This is a pricing template spreadsheet that breaks down Construction Line Item Numbers (CLINs) for the renovation of an Indoor Firing Range (IFR) facility. The document outlines 12 major CLIN categories: Mobilization Plan, Site Prep, Civil, Structural, Plumbing, HVAC, Electrical, Communications, Fire Protection, and Demobilization. The total site area is 8,931.69 m² with a building footprint of 3,148.09 m².

Key work elements include foundational erosion remediation, waterproofing, HVAC system redesign with installation of 3 rooftop units, electrical system upgrades including new 885 amp/600V cable installation, plumbing repairs with municipal water connections, and comprehensive fire protection system improvements including new sprinklers and pump installation. The document includes specific subgroup descriptions under each CLIN and notes that labor hours are based on USACE JCMS data and local salary information, with an emphasis on manual labor over machinery usage except for material movement.

View the file

Other files

File Type Posted
Solicitation Amendment 0001-0005 W519TC25RA0030004 CONFORMED.pdf PDF
Attachment 0020 Question and Answers IFR Amendment 0004_26 February 2025.pdf PDF
W519TC25RA0030004_Conformed Copy.pdf PDF
Solicitation Amendment - W519TC25RA0030003_CONFORMED COPY.pdf PDF
Attachment 0011 Section M dated 10 February 2025.pdf PDF
Attachment 0017 Change Orders IFR_Redacted.pdf PDF
Solicitation Amendment - W519TC25RA0030003_CONFORMED COPY.pdf PDF
Attachment 0010 Section L dated 10 February 2025.pdf PDF
Attachment 0016 Questions and Answers received via email prior to 11 December 2024.pdf PDF
Attachment 0018 Supplementary Reference IFR Specifications Book.pdf PDF
Attachment 0001 IFR Scope of Work 06 February 2025.pdf PDF
Attachment 0019 Historical Quantities Proposal QTN 18.12.21-Rev01-Discounted dtd 27.01.2022 AAS (1)_Redacted.pdf PDF
Solicitation Amendment W519TC25RA0030002 SF 30.pdf PDF
Attachment 0010 Section L dated 06 December 2024.pdf PDF
Attachment 0013 Bill of Quantity IFR 2020.xls XLS spreadsheet
Attachment 0015- Final Structural Report - IFR.pdf PDF
Solicitation Amendment W519TC25RA0030001 SF 30.pdf PDF
Attachment 0014 Questions and Answers received from Industry Day and Site visit 03-04 December 2024.pdf PDF
Attachment 0002 - Pricing Matrix.xlsx XLSX spreadsheet
Attachment 0001 - Indoor Firing Range SOW.pdf PDF
Attachment 0007 - IFR Inspection Plan.pdf PDF
Solicitation - W519TC25RA003.pdf PDF
Attachment 0010 - Section L.pdf PDF
Attachment 0011 - Section M.pdf PDF
Attachment 0003 Bid Bond SF24-23a.pdf PDF
Attachment 0006 - Drawings and Specifications.zip ZIP file
Attachment 0004 Surety Bond SF28-23a.pdf PDF
Attachment 0008 QASP IFR 11-13-2024.pdf PDF
Attachment 0009 - Past Performance Questionaire.pdf PDF
Attachment 0005 - Requirements for Access to MNG Base OPM-SANG.pptx PPTX presentation
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Total Costs IFR Independent Government Estimate

CLIN
Mobalization Plan
Site Prep
Civil
Structural
Plumbing
HVAC
Electrical
Communications
Environmental
Fire Protection
MISC
De-Mobilization

Mobilization Plan

1) IFR Mobilization Plan
CLIN SubgroupDescription
1.ASafety Procedures Plan
1.BTemporary Potable Water Plan
1.CTemporary Construction Facilities
1.DSite Layout Plan
1.EClear and Grub Plan
1.FSWPPP
1.GQuality Control Plan

Site Prep

2) IFR Site Prep
CLIN SubgroupDescription
2.AClear and Grub
2.BConnection to Municipal WaterSite Area
2.CConnection to Municipal Electricity5,783.60m
2.DConnection to Municipal SewageTotal Site8,931.691.429156478Acres
2.ESWPPP InstallationBLD Footprint3,148.09
Totals
Clear and Grub
Connection to Municipal Water
Connection to Municipal Electricity
Connection to Municipal Sewage
SWPPP Installation

Civil

3) IFR Civil
CLIN SubgroupDescription
3.ACompaction Testing
3.BSite Grading
3.CDrainage
3.DAsphalt Pavement
3.EWater and Sewer Excavation
3.FSoil Remediation
Compaction Testing
Site Grading
Drainage
Asphalt Pavement
Water and Sewer Excavation

Structural

4) IFR Structural
CLIN SubgroupDescription
4.ATesting Foundational Erosion
4.BRemediating Foundational Erosion
4.CBackfill Eroded area
4.DWaterproof Building by Sealing Roofs, Walls, and other Penetrations
4.EInstall Proper Door Hardware
4.FInvestigate Interior Cracks
4.GEpoxy Fill Interior Cracks
4.HRestucco and Paint effected areas
4.IRebond Interior Tiles
4.JCMU Bracing- Load Test and Remediation
4.KTest Bullet and Repair Proof Pannels
4.LReroute Gutters off Flat Roof
4.MFoundational Structure Remediation
Testing Foundational Erosion
Remediating Foundational Erosion
Backfill Eroded area
Waterproof Building by Sealing Roofs, Walls, and other Penetrations
Install Proper Door Hardware
Investigate Interior Cracks
Epoxy Fill Interior Cracks
Restucco and Paint effected areas
Rebond Interior Tiles
CMU Bracing- Test and Install
Test Bullet Proof Pannels
Reroute Gutters off Flat Roof

Plumbing

5) IFR Plumbing
CLIN SubgroupDescription
5.ATesting Connection to Municipal Water and Pressure
5.BInstalling Metered Connection
5.CConnecting and Testing Water Fixtures and HVAC in Building
5.DPlumbing Fixture Cleaning and Repair
5.EWater Heater Testing and Remediation
5.FCleaning, Testing Sewage Pipelines, and Repairing
Testing Connection to Municipal Water
Installing Metered Connection
Connecting and Testing Water Fixtures in Building
Plumbing Fixture Cleaning and Repair
Water Heater Testing and Remediation
Cleaning and Testing Sewage Pipelines
Ft0.0416

HVAC

6) IFR HVAC
CLIN SubgroupDescription
6.AClean, Test and Redesign HVAC system
6.BInstall 3 Rooftop Air Conditioner Units
6.CSupply Ductwork and Interior Radial Diffusers Installed
6.DReplace and Install Interior Filters
6.EInstall Ductless Mini-Splits
6.FInstall Exhaust Vents
6.GInstall Condensing Units
Clean and Test Air Handling Units
Install Additional Air Handling Unit
Supply Ductwork and Interior Radial Diffusers Installed
Replace and Install Interior Filters
Install Ductless Mini-Splits
Install Exhaust Vents

Electrical

7) IFR Electrical
CLIN SubgroupDescription
7.AClean and Test System
7.BTransformer Cleaning and Testing
7.CTest Connection to Municipal System
7.DConduit and Wiring Testing and Installation
7.EInstall Pannel Boards and Disconnect Switches
7.FInstall and Connect Lighting Fixtures
7.GInstall Connection to Additional HVAC units_ 900 M of 885 amps and 600 V cable
Clean and Test System
Transformer Cleaning and Testing
Test Connection to Municipal System
Conduit Testing and Installation
Install Pannel Boards and Disconnect Switches
Install and Connect Lighting Fixtures
Install Connection to Additional HVAC unit

Communications

8) IFR Communication
CLIN SubgroupDescription
8.ATest Current System
8.BInstall Speakers
8.CInstall Control Pannel and Servers
Test Current System
Install Speakers
Install Control Pannel and main room

Fire Protection

10) IFR Fire Protection
CLIN SubgroupDescription
10.ATest Fire Alarms
10.BInstall Missing and Misplaced Fire Alarms
10.CReplace Exit Signs
10.DInspect and Test Fire Suppression System
10.EReplace Fire Extinguishers
10.FRefit Fire Suppression System with Fire Sprinklers
10.GInstall Fire Sprinkler Pump and Risers
Test Fire Alarms
Install Missing and Misplaced Fire Alarms
Replace Exit Signs
Inspect and Test Fire Suppression System
Replace Fire Extinguishers

DeMOB

12) IFR DEMOB
CLIN SubgroupDescription
12.ARemove all Temporary Structures from Jobsite
12.BClean Trash, Clear and Grub any Weed
12.CSweep, and Mop Interior, Ensure Fixtures are clean
12.DClean Pavement and Ashpalt
12.EComplete Final Punch List with COR

Assumptions

Assumptions* All labor hours are based of JCMS data provided by USACE or from professionals in the tradeTotal Site8,931.69m2
*Labor costs are an average based on local monthly salaries / by 160 hours. Information provided by local expertsBLD Footprint3,148.09m2
Mobilization Plan
1)All Plans will be created by GC and include cost overheads. Temporary facilities include latrines, potable water, Job trailer and rest area for employees.Non BLDING Site Area
5783.6m
Site Prep1.429156478Acres
1)Machinary will not be used in any process, except movement of materials
120
Structural
1)Remediation of eroded area will hand replaced with riprap. Estimated eroded area is 5,080 yd²
2)Backfill erosion by hand with tamping compactionTotal Site8,931.69Non BLD Area Area
3)Retile entire front part of IFRBLD Footprint3,148.095,783.60m
4)Reroute gutters perimiter of Front Building1.429156478Acres