This document contains questions and answers regarding a construction project at Building 844 at Fort Leonard Wood, Missouri. There is no existing chiller at the building, so the contractor shall include a new chiller in their design for the 4 pipe HVAC system. While additional lightning protection is not required, the contractor must perform a lightning risk analysis and may propose adding new lightning protection if proven necessary through the analysis.

The related federal contract opportunity is a Multiple Award Task Order Contract solicitation to be issued by the Mission and Installation Contracting Command - Fort Leonard Wood. The solicitation number is W911S7-19-R-0008 and will be posted on January 3rd, 2019, with quotes due February 4th, 2019. The NAICS code is 236220 with a small business size standard of $36.5M. The PSC is Y1AA for construction of office buildings. The place of performance is Fort Leonard Wood and Lake of the Ozarks Recreational Area in Missouri. This will be a total small business set-aside multiple award firm fixed price IDIQ contract for construction requirements.

Q&A (addendum)

View the file

Other files for this federal contract opportunity

Other files attached to MATOC, newest first.
File Type Posted
W911S719R0008_0006.pdf PDF
STO-01_11_00_-_Summary_of_Work_Revision_TWO_6-18-19_for_solicitation.pdf PDF
W911S719R00080005.pdf PDF
Q&A.pdf PDF
STO-01_11_00_-_Summary_of_Work_Revised_5-10-19_for_solicitation.docx DOCX document
LNS_QCchecklist_appendixA.doc DOC document
FLW_advanced_meter_guidance.docx DOCX document
Fort_Leonard_Wood_List_of_Approved_Instrumentation_and_Control_for_HVAC_Devices_and_software.docx DOCX document
Niagara-Lonworks_QCchecklist_appendixA.doc DOC document
Inventory_Spreadsheet_2017-12-07.xlsx XLSX spreadsheet
Distech_JCI_LX_GPI_4.X.pdf PDF
W911S7-19-R-0008_0004.pdf PDF
Distech_JCI_Confirmation.pdf PDF
LonScanner_CON.pdf PDF
EC-gfx_Program_6.X.pdf PDF
Point_Schedule_Lonworks_BACnet_Niagara_2015-07-15.xlsx XLSX spreadsheet
IZoT_Commissioning_Tool_(CT)_Pro_4.X.pdf PDF
Temp_IP_Network_Compliance_Statement.docx DOCX document
Jace_CON_201722158.pdf PDF
TAC_vista_201620463.pdf PDF
844_Index_and_Combined_DDC_Specifications_May_10,_2019.docx DOCX document
W911S719R00080003.pdf PDF
W911S717R00080002.pdf PDF
W911S7-17-R-0008,_Site_Visit,_19_Apr_2019.pdf PDF
ecb_2018_17.pdf PDF
W911S719R00080001.pdf PDF
Attachment-11-Contractor's-Price-Schedule-Worksheet.xlsx XLSX spreadsheet
STO-(Sh_24)_2nd_Floor_Plan.pdf PDF
MO180061.pdf PDF
STO-(Sh_23)_1st_Floor_Plan.pdf PDF
MO180005.pdf PDF
STO-Red_Line_Plans.pdf PDF
SOW(rev_1).pdf PDF
STO-01_11_00_-_Summary_of_Work.pdf PDF
STO-(Sh_22)_Basement_Plan.pdf PDF
MO180019.pdf PDF
MO180001.pdf PDF
W911S7-19-R-0008.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q. How do we bid “Evaluate existing chiller for condition, age and possible incorporation into the new 4‐ pipe HVAC system.”

A: There is NO existing chiller at bldg. 844. Contractor shall include in their design a chiller complete for the HVAC system.

Q. How do we bid “Perform a lightning risk analysis. And Lightning protection if required”?

A: Additional lightning protection is not required for the project. The Contractor shall perform a lightning risk analysis. If the Contractor proves that additional lightning protection is required, a modification to the project will be allowed to pay for a new lightning protection complete.