AMENDMENT 6 DPW15-123 REVISED Submittal Register 27 OCT 2020.xls
XLS spreadsheet 58 KB Posted
- Attached to
- DPW15-123 Interior Improvement B1218
- Solicitation number
- W911RZ-20-B-0001
About this file
This submittal register outlines 59 line items of products and services required for the renovation of Building B1218 under Solicitation Number W911RZ-20-B-0001 from the Department of the Army Materiel Command Mission and Installation Contracting Command at Fort Hood. Key requirements include interior and exterior doors, metal door frames, toilet partitions, suspended ceiling tiles and grid, various flooring types, countertops, cabinets, plumbing fixtures, fire sprinkler systems, HVAC equipment, electrical switchboards and panels, lighting fixtures, data and communications cabling, and fire alarm systems. The contractor must submit shop drawings, product data, samples, and other submittals for government approval within 3 to 6 weeks of notice to proceed or contract award with some pressure testing and reports due prior to final inspection.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet 1
| SUBMITTAL REGISTER | CONTRACT NO. | ||||||||||||||||||||||||||
| (ER 415-1-10) | |||||||||||||||||||||||||||
| TITLE AND LOCATION | CONTRACTOR | SPECIFICATION SECTION | |||||||||||||||||||||||||
| DPW15-123 Repair B1218 | |||||||||||||||||||||||||||
| CLASSI- | |||||||||||||||||||||||||||
| TYPE OF SUBMITTAL | FICATION | CONTRACTOR | CONTRACTOR | GOVERNMENT | |||||||||||||||||||||||
| SCHEDULED DATES | ACTION | ACTION | |||||||||||||||||||||||||
| I | C | ||||||||||||||||||||||||||
| N | E | I | |||||||||||||||||||||||||
| S | S | R | N | G | |||||||||||||||||||||||
| TRANS- | SPECIFICATION | T | S | T | T | F | O | ||||||||||||||||||||
| MITTAL | ITEM | PARAGRAPH | DESCRIPTION OF | D | R | C | A | I | O | V | A | R | |||||||||||||||
| NO. | NO. | NUMBER | ITEM SUBMITTED | R | U | H | T | R | F | S | R | R | E | P | E | APPROVAL | MATERIAL | SUBMIT | |||||||||
| A | C | E | E | E | I | A | E | M | R | P | V | SUBMIT | NEEDED | NEEDED | CODE | DATE | TO | CODE | DATE | REMARKS | |||||||
| W | T | D | M | P | C | M | C | A | N | R | I | BY | BY | GOVERN- | |||||||||||||
| D | I | I | U | E | O | A | P | O | T | O | M | O | E | MENT | |||||||||||||
| A | N | O | L | N | R | T | L | R | I | N | E | V | W | ||||||||||||||
| T | G | N | E | T | T | E | E | D | O | L | N | E | E | ||||||||||||||
| A | S | S | S | S | S | S | S | S | N | Y | T | D | R | ||||||||||||||
| a. | b. | c. | d. | e. | f. | g. | h. | i. | j. | k. | l. | m. | n. | o. | p. | q. | r. | s. | t. | u. | v. | w. | x. | ||||
| 1 | 1 | Interior and Exterior Doors | X | X | X | NLT 3 weeks after NTP | |||||||||||||||||||||
| 2 | 2 | Interior Metal Door Frames | X | X | X | NLT 3 weeks after NTP | |||||||||||||||||||||
| 3 | 3 | Toilet Partitions | X | X | X | NLT 3 weeks after NTP | |||||||||||||||||||||
| 4 | 4 | Construction Schedule showing Key Milestones and Inspection Points, As Often | |||||||||||||||||||||||||
| As Required to Maintain Accuracy | X | X | NLT 3 weeks after NTP | ||||||||||||||||||||||||
| 5 | 5 | Quality Control and Safety Plans | X | X | NL T2 weeks after NTP | ||||||||||||||||||||||
| 6 | 6 | DPW Approved Outage Requests, Signed by Required Signators, Including Traffic Contol and Phasing Plan | X | X | NLT2 weeks after NTP | ||||||||||||||||||||||
| 7 | 7 | Suspended Ceiling Tile | X | X | X | NLT 3 weeks after NTP | |||||||||||||||||||||
| 8 | 8 | Suspended Ceiling Grid | X | X | X | NLT 3 weeks after NTP | |||||||||||||||||||||
| 9 | 9 | Paint Colors | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 10 | 10 | Carpet Tile | X | X | X | NLT 3 weeks after NTP | |||||||||||||||||||||
| 11 | 11 | Vinyl Composition Floor Tile | X | X | NLT 2 weeks after CCD | ||||||||||||||||||||||
| 12 | 12 | Resilient Base | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 13 | 13 | Resilient Stair Treads and Risers | X | X | NLT6 weeks after NTP | ||||||||||||||||||||||
| 14 | 14 | Laminate Countertops | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 15 | 15 | Kitchen Cabinets | X | X | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||
| 16 | 16 | Automatic Door Openers | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 17 | 17 | Door Hardware | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 18 | 18 | Signage | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 19 | 19 | Operations and Maintenance Manuals | X | upon project completion | |||||||||||||||||||||||
| 20 | 20 | As-Built Drawings | X | upon project completion | |||||||||||||||||||||||
| 21 | 21 | Mirrors | X | X | upon project completion | ||||||||||||||||||||||
| 22 | 22 | Light Gage Metal Framing | X | X | NLT 3 weeks after NTP | ||||||||||||||||||||||
| 23 | 23 | Paper Towel Dispenser | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 24 | 24 | ADA Grab Bars | X | X | NTL 6 weeks afte NTP | ||||||||||||||||||||||
| 25 | 25 | Soap Dispensers | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 26 | 26 | Trash Receptor | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 27 | 27 | ADA Handrails (Ramp) | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 28 | 28 | Double Roll Toilet Paper Holder | X | X | |||||||||||||||||||||||
| 29 | 29 | Face Brick | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 30 | 30 | Porcelain Floor Tile | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 31 | 31 | Fire Sprinkler Riser | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 32 | 32 | Fire Pump | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 33 | 33 | Fire Sprinkler Layout | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 34 | 34 | Fire Sprinkler Heads | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 35 | 35 | Fire Service Line | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 36 | 36 | Variable Air Volume Boxes with reheat coils | X | X | NLT 3 weeks after NTP | ||||||||||||||||||||||
| 37 | 37 | Air Handling Units | X | X | NLT 3 weeks after NTP | ||||||||||||||||||||||
| 38 | 38 | Duct fittings and accessories | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 39 | 39 | Pressure testing reports for hydronic and fire protection piping | X | X | Prior to scheduling pre-final | ||||||||||||||||||||||
| 40 | 40 | Duct Insulation | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 41 | 41 | HVAC GRDS | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 42 | 42 | Fire Dampers | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 43 | 43 | Louvers | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 44 | 44 | Hydronic pipe and fitings | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 45 | 45 | Pumps | X | X | NLT 3 weeks after NTP | ||||||||||||||||||||||
| 46 | 46 | DDC controls | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 47 | 47 | DDC controls shop drawings | X | X | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||
| 48 | 48 | Testing, Adjusting, Balancing report | X | X | X | X | X | Prior to scheduling pre-final | |||||||||||||||||||
| 49 | 49 | Exhaust fans | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 50 | 50 | HVAC system commissioning report | X | X | 30 DAYS prior to project completion | ||||||||||||||||||||||
| 51 | 51 | Boilers | X | X | NLT 3 weeks after NTP | ||||||||||||||||||||||
| 52 | 52 | Chiller | X | X | NLT 3 weeks after NTP | ||||||||||||||||||||||
| 53 | 53 | Expansion Tank, Buffer Tank, Air Seperator | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 54 | 54 | Glycol Feeder | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 55 | 55 | Final As-Builts Shop Telecommunications Drawings With outlet numbering schemes | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 56 | 56 | Product Data Telecommunications cabling Category 6 unshielded Twisted pair and Shielded Twisted pair | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 57 | 57 | Product Data Telecommunications Patch Panels, Outlet/connector assemblies, Outlet Covers, blank inserts | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 58 | 58 | Telecommunications Cabling testing | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 59 | 59 | Telecommunications Contractor Key Personnel | X | X | NLT 6 weeks after NTP | ||||||||||||||||||||||
| 60 | 60 | Telecommunications Contractor Qualifications ISP CAT 6 Installation | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 61 | 61 | Product Data Telecommunications cabling 12"x4" basket tray and accsessories , 12" ladder tray and accsessories | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 62 | 62 | Product Data Telecommunications cabling Telecomm Room Racks , Cabinets, Cable management, Power Distro Panels | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 63 | 63 | Product Data Telecommunications cabling Outside plant BEP, LIU, Cat3 Riser cable and 110 block terminations. | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 64 | 64 | Product Data Telecommunications cabling Cat 6 patch cords ,Voice , Data, SIPRNet | X | X | X | NLT 6 weeks after NTP | |||||||||||||||||||||
| 65 | 65 | Product Data Telecommunications cabling, EMT, 411/16' boxes, 6x6" consolidation /pull box 2"EMT. | x | x | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||
| 66 | 66 | Electrical Switchboards, Panelboards | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 67 | 67 | Circuit Breaker | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 68 | 68 | MDP Circuit Breaker Locking Device | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 69 | 69 | Ground Kits | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 70 | 70 | Safety Switches & Disconnects | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 71 | 71 | Electric Equipment Label Material | x | x | x | x | x | DPW/EE | NLT 3 weeks after NTP | ||||||||||||||||||
| 72 | 72 | Transformers | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 73 | 73 | 15kv Terminations | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 74 | 74 | Conduits | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 75 | 75 | Conduit Supports | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 76 | 76 | Conductors- Wires - Cables | x | x | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||
| 77 | 77 | Lighting Level Point to Point Calculations | x | x | x | DPW/EE | NLT 3 weeks after NTP | ||||||||||||||||||||
| 78 | 78 | Lighting Level Light Point to Point Layouts | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 79 | 79 | Light Fixtures | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 80 | 80 | Light Fixtures Emergency Battery | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 81 | 81 | Exit Signs | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 82 | 82 | Emergency Light Fixture | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 83 | 83 | Light Fixture Support System Attachment | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 84 | 84 | Light Control Relays | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 85 | 85 | Light Control Occupancy Sensors | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 86 | 86 | Light Control Vacancy Sensors | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 87 | 87 | Light Control Switches and Dimmers | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 88 | 88 | Receptacle Devices | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 89 | 89 | Light Switch Devices | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 90 | 90 | Device Cover Plates | x | x | x | x | x | x | x | x | x | DPW/EE | NLT 3 weeks after NTP | ||||||||||||||
| 91 | 91 | Fire Alarm Shop Drawing For Govt Approval | x | x | x | DPW/EE | NLT 3 weeks after NTP | ||||||||||||||||||||
| 92 | 92 | Fire Alarm System Calculations | x | x | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||
| 93 | 93 | FAMNS Control Panel | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 94 | 94 | FAMNS Transmitter | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 95 | 95 | FAMNS Local Operator Console (LOC) | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 96 | 96 | Initiation Devices | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 97 | 97 | Notification Devices | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 98 | 98 | Supervisory Devices | x | x | DPW/EE | NLT 3 weeks after NTP | |||||||||||||||||||||
| 99 | 99 | Fire Alarm Cable & Wire | x | x | x | DPW/EE | NLT 3 weeks after NTP | ||||||||||||||||||||
| 100 | 100 | MNS, Fire LED Text Signs | x | ||||||||||||||||||||||||
| 101 | 101 | Plumbing Fixtures | x | x | DPW/ME | NLT 6 weeks after NTP | Include valves, faucets, drains, hammer arresters etc. | ||||||||||||||||||||
| 102 | 102 | Backflow Preventer | x | x | DPW/ME | NLT 6 weeks after NTP | |||||||||||||||||||||
| 103 | 103 | Pipe and Duct Insulation and Duct Liner | x | x | DPW/ME | NLT 6 weeks after NTP | |||||||||||||||||||||
| 104 | 104 | Gas Water Heater | x | x | DPW/ME | NLT 6 weeks after NTP | |||||||||||||||||||||
| 105 | 105 | Expansion Tank | x | x | DPW/ME | NLT 6 weeks after NTP | |||||||||||||||||||||
| 106 | 106 | Recirculating Pump | x | x | DPW/ME | NLT 6 weeks after NTP | |||||||||||||||||||||
| 107 | 107 | Thermostatic Mixing Valve | x | x | DPW/ME | NLT 6 weeks after NTP | |||||||||||||||||||||
| 108 | 108 | Water Bottle Filler | x | x | DPW/ME | NLT 6 weeks after NTP | |||||||||||||||||||||