ATTCH 15_ 22-0503 HIANG_ADDENDUM_004.pdf

PDF 61 KB Posted

Attached to
UPGRADE BUILDING COMPLEX HILO
Solicitation number
W50SLF-22-R-0001
Issued by

About this file

This solicitation seeks proposals for the construction project "Upgrade Building Complex Hilo" located at the Hawaii Air National Guard in Keaukaha, Hilo, Hawaii. The project scope includes replacing windows and doors, repairing and coating the roof, installing suspended ceilings and lights, and upgrading HVAC systems for five buildings. The estimated value is between $1 million and $5 million to be fully funded by the Department of the Army National Guard. The pre-proposal conference will be held on March 25, 2022 and the response deadline is April 21, 2022. This is a total small business set-aside with a size standard of $39.5 million average annual revenue. The contractor must coordinate work access and hazardous materials handling with the 154th Civil Engineer Squadron. The project completion time is 360 calendar days from notice to proceed.

View the file

Other files

File Type Posted
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (10-May-2022).pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (9-May-2022).pdf PDF
Solicitation RFP W50SLF22R0001 (5.5.2022 Conformed Document).pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (4-May-2022).pdf PDF
Solicitation Amendment W50SLF22R0001 0003.pdf PDF
Solicitation Amendment W50SLF22R0001 0002.pdf PDF
Solicitation RFP W50SLF22R0001 (Conformed Document).pdf PDF
ATTCH 12_22-0427_HIANG_ADDENDUM_003.pdf PDF
ATTCH 13_ 22-0428_HIANG_ADDENDUM_003.pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (28-Apr-2022).pdf PDF
ATTCH 14_22-0428-HIANG-Drwgs-ADD_3.pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (13-Apr-2022).pdf PDF
Solicitation Amendment W50SLF22R0001 0001.pdf PDF
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (12-Apr-2022).pdf PDF
5. A10-KTR Laydown Area.xlsx XLSX spreadsheet
3. Pre-Proposal Meeting PPT Upgrade Bldg Complex Hilo.pptx PPTX presentation
4. Q&A for Solicitation RFP W50SLF-22-R-0001 (27-Mar-2022).pdf PDF
1. MFR - Pre-Proposal Conference Site Visit.pdf PDF
2. Attendance Sheet - Upgrade Bldg Complex Hilo.pdf PDF
ATTCH 5_Addendum 01 - Clarification Minor Construction_dwgs.pdf PDF
ATTCH 7_Addendum 02 - SOW Add Haz Matl Survey Info.pdf PDF
ATTCH 9_88127 - Basis of Design - Mechanical.pdf PDF
EXHIBIT D_Letter of Commitment.docx DOCX document
ATTCH 10_88127 - Drawings - Mechanical R02 - Certified.pdf PDF
ATTCH 2_Appendix B - Drawings FINAL.pdf PDF
ATTCH 3_Appendix F - Calcs (FOUO).pdf PDF
ATTCH 1_SOW_MABE152003 Upgrade Building Complex Hilo.docx DOCX document
EXHIBIT C_Reference_Questionnaire_Package.docx DOCX document
ATTCH 8_Narrative of changes (Mech).pdf PDF
ATTCH 4_Appendix G - Specs FINAL.pdf PDF
Solicitation RFP W50SLF22R0001.pdf PDF
ATTCH 11_22-0128-HILO-ARCH-FINAL-PERMIT.pdf PDF
EXHIBIT A_Performance Relevancy Questionnaire.docx DOCX document
ATTCH 6_Addendum 01 - Drawings.pdf PDF
EXHIBIT B_Subcontractor Information and Consent Form.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HAWAII AIR NATIONAL GUARD Addendum No. 4 (05/03/22) KEAUKAHA ANG STATION Page 1 of 1 Project No. MABE 152003

ADDENDUM NO. 4

TO THE PLANS AND SPECIFICATIONS FOR:

HAWAII AIR NATIONAL GUARD

KEAUKAHA ANG STATION, HAWWAII

PROJECT NO. MABE 152003

May 03, 2022

This addendum modifies the original Bid Documents for the Project dated January 26, 2018. The items in this addendum shall govern the work, taking precedence over previously issued specifications and drawings governing the items mentioned.

A. DRAWINGS: N/A

B. SPECIFICATIONS:

1. SECTION 07 56 00 FLUID APPLIED ROOFING SYSTEM

a. Paragraph 2.2

ADD the following notation after paragraph 2.2.2:

“2.2.3 Roof Scuttle (Basis of Design):Bilco S-20 or approved equal.

2.2.4 Safety Post (Basis of Design): Bilco LU-1 or approved equal.

2.2.5 Roof Hatch Guard (Basis of Design): Bilco RL-2-S or approved equal.”

b. Paragraph 3.6

ADD the following notation after paragraph 3.6, Form 1

“3.7 ROOF SCUTTLE

Furnish and install roof scuttle per manufacturer recommendations.

3.8 SAFETY POST

Furnish and install safety post per manufacturer recommendations.

3.9 ROOF HATCH GUARD

Furnish and install roof hatch guard per manufacturer recommendations.”

END OF ADDENDUM NO. 4