About this file

This document contains a quality control checklist appendix for a building automation system project and details of a related federal multiple award task order contract solicitation. The quality control checklist appendix outlines 18 items to be verified at different project stages for a Niagara Framework-based control system. The related federal contract solicitation will be a small business set-aside multiple award task order contract issued by the Department of the Army for construction requirements at Fort Leonard Wood, Missouri. Responses to the solicitation are due February 4, 2019 under solicitation number W911S7-19-R-0008. The resulting contracts will have an indefinite-delivery indefinite-quantity structure for fixed price task orders.

Niagara-Lonworks QC checklist appendix A

View the file

Other files for this federal contract opportunity

Other files attached to MATOC, newest first.
File Type Posted
W911S719R0008_0006.pdf PDF
Q&A_(addendum).pdf PDF
STO-01_11_00_-_Summary_of_Work_Revision_TWO_6-18-19_for_solicitation.pdf PDF
Q&A.pdf PDF
W911S719R00080005.pdf PDF
STO-01_11_00_-_Summary_of_Work_Revised_5-10-19_for_solicitation.docx DOCX document
LNS_QCchecklist_appendixA.doc DOC document
FLW_advanced_meter_guidance.docx DOCX document
Fort_Leonard_Wood_List_of_Approved_Instrumentation_and_Control_for_HVAC_Devices_and_software.docx DOCX document
Inventory_Spreadsheet_2017-12-07.xlsx XLSX spreadsheet
IZoT_Commissioning_Tool_(CT)_Pro_4.X.pdf PDF
Temp_IP_Network_Compliance_Statement.docx DOCX document
Jace_CON_201722158.pdf PDF
TAC_vista_201620463.pdf PDF
844_Index_and_Combined_DDC_Specifications_May_10,_2019.docx DOCX document
Distech_JCI_LX_GPI_4.X.pdf PDF
W911S7-19-R-0008_0004.pdf PDF
Distech_JCI_Confirmation.pdf PDF
LonScanner_CON.pdf PDF
EC-gfx_Program_6.X.pdf PDF
Point_Schedule_Lonworks_BACnet_Niagara_2015-07-15.xlsx XLSX spreadsheet
W911S719R00080003.pdf PDF
ecb_2018_17.pdf PDF
W911S717R00080002.pdf PDF
W911S7-17-R-0008,_Site_Visit,_19_Apr_2019.pdf PDF
W911S719R00080001.pdf PDF
Attachment-11-Contractor's-Price-Schedule-Worksheet.xlsx XLSX spreadsheet
STO-(Sh_24)_2nd_Floor_Plan.pdf PDF
MO180061.pdf PDF
STO-(Sh_23)_1st_Floor_Plan.pdf PDF
MO180005.pdf PDF
STO-Red_Line_Plans.pdf PDF
SOW(rev_1).pdf PDF
STO-01_11_00_-_Summary_of_Work.pdf PDF
STO-(Sh_22)_Basement_Plan.pdf PDF
MO180019.pdf PDF
MO180001.pdf PDF
W911S7-19-R-0008.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX A

QC CHECKLIST: Niagara Lonworks This checklist is not all-inclusive of the requirements of this specification and should not be interpreted as such.

This checklist is for (check one:)

Pre-Construction QC Checklist Submittal
(Items 1-3)
Post-Construction QC Checklist Submittal
(Items 1-10)
Close-out QC Checklist Submittal
(Items 1-18)

Initial and date each item in the spaces provided verifying that each requirement has been met.

Items verified for Pre-Construction, Post-Construction and Closeout QC Checklists Submittal:

Item
Initial
Date
1
All DDC Hardware is numbered on Control System Schematic Drawings.
2
Signal lines on Control System Schematic are labeled with the signal type.
3
Local Display Panel (LDP) Locations are shown on Control System Schematic drawings.

Items verified for Post-Construction and Closeout QC Checklist Submittal:

Item
Initial
Date
4
All sequences are performed as specified using DDC Hardware.
5
Training schedule and course attendee list has been developed and coordinated with shops and submitted.
6
All DDC Hardware except Niagara Framework Supervisory Gateways is installed on a TP/FT-10 Channel.
7
All Application Specific Controllers (ASCs) are LonMark certified.
8
Except for communication between two Niagara Framework Supervisory Gateways, Communication between DDC Hardware is only via <RID>CEA-709.1-D</RID> using SNVTs. Other protocols have not been used. Network variables other than SNVTs have not been used. Communication between Niagara Framework Supervisory Gateways is via Fox Protocol.
9
Explicit messaging has not been used.
10
Scheduling is performed in Niagara Framework Supervisory Gateways.

Items verified for Closeout QC Checklists Submittal:

Item
Initial
Date
11
Final As-built Drawings, including all Points Schedule drawings, accurately represent the final installed system.
12
Programming software has been submitted for all programmable controllers.
13
All software has been licensed to the Government.
14
O&M Instructions have been completed and submitted.
15
Training course has been completed.
16
The database in each Niagara Framework Supervisory Gateway is up-to-date and accurately represents the building control network beneath that Niagara Framework Supervisory Gateway.
17
Niagara Wizards have been submitted for all Application Specific Controllers (ASCs) for which a Wizard is available and for all Application Generic Controllers (AGCs).
18
Programming software has been submitted for all General Purpose Programmable Controllers (GPPCs) and all Application Generic Controllers (AGCs).

(QC Representative Signature) (Date)

Section 23 09 23 Appendix Page 1