This document provides specifications for wall and door protection products required for a Cyber Operations Facility project. Stainless steel corner guards made of 16 gauge 302 or 304 material and extending floor to ceiling are required and must meet minimum 18 ft-lb/sq in impact resistance, Class 1 fire rating, and be resistant to chemicals, stains, fungi and bacteria. Adhesives used must meet emissions standards of CDPH Section 01350, SCAQMD Rule 1168 or GS-36. Color samples must be submitted and installation must follow manufacturer's recommendations. The related federal contract opportunity is solicitation number W91236-21-B-2013 for the Cyber Operations Facility project issued by the Department of the Army Corps of Engineers Norfolk District.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

185th CYBER OPS FACILITY W91236-17-D-0001

JOINT BASE LANGLEY-EUSTIS, VA

SECTION 10 26 00

WALL AND DOOR PROTECTION

08/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM A240/A240M (2017) Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications

ASTM D256 (2010) Determining the Izod Pendulum Impact Resistance of Plastics

ASTM D543 (2014) Standard Practices for Evaluating the Resistance of Plastics to Chemical Reagents

ASTM D635 (2014) Standard Test Method for Rate of Burning and/or Extent and Time of Burning of Self-Supporting Plastics in a Horizontal Position

ASTM E84 (2018a) Standard Test Method for Surface Burning Characteristics of Building Materials

ASTM G21 (2015) Standard Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi

CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)

CDPH SECTION 01350 (2010; Version 1.1) Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers

GREEN SEAL (GS)

GS-36 (2013) Adhesives for Commercial Use

SCIENTIFIC CERTIFICATION SYSTEMS (SCS)

SCS SCS Global Services (SCS) Indoor Advantage

SECTION 10 26 00 PAGE 1 RTA Submittal Amendment 001

SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)

SCAQMD Rule 1168 (2017) Adhesive and Sealant Applications

UNDERWRITERS LABORATORIES (UL)

UL 2818 (2013) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Corner Guards ; G

SD-03 Product Data

Corner Guards ; G

Recycled content for steel component of corner guards ; S

SD-04 Samples

Finish ; G

SD-06 Test Reports

Corner Guards

SD-07 Certificates

Corner Guards

Indoor air quality for adhesives ; S

1.3 CERTIFICATIONS

1.3.1 Indoor Air Quality

1.3.1.1 Adhesives and Sealants

Provide products certified to meet indoor air quality requirements by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification or validation by other third-party program that products meet the requirements of this section. Provide current product certification documentation from certification body When product does not have certification, provide validation that product meets the indoor air quality product requirements cited herein..

SECTION 10 26 00 PAGE 2 RTA Submittal

1.4 DELIVERY, STORAGE, AND HANDLING

Deliver materials to the project site in manufacturer's original unopened containers with seals unbroken and labels and trademarks intact. Keep materials dry, protected from weather and damage, and stored under cover.

Materials must be stored at approximately 70 degrees F for at least 48 hours prior to installation.

1.5 WARRANTY

Provide manufacturer's standard performance guarantees or warranties that extend beyond a 1 year period.

PART 2 PRODUCTS

2.1 STANDARD PRODUCTS

To the maximum extent possible, corner guards must be the standard products of a single manufacturer and must be furnished as detailed.

Drawings show general configuration of products required, and items differing in minor details from those shown will be acceptable.

2.1.1 Material

2.1.1.1 Minimum Impact Resistance

Minimum impact resistance must be 18 ft-lbs/sq. inch when tested in accordance with ASTM D256, (Izod impact, ft-lbs per sq inch notched).

2.1.1.2 Fire Rating

Fire rating must be Class 1 when tested in accordance with ASTM E84, having a maximum flame spread of 25 and a smoke developed rating of 450 or less. Material must be rated self extinguishing when tested in accordance with ASTM D635. Material must be labeled and tested by an approved nationally known testing laboratory. Resilient material used for protection on fire rated doors and frames must be listed by the testing laboratory performing the tests. Resilient material installed on fire rated wood/steel door and frame assemblies must have been tested on similar type assemblies. Test results of material tested on any other combination of door/frame assembly will not be acceptable.

2.1.1.3 Chemical and Stain Resistance

Materials must be resistant to chemicals and stains reagents in accordance with ASTM D543.

2.1.1.4 Fungal and Bacterial Resistance

Materials must be resistant to fungi and bacteria in accordance with ASTM G21, as applicable.

2.2 CORNER GUARDS

2.2.1 Stainless Steel Corner Guards

Stainless steel corner guards must be fabricated of 16 gauge thick material conforming to ASTM A240/A240M , type 302 or 304. Provide data identifying percentage of recycled content for steel component of corner

SECTION 10 26 00 PAGE 3 RTA Submittal guards . Corner guards must extend from floor to ceiling Refer to finish schedule for height . Corner guard must be formed to dimensions shown.

2.3 TRIM, FASTENERS AND ANCHORS

Provide vinyl trim, fasteners and anchors for each specific installation as shown.

2.4 FINISH

Submit three samples indicating color and texture of materials requiring color and finish.

2.4.1 Stainless Steel Finish

Finish for stainless steel must be in accordance with ASTM A240/A240M , Type 302 or 304, finish number 4.

2.5 ADHESIVES

Adhesive for resilient material must be in accordance with manufacturers recommendations. Provide sealants and non-aerosol adhesive products used on the interior of the building (defined as inside of the weatherproofing system) that meet either emissions requirements of CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type) the VOC content requirements of SCAQMD Rule 1168 , or VOC content requirements of GS-36. Provide certification or validation of indoor air quality for adhesives .

2.6 COLOR

Color must be as indicated. Color listed is not intended to limit the selection of equal colors from other manufacturers.

PART 3 EXECUTION

3.1 INSTALLATION

Do not install items that show visual evidence of biological growth.

3.1.1 Corner Guards and Wall Guards (Bumper Guards)

Material must be mounted at location indicated in accordance with manufacturer's recommendations.

3.1.2 Stainless Steel Guards

a. Mount guards on external corners of interior walls, partitions and columns as shown.

b. Where corner guards are installed on gypsum board, clean surfaces and anchor guards with a neoprene solvent-type contact adhesive specifically manufactured for use on gypsum board construction.

Remove excess adhesive from the guard edges and allow to cure undisturbed for 24 hours.

-- End of Section --