_Amend_5.xlsx XLSX spreadsheet
W91238-17-R-0006-0005.pdf PDF
Sample_Breakout_Format.xlsx XLSX spreadsheet
31_09_13.pdf PDF
1966_AMENDMENT_0004__SUMMARY.pdf PDF
01_14_00.10.pdf PDF
W91238-17-R-0006-0004.pdf PDF
SEA_3_USFS_AdminandRec_Facilities_Relo_SEA_and_FONSI.pdf PDF
W91238-17-R-0006-0003.pdf PDF
Price_Schedule_-_Isabella_Ph_II_(17-R-0006).pdf PDF
Specification_02_82_13.pdf PDF
1966_AMENDMENT_0003__SUMMARY.pdf PDF
Attachment_C_-_Past_Performance_Questionnaire.pdf PDF
Attachment_B_-_Contractor's_Project_Experience.pdf PDF
Attachment_D_-_Small_Business_Participation_Commitment_Document.pdf PDF
Specification_01_22_00.pdf PDF
Attachment_A_-_Pre-Award_Survey_Info.pdf PDF
W91238-17-R-0006-0002.pdf PDF
Isabella-_Site_Vist_Presentation_6APR2017.pdf PDF
Isabella_Phase_II_Site_Visit_Sign_In_Roster.pdf PDF
W91238-17-R-0006-0001.pdf PDF
A01.10_Attachment_05_Stone_and_Aggregate_Report_(17-R-0006).pdf PDF
A01.10_Attachment_14_01_50_00_Isabella_Government_Testing_Laboratory_GER_(17-R-0006).pdf PDF
A01.10_Attachment_11_Supplemental_Info_-_Topo_and_Utility_Surveys_(17-R-0006).pdf PDF
A01.10_Attachment_07_Supplemental_Info_List_of_Isabella_Env_Docs_(17-R-0006)_.pdf PDF
W91238-17-R-0006,_Isabella_Lake_Dam_Safety_Modification_Project_(DSMP),_Phase_II__Dams_and_Spillway.pdf PDF
A01.10_Attachment_10_Supplemental_Info_As-Builts_(17-R-0006).pdf PDF
A01.10_Attachment_13_01_57_20_Isabella_Lake_Water_Quality_Baseline_2016_(17-R-0006).pdf PDF
A01.10_Attachment_04_Water_Testing_and_Evaluation_Report_(17-R-0006).pdf PDF
Show 40 more

Latest 50 of 59 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Isabella Lake DSMP - Dams and Spillways 1966 April 21, 2017

SECTION TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 02 41 00

DEMOLITION

PART 1 GENERAL

1.1 REFERENCES

1.2 PROJECT DESCRIPTION

1.2.1 Demolition Plan

1.2.2 General Requirements

1.3 ITEMS TO REMAIN IN PLACE

1.3.1 Existing Construction Limits and Protection

1.3.2 Weather Protection

1.3.3 Trees

1.3.4 Utility Service

1.3.5 Facilities

1.4 BURNING

1.5 SUBMITTALS

1.6 QUALITY CONTROL

1.6.1 Dust and Debris Control

1.7 PROTECTION

1.7.1 Traffic Control Signs

1.7.2 Protection of Personnel

1.8 RELOCATIONS

PART 2 PRODUCTS

2.1 FILL MATERIAL

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

3.1.1 Structures

3.1.2 Utilities and Related Equipment

3.1.2.1 General Requirements

3.1.2.2 Disconnecting Existing Utilities

3.1.3 Chain Link Fencing

3.1.4 Slabs

3.1.5 Roofing

3.1.5.1 Temporary Roofing

3.1.6 Concrete

3.1.7 Structural Steel

3.1.8 Miscellaneous Metal

3.1.9 Patching

3.1.10 Mechanical Equipment and Fixtures

3.1.10.1 Preparation for Storage

3.1.10.2 Piping

3.1.10.3 Ducts

3.1.10.4 Fixtures, Motors and Machines

3.1.11 Electrical Equipment and Fixtures

02 41 00 - 1 Amendment 0004

3.1.11.1 Fixtures

3.1.11.2 Electrical Devices

3.1.11.3 Wiring Ducts or Troughs

3.1.11.4 Conduit and Miscellaneous Items

3.1.12 Elevators and Hoists

3.2 CONCURRENT EARTH-MOVING OPERATIONS

3.3 DISPOSITION OF MATERIAL

3.3.1 Title to Materials

3.3.2 Salvaged Materials and Equipment

3.4 CLEANUP

3.5 DISPOSAL OF REMOVED MATERIALS

3.5.1 Regulation of Removed Materials

3.5.2 Burning on Government Property

3.5.3 Removal from Government Property

3.6 REUSE OF SALVAGED ITEMS

-- End of Section Table of Contents --

02 41 00 - 2

SECTION 02 41 00

DEMOLITION

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.6 (2006) Safety Requirements for Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 61 National Emission Standards for Hazardous Air Pollutants

1.2 PROJECT DESCRIPTION

1.2.1 Demolition Plan

This Demolition Specificaiton requirements apply to Demolition Features within the Dam and Spillway Construction Work Limit shown on Sheet G-102 (KE1-09-0507). For Demolition Features within the Recreation Facilitiies work limit, refer to SECTION 02 41 00.16 DEMOLITION FOR RECREATION SITES.

Refer to Sheet C-110, C-111 and C-112 (KE1-09-0516) and SECTION 02 41 00.16 for Auxilary Dam Recreation Facility Relocation Demolition Requirements.

Prepare a Demolition Plan and submit proposed salvage, demolition, deconstruction, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Coordinate with the Waste Management Plan as in Section 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT. Provide procedures for safe conduct of the work in accordance with EM 385-1-1.

Plan will be approved by Contracting Officer prior to work beginning.

1.2.2 General Requirements

Do not begin demolition until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site; do not allow accumulations. The work includes demolition, deconstruction, and removal of resulting rubbish and debris. Remove rubbish and debris from

02 41 00 - 3

Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections.

1.3 ITEMS TO REMAIN IN PLACE

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.

Coordinate the work of this section with all other work indicated.

Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload structural elements. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.

1.3.1 Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.

1.3.2 Weather Protection

For portions of the structure to remain, protect materials and equipment from the weather at all times. Where removal of existing roofing is necessary to accomplish work, have materials and workmen ready to provide adequate and temporary covering of exposed areas.

1.3.3 Trees

Protect trees within the project site as indicated on drawing which might be damaged during demolition, by a 6 foot high fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer.

1.3.4 Utility Service

Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, utilities serving each area of alteration or removal will be shut off by the Government and disconnected and sealed by the Contractor the Government will disconnect and seal utilities serving each area of alteration or removal upon written request from the Contractor.

1.3.5 Facilities

Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or

02 41 00 - 4 connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer. Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.

1.4 BURNING

The use of burning at the project site for the disposal of refuse and debris will not be permitted.

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Demolition Plan; G, DO

SD-07 Certificates

Notification; G

1.6 QUALITY CONTROL

Submit timely notification of demolition projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61, Subpart M.

Notify the the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61, Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSE/SAFE A10.6. Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.

1.6.1 Dust and Debris Control

Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Refer to specification section 01 57 20 for dust and debris control requirements.

1.7 PROTECTION

1.7.1 Traffic Control Signs

Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind. Notify the Contracting Officer

02 41 00 - 5 prior to beginning such work.

1.7.2 Protection of Personnel

Before, during and after the demolition and deconstruction work continuously evaluate the condition of the structure being demolished and deconstructed and take immediate action to protect all personnel working in and around the project site. No area, section, or component of structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.

1.8 RELOCATIONS

Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.

PART 2 PRODUCTS

2.1 FILL MATERIAL

a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures facilities, pipes, and utilities. Backfill material requirements for areas within the embankment footprint and excavation limits, refer to Section 31 23 16 EXCAVATION and Section 35 73 13 EMBANKMENT FOR EARTH DAMS; backfill material requirements for areas outside the embankment footprint, refer to Section 31 00 00 EARTHWORK. Grout existing float well intake pipes requirements, refer to Section 33 11 2302 41 13.26

PIPELINE ABANDONMENT.

PART 3 EXECUTION

3.1 EXISTING FACILITIES TO BE REMOVED

Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled.

Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified.

Materials shall be designated for reuse onsite whenever possible.

3.1.1 Structures

a. Remove existing structures indicated to be removed to grade as shown on contract drawings.

b. Demolish structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed.

Demolish concrete walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer.

c. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting

02 41 00 - 6 walls, floors, or framing.

3.1.2 Utilities and Related Equipment

3.1.2.1 General Requirements

Remove existing utility, instrumentations, equipments and material as shown on contract drawings.

Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made.

Shut off and cap utilities for future use, as indicated.

3.1.2.2 Disconnecting Existing Utilities

Remove existing utilities, as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the Contracting Officer.

3.1.3 Chain Link Fencing

Remove chain link fencing, gates and other related salvaged items scheduled for removal and transport to designated areas. Remove gates as whole units. Cut chain link fabric to 25 foot lengths and store in rolls off the ground.

3.1.4 Slabs

Remove concrete and slabs including aggregate base as indicated. Slabs not to be used in this project shall be removed from the project site at Contractor's expense.

3.1.5 Roofing

Remove existing roof system and associated components in their entirety down to existing roof deck. Sequence work to minimize building exposure between demolition or deconstruction and new roof materials installation.

3.1.5.1 Temporary Roofing

Install temporary roofing and flashing as necessary to maintain a watertight condition throughout the course of the work. Remove temporary work prior to installation of permanent roof system materials unless approved otherwise by the Contracting Officer.

3.1.6 Concrete

Saw concrete along straight lines to a depth of a minimum 2 inch. Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining

02 41 00 - 7 concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete.

3.1.7 Structural Steel

Dismantle structural steel at field connections and in a manner that will prevent bending or damage. Salvage for recycle structural steel, steel joists, girders, angles, plates, columns and shapes. Do not use flame-cutting torches. Transport steel joists and girders as whole units and not dismantled. Transport structural steel shapes to a designated area as directed by the Contracting Officer, stacked according to size, type of member and length, and stored off the ground, protected from the weather.

3.1.8 Miscellaneous Metal

Salvage shop-fabricated items such as frames, steel gratings, metal ladders, wire mesh partitions, metal railings, and similar items as whole units. Salvage light-gage and cold-formed metal framing, such as steel studs, steel trusses, roofing and siding, metal toilet partitions, toilet accessories and similar items. Recycle scrap metal as part of demolition and deconstruction operations. Provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the Waste Management Plan.

3.1.9 Patching

Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish. Patching shall be as specified and indicated, and shall include:

a. Concrete: Completely fill holes and depressions, left as a result of removals in existing walls to remain, with an approved patching material, applied in accordance with the manufacturer's printed instructions.

3.1.10 Mechanical Equipment and Fixtures

Disconnect mechanical hardware at the nearest connection to existing services to remain, unless otherwise noted. Disconnect mechanical equipment and fixtures at fittings. Remove service valves attached to the unit. Salvage each item of equipment and fixtures as a whole unit; listed, indexed, tagged, and stored. Salvage each unit with its normal operating auxiliary equipment. Transport salvaged equipment and fixtures, including motors and machines, to a designated storage area as directed by the Contracting Officer. Do not remove equipment until approved. Do not offer low-efficiency equipment for reuse.

3.1.10.1 Preparation for Storage

Remove water, dirt, dust, and foreign matter from units; tanks, piping and fixtures shall be drained; interiors, if previously used to store flammable, explosive, or other dangerous liquids, shall be steam cleaned.

Seal openings with caps, plates, or plugs. Secure motors attached by

02 41 00 - 8 flexible connections to the unit.

3.1.10.2 Piping

Disconnect piping at unions, flanges and valves, and fittings as required to reduce the pipe into straight lengths for practical storage. Store salvaged piping according to size and type. If the piping that remains can become pressurized due to upstream valve failure, end caps, blind flanges, or other types of plugs or fittings with a pressure gage and bleed valve shall be attached to the open end of the pipe to ensure positive leak control. Carefully dismantle piping that previously contained gas, gasoline, oil, or other dangerous fluids, with precautions taken to prevent injury to persons and property. Store piping outdoors until all fumes and residues are removed. Box prefabricated supports, hangers, plates, valves, and specialty items according to size and type. Wrap sprinkler heads individually in plastic bags before boxing. Classify piping not designated for salvage, or not reusable, as scrap metal.

3.1.10.3 Ducts

Classify removed duct work as scrap metal.

3.1.10.4 Fixtures, Motors and Machines

Remove and salvage fixtures, motors and machines associated with plumbing, heating, air conditioning, refrigeration, and other mechanical system installations. Salvage, box and store auxiliary units and accessories with the main motor and machines. Tag salvaged items for identification, storage, and protection from damage. Classify non-porcelain broken, damaged, or otherwise unserviceable units and not caused to be broken, damaged, or otherwise unserviceable as debris to be disposed of by the Contractor.

3.1.11 Electrical Equipment and Fixtures

Salvage motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Salvage wiring systems and components. Box loose items and tag for identification. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.

3.1.11.1 Fixtures

Remove and salvage electrical fixtures. Salvage unprotected glassware from the fixture and salvage separately. Salvage incandescent, mercury-vapor, and fluorescent lamps and fluorescent ballasts manufactured prior to 1978, boxed and tagged for identification, and protected from breakage.

3.1.11.2 Electrical Devices

Remove and salvage switches, switchgear, transformers, conductors including wire and nonmetallic sheathed and flexible armored cable, regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items. Box and tag these items for identification according to type and size.

3.1.11.3 Wiring Ducts or Troughs

Remove and salvage wiring ducts or troughs. Dismantle plug-in ducts and

02 41 00 - 9 wiring troughs into unit lengths. Remove plug-in or disconnecting devices from the busway and store separately.

3.1.11.4 Conduit and Miscellaneous Items

Salvage conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.

3.1.12 Elevators and Hoists

Remove elevators, hoists, and similar conveying equipment and salvage as whole units, to the most practical extent. Remove and prepare items for salvage without damage to any of the various parts. Salvage and store rails for structural steel with the equipment as an integral part of the unit.

3.2 CONCURRENT EARTH-MOVING OPERATIONS

Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.

3.3 DISPOSITION OF MATERIAL

3.3.1 Title to Materials

Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.

3.3.2 Salvaged Materials and Equipment

a. Salvage items and material to the maximum extent possible.

b. Store all materials salvaged for the Contractor as approved by the Contracting Officer and remove from Government property before completion of the contract. On site sales of salvaged material is prohibited.

c. Remove salvaged items to remain the property of the Government in a manner to prevent damage, and packed or crated to protect the items from damage while in storage or during shipment. Items damaged during removal or storage must be repaired or replaced to match existing items. Properly identify the contents of containers.

02 41 00 - 10

d. Remove the following items reserved as property of the using service prior to commencement of work under this contract: None. Any remaining equipment or materials will become the property of the Contractor for disposal or salvage at the Contractor's option.

e. Remove historical items in a manner to prevent damage. Deliver the following historical items to the Government for disposition: Corner stones, contents of corner stones, and document boxes wherever located on the site.

3.4 CLEANUP

Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

3.5 DISPOSAL OF REMOVED MATERIALS

3.5.1 Regulation of Removed Materials

Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan. Storage of removed materials on the project site is prohibited. See Section 01 57 20 ENVIRONMENTAL PROTECTION, Section 01 74 19 CONSTRUCTION AND DEMOLITION WASTE, and Section 01 71 10 MOBILIZATION AND DEMOBILIZATION for details.

3.5.2 Burning on Government Property

Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.

3.5.3 Removal from Government Property

Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal. Dispose of waste soil as directed.

3.6 REUSE OF SALVAGED ITEMS

Recondition salvaged materials and equipment designated for reuse before installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.

-- End of Section --

02 41 00 - 11

02 41 00 - DEMOLITION
02 41 00 - DEMOLITION
PART 1 GENERAL
1.1 REFERENCES
1.2 PROJECT DESCRIPTION
1.2.1 Demolition Plan
1.2.2 General Requirements
1.3 ITEMS TO REMAIN IN PLACE
1.3.1 Existing Construction Limits and Protection
1.3.2 Weather Protection
1.3.3 Trees
1.3.4 Utility Service
1.3.5 Facilities
1.4 BURNING
1.5 SUBMITTALS
1.6 QUALITY CONTROL
1.6.1 Dust and Debris Control
1.7 PROTECTION
1.7.1 Traffic Control Signs
1.7.2 Protection of Personnel

1.8 RELOCATIONS

PART 2 PRODUCTS
2.1 FILL MATERIAL
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Structures
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
3.1.2.2 Disconnecting Existing Utilities
3.1.3 Chain Link Fencing
3.1.4 Slabs
3.1.5 Roofing
3.1.5.1 Temporary Roofing
3.1.6 Concrete
3.1.7 Structural Steel
3.1.8 Miscellaneous Metal
3.1.9 Patching
3.1.10 Mechanical Equipment and Fixtures
3.1.10.1 Preparation for Storage
3.1.10.2 Piping
3.1.10.3 Ducts
3.1.10.4 Fixtures, Motors and Machines
3.1.11 Electrical Equipment and Fixtures
3.1.11.1 Fixtures
3.1.11.2 Electrical Devices
3.1.11.3 Wiring Ducts or Troughs
3.1.11.4 Conduit and Miscellaneous Items

3.1.12 Elevators and Hoists

3.2 CONCURRENT EARTH-MOVING OPERATIONS
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
3.3.2 Salvaged Materials and Equipment
3.4 CLEANUP
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
3.5.2 Burning on Government Property
3.5.3 Removal from Government Property

3.6 REUSE OF SALVAGED ITEMS