W911KB-17-R-0011-0015.pdf

PDF 61 KB Posted

Attached to
JBE041 Add/Alter Hangar JBER, Alaska
Solicitation number
W911KB-17-R-0011
Issued by

About this file

This solicitation and related federal contract opportunity documents seek proposals for a design-build project to upgrade aircraft sheltering and maintenance hangar space as well as repair and expand existing squadron operations spaces and construct missing AWACS alert crew quarters at Joint Base Elmendorf-Richardson in Alaska. Offerors should submit proposals in two phases, with Phase 1 proposals due by 20 October 2016 and Phase 2 proposals due from shortlisted firms by the date specified in the solicitation. The award will be made as a firm fixed-price contract valued at an anticipated $25 million to the best-valued proposal based on specialized experience, past performance, organization, technical approach, design technical merit, small business participation, and price factors. The period of performance is 575 calendar days with a notice to proceed anticipated in the second quarter of 2017. The contracting office is the U.S. Army Corps of Engineers District, Alaska.

W911KB-17-R-0011 JBE041 AM#15 Note: Fed Biz Opps will show as AM#16.

View the file

Other files

Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT TITLE/LOCATION: JBE041 ADD/ALTER AWACS Alert Hangar, JBER, Alaska

PROPOSAL DUE DATE: Phase 2 proposal due date has not been extended.

Proposals shall be submitted in accordance w ith Section 00 21 00, Para 1.9, Proposal Submittals.

This amendment provides changes to the solicitation as indicated on the continuation page of this document.

YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THIS STANDARD FOR 1442.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-Apr-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB-17-R-0011

X 9B. DATED (SEE ITEM 11)

20-Oct-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Apr-2017

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

PO BOX 6898

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SECTION 00 11 00 - STANDARD FORM (SF) 1442

The required response date/time has not been extended.

SUMMARY OF CHANGES

a. The following drawings are substituted for the superseded drawings.

NONE

b. The following revised documents are substituted for the superseded documents. The identifier “AM#15” appears before and after new and/or revised material, except as noted below.

• SECTION 00 11 01, Proposal Schedule

NOTE: Revisions within the following documents do not contain the above referenced identifiers.

c. The following clause has been added:

N/A

d. The following clauses have been updated:

N/A

e. The following section is deleted.

f. The following documents are added.

g. The following revisions are incorporated.

h. Other:

W911KB-17-R-0011

PS-1

PROPOSAL SCHEDULE

ADD/ALTER AWACS ALERT HANGAR

JBER-ELMENDORF, ALASKA

AM#012… BASE ITEMS

Item No.

Description Estimated Quantity

Unit Unit Price Amount

0001 Design AWACS Alert hangar, Complete 1 Job $_________ $_________

0002 Renovation of bldg 14410, Complete 1 Job $_________ $_________

0003 Construct additional AWACS Alert Crew and Squadron Operation areas within the 5-foot line, Complete

1 Job $_________ $_________

0004 Construct Sitework beyond the building 5-foot line, Complete 1 Job $_________ $_________

0005 Design Foundation Overturning Upgrades, Area 5, Complete 1 Job $_________ $_________

0006 Construct Foundation Overturning Upgrades, Area 5, Complete 1 Job $_________ $_________

Total of Base Items 0001 thru 0004 $_________

AM#015… OPTION ITEMS

Item No.

Description Estimated Quantity

Unit Unit Price Amount

Remove, Sample stockpile 10 Cubic Yards of POL Contaminated Soil including Construction of Holding Cells, Complete*

10 CY $_________ $_________

0008 Sample suspect materials for asbestos 1 EA $_________ $_________

0009 Remove asbestos containing building materials, complete 10 LF $_________ $_________

0010 Remove asbestos containing building materials, complete 10 SF $_________ $_________

0011 Dispose of asbestos containing building materials 1 CY $_________ $_________

PS-2

Construct fall prevention system, complete** 1 Job $_________ $_________

Construct Hangar catwalk system and associated structural upgrades, complete

1 Job $_________ $_________

Total of Option Item 0005 thru 00130986 $_________

Total of Base and Optional Items 0001 thru 000986 $_________

Proposed Contract Duration: ____________________

* Work on CLIN 0005 shall be the cost for work identified in Specs 02 61 13 “Excavation and Handling of Contaminated Material” and Section 01 57 20.01 29 “Environmental Protection” that is additional to the requirements of the normal project excavation and the field screening identified in Section 31 09 20.00 29 “Field Screen Testing of Soils for POL Contamination”. For CLIN 0005, the Contractor shall keep a record of the amount of contaminated soil being excavated and disposed of. If the amount of contaminated soil being excavated & disposed of is above 115% or below 85% of the estimated quantity, the equitable adjustment will be in accordance with FAR CLAUSE 52.211-18, VARIATION IN ESTIMATED QUANTITY.

** CLIN 0012 can be exercised at any time during the construction period. …AM#012

*** For CLIN 0009 – CLIN 0011, the Contractor shall keep a record of the amount of the asbestos containing building materials removed and disposed of. If the amount of asbestos containing building materials being removed & disposed of is above 115% or below 85% of the estimated quantity, the equitable adjustment will be in accordance with FAR CLAUSE 52.211-18, VARIATION IN ESTIMATED QUANTITY.

EVALUATION OF OFFERS.

1. AWARD: Award will be made in accordance with Section 00 22 101 - EVALUATION

FACTORS FOR AWARD. …AM#015

2. INCOMPLETE OFFERS: Failure to submit an offer on all items in the schedule constitutes an incomplete offer. Incomplete offers may be rejected. Lump sum or unit prices must be shown for each item within the schedule.

3. EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

4. SPECIAL CONDITION: If a modification to an offer based on unit prices is submitted which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the proposal schedule must be stated. If it is not stated, the offeror agrees that the lump sum adjustment shall be applied on a pro rata basis to every unit price in the proposal schedule.

-- END OF PROPOSAL SCHEDULE --

File details come from the government source that posted it. Updated .