This document contains questions and answers for solicitation W519TC25RA003 related to the renovation of an Indoor Firing Range. The Q&A covers technical requirements across civil, electrical, and mechanical aspects of the project.

Key details include: total survey area of 8932m2, HVAC system specifications for Zamil Air Conditioners Model PTX140 with 380/400V power supply, requirement for 5 water heaters, and fire suppression system compliance with SBC 801 and 802. The bullet trap system must comply with UFC 4-179-02 standards, with baffles requiring sufficient overlap to prevent projectile bypass. The contract will be Firm Fixed Price, with potential modifications for differing site conditions. Award will be based on best value considering technical factors (significantly more important), past performance, and price. Contractors must submit one proposal containing 35% complete structural remediation plans, 35% HVAC plans, 35% fire sprinkler plans, and 100% complete premobilization plan. CLINs 0005 and 0008 are surrogate CLINs that will be negotiated after award if additional remediation is required.

View the file

Other files

File Type Posted
Solicitation Amendment 0001-0005 W519TC25RA0030004 CONFORMED.pdf PDF
Attachment 0020 Question and Answers IFR Amendment 0004_26 February 2025.pdf PDF
W519TC25RA0030004_Conformed Copy.pdf PDF
Solicitation Amendment - W519TC25RA0030003_CONFORMED COPY.pdf PDF
Attachment 0011 Section M dated 10 February 2025.pdf PDF
Attachment 0017 Change Orders IFR_Redacted.pdf PDF
Solicitation Amendment - W519TC25RA0030003_CONFORMED COPY.pdf PDF
Attachment 0010 Section L dated 10 February 2025.pdf PDF
Attachment 0018 Supplementary Reference IFR Specifications Book.pdf PDF
Attachment 0001 IFR Scope of Work 06 February 2025.pdf PDF
Attachment 0019 Historical Quantities Proposal QTN 18.12.21-Rev01-Discounted dtd 27.01.2022 AAS (1)_Redacted.pdf PDF
Solicitation Amendment W519TC25RA0030002 SF 30.pdf PDF
ATTACHMENT 0012 BREAKDOWN OF CLINS.xlsx XLSX spreadsheet
Attachment 0010 Section L dated 06 December 2024.pdf PDF
Attachment 0013 Bill of Quantity IFR 2020.xls XLS spreadsheet
Attachment 0015- Final Structural Report - IFR.pdf PDF
Solicitation Amendment W519TC25RA0030001 SF 30.pdf PDF
Attachment 0014 Questions and Answers received from Industry Day and Site visit 03-04 December 2024.pdf PDF
Attachment 0002 - Pricing Matrix.xlsx XLSX spreadsheet
Attachment 0001 - Indoor Firing Range SOW.pdf PDF
Attachment 0007 - IFR Inspection Plan.pdf PDF
Solicitation - W519TC25RA003.pdf PDF
Attachment 0010 - Section L.pdf PDF
Attachment 0011 - Section M.pdf PDF
Attachment 0003 Bid Bond SF24-23a.pdf PDF
Attachment 0006 - Drawings and Specifications.zip ZIP file
Attachment 0004 Surety Bond SF28-23a.pdf PDF
Attachment 0008 QASP IFR 11-13-2024.pdf PDF
Attachment 0009 - Past Performance Questionaire.pdf PDF
Attachment 0005 - Requirements for Access to MNG Base OPM-SANG.pptx PPTX presentation
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. Reference (i.e.

document - ) Reference Text (i.e. paragraph #) Vendor Question/Comment Government Response:

1 Indoor Firing Range SOW Draft

2.1.1. Safety Plan

Contractor is responsible for all pest control during construction

Please clarify whether the pest control to be done for the balance works which is going to start or all the completed works too

Pest control is required during the comencement of work. This includes limiting pests on site during construction and testing.

2 Indoor Firing Range SOW Draft

Page 6,7

2.2.1 Site Grading and Storm Drainage

Perform a topographic survey to verify the condition of existing grade elevation and ground level

Please provide the total area to be surveyed Total Area surveyed is 8932m2.

3 Indoor Firing Range SOW Draft

Page 6,7

2.2.1 Site Grading and Storm Drainage

Grading leading from buildings foundation outward to perimeter fence into sewer lines

Please provide the distance from building foundation to perimeter fence into sewer lines

Sewer Line location will need to be established by the contractor during testing.

4 Indoor Firing Range SOW Draft

Page 6,7

2.2.1 Site Grading and Storm Drainage

Storm gutters on roof need to be extended

Please provide the length of gutters on roof to be extended

The gutters will need to have downspouts installed and extended by .5 meters at the bottom of the downspout away from the foundation

5 Indoor Firing Range SOW Draft

Page 6,7

2.2.1 Site Grading and Storm Drainage

Proper drainage from roof to lower level away from the building

Please provide the height of roof to lower level from the building

Assumption the height is 3.5 meters.

6 Indoor Firing Range SOW Draft

Page 6,7

2.2.1 Site Grading and Storm Drainage

Grading needs to prevent previous water pooling areas from reappearing

Please provide the number of locations neeeded for grading at water pooling areas

The entire site will require recompaction and re-grading.

7 Indoor Firing Range SOW Draft

Page 6,7

2.2.1 Site Grading and Storm Drainage

Provide bituminous damp proofing to concrete surface in direct contact with soil

Please provide the area of damp proofing required

All new installed concrete will require dampproofing at contact with soil.

8 Indoor Firing Range SOW Draft

2.2.2 Pavement

Concrete curbing was installed; vehicular asphalt pavement still needs to be constructed between the curb and the facility along with proper vehicle markings for parking

Please provide the length of curb, area of asphalt and area of vehicle markings for parking

The entire non building site will require asphalt and a concrete curb around. Vehicle parking will only be required in front of the structure and to the south side of the structure.

9 Indoor Firing Range SOW Draft

2.2.3 Water and Sewer

Clean out manholes and inspect all lines for obstruction of debris and vegetation

Please provide the number of manholes to be cleaned

This will be determined by the contractor and testing that is conducted by contractor.

Civil Questions

10 Indoor Firing Range SOW Draft

2.3.1 Exterior Recommendations

Required Actions Filling of erosion areas with the proper foundation repair such as soil fill or polyurethane foam to close openings

Please provide the size and number of openings This will be determined by the contractor and testing that is conducted by contractor.

11 Indoor Firing Range SOW Draft

2.3.1 Exterior Recommendations

Required Actions Excavate ponded areas to foundation and backfill in compacted lifts.

Please provide the size and number of footings/foundation

Please refrence autocad structural drawings for this data found in solicitation.

12 Indoor Firing Range SOW Draft Page 10,11

2.4.1 Plumbing Fixtures

Connection the city water line must be tested by a 3rd party engineer

Please provide the distance from the building to city water main line

The assumed main water line is located at the south side of the strucutre and is approximately 4 meters from the building. Limited water connection has been established on the south side bathrooms.

13 Indoor Firing Range SOW Draft Page 10,11

2.4.1 Plumbing Fixtures

All drains should be vacuumed

Please provide the length of drain pipes, diamater and number of pipes

This will be determined by the contractor and testing that is conducted by contractor.

14 Indoor Firing Range SOW Draft

2.4.2 Water Heaters

Operation could not be verified for wall mount water heater. All water heaters must be replaced

Please provide the number of water heaters and specification

There are 5 water heaters.

15 Indoor Firing Range SOW Draft

Please provide the drawings for existing buildings and external works

There are no assbuilt drawings. Change orders and original drawings posted with solicitation.

16 IFR+Combined+Report _Redacted

Evaluation Report, (Page 63/67 in the complete doc.)

a. Architecture Exterior Inspect doors and hardware, replace as needed

Please clarify the material of the doors, sizes and specifications

Specifications of doors found in the autocad drawings, posted with solicitation.

17 IFR+Combined+Report _Redacted

Evaluation Report, (Page 63/67 in the complete doc.)

a. Architecture Exterior Paint ot match where required

Please provide the RAL of the paint and specifications

Paint specifications found with in attachment documents posted in amendment 0003.

18 IFR+Combined+Report _Redacted

Evaluation Report, (Page 63/67 in the complete doc.)

a. Architecture Interior Repair and replace stainless steel and procelain fixtures

Please provide the brand and specifications for fixtures

Specifications for fixtures found with in attachment documents posted in amendment 0003. Contractor is required to use saudi made furniture.

19 IFR+Combined+Report _Redacted

Appendix1 - Observations and Recommendations (Page 20/67 in the complete doc.)

Figure 21 Evidence of ponding and settling Excavation of ponding areas

Please clarify whether the area surrounding the assest to be excavated.

Kindly mention the depth of the excavation.

Testing has shown that at 2 meters compaction is less then required 95%. Entire sit needs to be recompacted and regraded to ensure it meets Saudi Building Code (SBC) 301.

20 Site visit It is informed that the strength of front concrete wall is 25/26MPa and back wall is 33Mpa. Do we need to replace the concrete blocks with new blocks and do plastering or construct RCC concrete wall. Please clarify.

Contractor is required to ensure the strucuture meets the SBC 304 requirements. This means that a redesign to assess loads needs to be conducted or a remediation plan on how to increase column strength.

21 Site visit To increase the bullet trap system 1m height, only colums height is enough to raise/replace or any concrete footing pad is required to raise the height. Please clarify.

Column height should not be impacted by the bullet trap system. By increasing the range ceiling by 1 meter, bullet trap system will need to adapt to meet this requirement.

No. Reference (i.e.

document - ) Reference Text (i.e. paragraph #) Vendor Question/Comment Government Response:

1 Page 10, Required Actions

On North side storage room, installation of a secured cage for ammunition storage and mini split Air Conditioner (AC) and other requirements to make the isolated room sustainable for inhabitance.

Please provide the small power and lighting requirements for the north side storage room, along with site layouts based on these requirement. Additionally, please share the existing single line diagram (SLD) and distribution board (DB) schedules to assess the load distribution?

Contractor will determin the best course of action and design the requirements of this storage room. Room will only require 1 cage located in the center and a minisplit to ensure climate control. Electrical drawings can be found in the autocad drawings provided.

Electrical Questions

2 Page 11, 2.4.1 Plumbing Fixtures

Plan of inspection of the plumbing system must be submitted and approved by COR prior to start of work. Plan must includes Closed-circuit television (CCTV) pipe inspection, seepage test and verification materials installed meet IBC Chapter 29 requirements.

Please confirm whether a seepage test is required for the closed-circuit television (CCTV) pipe or conduit?

A seepage test is required for all existing plumbing pipes and underground plumbing planned on being salavaged. A seepage test is also required to be done after installation of new plumbing system.

3 Page 11, 2.5.1 2.5.1 Packaged Units

Contractor must verify that the 3 existing units are equivalent in both airflow and cooling capacity to the original 4 units on the design drawings.

Please provide the single line diagram (SLD) drawings for the existing main distribution panel (MDP) to assess the current load distribution

Contractor will determine this based on the electrical diagram provided in the autocad drawings and the HVAC required energy.

4 Page 12, 2.5.1 Packaged Units

Digital control systems utilizing programmable logic controllers (PLCs) shall be used for the interlocks and controls. Existing facilities may rely on analog systems if they can be retrofitted in an economic manner to accommodate the necessary interlocks and alarms.

Please provide the existing Direct Digital Control (DDC) layout drawings, including the types and brands of controllers currently employed on site along with the input/output (I/O) list of control points that are required.

Contractor will determine based on information provided in the autocad drawings and the HVAC required energy.

5 Page 13, 2.5.3 Exhaust Fans

Required installation of Centrifugal Down blast Exhaust Fans designed for roof mount applications exhausting relatively clean air.

Please provide the site layout drawings to determine the location and distance of the proposed fan from the main distribution panel (MDP)? Additionally, the single line diagram (SLD) drawings are requiored for the existing MDP to assess the current load distribution.

Contractor will determine the best course of action and location of fans based on the HVAC plan and airflow design created by contractor.

Page 14, 2.6.3 Transformer and Distribution Cabinets

Inspect and test the 1000 Kilovolt-amps (KVA) transformers (2) and distribution cabinets, ensuring compliance with the IBC Chapter 27.

Exercise caution during the inspection of the energized transformer and perform necessary repairs if required. Verify the adequacy of power supply for the indoor firing range air handlers.

Verify the adequacy of power supply for the indoor firing range building, appliances, and fixtures per the drawings

Please provide the site drawings referenced in the paragraph.

Please refrence autocad drawings for all existing drawings available. No as-built drawing are available.

7 Page 15, 2.6.5 HVAC System Installaion

Install power cables of appropriate size for the HVAC system, adhering to electrical schematics for the electrical room. Ensure proper securing of all power cables.

Please provide the equipment schedules for the HVAC systems to determine the power supply requirements and to determine with the cable and breaker selections.

HVAC system is a Zamil Air Conditioners; Model:

PTX140, Power Supply: 380/400 V.

Page 15, 2.6.7 Disconnect Switches and Panelboard Connection

Install disconnect switches for all mechanical equipment and make final connections to corresponding panelboards as per contract drawings. New panelboards will need to be installed in initial wall cutout areas of placement.

Please confirm the load requirements and provide the details of the new mechanical equipment for the panel boards that are to be installed?

Load requirements will be determined by the contractor based on the requirments for the HVAC system plan the contractor designs. Panel boards must adhere to the specifications listed in the amendment 0003.

Page 16. 2.6.8 Grounding System Inspection and Maintenance

Inspect grounding rods and ensure grounding for all equipment. Inspect grounding loop around the facility and resolve any deficiencies. Verify proper grounding and bonding for all equipment and inspect grounding bars for electrical and communication systems within the facility

Please provide the layouts for the existing earthing and lightning protection systems?

Please advise on the specific ohm readings that should be achieved for both the earthing system and the lightning protection system separately?

No as built drawings exist. Ohm readings must meet the requirements of Saudi Building Code (SBC) 600 and IEC guidelines. Based on this information readings shall not exceed 5 ohms.

10 Page 16, 2.6.9 Cable Inspection and Repair

Inspect and test all cables, conduits, connections, and terminations from the transformer to the Main distribution panel in the facility. Perform repairs as required to ensure functionality

Please provide the single line diagram (SLD) to determine the size, lengths, number of runs, and duct bank requirements?

Contractor will determine this based on the electrical diagram provided in the autocad drawings and onsite testing.

Page 16, 2.6.10 Exterior Cleanup and Manholes

Clean up all exterior manholes, handholes, and trenches from debris or trash. Provide lids labeled "Electric" for all missing manholes/handholes.

To check and inspect the existing manhole size and dimentions

Contractor shall refrence the autocad drawings for the dimensions related to exterior manhole.

12 Page 16, 2.6.11 Lighting System

Lighting fixtures are not installed in some areas, install lighting as shown on the contractor drawings. This includes, but not limited to wiring conduits, protective devices, cable trays, light switches, etc. Terminate all lighting circuits at the corresponding panelboards. After installation, perform testing to ensure all light fixtures are operational. Install exit lights and emergency lights as per contract drawings

Please provide the lighting layouts to determine the quantity and specifications required?

Lighting diagrams can be found on the electrical autocad drawings.

13 Page 17, 2.9.1 Fire Alarm Replacement

Fire alarm systems have been installed, few are misplaced on the exterior of building and need to be removed and reinstalled on interior.

Please provide details with the existing fire alarm system being employed at the site along with the layout and schematic

Fire Alarm system can be found on the specifications section. New fire suppression system must be presented by the contractor and adhere to SBC 801 and SBC 802.

No. Reference (i.e.

document - ) Reference Text (i.e. paragraph #) Vendor Question/Comment Government Response:

1 Indoor Firing Range

SOW DRAFT

Paragraph 2.4.1.Inspect, disinfect as necessary, and test water system to verify required flow and pressure are being supplied to the building

Kindly proovide us the Extising drainage and Water supply layout drawing

No As built drawings exist, contractor is responsible for verifying the existing conditions.

2 Indoor Firing Range

SOW DRAFT

Paragraph 2.4.2. Operation could not be verified for wall mount water heater. All water heaters must be replaced.

Kindlty mention us the water heater capacity, brand and quantity

Specifications of the waterheater can be found in the amendment 0003.

3 Indoor Firing Range

SOW DRAFT

Paragraph 2.5.1. The original design drawings indicate 4 packaged units on the roof of the building. Each unit should be 100% fresh air with a design flow rate of 24,220 Cubic Feet Per Minute (CFM) each. Site conditions do not match the design drawings, there are only 3 packed units on the roof

Kindlky provide us he complete HVAC Layout drawing , Schedule and Design details for building

All available drawings can be found on Autocad.

There is a change order (posted with amendment 0003) regarding the redesign of the HVAC system.

Mechanical Questions

4 Indoor Firing Range

SOW DRAFT

Paragraph 2.5.1. Supply ductwork and interior radial diffusers to be installed as per the drawings.

Interior filters need to be replaced from debris buildup.

Kindly provide us the design drawing for Diffuser to be installed

Specifications can be found in the amendment 0003.

All available drawings can be found in the autocad drawings and change orders.

5 Indoor Firing Range

SOW DRAFT

Paragraph 2.5.1. To utilize the existing Packaged AC units, the manufacturer must inspect and test the units and provide a written certification confirming that the systems are in good working condition.

Kindly provide us the extising units name plates Zamil Air Conditioners; Model: PTX140, Power Supply: 380/400 V.

6 Indoor Firing Range

SOW DRAFT

Paragraph 2.5.3.Smaller exhaust fans (not shooting range) do not appear to be installed at any of the locations on the roof or wall

Kindly Provide us the Exhaust Fan Schedule and layout for the building

Original drawings and change order have design for exhaust fans. Contractor must ensure that all work meets the UFC requirements outlines in the SOW.

7 Indoor Firing Range

SOW DRAFT

Paragraph 2.9.2.Fire Suppression system is not installed in the building. A fire suppression sprinkler system will need to be installed in the building that covers all rooms

Kindly provide us the building layout drawing , where to be installaled and exiting fire line connection for the project

All drawings can be found in the autocad drawings.

8 Indoor Firing Range

SOW DRAFT

Paragraph 2.4.1.Inspect, disinfect as necessary, and test water system to verify required flow and pressure are being supplied to the building

Kindly proovide us the Extising drainage and Water supply layout drawing

No As built drawings exist, contractor is responsible for verifying the existing conditions.

9 Indoor Firing Range

SOW DRAFT

Paragraph 2.4.2. Operation could not be verified for wall mount water heater. All water heaters must be replaced.

Kindlty mention us the water heater capacity, brand and quantity

Specifications of the waterheater can be found in the amendment 0003 and attachments.

10 Indoor Firing Range

SOW DRAFT

Paragraph 2.5.3.Smaller exhaust fans (not shooting range) do not appear to be installed at any of the locations on the roof or wall

Kindly Provide us the Exhaust Fan Schedule and layout for the building

Original drawings and change order will have design for exhaust fans. Contractor must ensure that all work meets the UFC requirements outlines in the SOW.

11 Indoor Firing Range

SOW DRAFT

Paragraph 2.9.2.Fire Suppression system is not installed in the building. A fire suppression sprinkler system will need to be installed in the

Kindly provide us the building layout drawing , where to be installaled and exiting fire line connection for the project

All drawings can be found in the autocad attachments.

12 SOW

General Kindly inform us in which location FM 200 should be installed. Please provide us the concept drawing.

Supression system can be installed in any covered and climatized location, proposed by the contractor.

COR approval is required for the location of installation.

Misc. Questions

No. Reference (i.e.

document - ) Reference Text (i.e. paragraph #) Vendor Question/Comment Government Response:

1 With out completing CLINs 0004 and 0007 (testing) the values of these CLINs can not be accurately/fairly proposed and therefore evaluated.

Report has been posted with this solicitaion.

CLINs 0005 and 0008 are surrogate CLINs. For these CLINs the price will not be evaluated. If testing determines additional remediation above proposed is required then the prices will be negotiated after award in accordance with FAR 15.

No pricing input is necessary. Structural repair work pricing shall be limited to the cost of testing, CLIN 0004. Assumption for proposal should be that cost for repairs will be $500.00 USD.

This contract is Firm Fixed Price. A modification/ change order would occur if differing site conditions vary from orginal accepted proposal.

No. Proposal shall contain only one best value solution. Technical Proposal shall contain submittal of 35% complete structural remediation plans, 35% complete HVAC plans, 35% Fire Sprinkler Plans and 100% complete Premobilization Plan.

No. Proposal shall contain only one best value solution. Technical Proposal shall contain submittal of 35% complete structural remediation plans, 35% complete HVAC plans, 35% Fire Sprinkler Plans and 100% complete Premobilization Plan.

8 No as built drawings exist.

Referring to Attachment-2 Price Matrix, please give us the details of CLIN 0005 and 0008? Why OPM-SANG added the $500 in the sheet?

Referring to Attachment-2 Price Matrix CLIN 0005 and 0008; as it was mentioned during site visit and meeting that the government will share the existing structure report – please share the report.

Referring to Attachment-2 Price Matrix CLIN 0005 and 0008; the price of these 2 CLINs, how the government will evaluate our price? Will the government provide unit rate or will the government negotiate?

Referring to Attachment-2 Price Matrix, where we will add the price for structure repair work?

Referring to site visit and meeting at Crown Plaza, the contracting officer mentioned that they can issue the MOD/Change Order in future, so this contract will be FFP or Cost-Plus, what type of the contract it will be?

Can we submit multiple options with different prices?

As the client required 10-Year warranty of this structure, which is only possible if we demolish this building and construct new one, but this way our price will go up, so we want to propose 2 options to the government, can we do that?

Please share the approved drawing package which was submitted by the previous contractor.

9 All available and relevant documents/drawings have been posted with solicitation.

10 All available drawings have been shared. Please see autocad drawings and change order drawings.

11 Please provide more information on what you mean by "VCC".

Ensure that all doors have locks associated. No special entry system is required.

13 Yes, Building must meet SBC Fire Code 801, and 802.

14 Yes. Furniture must meet specifications and be manufactured in KSA.

15 No, CCTV is not required.

Material on currently located on the walls and ceiling of the firing line meets the requirements outlined in the SOW.

The price is a factor. This award will be made based on the best overall (i.e., best value) proposal that is determined to be the most beneficial to the Government, with appropriate consideration given to the three evaluation factors: Technical, Past Performance, and Price. The Technical factor is significantly more important than the Past Performance and Price factors, which are of equal importance.

No. This award will be made based on the best overall (i.e., best value) proposal that is determined to be the most beneficial to the Government, with appropriate consideration given to the three evaluation factors.

19 SOW has been amended, please reference most recent version dated 05 February 2025.

Please share all the previous data/information, to evaluate discrepancies on the site.

Shooting Range: please share the wall cross section details, we need to check if steel plates are installed or not.

Do you need VCC during entrance?

Do you need access control system ?

Do you need Fire Alarm System?

Do you want us to propose furniture for the buildings?

Do you need CCTV Security Camera System?

Shooting Range; the installed material on walls & ceiling – please confirm if this is as per military standards, because if the government/OPM-SANG approved this material, we will not add the price for replacement and If OPM-SANG wants to replace it than we will add this item in our price, please advise.

Referring to the meeting (industry day), the COR mentioned that everything is depends on contractor’s methodology and approach and price is not a big factor here – so referring to this statement, if multiple contractors proposing same material/methodology, so how the government will evaluate the proposals?

Referring to question# 15, it means government will go with lowest price contractor?

OPM-SANG has experienced engineering team, so if OPM-SANG can give us the scope which states the clear SOW that either they want us to demolish the existing structure or repair the existing one – it will be much better.

20 SOW has been amended, please reference most recent version dated 05 February 2025.

21 Autocad have been provided.

22 Site drawings can be found on the Autocad section.

SOW Reference 2.3.2 (Page 10) - Shooting Range

Is the client’s intent to provide a UFC 4-179-02 compliant range project for all elements of the range or only for those specifically identified in the Scope of Work statement. UFC 4-179-02 must be adherent to only the sectioned outline and pertaining to the actual firing line.

Please confirm the location of the wall is at Gridline 2 along the rear of the range. Contractor will need to verify.

Please confirm the specification of ballistic resistance as the current wall is protected by a non UFC 4-179-02 compliant bullet trap. Contractor is required to verify balistic resistance and if inadequate provide plan to remediate bullet trap.

SOW Bullet trap cleanout system must be installed. Please confirm if the existing removable tray at the base of the trap is acceptable. If not, please advise the required specification.

Contractor must present a plan on new system they plan to install. With COR and KO approval previous trap can be removed and the redesigned installed.

The current ceiling is non compliant with UFC 4-179 – 02 Figure 4.3 as there is not a 6 inch overlap between baffles. Please confirm that this non compliant ceiling is acceptable for the project when raised.

UFC 4-179-02 specifies that baffles must overlap by a minimum distance sufficient to prevent projectile bypass. While the exact minimum overlap may vary depending on the projectile characteristics, impact angles, and system configuration, the standard typically requires that the overlap be large enough to eliminate any potential gap that might compromise containment.

Please confirm “range area” as meaning between firing line and bullet trap or otherwise. Range area is the entire room where the firing line is located.

SOW

SOW

Our concern is, we need SOW where clearly mentioned the task, whether need replacement or repair or maintenance or inspection & cleaning only. This way, we can estimate and submit a fixed to price to the government.

Need complete approved design drawing package in good pdf or AutoCAD format, the given drawings are blurry.

Need a complete site drawing, by which we can calculate the area of Required Asphalt.

CMU wall at the end of the firing range on the west side of the building needs to be properly tied into the building walls and fitted with sound proofing and ballistic resistance in accordance with (Unified Facility Criteria) UFC 4-179-02.

Load calculations and foundation plans need to be created to ensure that the additional weight will

Raise bullet range ceiling by 1 meter. Extend roofing to cover all of range area.

The current bullet trap design is non compliant with UFC 4-179 – 02 Section 4-17 as the trap is neither a steel “snail” trap or granulated rubber.

Please confirm that this non compliant bullet trap is acceptable for the project.

Only bullet traps compliant with UFC 4-179-02 are acceptable for this project. If current bullet trap is proven to not be acceptable, contractor must submit a design and change order to replace the system.

Please confirm specification, number of layers and thickness of self healing rubber requested as UFC 4-179-02 does not specify requirements.

The specefication of the self healing rubber is dependent on the bullet trap system and shall be provided by the manufacturer as well as verification it meets UFC 4-179-02 standards.

Please advise the testing requirement for the bullet resistance of bullet proof backing. Is this a live fire test or Brinnell hardness measurement.

To determine the bullet resistance of bulletproof backing in a manner consistent with UFC 4-179-02, a live-fire test is required. However, due to the potentially dangerous nature of this, a manufactures guarantee is acceptable.

Please confirm which bullet proof backing is to be tested i.e. location/elements.

The Venitial bullet proof backing located at the end of the firing range must be tested.

If the bullet resistance of the bullet proof backing is not adequate, will be contractor be required to submit a cost proposal for a new compliant bullet trap.

Yes, contractor will present a change order and plan for a new compliant bullet trap.

SOW Airflow test, Leakage test and Noise test are required to be conducted. System must meet the required CFM as outlined above. Must adhere to American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) 111, ASTM E1554, and ASHRAE 70. Tests must be done on completion of HVAC system and approval is required from COR.

Please confirm if testing can done prior to commencement of works to determine suitability of the units to meet the requirements of UFC 4-179-02.

Contractor can conduct testing of systems once the NTP has been issued.

Do the requirements of UFC 4-179-02 Section 4-6 apply for the shooting range area?

Section 4‑6 of UFC 4‑179‑02 is focused on the rigorous live-fire testing required to qualify bullet trap systems. However, due to the potentially dangerous nature of this, a manufactures guarantee is acceptable.

Install self-healing rubber curtains suspended from the ceiling. Submittal must be approved by COR prior to installation.

SOW

Testing of the bullet resistance of the bullet proof backing. If inadequate, then create new bullet trap plan.

SOW

Fire Suppression system is not installed in the building. A fire suppression sprinkler system will need to be installed in the building and will cover all rooms. This includes a fire pump, risers, and a water study to ensure adequate water pressure. A detailed plan for the water suppression system

SOW

Please identify the area where will be the pump room and underground water tank?

Supression system/ pump room can be installed in any covered and climatized location proposed by the contractor. COR approval is required for the location of installation.

p pp y needs to be created and approved by COR prior to installation.